1 AMRC 2012 MODULE 8 Horizontal Alignment CONTENTS Overview Objectives Procedures Design Considerations and Circular Curves Superelevation and Transitional Spiral Geometry of Circular Curves Circular Arc Geometrics Arc Length BC (Beginning of Curve) and EC (End of Curve) Stationing Circular Curves and Stopping Sight Distances External Distance Self-Test WPC # /09
2
3 Module 8 Horizontal Alignment Overview This module explains the technical details of horizontal curves and how to apply them in design. Objectives Upon completion of this module, the student will be able to: describe the horizontal alignment as a design consideration describe the elements of a circular curve describe the elements of superelevation. Procedures Study the module materials and make notes as required. Perform the self-test on these principles and review the course materials in such a manner as to be able to successfully complete similar questions upon examination. WPC # /09 AMRC
4 8-2 AMRC 2012 WPC # /09
5 SECTION 8.1 Design Considerations and Circular Curves Horizontal curves are used to provide a travel path between two intersecting tangents. When a vehicle moves along a circular path, it creates a centrifugal force causing the vehicle to slide radially outward. The centrifugal force is counteracted by the vehicle mass acting in consort with the friction between the tire and the pavement. When the friction force is insufficient to hold the vehicle to the pavement, the road needs to be banked to further counteract the centrifugal force. The banking of the road is called superelevation. The basic relationship between the radius of the roadway, the speed of the vehicle, the friction factor, and the superelevation is given by the following equation: 2 V R 127 (e f ) Where: R = Radius of the curve linking two tangents, m V = Speed of vehicle, km/h e = Rate of superelevation, m/m f = Lateral friction of pavement at the travelling speed Section of the Ministry of Transportation s supplement to the TAC Manual provides a more comprehensive formula for rural and high speed urban roadways. The minimum radius of a curve linking two tangents can, therefore, be developed, given the design speed, V, the corresponding lateral friction, and the maximum superelevation. The minimum radius is used to provide driver comfort and safety against side skid of the vehicle. Figure 8.1 Typical Horizontal Tangents and Curves WPC # /09 AMRC
6 The TAC design manual, Section 2.1.2, and the horizontal section of the AASHTO design policy provide detailed explanation on the equation and on the concept of minimum curve radius. 8-4 AMRC 2012 WPC # /09
7 SECTION 8.2 Superelevation and Transitional Spiral Superelevation is the banking of the road cross section to counteract the centrifugal force along a curve. The minimum curve radius can be established given a maximum superelevation. A maximum superelevation is required because the maximum lateral friction is assumed to hold the vehicle to the pavement without side skid. The lateral friction is affected by the frequency of snow and icing on the road surface. The frequency of slow moving vehicles is also a factor since they may slide sideways due to icy road conditions. Other factors include the terrain and whether the highway is located in rural or urban areas. Figure 8.2 Typical Superelevated Road Cross Section The Ministry of Transportation has established a maximum rate of superelevation of 0.08 m/m. The cross section of the road provides a normal crown for drainage. A normal crown exists when the highest point of the pavement cross section is at the centre and slopes to both sides, usually at 2 percent. To achieve superelevation, the outside pavement edge of a circular curve will be raised from a minus 2 percent to the desired elevation. The inside pavement edge will also be lowered from its +2 percent normal crown to the desired elevation. The section of the roadway for the adjustment of the cross section from an adverse crown to the design superelevation is called a transitional spiral. The rate of this change is called rate of superelevation. The length of this transition is called a spiral curve. Section of the TAC Manual provides typical superelevation development with tangent runoff options. WPC # /09 AMRC
8 Figure 8.3 Typical Normal Crown to Full Superelevation Transition Note: If the road enters the curve with normal crown, the outside lanes are sloping the wrong way. This is known as adverse crown and should be avoided in most cases. 8-6 AMRC 2012 WPC # /09
9 SECTION 8.3 Geometry of Circular Curves The following are some terminologies and calculation procedures of circular curves. Though detailed calculations are given in the following sections, they will not form part of the final exam and are included for information only Circular Arc Geometrics Prior to computation of the curve data required for layout of the curve, two variables must be known. They are: radius (R) which is selected by the designer and is based partially on the previously mentioned safety rules intersection angle (Δ) external angle between tangents (difference between bearings). Once these have been established, all other curve data can be computed. The essential additional data required for layout is as follows: curve tangent length (T) arc length (L) external distance (E) station at BC station at EC. These are illustrated in Figure 8.4. WPC # /09 AMRC
10 Figure 8.4 Simple Circular Arc Where: Δ intersection angle PI point of intersection of tangents of road C L) BC beginning of curve EC end of curve L length of curve (arc length) T tangent length E external distance From Figure 8.4, the tangent length T is the distance from the BC to the PI and also the distance from the EC to the PI. Other terms used for this length are subtangent length and apex distance. Using Figure 8.5 it can be seen that a line from the PI to 0 (the centre of the radius) bisects the angle Δ at 0. Consequently, Tan (Δ/2) = T/R Therefore: T = R tan (Δ/2) 8-8 AMRC 2012 WPC # /09
11 Figure Arc Length As shown in Figure 8.6, the circumference of a circle of radius, R, is 2πR and 360 is swept by that circumference. Therefore, the arc length: L 1 circumference 360 R L 2R L R 180 Where: Δ is in degrees. For Δ in radians L = RΔ WPC # /09 AMRC
12 Figure 8.6 Figure 8.7 Simple Circular Arc BC (Beginning of Curve) and EC (End of Curve) Stationing In order to establish the station of the BC of the curve, it is necessary to know the distance of the BC from a reference point before the curve. This reference point is very often the EC or the PI of the previous curve. Using the following example where the coordinates of PI #1 and PI #2 are known, you can calculate the curve data for curve # AMRC 2012 WPC # /09
13 Figure 8.8 Given: Tangent length, T1 = m Tangent length, T2 = m Length of curve #1 = m Length of curve #2 = m Calculate the distance D between PI #1 and PI #2. Figure 8.9 Distance D = 2 2 ( ) ( ) = m Distance 1 = D T 2 T 1 = = Chainage of EC Curve #1 = WPC # /09 AMRC
14 Distance from EC 1 to PI #2 = D T1 = = Chainage of PI #2 = ( ) = Chainage of BC Curve #2 = ( ) T2 = ( ) = Chainage of EC Curve #2 = ( ) + Length of Curve = ( ) = Note: The chainage given to the PI is derived as you travel forward (i.e., increasing chainage) along the alignment and once you have passed through the curve the PI chainage no longer has any use in your design. It is important that you realize that you do not calculate the chainage through the curve to the EC point, travel back along the target at EC to the PI, and then expect to get the same PI chainage as had previously been calculated. Figure 8.10 emphasizes this point. Figure 8.10 From the previous, it can be seen that: BC chainage & distance T BC chainage + distance L distance T AMRC 2012 WPC # /09
15 The following example of curve data computation may serve to explain this point fully. Figure 8.11 Intersection Angle: Δ = = Curve Data: Tangent Length = R tan (Δ/2) = 400 tan = m Arc Length = = m 180 Note: L < 2T BC Chainage = PI Station Distance T = [ ] = EC Chainage = BC Station + Distance L = [ ] = PI Station (if req d.) = EC Station Distance T = [ ] = m Hence, the two chainages do not equal each other. Therefore, only use the forward chainage. WPC # /09 AMRC
16 Note: At this point, we could introduce spiral curves. These are used to ease the transition from a straight to a curve and are used where cars are expected to be travelling at higher speeds. Their provision improves driver safety and comfort; however, they are not in the scope of this course AMRC 2012 WPC # /09
17 SECTION 8.4 Circular Curves and Stopping Sight Distances External Distance The external distance is the distance between the PI and the centre of the curve. This distance may be required where right-of-way restrictions occur or where the PI is inaccessible during setting out. Using Figure 8.12, it can be seen that: R cos 2 R E Therefore: R RE cos 2 Therefore: R E cos 2 R Or: E R 1 cos 2 cos 2 There are various forms of this equation but the above is the easiest for use with a calculator. Note: The terms station and chainage are interchangeable; each means the distance along the alignment from a point of known chainage. WPC # /09 AMRC
18 Figure 8.12 Review Figures , , and in the TAC Manual. The term stopping sight distance and the factors relative to its determination based on speed, reaction, friction, etc. were detailed in earlier modules. The provision of a minimum clear line of sight, for the driver, around a horizontal curve is essential in order to avoid accidents. Obstacles (e.g., rocks, deer, etc.) which may be on the road ahead must be visible in time for the driver to execute a braking stop without collision occurring. The greater this forward line of sight, the safer the curve is to negotiate. The diagram in Figures and in the TAC Manual show this line of sight to be established from the centreline of the inside lane inbound to the curve to a point on the centreline of the inside lane outbound from the curve. The critical distance is C, the offset distance from the centreline of the inside lane to the line of sight. To provide visual safety, the determination of clearing boundaries, rock removal, cut slope variations, and building relocation can be determined at the preliminary design stage using the nomograph provided in Figures and For a selected curve radii, R, and a known design speed, V, the value of C, the clearance, can be determined from the nomograph. The typical road section must be taken into account in the preliminary calculation of clearing boundaries or the checking for obstructions to visibility AMRC 2012 WPC # /09
19 This is achieved by using the value of E, the external distance for a simple circular curve. This is the distance from the PI of a curve to the centreline of the highway. However, the value C, given in Figures and , is the distance from the centre of the inside lane and it leaves a minimum half lane width for a two-lane road or one and a half lanes for a four-lane road. These must be added together. Required distance from PI to obstacle for two-lane highway = E + C + 1/2 lane width. This is illustrated in Figure Figure 8.13 Required distance from PI to sight obstacle for a four-lane highway = E + C + 1 1/2 lane widths (plus 1/2 median width where applicable). Note: Where it is not possible to achieve the required clearance, the design speed should be lowered to match the available value of C. Using the following as an example: R 300 m km V 80 desirable h km C 8 m for 80 h Say we have an actual C value of 4 m and the obstacle cannot be moved, a posted speed reduction warning would be required. The design speed for a C value of 4 m is approximately 65 km/h. WPC # /09 AMRC
20 8-18 AMRC 2012 WPC # /09
21 SECTION 8.5 Self-Test Provided below is a self-test for this module. Perform the test and compare your answers with those given in your student guide. If you have difficulty with the self-test, review the course materials and make notes in order to be able to successfully complete similar questions upon examination. 1. Explain the terms of the equation used in calculating minimum radius. 2. Why do we need superelevation on a horizontal curve? 3. What is the purpose of a transitional spiral? 4. What is the distance from the PI of a horizontal curve to the BC or EC of the curve called? 5. To find the station of the EC, which of the following would you do? A. Add the tangent length to the PI station. B. Add the curve length to the BC station. C. Add the spiral length to the BC station. D. None of the above. 6. Which of the following is likely to have the largest value? A. curve tangent length B. arc length C. external length 7. Minimum curve radius is calculated for which of the following? A. dry road B. wet road C. icy road D. snow WPC # /09 AMRC
22 8. Which of the following situations might adversely affect stopping sight distance around the inside of a curve? A. building B. trees C. rock cut D. widened shoulder 9. What is the minimum acceptable radius for each of the following road classifications? A. RLU 80 B. RAD 100 C. UAU 60 D. UFD 100 The following questions are not typical exam questions; they are included for information only. 10. Two horizontal centreline tangents on a proposed UFD 110 highway intersect at 15. A 700 m radius curve has been proposed between the two tangents. Is this radius acceptable? Calculate the curve data required to lay out this curve using a PI chainage of Two horizontal centreline tangents of a four-lane RAU 110 road, with bearings of and 88.3 respectively, intersect at a PI with a chainage of A 400 m curve has been recommended. A. Is the suggested radius satisfactory? B. Calculate the curve data for this curve (using the suggested radius if it was found to be satisfactory, or using the minimum acceptable radius if the suggested radius was not found to be adequate). C. Find the minimum clearance required from the centre of the nearside lane around the inside of the curve. 12. The sketch on the page following shows the horizontal alignment of the centreline of an existing two-lane highway that is to be upgraded to a four-lane RAD 100. From the information given: A. Calculate the existing radius. B. Calculate the station of the EC. C. Is the existing alignment satisfactory for the upgraded classification? If not, what speed restriction do you suggest might be posted? D. How far back will the existing bush have to be cleared to provide adequate stopping sight distance around the inside of the curve for a driver travelling at 95 km/h? (Use 3.75 m lane width.) 8-20 AMRC 2012 WPC # /09
23 WPC # /09 AMRC
24 8-22 AMRC 2012 WPC # /09
SURVEYING AND ROAD DESIGN FUNDAMENTALS
AREA MANAGER ROADS CERTIFICATION PROGRAM AMRC 2012 SURVEYING AND ROAD DESIGN FUNDAMENTALS STUDENT GUIDE FOR EDUCATIONAL PURPOSES ONLY April, 2006 WPC #27810 07/09 2009 by British Columbia Institute of
More informationThe Transition Curves (Spiral Curves)
The Transition Curves (Spiral Curves) The transition curve (spiral) is a curve that has a varying radius. It is used on railroads and most modem highways. It has the following purposes: 1- Provide a gradual
More informationDesign Elements Horizontal Milos N. Mladenovic Assistant Professor Department of Built Environment
Design Elements Horizontal Milos N. Mladenovic Assistant Professor Department of Built Environment 01.03.2017 Outline Highway alignment Vehicle cornering forces Minimum radius Circular curve elements Transition
More informationPE Exam Review - Surveying Demonstration Problem Solutions
PE Exam Review - Surveying Demonstration Problem Solutions I. Demonstration Problem Solutions... 1. Circular Curves Part A.... Circular Curves Part B... 9 3. Vertical Curves Part A... 18 4. Vertical Curves
More informationJCE 4600 Fundamentals of Traffic Engineering. Horizontal and Vertical Curves
JCE 4600 Fundamentals of Traffic Engineering Horizontal and Vertical Curves Agenda Horizontal Curves Vertical Curves Passing Sight Distance 1 Roadway Design Motivations Vehicle performance Acceleration
More information1.4.3 OPERATING SPEED CONSISTENCY
Geometric Design Guide for Canadian oads 1.4.3 OPEATING SPEED CONSISTENCY The safety of a road is closely linked to variations in the speed of vehicles travelling on it. These variations are of two kinds:
More informationENGINEERING SURVEYING (221 BE)
ENGINEERING SURVEYING (221 BE) Horizontal Circular Curves Sr Tan Liat Choon Email: tanliatchoon@gmail.com Mobile: 016-4975551 INTRODUCTION The centre line of road consists of series of straight lines interconnected
More informationHorizontal and Vertical Curve Design
Horizontal and Vertical Curve Design CE 576 Highway Design and Traffic Safety Dr. Ahmed Abdel-Rahim Horizontal Alignment Horizontal curve is critical. Vehicle cornering capability is thus a key concern
More informationAED Design Requirements: Superelevation Road Design
US Army Corps of Engineers Afghanistan Engineer District AED Design Requirements: Various Locations, Afghanistan MARCH 2009 TABLE OF CONTENTS AED DESIGN REQUIREMENTS FOR SUPERELEVATION ROAD DESIGN VARIOUS
More informationGeometric Layout for Roadway Design with CAiCE Visual Roads
December 2-5, 2003 MGM Grand Hotel Las Vegas Geometric Layout for Roadway Design with CAiCE Visual Roads Mathews Mathai CV32-3 This course describes and demonstrates various tools for defining horizontal
More informationTransition Curves for Roads Designers Manual
Transition Curves for Roads Designers Manual Muthanna Husham Alfityan 1 and Adnan Bin Zulkiple 2 1 PhD Student, Universiti Malaysia Pahang muthanaalfit@hotmail.com 2 Faculty of Civil Engineering & Earth
More informationENGI 3703 Surveying and Geomatics
Horizontal Curves (Chapter 24) We ll jump ahead a little today to support the last field school activity, Lab 6 - Horizontal Curve Layout. Today we ll define i) the properties of a horizontal curve and
More informationThe Mathematics of Highway Design
The Mathematics of Highway Design Scenario As a new graduate you have gained employment as a graduate engineer working for a major contractor that employs 000 staff and has an annual turnover of 600m.
More informationEngineering Surveying - II CE313. Route Survey Lecture 03 Muhammad Noman
Engineering Surveying - II CE313 Route Survey Lecture 03 Muhammad Noman Route Survey Route surveying is comprised of all survey operations required for design and construction of engineering works such
More informationCASE 1 TWO LANE TO FOUR LANE DIVIDED TRANSITION GEO-610-C NOT TO SCALE GEOMETRIC DESIGN GUIDE FOR MATCH LINE LINE MATCH. 2 (0.6m) shoulder transition
CASE 1 2 (0.6m) Joint Line See sheet #5 for description of variables 4 (1.2m) Transition taper is tangent to Edge of Pavement curve at this point. 1:25 Paved shoulder transition 16 (4.m) Median width 16
More informationCourse Instructions. 3 Easy Steps to Complete the Course: 1.) Read the Course PDF Below.
Course Instructions NOTE: The following pages contain a preview of the final exam This final exam is identical to the final exam that you will take online after you purchase the course After you purchase
More informationEstimation of Suitable Grade Value for Stopping Sight Distance Computation on Vertical Curves
Estimation of Suitable Grade Value for Stopping Sight Distance Computation on Vertical Curves Ahmed H. Farhan Assist. ecturer / Civil Eng. Dept. / Anbar University Abstract The purpose of highway geometric
More informationCIV : CURVES. Table of Contents
Unit CIV2202: Surveying 12.1 CIV2202.12: CURVES Table of Contents PREVIEW...3 Introduction...3 Objectives...3 Readings...3 HORIZONTAL CURVES...3 CIRCULAR HORIZONTAL CURVES...4 Types of Circular Curves...4
More informationCEE 3604 Transportation Geometric Design. Highways. Transportation Engineering (A.A. Trani)
CEE 3604 Transportation Geometric Design Highways 1 History Roads have been developed in ancient cultures for trade and military reasons Silk Road - 6000 km in length Appian Road - Rome to Brindisi (Italy)
More informationA parabolic curve that is applied to make a smooth and safe transition between two grades on a roadway or a highway.
A parabolic curve that is applied to make a smooth and safe transition between two grades on a roadway or a highway. VPC: Vertical Point of Curvature VPI: Vertical Point of Intersection VPT: Vertical Point
More informationComponents of Alignment. Horizontal Alignment. Vertical Alignment. Highway Design Project. Vertical Alignment. Vertical Alignment.
1/35 Components of Alignment Highway Design Project Horizontal Alignment Vertical Alignment Vertical Alignment Amir Samimi Civil Engineering Department Sharif University of Technology Cross-section /35
More informationSight Distance on Horizontal Alignments with Continuous Lateral Obstructions
TRANSPORTATION RESEARCH RECORD 1500 31 Sight Distance on Horizontal Alignments with Continuous Lateral Obstructions YASSER HASSAN, SAID M. EASA, AND A. 0. ABD EL HALIM For safe and efficient highway operation,
More informationHW3 due today Feedback form online Midterms distributed HW4 available tomorrow No class Wednesday CEE 320
Course Logistics HW3 due today Feedback form online Midterms distributed HW4 available tomorrow No class Wednesday Midterm, 11/5 Geometric Design Anne Goodchild Introduction http://www.youtube.com/watch?v=u_jf_x
More informationConstruction Surveying Curves
Construction Surveying Curves Three(3) Continuing Education Hours Course #LS1003 Approved Continuing Education for Licensed Professional Engineers EZ-pdhcom Ezekiel Enterprises, LLC 301 Mission Dr Unit
More informationThree-Dimensional Analysis of Sight Distance on Interchange Connectors
TRANSPOR'IAT/ON RESEARCH RECORD 1445 101 Three-Dimensional Analysis of Sight Distance on Interchange Connectors EDDIE SANCHEZ The design of interchange ramps and connectors, especially in large freeway-to-freeway
More informationDesign Elements Vertical Milos N. Mladenovic Assistant Professor Department of Built Environment
Design Elements Vertical Milos N. Mladenovic Assistant Professor Department of Built Environment 02.03.2017 Outline Basic elements of roadway vertical profile design Basic parameters of a vertical curve
More informationAUTODESK AUTOCAD CIVIL 2009 AND AUTOCAD CIVIL 3D Rule-Based Road Design using AutoCAD Civil and AutoCAD Civil 3D
AUTODESK AUTOCAD CIVIL 2009 AND AUTOCAD CIVIL 3D 2009 Rule-Based Road Design using AutoCAD Civil and AutoCAD Civil 3D Contents Introduction... 3 Design Criteria Files... 3 Alignment Geometry... 4 Applying
More informationTransportation Engineering - II Dr.Rajat Rastogi Department of Civil Engineering Indian Institute of Technology - Roorkee
Transportation Engineering - II Dr.Rajat Rastogi Department of Civil Engineering Indian Institute of Technology - Roorkee Lecture 18 Vertical Curves and Gradients Dear students, I welcome you back to the
More informationRoadway Alignments and Profiles
NOTES Module 15 Roadway Alignments and Profiles In this module, you learn how to create horizontal alignments, surface profiles, layout (design) profiles, and profile views in AutoCAD Civil 3D. This module
More informationCONTRIBUTION TO THE INVESTIGATION OF STOPPING SIGHT DISTANCE IN THREE-DIMENSIONAL SPACE
National Technical University of Athens School of Civil Engineering Department of Transportation Planning and Engineering Doctoral Dissertation CONTRIBUTION TO THE INVESTIGATION OF STOPPING SIGHT DISTANCE
More informationHighway Alignment. Three-Dimensional Problem and Three-Dimensional Solution YASSER HASSAN, SAID M. EASA, AND A. O. ABD EL HALIM
TRANSPORTATION RESEARCH RECORD 1612 Paper No. 98-0257 17 Highway Alignment Three-Dimensional Problem and Three-Dimensional Solution YASSER HASSAN, SAID M. EASA, AND A. O. ABD EL HALIM Highway geometric
More informationRequest for FTE Design Exceptions & Variations Checklist
District: Project Name: Project Section BMP: EMP: Exemption BMP: EMP: Request for FTE Design Exceptions & Variations Checklist FPID: New Construction RRR Requested Control Element(s): Design Speed* Horizontal
More informationRoute Surveying. Topic Outline
Route Surveying CE 305 Intro To Geomatics By Darrell R. Dean, Jr., P.S., Ph.D. Topic Outline Horizontal alignment Types of Horizontal Curves Degree of Curve Geometric elements of curve Station ti number
More informationParticular attention has been paid to the editor s graphics (highlighting of IPs and Elements, tangent points and chainage direction).
12D Super Alignment Parametric Design: The new super alignment utilises not only alignment design by the Fixed and Free method, but introduces a complete new approach to horizontal and vertical road design.
More informationAlignments CHAPTER INTRODUCTION OBJECTIVES
CHAPTER 5 Alignments INTRODUCTION This and the next four chapters focus on roadway design and its documentation. This chapter concentrates on roadway plan design. The next three chapters focus on the roadway
More informationCE 371 Surveying Circular Curves
Lec. 25 1 CE 371 Surveying Circular Curves Dr. Ragab Khalil Department of Landscape Architecture Faculty of Environmental Design King AbdulAziz University Room LIE15 Overview Introduction Definition of
More informationFINAL Examination Paper (COVER PAGE) Time : 8.00 am am Reading Time : 10 Minutes
Session : August 2013 FINAL Examination Paper (COVER PAGE) Programme : Diploma in Civil Engineering Course : EGC2170 : Surveying 2 Date of Examination : December 09, 2013 Time : 8.00 am 10.10 am Reading
More informationNCDOT Civil Geometry for GEOPAK Users
2018 NCDOT Civil Geometry for GEOPAK Users Oak Thammavong NCDOT Roadway Design Unit 7/31/2018 This page left intentionally blank Copyright 2018 NCDOT DO NOT DISTRIBUTE Printing for student use is permitted
More informationSight Distance on Vertical Curves
Iowa Department of Transportation Office of Design Sight Distance on Vertical Curves 6D-5 Design Manual Chapter 6 Geometric Design Originally Issued: 01-04-0 Stopping sight distance is an important factor
More informationSight Distance Relationships Involving Horizontal Curves
96 TRANSPORTATON RESEARCH RECORD 1122 Sight Distance Relationships nvolving Horizontal Curves GARY R. WASS! AND DONALD E. CLEVELAND Recent AASHTO design policy developments and research have ncreased needed
More informationINPUT DATA PROCEDURES
79 SECTION 7 INPUT DATA PROCEDURES This section describes the forms and message boxes used to enter input data for an RSRAP optimization problem. These forms and message boxes implement Steps 1 through
More informationOPTIMAL 3D COORDINATION TO MAXIMIZE THE AVAILABLE STOPPING SIGHT DISTANCE IN TWO-LANE ROADS
0 0 0 Moreno, Ana Tsui; Ferrer-Pérez, Vicente; Garcia, Alfredo; Romero, Mario Alfonso. (00). Optimal D Coordination to Mazimize the Available Stopping Sight Distance in Two-Lane Roads In: Proceedings of
More informationADVANCED SURVEYING (S-II)
ADVANCED SURVEYING (S-II) (LAB) KISHANGANJ COLLEGE OF ENGINEERING AND TECHNOLOGY, KISHANGANJ. Experiment No- 1 ADVANCED SURVEYING (S-II) LAB Aim: Determination of the Multiplying and additive constant
More informationChapter V Earth Work & Quantities. Tewodros N.
Chapter V Earth Work & Quantities Tewodros N. www.tnigatu.wordpress.com tedynihe@gmail.com Introduction Is the phase during a highways construction when the right of way is converted from its natural condition
More informationA COST-EFFECTIVE ROAD SURVEYING METHOD FOR THE ASSESSMENT OF ROAD ALIGNMENTS
A COST-EFFECTIVE ROAD SURVEYING METHOD FOR THE ASSESSMENT OF ROAD ALIGNMENTS Basil Psarianos 1, Demetre Paradisis 2, Byron. Nakos 3 and George. Karras 4 1 Laboratory of Transportation Engineering, 2 Satellite
More informationCHAPTER 11. Learn to use GEOPAK Automated Superelevation dialog box and Autoshape Builder to apply superelevation to a roadway.
CHAPTER 11 Superelevation 11.1 Introduction Objectives Project Manager Learn to use GEOPAK Automated Superelevation dialog box and Autoshape Builder to apply superelevation to a roadway. Calculate Superelevation
More informationTrimble s RoadLink Utility Tutorials
Trimble s RoadLink utility is an interface between third-party road definitions and Trimble survey devices. It lets you import or key in road definitions, view them graphically, edit them if required,
More informationClearance in Order to Provide Stopping Sight Distances
Journal of Transportation Technologies, 2017, 7, 221-239 http://www.scirp.org/journal/jtts ISSN Online: 2160-0481 ISSN Print: 2160-0473 Suitability of the Euler s Spiral for Roadside Clearance in Order
More informationBentley Civil Guide. SELECT series 3. Setting Up Superelevation SEP Files. Written By: Lou Barrett, BSW-Development, Civil Design
Bentley Civil Guide SELECT series 3 Setting Up Superelevation SEP Files Written By: Lou Barrett, BSW-Development, Civil Design Bentley Systems, Incorporated 685 Stockton Drive Exton, PA 19341 www.bentley.com
More informationDESIGN CRITERIA MEMORANDUM
State Route 49 Realignment Study DESIGN CRITERIA MEMORANDUM ATTACHMENT G SR 49 Realignment Study STATE ROUTE 49 El Dorado to Coloma El Dorado County, CA DESIGN CRITERIA MEMORANDUM Introduction The El
More informationApproximating Maximum Speed on Road from Curvature Information of Bezier Curve
Approximating Maximum Speed on Road from Curvature Information of Bezier Curve M. Y. Misro, A. Ramli, J. M. Ali Abstract Bezier curves have useful properties for path generation problem, for instance,
More informationInteractive Highway Safety Design Model (IHSDM) Workshop Nevada DOT Las Vegas, NV February 13, 2014
Interactive Highway Safety Design Model (IHSDM) Workshop Nevada DOT Las Vegas, NV February 13, 2014 Overview Hands-on Exercises: IHSDM Crash Prediction Module (CPM) The Crash Prediction Module estimates
More informationFACULTY OF CIVIL ENGINEERING & EARTH RESOURCES ENGINEERING SURVEY FIELDWORK. CURVE RANGING COMPUTATION & SETTING-OUT (Standard Of Procedure)
FACULTY OF CIVIL ENGINEERING & EARTH RESOURCES ENGINEERING SURVEY FIELDWORK CURVE RANGING COMPUTATION & SETTING-OUT (Standard Of Procedure) Subject Code Date Group Number Student Name & ID Number Group
More informationCivil 3D Introduction
Civil 3D Introduction Points Overview Points are data collected by surveyors which represent existing site conditions (elevations, boundaries, utilities, etc.). Each point is numbered (or named) and has
More informationOPTIMIZING HIGHWAY PROFILES FOR INDIVIDUAL COST ITEMS
Dabbour E. Optimizing Highway Profiles for Individual Cost Items UDC: 656.11.02 DOI: http://dx.doi.org/10.7708/ijtte.2013.3(4).07 OPTIMIZING HIGHWAY PROFILES FOR INDIVIDUAL COST ITEMS Essam Dabbour 1 1
More informationFRST 557. Lecture 9c. Switchbacks Vertical and Horizontal Design. Lesson Background and Overview:
FST 557 Lecture 9c Switchbacks Vertical and Horizontal Design J u s t g iv e it o n e try, a n d if it don t w o rk w e ll c a ll in th e road crew to fix er up Lesson Background and Overview: Switchbacks
More informationAppendix E. Plane Geometry
Appendix E Plane Geometry A. Circle A circle is defined as a closed plane curve every point of which is equidistant from a fixed point within the curve. Figure E-1. Circle components. 1. Pi In mathematics,
More informationPi at School. Arindama Singh Department of Mathematics Indian Institute of Technology Madras Chennai , India
Pi at School rindama Singh epartment of Mathematics Indian Institute of Technology Madras Chennai-600036, India Email: asingh@iitm.ac.in bstract: In this paper, an attempt has been made to define π by
More information(a) Barometric levelling (b) Trigonometric levelling (c) Spirit levelling [16]
Code No: R050210103 Set No. 1 II B.Tech I Semester Supplementary Examinations, February 2007 SURVEYING (Civil Engineering) Time: 3 hours Max Marks: 80 Answer any FIVE Questions All Questions carry equal
More informationWYOMING DEPARTMENT OF TRANSPORTATION
PAGE 1 OF 5 WYOMING DEPARTMENT OF TRANSPORTATION ROAD DESIGN MEMORANDUM #02 DATE OF ISSUE: December 01, 2004 Approved by: Paul P. Bercich, P.E. Highway Development Engineer Issued by: Engineering Services,
More informationComputation of Curve Staking out Coordinates on the Excel Spreadsheet
Computation of Curve Staking out Coordinates on the Excel Spreadsheet This is a Peer Reviewed Paper T.G.Gacoki Kenya National Highways Authority, Kenha SUMMARY A procedure for the computation of curve
More informationAnother Look at the Safety Effects of Horizontal Curvature on Rural Two-Lane Highways
1 2 Another Look at the Safety Effects of Horizontal Curvature on Rural Two-Lane Highways 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
More informationUNIT 5 GEOMETRY TEMPLATE CREATED BY REGION 1 ESA UNIT 5
UNIT 5 GEOMETRY TEMPLATE CREATED BY REGION 1 ESA UNIT 5 Geometry Unit 5 Overview: Circles With and Without Coordinates In this unit, students prove basic theorems about circles, with particular attention
More informationAUTOCAD CIVIL 2009 AND AUTOCAD CIVIL 3D Road Rehabilitation and Reconstruction with AutoCAD Civil and AutoCAD. Civil 3D
AUTOCAD CIVIL 2009 AND AUTOCAD CIVIL 3D 2009 Road Rehabilitation and Reconstruction with AutoCAD Civil and AutoCAD Civil 3D 1 Contents Introduction... 3 Introduction to Corridor Targets... 3 Surface Targets...
More informationPage 2D-12 Revised the following language in the last sentence on the page from; as shown in Figure 2D-3. To; as shown in Chapter 2H, Figure 2H-35.
IMPERIAL ROAD DESIGN MANUAL REVISIONS January, 2015 CHAPTER 2A Page 2A-1 Revised the following language at the end of the paragraph under PRELIMINARY ENGINEERING AUTHORIZATION from; Funding Allocation/Verification/Submittal
More informationMath 124 Final Examination Autumn Turn off all cell phones, pagers, radios, mp3 players, and other similar devices.
Math 124 Final Examination Autumn 2016 Your Name Your Signature Student ID # Quiz Section Professor s Name TA s Name Turn off all cell phones, pagers, radios, mp3 players, and other similar devices. This
More informationProperties of a Circle Diagram Source:
Properties of a Circle Diagram Source: http://www.ricksmath.com/circles.html Definitions: Circumference (c): The perimeter of a circle is called its circumference Diameter (d): Any straight line drawn
More informationInternational Journal of Advance Engineering and Research Development. Modelling to Track Negative Externalities Influencing on Speed Control with GIS
Scientific Journal of Impact Factor (SJIF): 4.72 International Journal of Advance Engineering and Research Development Volume 4, Issue 11, November -2017 Modelling to Track Negative Externalities Influencing
More informationThe diagram above shows a sketch of the curve C with parametric equations
1. The diagram above shows a sketch of the curve C with parametric equations x = 5t 4, y = t(9 t ) The curve C cuts the x-axis at the points A and B. (a) Find the x-coordinate at the point A and the x-coordinate
More informationBentley Civil Workshop
Bentley Civil Workshop 2013 MACC Conference Day 2 OpenRoads Technology Workshop: Horizontal and Vertical Geometry Team Leader: Bob Rolle Team Members: Ray Filipiak, Dave Hoerner Bentley Systems, Incorporated
More informationMastering Corridor Transitions and Superelevation with Autodesk Civil 3D 2006
12/1/2005-8:00 am - 11:30 am Room:Swan 4 (Swan) Walt Disney World Swan and Dolphin Resort Orlando, Florida Mastering Corridor Transitions and Superelevation with Autodesk Civil 3D 2006 Michael Choquette
More informationChapter 6 Review. Extending Skills with Trigonometry. Check Your Understanding
hapter 6 Review Extending Skills with Trigonometry heck Your Understanding. Explain why the sine law holds true for obtuse angle triangles as well as acute angle triangles. 2. What dimensions of a triangle
More informationBentleyuser.dk Årsmøde 2012 Nordic Civil 2012
Bentleyuser.dk Årsmøde 2012 Nordic Civil 2012 5.-7. November 2012, Munkebjerg Hotel, Vejle Workshop X13 Advanced Geometrical Layout for Compound and Reversed Curves Team Leader: Richard Bradshaw Bentley
More informationTRANSITION CURVES E.M.G.S. MANUAL ( 1) Transition Curves (or Easement Curves) SHEET 1 Issue Introduction. 1. Introduction.
TRANSITION CURVES SHEET 1 Transition Curves (or Easement Curves) 1. Introduction. 2. Development of Transition Curves and the Adoption of Superelevation (Cant). 3. General Application of Transition Curves
More informationSHORT ANSWER. Write the word or phrase that best completes each statement or answers the question.
Review for Test 2 MATH 116 SHORT ANSWER. Write the word or phrase that best completes each statement or answers the question. Solve the right triangle. If two sides are given, give angles in degrees and
More informationMath 3C Section 9.1 & 9.2
Math 3C Section 9.1 & 9.2 Yucheng Tu 11/14/2018 1 Unit Circle The unit circle comes to the stage when we enter the field of trigonometry, i.e. the study of relations among the sides and angles of an arbitrary
More informationAN AUTOMATIC HORIZONTAL CURVE RADII MEASUREMENT METHOD FOR ROADWAY SAFETY ANALYSIS USING GPS DATA
Ai and Tsai 0 AN AUTOMATIC HORIZONTAL CURVE RADII MEASUREMENT METHOD FOR ROADWAY SAFETY ANALYSIS USING GPS DATA Chengbo Ai (corresponding author) Post-Doctoral Fellow School of Civil and Environmental
More informationParametric Representation of Scroll Geometry with Variable Wall Thickness. * Corresponding Author: ABSTRACT 1.
1268, Page 1 Parametric Representation of Scroll Geometry with Variable Wall Thickness Bryce R. Shaffer 1 * and Eckhard A. Groll 2 1 Air Squared Inc. Broomfield, CO, USA 2 Purdue University, Mechanical
More informationBentley ConceptStation Workshop 2017 FLUG Spring Training Event
Bentley ConceptStation Workshop 2017 FLUG Spring Training Event 430 - QuickStart using OpenRoads ConceptStation Bentley Systems, Incorporated 685 Stockton Drive Exton, PA 19341 www.bentley.com Practice
More information1. Report No. 2. Government Accession No. 3. Recipient's Catalog No. FHWA/IN/JTRP-2003/14
1. Report No. 2. Government Accession No. 3. Recipient's Catalog No. FHWA/IN/JTRP-2003/14 TECHNICAL REPORT STANDARD TITLE PAGE 4. Title and Subtitle INDOT Highway Needs Analysis Impacts of Physical Features
More informationMODELLING, ANALYZING, AND VISUALIZING VEHICLE SWEPT PATH
MODELLING, ANALYZING, AND VISUALIZING VEHICLE SWEPT PATH AutoTURN Pro is the state-of-the-art tool for performing swept path analysis. With the Swept Path 2.0 technology builtin, it takes the analysis
More informationLevel 6 Graduate Diploma in Engineering Engineering surveying
9210-104 Level 6 Graduate Diploma in Engineering Engineering surveying Sample Paper You should have the following for this examination answer booklets non-programmable calculator pens, pencils, drawing
More informationCARIBBEAN CORRESPONDENCE SCHOOL
Final Examination CARIBBEAN CORRESPONDENCE SCHOOL Module Name: Groups: Duration: MATHEMATICS Online 3 Hours INSTRUCTIONS TO CANDIDATES 1. This Paper consists of THREE sections. 2. There is one question
More informationNCHRP Project Median Cross-Section Design for Rural Divided Highways
NCHRP Project 22-21 Median Cross-Section Design for Rural Divided Highways Acknowledgements NCHRP Projects Officer, Ray Derr Project Team Midwest Research Institute PI Jerry Graham Pennsylvania Transportation
More informationTin Ka Ping Secondary School F.3 Mathematics Teaching Syllabus
Tin Ka Ping Secondary School 05-06 F. Mathematics Syllabus Chapter Linear Inequalities in One Unknown Time Guide. Basic Concept of Inequalities A. What are Inequalities? B. Solutions of Inequalities C.
More information10600 sq. feet. Left 33.8 left of CL at elev Right 33.4 right of CL at elev 871.1
NAME Score CEEN 113-1 Engineering Measurements Final Exam Fall 1999 Open Book, Closed Note, Calculator Required 3 Hour Time Limit 1 point deduction for every two minutes over 1. (5 pts) Your boss has asked
More informationBentley Civil Workshop
Bentley Civil Workshop 2013 Bentley LEARNing Conference BCR3WK1 OpenRoads Technology Workshop: Horizontal Geometry Team Leader: Lou Barrett, Product Manager (BSW Civil Design) Team Members: Mike Wilson,
More informationTheodolite and Angles Measurement
Building & Construction Technology Engineering Department Theodolite and Angles Measurement Lecture 1 Theodolite and Angles Measurement Lecture No. 1 Main Objectives Lecturer Date of Lecture General advices
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
Exam Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Convert the angle to decimal degrees and round to the nearest hundredth of a degree. 1)
More informationChapter 5. An Introduction to Trigonometric Functions 1-1
Chapter 5 An Introduction to Trigonometric Functions Copyright (c) The McGraw-Hill Companies, Inc. Permission required for reproduction or display. 1-1 5.1 A half line or all points extended from a single
More informationSafety Impacts at Intersections on Curved Segments
Safety Impacts at Intersections on Curved Segments Peter T. Savolainen Phone: 765-47-606 E-mail: psavolai@purdue.edu Andrew P. Tarko Phone: 765-494-507 E-mail: tarko@purdue.edu Purdue University School
More informationDigital Terrain Model V 6.5
TCP MDT Digital Terrain Model V 6.5 Professional Version Introduction The Professional Version is designed to assist users in all the phases of carrying out a Surveying or Civil Engineering project. Its
More information1. Use the Trapezium Rule with five ordinates to find an approximate value for the integral
1. Use the Trapezium Rule with five ordinates to find an approximate value for the integral Show your working and give your answer correct to three decimal places. 2 2.5 3 3.5 4 When When When When When
More informationPerimeter. Area. Surface Area. Volume. Circle (circumference) C = 2πr. Square. Rectangle. Triangle. Rectangle/Parallelogram A = bh
Perimeter Circle (circumference) C = 2πr Square P = 4s Rectangle P = 2b + 2h Area Circle A = πr Triangle A = bh Rectangle/Parallelogram A = bh Rhombus/Kite A = d d Trapezoid A = b + b h A area a apothem
More informationAnswer Key: Three-Dimensional Cross Sections
Geometry A Unit Answer Key: Three-Dimensional Cross Sections Name Date Objectives In this lesson, you will: visualize three-dimensional objects from different perspectives be able to create a projection
More informationISO/TS TECHNICAL SPECIFICATION. Transport information and control systems Traffic Impediment Warning Systems (TIWS) System requirements
TECHNICAL SPECIFICATION ISO/TS 15624 First edition 2001-01-15 Transport information and control systems Traffic Impediment Warning Systems (TIWS) System requirements Systèmes de commande et d'information
More informationBentley OpenRoads Workshop 2017 FLUG Fall Training Event
Bentley OpenRoads Workshop 2017 FLUG Fall Training Event F-2P - QuickStart for Roadway Modeling in OpenRoads Technology Bentley Systems, Incorporated 685 Stockton Drive Exton, PA 19341 www.bentley.com
More informationMAHALAKSHMI ENGINEERING COLLEGE
MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI - 6113. DEPARTMENT: CIVIL QUESTION BANK SUBJECT CODE / Name: CE 04 / Surveying -I Unit 5 ENGINEERING SURVEYS PART A ( marks) SEMESTER: III 1. What are the
More informationGeometry B. The University of Texas at Austin Continuing & Innovative Education K 16 Education Center 1
Geometry B Credit By Exam This Credit By Exam can help you prepare for the exam by giving you an idea of what you need to study, review, and learn. To succeed, you should be thoroughly familiar with the
More informationME 111: Engineering Drawing. Geometric Constructions
ME 111: Engineering Drawing Lecture 2 01-08-2011 Geometric Constructions Indian Institute of Technology Guwahati Guwahati 781039 Geometric Construction Construction of primitive geometric forms (points,
More information