T2S high level programme plan and work streams
|
|
- Pearl White
- 6 years ago
- Views:
Transcription
1 T2S high level programme plan and work streams First meeting of the T2S central bank experts network March 2009 Flora Laszlo T2S Division Technical Programme Management European Central Bank 1
2 Agenda Programme management - planning of work Building the plan top down and bottom up Workstreams - objectives and main deliverables High level plan and major dependencies between the workstreams Rolling plans - monitoring 2
3 Programme management planning of project work Final goal is to have a secure, legally sound and wellfunctioning system In order to achieve this target: plan tasks and the way of executing them; create a feasible work plan; schedule the tasks; visualise them; track the status and revise the future plans (if needed). High level programme plan and short term rolling plans 3
4 Building the plan Top-down approach high level plan: Identification of 9 core workstreams, 2 supporting and 2 value adding works streams Gather information for core workstreams and prepare a high level plan Consolidate these high level plans into a master plan Bottom-up approach short term rolling plans: Detailed plans for the next 6 months for each core workstream Monitoring status, rolling them over Each core workstream has: Its general objectives and main deliverables Interdependencies with other workstreams and tasks Timing 4
5 The workstreams 9 core workstreams I Governance II User requirements III Functional Specifications IV Non-Functional Specifications V Technical Infrastructure VI Financial framework VII Legal framework VIII Testing and Migration IX Information Security Management 2 value-adding workstreams Harmonisation Non-euro business 2 supporting workstreams Programme management Communication 5
6 Objectives and main deliverables of the core workstreams I. Governance what is the appropriate decision making structure? responsibilities within the Eurosystem Document(s) on governance arrangements II. III. User requirements which service T2S should deliver (UR)? various changes proposed by stakeholders Functional specifications basis for the 4CB to develop the T2S application update of the GFS/UDFS triggered by UR change requests UR documents (annual) Change requests to UR GFS document(s) UDFS document(s) User handbook (UHB) 6
7 Objectives and main deliverables of the core workstreams (cont.) IV. Non-functional specifications arrangements on technical performance of system (processing capacity, response time etc) operational requirements (support, escalation procedures etc) V. Technical infrastructure building the technical system VI. Financial framework Cost assessment of the 4CB Fees received from CSDs SLA with 4CB SLA with CSDs Manual of Operational Procedures (MOP) Technical design Testing and production platforms Conditional final offer Pricing policy Pricing scheme and its implementation 7
8 Objectives and main deliverables of the core workstreams (cont) VII. Legal framework contractual relationship of CSDs with Eurosystem Eurosystem internal legal set-up VIII. Testing and migration acceptance of the software application (on the basis of UR and UDFS) verification of functions (user tests) move the settlement activity to T2S IX. Information security policy Check of confidentiality, integrity and availability of information in T2S management and operations Contracts with CSD Intra-Eurosystem arrangements Other arrangements (noneuro NCB and third party providers) Testing strategy, testing plans Migration strategy, migration plans Acceptance test; user test Information Security Policy Sec. requirements & controls Risk analysis 8 Security assessment report
9 I. Governance, IV. non-functional specifications, VI. financial, IX. information security and VII. legal workstreams Governance: substantial elements of governance Governance arrangements for the operation phase Technical and operational commitments: substantial elements of SLAs Pricing policy Security Requirements/controls Pricing scheme Final SLAs Security Assessment Report MoU Framework Agreement Final agreements for operation phase (CSD, internal Eurosystem) Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
10 II. User requirements, III. functional specifications, V. technical infrastructure and VIII. testing/migration workstreams User requirements management: URD 4.1 URD 5.0 URD 6.0 GFS 2.0 UDFS 1.0 UDFS 2.0 UDFS 3.0 UHB 1.0 UHB 2.0 Test platform Production platform Testing and migration strategies Acceptance test plans Start user testing Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
11 Major dependencies between the workstreams Harmonisation Non-euro business II. User requirements III. functional specifications V. technical infrastructure VIII. Testing and migration G O IX. Information security IV. non-functional specifications L I V E I. Governance VII. legal VI. financial 11
12 Rolling plans Planning and monitoring the activities at a more granular level with a detailed 6 month rolling plan Summarising the workstream reports, holding status review meetings, discussing task interdependencies Monitoring progress compared to previous cycle and to the high level plan top down meets bottom up! Regular status tracking internally and presentations to the AG 12
13 Rolling plans 13
14 Questions 14
T2S PROGRAMME STATUS AS OF MID-SEPTEMBER
T2S PROGRAMME OFFICE ECB-PUBLIC AG Meeting 18/19 September 2012 Item 2 09.04.01/2012/007820 T2S PROGRAMME STATUS AS OF MID-SEPTEMBER 2012-1. Introduction In this note the T2S Programme Office provides
More information1. Legal/business importance parameter: High 2. Market implementation efforts parameter: Low
General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: 4CB Institute: 4CB Date raised: 05/01/2017 Request title: Handling
More information1. Legal/business importance parameter: High 2. Market implementation efforts parameter: Low
General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: 4CB Institute: 4CB Date raised: 05/01/2017 Request title: Handling
More informationUrgency: Normal. 1. Legal/business importance parameter: Medium 2. Market implementation efforts parameter: Medium
General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: Deutsche Bundesbank Institute: NCB Date raised: 23/11/2015 Request
More information1. Legal/business importance parameter: Medium 2. Market implementation efforts parameter: Low
General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: 4CB Institute: 4CB Date raised: 01/10/2014 Request title: Securities
More informationT2S Dedicated Link Connectivity Solution
T2S Dedicated Link Connectivity Solution Presentation Meeting, 22 April 2013 T2S Programme Office European Central Bank 0 Dedicated Link Presentation Agenda Dedicated Link Origin Dedicated Link Overview
More information/2011/ Item 8.2
09.04.01/2011/010381 Item 8.2 Change request form Page 1 of 15 REFERENCES L2 reference T2S 0300 URD created on 28/09/2011 (AG) Referenced documents CR_T2S_0300_URD_v0-0- 1.doc General Information (Origin
More informationUNITAS Crisis communication exercise report
UNITAS Crisis communication exercise report December 2018 Contents Executive summary 2 1 Introduction 3 2 Exercise objectives 4 3 Organisation 5 4 Exercise findings 6 4.1 Participants 6 4.2 Overseers 7
More informationT2S Connectivity Guide
T2S Connectivity Guide Page 1 of 23 T2S Connectivity Guide Author 4CB Version 1.0 Date 29/11/2013 Status Classification Classified until Final Public N/A T2S Connectivity Guide Page 2 of 23 TABLE OF CONTENTS
More informationSpecification Requirements T2S GUI. 08 th December 2011 ECB - 4CB
08 th December 2011 ECB - 4CB 1. Technical Description Architecture/Infrastructure Web-based GUI supported by browsers and versions Other software requirements and related versions /N Not clear Standard
More informationMemorandum of Understanding
Memorandum of Understanding between the European Commission, the European Union Agency for Railways and the European rail sector associations (CER, EIM, EPTTOLA, ERFA, the ERTMS Users Group, GSM-R Industry
More informationDetermining Best Fit for ITIL Implementation
Determining Best Fit for ITIL Implementation Presentation to the DC SPIN October 4, 2006 www.davidconsultinggroup.com Agenda Introduction to ITIL Preparing for ITIL Best Fit Analysis Relationship of ITIL
More informationInsights on Configuration of Restriction Types in T2S
Insights on Configuration of Restriction Types in T2S June 2014 T2S Programme Office European Central Bank 0 Scope of the Presentation The presentation aims to address following key questions related to
More informationREPORT 2015/149 INTERNAL AUDIT DIVISION
INTERNAL AUDIT DIVISION REPORT 2015/149 Audit of the information and communications technology operations in the Investment Management Division of the United Nations Joint Staff Pension Fund Overall results
More informationMunicipal Broadband Project. City Council Meeting February 4, 2016
Municipal Broadband Project City Council Meeting February 4, 2016 Broadband Timeline 12 Months February March 2015 Feasibility Study April May 2015 Business Plan Development June August 2015 Renegotiation
More informationInsight Session: T2S User Testing and Migration
Insight Session: T2S User Testing and Migration T2S Info Session Vienna, 5 October 2012 T2S Programme Office European Central Bank ECB-PUBLIC 0 Agenda 1 T2S User Testing 2 T2S Migration 1 User testing
More informationOUTCOME OF THE 8 TH MEETING OF TARGET INSTANT PAYMENT SETTLEMENT (TIPS) CONTACT GROUP
23 August 2018 OUTCOME OF THE 8 TH MEETING OF TARGET INSTANT PAYMENT SETTLEMENT (TIPS) CONTACT GROUP 4 July 2018 10:00 to 17:00 held at the premises of the European Central Bank, Sonnemannstraße 20, meeting
More informationIT Expert (Enterprise Network and Infrastructure Architect)
IT Expert (Enterprise Network and Infrastructure Architect) Reference 2015-221-EXT Type of contract Who can apply Salary Working time Place of work Closing date for applications Fixed-term contract which
More informationData Quality Blueprint for Pentaho: Better Data Leads to Better Results. Charles Gaddy Director Global Sales & Alliances, Melissa Data
Data Quality Blueprint for Pentaho: Better Data Leads to Better Results Charles Gaddy Director Global Sales & Alliances, Melissa Data Agenda What is Data Quality, and What Role Does it Play? 6 Concepts
More informationDECISION OF THE EUROPEAN CENTRAL BANK
L 74/30 Official Journal of the European Union 16.3.2013 DECISIONS DECISION OF THE EUROPEAN CENTRAL BANK of 11 January 2013 laying down the framework for a public key infrastructure for the European System
More informationStruxureWare TM Data Center Operation Periodic Maintenance. Statement Of Work. 2.0 Features & Benefits
- 1 - StruxureWare TM DC Operation Periodic Maintenance Service Integration Service Statement Of Work 1. Executive summary StruxureWare TM Data Center Operation Periodic Maintenance Table of Contents 1.0
More informationWiebe Ruttenberg & Emran Islam DG Market Infrastructure & Payments. From Cyber Threats via Cyber Security to Cyber Resilience
Wiebe Ruttenberg & Emran Islam DG Market Infrastructure & Payments From Cyber Threats via Cyber Security to Cyber Resilience AMISeCo meeting, 7 March 2017 Rubric Cyber threats landscape Cyber threats are
More information1. Legal/business importance parameter: Low 2. Market implementation efforts parameter: Low
General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: 4CB Institute: 4CB Date raised: 30.09.2016 Request title: Multiplex
More informationThe Role of ENISA in the Implementation of the NIS Directive Anna Sarri Officer in NIS CIP Workshop Vienna 19 th September 2017
The Role of ENISA in the Implementation of the NIS Directive Anna Sarri Officer in NIS CIP Workshop Vienna 19 th September 2017 European Union Agency for Network and Information Security Positioning ENISA
More informationInsight Session on T2S User Testing
Insight Session on T2S User Testing Dedicated Info Session on T2S User Testing and Migration: an urgent matter Frankfurt, 3 July 2013 T2S Programme Office European Central Bank 1 T2S User Testing Agenda
More informationRed Flags/Identity Theft Prevention Policy: Purpose
Red Flags/Identity Theft Prevention Policy: 200.3 Purpose Employees and students depend on Morehouse College ( Morehouse ) to properly protect their personal non-public information, which is gathered and
More informationRecommendations of the 18 Nov 2009 UR Management Subgroup meeting
09.04.01/2009/012083 Recommendations of the 18 Nov 2009 UR Management Subgroup meeting T2S AG meeting 09-10 December 2009 1 Summary 10 th meeting of the UR Management Sub-Group (URM SG) took place on 18
More informationFinancing Data Centres
Financing Data Centres Data Centre strategies Presented by: John Wilson Date: 20 March 2012 Security may be required. Product fees may apply. Today s Agenda Funder s View on the Marketplace Types of Finance
More informationContracting for an IT General Controls Audit
Contracting for an IT General Controls Audit Lori Schubert, C.P.A. Internal Audit Manager age Waukesha County (WI) lschubert@waukeshacounty.gov Overview of Presentation Description of Waukesha County Information
More informationISACA Cincinnati Chapter March Meeting
ISACA Cincinnati Chapter March Meeting Recent and Proposed Changes to SOC Reports Impacting Service and User Organizations. March 3, 2015 Presenters: Sayontan Basu-Mallick Lori Johnson Agenda SOCR Overview
More informationManagement s Response to the Auditor General s Review of Management and Oversight of the Integrated Business Management System (IBMS)
APPENDI 2 ommendation () () 1. The City Manager in consultation with the Chief Information Officer give consideration to the establishment of an IBMS governance model which provides for senior management
More informationThe NIS Directive and Cybersecurity in
The NIS Directive and Cybersecurity in ehealth Dr. Athanasios Drougkas Officer in NIS Belgian Hospitals Meeting on Security Brussels 13 th October European Union Agency For Network And Information Security
More informationReadiness of Individual European Recycling Companies. Hosted by StorageTek
Readiness of Individual European Recycling Companies Hosted by StorageTek Research Project Overview Identify End-Of-Life Supply Chain Vendors in the European Union Develop and Distribute Questionnaire
More informationVendor: The Open Group. Exam Code: OG Exam Name: TOGAF 9 Part 1. Version: Demo
Vendor: The Open Group Exam Code: OG0-091 Exam Name: TOGAF 9 Part 1 Version: Demo QUESTION 1 According to TOGAF, Which of the following are the architecture domains that are commonly accepted subsets of
More informationOutcome 7 th Task Force on Future RTGS Services
Outcome 7 th Task Force on Future RTGS Services 19 July 2017, from 09:30 until 17:00 held at the ECB, Sonnemannstraße 20, Frankfurt am Main, room C2.06 16 August 2017 1. Introduction The Chairperson will
More informationService Description: Video Collaboration Advise and Implement Subscription Service
Page 1 of 7 Service Description: Video Collaboration Advise and Implement Subscription Service This document describes the Video Collaboration Advise and Implement Subscription Service. Related Documents:
More informationTARGET Instant Payment Settlement
Ignacio Terol DG-MIP/MID TARGET Instant Payment Settlement Status update AMI-Pay, 6 February 2018 ECB-UNRESTRICTED TIPS status update overview TIPS is on track to start operations on 30 November 2018 Since
More informationLast Revised (06/12) ACH Direct Control Totals & File Collection
Last Revised (06/12) ACH Direct Control Totals & File Collection ACH Direct Control Totals & File Collection Contents Page Section 1: File Collection Alerts 2 Overview of Service 2 Notification Overview
More informationChapter 8: SDLC Reviews and Audit Learning objectives Introduction Role of IS Auditor in SDLC
Chapter 8: SDLC Reviews and Audit... 2 8.1 Learning objectives... 2 8.1 Introduction... 2 8.2 Role of IS Auditor in SDLC... 2 8.2.1 IS Auditor as Team member... 2 8.2.2 Mid-project reviews... 3 8.2.3 Post
More informationISO 20022, T2S and coexistence Advisory Group, Vienna, 1-2 June 2010
Item 5.2 09.04.01/2010/005309 ISO 20022, T2S and coexistence Advisory Group, Vienna, 1-2 June 2010 T2S Project Team European Central Bank 1 Agenda 1. Why ISO20022 for T2S? 2. Coexistence: myths and facts
More informationVMware vcloud Air Accelerator Service
DATASHEET AT A GLANCE The VMware vcloud Air Accelerator Service assists customers with extending their private VMware vsphere environment to a VMware vcloud Air public cloud. This Accelerator Service engagement
More informationT2S GRAPHICAL USER INTERFACE BUSINESS FUNCTIONALITY
TS GRAPHICAL USER INTERFACE Reference: 0.0.0/0/000 Author: ECB TS Programme Office Date: 0-0-0 Version:. Status: Draft Classification: TABLE OF CONTENTS TS GRAPHICAL USER INTERFACE INTRODUCTION.... Structure
More informationCloud Computing and Its Impact on Software Licensing
Cloud Computing and Its Impact on Software Licensing By Gretchen Kwashnik & Jim Cecil January 25, 2012 What is Cloud Computing? Cloud computing is a model for enabling: on-demand network access to a shared
More informationSELF ASSESSMENT OF SEPA COMPLIANCE November, 2013
SELF ASSESSMENT OF SEPA COMPLIANCE November, 2013 Bucharest, November 2013 This document constitutes the self-assessment of TRANSFOND`s system SENT against the Eurosystem s SEPA-compliance criteria. The
More informationT2S GRAPHICAL USER INTERFACE BUSINESS FUNCTIONALITY
TS GRAPHICAL USER INTERFACE BUSINESS FUNCTIONALITY Reference: 0.0.01/01/00 Author: ECB TS Programme Office Date: 01-0- Version: 1. Status: Draft Classification: Public TS Graphical User Interface TABLE
More informationNYDFS Cybersecurity Regulations: What do they mean? What is their impact?
June 13, 2017 NYDFS Cybersecurity Regulations: What do they mean? What is their impact? Gus Coldebella Principal, Boston Caroline Simons Principal, Boston Agenda 1) Overview of the new regulations 2) Assessing
More informationDigital Signatures Act 1
Issuer: Riigikogu Type: act In force from: 01.07.2014 In force until: 25.10.2016 Translation published: 08.07.2014 Digital Signatures Act 1 Amended by the following acts Passed 08.03.2000 RT I 2000, 26,
More informationRisk Management in Electronic Banking: Concepts and Best Practices
Risk Management in Electronic Banking: Concepts and Best Practices Jayaram Kondabagil BICENTENNIAL B1CBNTENNIAL John Wiley & Sons (Asia) Pte Ltd. Contents List of Figures xiii List of Tables xv Preface
More informationChecklist According to ISO IEC 17065:2012 for bodies certifying products, process and services
Name of Certifying Body Address of Certifying Body Case number Date of assessment With several locations Yes No Assessed locations: (Name)/Address: (Name)/Address: (Name)/Address: Assessed area (technical
More informationModule 7 TOGAF Content Metamodel
Module 7 TOGAF Content Metamodel V9 Edition Copyright January 2009 All Slide rights reserved 1 of 45 Published by The Open Group, January 2009 TOGAF Content Metamodel TOGAF is a trademark of The Open Group
More informationNew York Department of Financial Services Cybersecurity Regulation Compliance and Certification Deadlines
New York Department of Financial Services Cybersecurity Regulation Compliance and Certification Deadlines New York Department of Financial Services ( DFS ) Regulation 23 NYCRR 500 requires that entities
More informationRoma, 28 Ottobre 2014 Centro Congressi Banca d Italia. Training Session: Access Rights
Roma, 28 Ottobre 2014 Centro Congressi Banca d Italia Training Session: Access Rights Access Rights Access rights General concepts Users o Configuration of users Privileges Roles Secured objects Secured
More informationTechnology Competence Initiative
THE INSTITUTE OF CHARTERED ACCOUNTANTS OF NIGERIA (Established by Act of Parliament No. 15 of 1965) Technology Competence Initiative Initial Implementation of IFAC Education Guideline No 11 on Information
More informationImplementation Status & Results Indonesia Local Government and Decentralization Project (P111577)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Operation Name: Local Government
More informationCalifornia AB-2430 Davis Stirling Act Set-up Reference Guide
Setup Overview Product Maintenance o Manage Documents Edit Document Alias name to include specific regulation section code. Activate additional documents, as needed. o o o Manage Fees Validate fees Configure
More informationBase Standard Program ISO Anti-Bribery Management Systems CB Application for Accreditation
Base Standard Program ISO 37001 Anti-Bribery Management Systems CB Application for Accreditation FA 5021 Authority: Accreditation Manager Effective: 2017/01/20 Section 1: CB Name, Contact Information,
More informationRegulation and Innovation: The Experience of Regulating Kenya s M-Pesa
Regulation and Innovation: The Experience of Regulating Kenya s M-Pesa Njuguna Ndung u 2018 Annual Conference of the Cambridge Centre for Alternative Finance (CCAF): Reimagining Alternative Finance: Global
More informationVMware BCDR Accelerator Service
AT A GLANCE The rapidly deploys a business continuity and disaster recovery (BCDR) solution with a limited, pre-defined scope in a non-production environment. The goal of this service is to prove the solution
More informationPRIVACY STATEMENT. The Island with Bear Grylls (the Programme ) Introduction and main purposes
PRIVACY STATEMENT The Island with Bear Grylls (the Programme ) Introduction and main purposes Shine TV Limited ("Company" or "we, us, our") is the data controller in respect of your personal data and will
More information"Charting the Course... Certified Information Systems Auditor (CISA) Course Summary
Course Summary Description In this course, you will perform evaluations of organizational policies, procedures, and processes to ensure that an organization's information systems align with overall business
More informationBase Standard Program ISO Trustworthy Digital Repositories MS CB Application for Accreditation
Base Standard Program ISO 16363 Trustworthy Digital Repositories MS CB Application for Accreditation FA 5041 Authority: Accreditation Manager Effective: 2017/08/25 Section 1: CB Name, Contact Information,
More informationITSM20F_Umang. Number: ITSM20F Passing Score: 800 Time Limit: 120 min File Version: 4.0. Exin ITSM20F
ITSM20F_Umang Number: ITSM20F Passing Score: 800 Time Limit: 120 min File Version: 4.0 http://www.gratisexam.com/ Exin ITSM20F IT Service Management Foundation based on ISO/IEC 20000 (ITSM20F.EN) Version:
More informationOverview of Sales Representative Qualification Examinations, Etc.
12th ASF Tokyo Round Table Overview of Sales Representative Qualification Examinations, Etc. November 28, 2016 (15:15 to 16:15) Noriaki Nakamura Assistant Manager Sales Representative Examination & Registration
More informationTARGET instant payments settlement (TIPS) how? Massimiliano Renzetti Banca d Italia (4CB) Focus session, 7 July 2017, Frankfurt
TARGET instant payments settlement (TIPS) how? Massimiliano Renzetti Banca d Italia (4CB) Focus session, 7 July 2017, Frankfurt Table of content 1 2 3 Project challenges Proof of concept Architecture overview
More informatione-sens Nordic & Baltic Area Meeting Stockholm April 23rd 2013
e-sens Nordic & Baltic Area Meeting Stockholm April 23rd 2013 Objectives of the afternoon parallel tracks sessions 2 Meeting objectives High level: Identification of shared interests with emphasis on those
More informationCredit Card Data Compromise: Incident Response Plan
Credit Card Data Compromise: Incident Response Plan Purpose It is the objective of the university to maintain secure financial transactions. In order to comply with state law and contractual obligations,
More informationModule B1 An Introduction to TOGAF 9.1 for those familiar with TOGAF 8
Informs the capability Ensures Realization of Business Vision Business needs feed into method Refines Understanding Informs the Business of the current state Sets targets, KPIs, budgets for architecture
More informationOG The Open Group OG TOGAF 9 Combined Part 1 and Part 2
The Open Group OG0-093 TOGAF 9 Combined Part 1 and Part 2 1 Set1, Part 1 QUESTION: 1 Which of the following TOGAF components was created to enable architects to design architectures addressing Boundaryless
More informationAccreditation Process. Trusted Digital Identity Framework February 2018, version 1.0
Accreditation Process Trusted Digital Identity Framework February 2018, version 1.0 Digital Transformation Agency This work is copyright. Apart from any use as permitted under the Copyright Act 1968 and
More informationTARGET Instant Payment Settlement User Requirements
User s Status: FINAL Executive Summary Introduction The market consultation on the TARGET Instant Payment (TIPS) User s Document (URD) was initiated on 9 January 2017 and ran until 24 February 2017. Financial
More informationToward Horizon 2020: INSPIRE, PSI and other EU policies on data sharing and standardization
Toward Horizon 2020: INSPIRE, PSI and other EU policies on data sharing and standardization www.jrc.ec.europa.eu Serving society Stimulating innovation Supporting legislation The Mission of the Joint Research
More informationTARGET Instant Payment Settlement
TARGET Instant Payment Settlement Karen Birkel - ECB Lorenzo Giammò - Banca d Italia Focus session, 13 December 2017, Paris TARGET Instant Payment Settlement (TIPS) 1 2 3 Status of the project Connectivity
More informationBusiness Cases. Configuration and Assignment of a Market-Specific Attribute. 2 GUI Workshop Frankfurt January 24 th, 2011
Business Cases Configuration and Assignment of a Market-Specific Attribute 2 GUI Workshop Frankfurt January 24 th, 2011 Business case: a CSD assigns a Market-Specific Attribute to an existing participant.
More informationGeneral Information for Service Bureau
SWIFTNet Connectivity Service Bureau General Information for Service Bureau This document provides an overview of how to establish and use a SWIFT Service Bureau. 12 October 2006 Service Bureau Legal Notices
More informationPrivacy Policy I. COOKEVILLE COMMUNICATIONS PRIVACY POLICY II. GENERAL PRIVACY GUIDELINES
Privacy Policy I. COOKEVILLE COMMUNICATIONS PRIVACY POLICY Cookeville Communications Media is committed to maintaining robust privacy protections for its users. Our privacy policy is designed to help you
More information"Charting the Course... ITIL 2011 Service Offerings & Agreement (SOA) Certification Program. Course Summary
Course Summary Description ITIL is a set of best practices guidance that has become a worldwide-adopted framework for IT Service Management by many public and private organizations. Since early 1990, ITIL
More informationIT Audit Process Prof. Liang Yao Week Six IT Audit Planning
Week Six IT Audit Planning IT Audit Planning Process Institute of Internal Audit Standards - Section 2010: Planning The chief audit executive must establish a risk-based plan to determine the priorities
More informationOverview Bank IT examination perspective Background information Elements of a sound plan Customer notifications
Gramm-Leach Bliley Act Section 501(b) and Customer Notification Roger Pittman Director of Operations Risk Federal Reserve Bank of Atlanta Overview Bank IT examination perspective Background information
More informationAgenda. Bibliography
Humor 2 1 Agenda 3 Trusted Digital Repositories (TDR) definition Open Archival Information System (OAIS) its relevance to TDRs Requirements for a TDR Trustworthy Repositories Audit & Certification: Criteria
More informationMDG100 Master Data Governance
MDG100 Master Data Governance. COURSE OUTLINE Course Version: 15 Course Duration: 5 Day(s) SAP Copyrights and Trademarks 2016 SAP SE or an SAP affiliate company. All rights reserved. No part of this publication
More informationPaper 1 BUSINESS LAWS
Paper 1 BUSINESS LAWS UNIT I INDIAN CONTRACT ATC 1872 Offer, acceptance, Essentials of valid contract. Company Lawsformation of company, memorandum of association, articles of association, Prospectus,
More informationCore Elements of HIPAA The Privacy Rule establishes individuals privacy rights and addresses the use and disclosure of protected health information ( PHI ) by covered entities and business associates The
More informationISO20022 Messages types and flows in future RTGS services. 14 February 2017 Ad-hoc Workshop on messages for the Future RTGS Services
ISO00 Messages types and flows in future RTGS s February 07 Ad-hoc Workshop on messages for the Future RTGS Services messages and message flow in TARGET (I) Background information for the RTGS s (today
More informationEGNOS and ESSP Certification. ESESA Aviation Workshop 26 th - 27 th October 2010
EGNOS and ESSP Certification ESESA Aviation Workshop 26 th - 27 th October 2010 Content 1. Certification needs and framework 2. SES Certification regulations 3. Certification activities 4. Current Status
More informationNHS Fife. 2015/16 Audit Computer Service Review Follow Up
NHS Fife 2015/16 Audit Computer Service Review Follow Up Prepared for NHS Fife April 2016 Audit Scotland is a statutory body set up in April 2000 under the Public Finance and Accountability (Scotland)
More informationChapter 1. Purpose, definitions and application
Regulation on toll service provision for tolls and ferry tickets (the Toll service provider Regulation) Legal authority: Laid down by Royal Decree on dd.mm.yyyy pursuant to the Act of 21 June 1963 no.
More informationEXAM PREPARATION GUIDE
EXAM PREPARATION GUIDE PECB Certified ISO/IEC 38500 Lead IT Corporate Governance Manager The objective of the PECB Certified ISO/IEC 38500 Lead IT Corporate Governance Manager examination is to ensure
More informationTARGET Instant Payment Settlement Access Rights Management. TIPS Contact Group #8
TARGET Instant Payment Settlement Access Rights Management TIPS Contact Group #8 Frankfurt am Main, 04.07.2018 Access rights configuration in CRDM TIPS To ensure a smooth integration within the T2-T2S
More informationPrevention of Identity Theft in Student Financial Transactions AP 5800
Reference: Fair and Accurate Credit Transactions Act (Pub. L. 108-159) The Board recognizes that some activities of the Shasta-Tehama-Trinity Joint Community College District, "District," are subject to
More informationTIER Program Funding Memorandum of Understanding For UCLA School of
TIER Program Funding Memorandum of Understanding For UCLA School of This Memorandum of Understanding is made between the Office of Information Technology (OIT) and the School of ( Department ) with reference
More informationPTSPAS Product Assessment HAPAS Equivalent in accordance with MCHW SHW Volume 1 Clause and
1. Policy It is the policy of Pavement Testing Services Ltd (hereafter PTS) to operate its certification/ assessment services in a non-discriminatory manner. PTS shall not use procedures / processes to
More informationExperience gained in monitoring IP interconnection agreements since Samih Souissi Open internet Unit
Experience gained in monitoring IP interconnection agreements since 2012 Samih Souissi Open internet Unit February, 2 nd 2017 Agenda 1. Arcep s public statements on IP interconnection 2. Formal proceedings
More informationSYLLABUS. Departmental Syllabus CIST Departmental Syllabus. Departmental Syllabus. Departmental Syllabus. Departmental Syllabus
SYLLABUS DATE OF LAST REVIEW: 02/2013 CIP CODE: 11.0901 SEMESTER: COURSE TITLE: Operating System Security (Windows 2008 Server) COURSE NUMBER: CIST-0254 CREDIT HOURS: 4 INSTRUCTOR: OFFICE LOCATION: OFFICE
More informationPartner Premier Service Program
SERVICE DESCRIPTION Partner Premier Service Program Polycom s Partner Premier Service Program provides Service Partners with technical telephone support, advance parts replacement, software upgrades &
More informationDraft Summary Meeting of the Change Review Group
T2S PROGRAMME OFFICE 17 July 2015 V0.1 Contact person: Alejandro del Campo Roiz de la Parra Phone: +49 69 1344 7910 E-mail: T2S.CRG@ecb.int Draft Summary Meeting of the Change Review Group 9 July 2015,
More informationUSER CORPORATE RULES. These User Corporate Rules are available to Users at any time via a link accessible in the applicable Service Privacy Policy.
These User Corporate Rules are available to Users at any time via a link accessible in the applicable Service Privacy Policy. I. OBJECTIVE ebay s goal is to apply uniform, adequate and global data protection
More informationCABINET PLANNING SYSTEM PROCUREMENT
Report No: 163/2017 PUBLIC REPORT CABINET 19 September 2017 PLANNING SYSTEM PROCUREMENT Report of the Director for Places (Development & Economy) Strategic Aim: Sustainable Growth Key Decision: Yes Exempt
More informationMinimum Requirements For The Operation of Management System Certification Bodies
ETHIOPIAN NATIONAL ACCREDITATION OFFICE Minimum Requirements For The Operation of Management System Certification Bodies April 2011 Page 1 of 11 No. Content Page 1. Introduction 2 2. Scope 2 3. Definitions
More informationDirective on security of network and information systems (NIS): State of Play
Directive on security of network and information systems (NIS): State of Play Svetlana Schuster Unit H1 Cybersecurity and Digital Privacy DG Communications Networks, Content and Technology, European Commission
More informationHow to choose a website design firm
How to choose a website design firm 22 questions to ask before engaging in an important partnership Website development projects can be fraught with risk. Organizations often wonder: How can we be sure
More information