ERP/CRM System Implementation Methodology

Size: px
Start display at page:

Download "ERP/CRM System Implementation Methodology"

Transcription

1 ERP/CRM System Implementation Methodology Prepared by Admiral Consulting Group Date Submitted May 27, 2016

2 TABLE OF CONTENTS Implementation Methodology Analysis (Solution Envisioning) Phase Form an ERP/CRM Steering Committee Detail Business Requirements Workshop AS-IS Conduct Solution Overview Workshop Conduct Fit Gap Analysis Solution Design Phase Conduct Core Team Training Create Functional Design Document (FDD) Configure and Setup Standard and ISV Solutions Solution Development Phase Conduct Proof of Concept (POC) Workshop Production Deployment Phase Conduct End-User Training Final Data Migration to PROD Go-Live Operation Phase... 8 Page 2 of 8

3 IMPLEMENTATION METHODOLOGY Admiral Consulting Group adheres to a standard implementation and project Management methodology, generally recognized as Good practice in the industry such as those outlined by Project Management Institute (PMI) and Microsoft Sure Steps, to help facilitate the successful delivery of the objectives and deliverables described herein. We define success as the ability to deliver our solutions reasonably on time and on budget. The following explains our implementation processes and phases, the services we render, which forms the basis for our estimates of the professional services fees. Analysis Form a Committee Detail Process Review Solution Overview Solution Selection Fit/Gap Analysis Purchase Software Sign Agrrement Project Kick-Off Project Plan Design Install Software Core Team Training Detail Design Update Project Plan Update FDD Development Deployment Operation System Configuration ISV Integration Customization POC Testing Data Migration Plan Update Project Plan Update FDD End User Training Data Migration Go-Live Post Go-Live Support Update Project Plan Lesson Learned Update FDD Project Closure 1.1. ANALYSIS (SOLUTION ENVISIONING) PHASE The primary objective of Analysis (Solution Envisioning) phase is to help determine the right solution to meet business needs. This includes forming the implementation committee, diagnosis of business requirements, and solution components using any number of available Decision Accelerator services such as detail Business Process & Requirements Review, Fit Gap and Solution Blueprint, and Proof of Concept FORM AN ERP/CRM STEERING COMMITTEE Page 3 of 8

4 Implementing an enterprise resource planning (ERP) solution requires a lot of people to be involved at various points of the project. These stakeholders also need effective leadership to guide the process so that it doesn't fall apart at critical junctures. The employees and management who have the most impact in the company can and will influence the overall result positively or negatively. The scope of ERP can be vast, especially when used in a fast pace environment with multiple locations. The primary role of this committee is to outline the goal and objectives and act as a liaison between the upper management and other team members. In addition to taking full responsibility for and setting the framework of the project, the steering committees also serves as the voice of reason for the entire implementation process, which naturally leads to a smoother and more efficient transition DETAIL BUSINESS REQUIREMENTS WORKSHOP AS-IS Gathering and documenting the functional area s detail business requirements is a critical step in implementing any system. This involves a series of detail workshop sessions conducted with the functional area and subject matter experts, resulting in their requirements being documented in the Functional Requirements Document (FRD). The FRD in turn becomes an input to the Ft Gap Analysis activity. While the FRD captures the what s that need to be accomplished, the Fit Gap Spreadsheet captures how the requirements are met. Deliverable: Functional Requirement Document with detail workflow diagrams CONDUCT SOLUTION OVE RVIEW WORKSHOP The goal of this exercise is to educate the Core Implementation team and ERP/CRM Steering Committee about the functionality of alternative systems. From an Organizational Change Management perspective, a demonstration of standard functionality and standard-solution flows is especially important because this is the first step toward creating awareness and acceptance among the users for the new solution (system). In particular, it provides an opportunity to demonstrate that it is possible to execute existing processes in a slightly different sequence or manner, yet still achieve the same or more optimal results. Deliverable: Steering Committee is to select an ERP/CRM System and recommend the procurement of such system CONDUCT FIT GAP ANALYSIS The detailed Fit-Gap workshop serves to identify gaps between the preferred ERP/CRM System functionality compared to the business requirements. Page 4 of 8

5 The Business processes that can be implemented using the native functionality of ERP/CRM System will thereby be confirmed as a Fit. Conversely, for those business processes that cannot be fully implemented using the native functionality of ERP/CRM System will be outlined as Gap. The corresponding Gap must be documented in a spreadsheet and serve as the basis for the steering committee to find resolutions, propose alternative workarounds, or suggest recommended business process updates. The final decision on which approach to adopt is based on comparing the cost versus the benefit of altering a process or solution as well as the priority of the Gap in the overall ERP implementation project. Deliverable: Fit-Gap Analysis Spreadsheet SOLUTION DESIGN PHASE The goal of the Design phase is to define how the business requirements will be implemented. The phase includes configuration of the overall ERP/CRM System and the design of specific customizations needed to satisfy business requirements (including gaps) identified during the Analysis phase. The customizations can range from simple user interface or report modifications to moderate-to-complex functionality additions or modifications. Customizations may also include the integrations and interfaces and data migration elements required to support the requirements CONDUCT CORE TEAM TRAINING In this part of the Design phase, we will provide an overview training to the ERP/CRM Committee focusing on the capability and functionality of the ERP/CRM System as well as any applicable ISV solutions (if needed) that make up the final solution. A review of the Business Requirements and Gap/Fit Analysis should occur to ensure that the correct modules are covered. This training will cover both functional and technical requirements and will therefore bring together both the key users and the IT Users of the project. It is envisioned that the users would attend all sessions to provide a complete understanding of the ERP/CRM System functionality. Deliverable: Training Material CREATE FUNCTIONAL DE SIGN DOCUMENT (FDD) In this Activity, our Application Consultants will work hand in hand with the ERP/CRM Committee to begin the documentation of configuration and parameter settings required in order for the standard functionality and ISV solution(s) to fully meet the business requirements. This is documented in the Functional Design Document (FDD), which captures all configuration settings. This will provide the ERP/CRM Committee a reinforcement on the training received. The ERP/CRM Committee will provide the business scenario to properly test the selected design and configuration. Page 5 of 8

6 Deliverable: Functional Design Document (FDD) CONFIGURE AND SETUP STANDARD AND ISV SOLUTIONS Our Application Consultants and the ERP/CRM Committee will typically begin to configure the application on the Development environment. This will allow for the initial baseline of the configurations to be established and facilitate any initial development effort. To test each configuration, the Application Consultants will guide the ERP/CRM Committee members through the process which will confirm the configuration meets the business requirement. No formal test scripts are required for this activity; however, it is essential the ERP/CRM Committee actively participate as it enhances the knowledge transfer gained from Core Team Training. As these settings are accepted by the Key Users, they are documented in the Functional Design Document. Knowledge gained from this activity also allows the Key Users to begin the identification and creation of process test scenarios and test scripts. Deliverable: Updated Functional Design Document (FDD), including preliminary development effort to support integration and interface, data migration, and custom code development SOLUTION DEVELOPMENT PHASE In the Solution Development phase, your complete solution will be built and configured. Key activities and deliverables include: Determine Security Roles to define which roles have different types of access to specific functionality Complete System Configuration and ISV Solution Setup to determine detailed settings for all system configuration screens Finalize Customization Code--to complete any customizations you need to meet unique requirements Conduct Acceptance Testing to ensure your new solution meets your functionality requirements Begin Developing Data Migration Scripts to plan detailed process and timing of data migration to your new solution CONDUCT PROOF OF CON CEPT (POC) WORKSHOP The objective of the proof of concept workshop is to build and test the system components defined and approved in the design specifications, including developing the customizations, integrations and interfaces, and data migration processes. The major deliverables include the complete system configuration, completion and freezing of code for customizations, integrations and interfaces, and data migration. Other key deliverables include finalization of the Functional Design Document (FDD), and the completion of Data Acceptance, Process and Integration Testing. Page 6 of 8

7 1.4. PRODUCTION DEPLOYMENT PHASE The Production Deployment phase is where all the efforts of the project team come together for a successful transition to the new ERP/CRM solution. Key activities in this phase include end-user training, final data migration, production environment readiness, and the actual cut-over to the new production environment. The infrastructure and technical teams prepare the production environment for the cutover tasks that lead to the go-live state. Required configurations and tweaks may be made, and performance tuning maybe performed if necessary. Another parallel activity that is performed upon completion of POC is the initial data load into the production environment by the data migration team. At this stage, we consider the system is ready for you to go-live and any subsequent environment changes are placed under the change control process CONDUCT END-USER TRAINING Adequate training is one of the most important steps in any successful implementation. It has been determined that the most appropriate view of training is to deliver short, directed sessions that begin with a broad overview and narrow successively to the End Users defined job tasks. A critical success factor is that the final task-oriented training takes place as close to Go-Live as possible to prevent knowledge erosion. This training may optionally be conducted by the ERP/CRM Committee members or our Application Consultants. This training can be formal, informal, onsite, or remote. If formal training is necessary, it is recommended to schedule the training sessions in advance with the End Users. Training logistics, which may include a conference room, projector, training materials, and computers, should be arranged FINAL DATA MIGRATION TO PROD Migration of data from the source or legacy systems is the final critical phase of the project and it is as equally important as user adoption. Data migrated into Production has to be timed accurately so as to ensure that users see the most recent data when the system is available to them. The effort is usually split into two phases: Phase 1 Initial migration: The initial migration of data into production is performed to avoid overloading the systems over the go-live weekend and is typically done a couple weeks before the actual go-live date. This data typically includes static data. Page 7 of 8

8 Phase II Final migration: The final data migration is done over the weekend prior to go-live. Since most of the initial data is loaded earlier than go-live, the final data load will take into account the data entered into the system after the initial data load. This concept expedites the migration process and eliminates last-minute glitches that can jeopardize the cutover. It is also mandatory to lock the system from end users while the final data migration tasks are being performed GO-LIVE Go-Live is the culmination of planning, design, testing, and execution activities for the implementation to the new ERP/CRM solution. Support activities have long been confirmed, allowing for the project team members to provide support for the end users. The support protocols and channels, including Help Desk functions, have been communicated, and the end users can utilize the proper support resources that help ensure timely and accurate resolution of issues OPERATION PHASE The Operation phase defines the activities that are required to close the project, provide post production support, and transition the solution and knowledge to the you. Key objectives of this phase include providing post go-live support, transitioning the solution to support, performing a final quality audit, and providing project closure. After go-live, it is important to ensure we delivered what was agreed upon at the beginning and to confirm your satisfaction with the end result. It is important to officially close the project and obtain formal sign-off on all deliverables. Page 8 of 8

VMware vcloud Air Accelerator Service

VMware vcloud Air Accelerator Service DATASHEET AT A GLANCE The VMware vcloud Air Accelerator Service assists customers with extending their private VMware vsphere environment to a VMware vcloud Air public cloud. This Accelerator Service engagement

More information

Service Description: CNS Federal High Touch Technical Support

Service Description: CNS Federal High Touch Technical Support Page 1 of 1 Service Description: CNS Federal High Touch Technical Support This service description ( Service Description ) describes Cisco s Federal High Touch Technical support (CNS-HTTS), a tier 2 in

More information

HPE Network Transformation Experience Workshop Service

HPE Network Transformation Experience Workshop Service Data sheet HPE Network Transformation Experience Workshop Service HPE Network and Mobility Consulting Led by experienced HPE technology consultants, HPE Network Transformation Experience Workshop Service

More information

Chapter 8: SDLC Reviews and Audit Learning objectives Introduction Role of IS Auditor in SDLC

Chapter 8: SDLC Reviews and Audit Learning objectives Introduction Role of IS Auditor in SDLC Chapter 8: SDLC Reviews and Audit... 2 8.1 Learning objectives... 2 8.1 Introduction... 2 8.2 Role of IS Auditor in SDLC... 2 8.2.1 IS Auditor as Team member... 2 8.2.2 Mid-project reviews... 3 8.2.3 Post

More information

VMware BCDR Accelerator Service

VMware BCDR Accelerator Service AT A GLANCE The rapidly deploys a business continuity and disaster recovery (BCDR) solution with a limited, pre-defined scope in a non-production environment. The goal of this service is to prove the solution

More information

Business Architecture Implementation Workshop

Business Architecture Implementation Workshop Delivering a Business Architecture Transformation Project using the Business Architecture Guild BIZBOK Hands-on Workshop In this turbulent and competitive global economy, and the rapid pace of change in

More information

Project Management Professional (PMP) Exam Preparation elearning Course

Project Management Professional (PMP) Exam Preparation elearning Course Project Management Professional (PMP) Exam Preparation elearning Course Course Code: PMC001CL Duration: 4 Days, 35 Hours Format: elearning Certification Exam: PMI s PMP Exam Certification Track: N/A Course

More information

Service Description: Advanced Services- Fixed Price: Cisco UCCE Branch Advise and Implement Services (ASF-CX-G-REBPB-CE)

Service Description: Advanced Services- Fixed Price: Cisco UCCE Branch Advise and Implement Services (ASF-CX-G-REBPB-CE) Page 1 of 1 Service Description: Advanced Services- Fixed Price: Cisco UCCE Branch Advise and Implement Services (ASF-CX-G-REBPB-CE) This document describes Advanced Services Fixed Price: Cisco UCCE Branch

More information

HPE Data Center Operations Consulting Service

HPE Data Center Operations Consulting Service Data sheet HPE Data Center Operations Consulting Service HPE Packaged Consulting Services Data centers are large-scale capital investments that may not meet their capacity, availability, and operational

More information

A guide for assembling your Jira Data Center team

A guide for assembling your Jira Data Center team A guide for assembling your Jira Data Center team Contents 01 Getting started 02 Helpful roles for your Jira Data Center team 03 Helpful expertise for your Jira Data Center team 04 Pro tips & best practices

More information

ORACLE SERVICES FOR APPLICATION MIGRATIONS TO ORACLE HARDWARE INFRASTRUCTURES

ORACLE SERVICES FOR APPLICATION MIGRATIONS TO ORACLE HARDWARE INFRASTRUCTURES ORACLE SERVICES FOR APPLICATION MIGRATIONS TO ORACLE HARDWARE INFRASTRUCTURES SERVICE, SUPPORT AND EXPERT GUIDANCE FOR THE MIGRATION AND IMPLEMENTATION OF YOUR ORACLE APPLICATIONS ON ORACLE INFRASTRUCTURE

More information

Professional (CBAP) version 3

Professional (CBAP) version 3 Certified Business Analysis Professional (CBAP) version 3 Amman Jordan July 29 th August 5 th, 2017 Instructor Mr. Tareq Al Nashawati Certified CBAP, PMP Table of Content 1 PROGRAM VALUE... 3 2 TARGET

More information

General Instructions

General Instructions Project Management Professional (PMP) General Instructions Introduction: Being a project manager in the organization is an ideal post that employees dream of. Don t let your dreams vanish in the air; stop

More information

Manager, Infrastructure Services. Position Number Community Division/Region Yellowknife Technology Service Centre

Manager, Infrastructure Services. Position Number Community Division/Region Yellowknife Technology Service Centre IDENTIFICATION Department Position Title Infrastructure Manager, Infrastructure Services Position Number Community Division/Region 32-11488 Yellowknife Technology Service Centre PURPOSE OF THE POSITION

More information

IT Governance ISO/IEC 27001:2013 ISMS Implementation. Service description. Protect Comply Thrive

IT Governance ISO/IEC 27001:2013 ISMS Implementation. Service description. Protect Comply Thrive IT Governance ISO/IEC 27001:2013 ISMS Implementation Service description Protect Comply Thrive 100% guaranteed ISO 27001 certification with the global experts With the IT Governance ISO 27001 Implementation

More information

ITEM 6D TO: FROM: SUBJECT: DATE: background groups. STRATEGY. transition to HIGHLIGHTS. Process for New Program.

ITEM 6D TO: FROM: SUBJECT: DATE: background groups. STRATEGY. transition to HIGHLIGHTS. Process for New Program. ITEM 6D TO: FROM: SUBJECT: DATE: APWA Board of Directors Becky Stein, Director of Education and Credentialing Education and Credentialing: DCS Reboot Plan Update January 31, 2017 BACKGROUND During the

More information

Data Virtualization Implementation Methodology and Best Practices

Data Virtualization Implementation Methodology and Best Practices White Paper Data Virtualization Implementation Methodology and Best Practices INTRODUCTION Cisco s proven Data Virtualization Implementation Methodology and Best Practices is compiled from our successful

More information

HPE Data Replication Solution Service for HPE Business Copy for P9000 XP Disk Array Family

HPE Data Replication Solution Service for HPE Business Copy for P9000 XP Disk Array Family Data sheet HPE Data Replication Solution Service for HPE Business Copy for P9000 XP Disk Array Family HPE Lifecycle Event Services HPE Data Replication Solution Service provides implementation of the HPE

More information

HPE File Data Migration Service

HPE File Data Migration Service Data sheet HPE File Data Migration Service HPE Consulting and Integration Services File migration simplified Available in convenient packaged offerings, HPE File Data Migration Service is designed to help

More information

Service Description: Software Support

Service Description: Software Support Page 1 of 1 Service Description: Software Support This document describes the service offers under Cisco Software Support. This includes Software Support Service (SWSS), Software Support Basic, Software

More information

Accelerate Your Enterprise Private Cloud Initiative

Accelerate Your Enterprise Private Cloud Initiative Cisco Cloud Comprehensive, enterprise cloud enablement services help you realize a secure, agile, and highly automated infrastructure-as-a-service (IaaS) environment for cost-effective, rapid IT service

More information

Tools & Techniques I: New Internal Auditor

Tools & Techniques I: New Internal Auditor About This Course Tools & Techniques I: New Internal Auditor Course Description Learn the basics of auditing at the new internal auditor level. This course provides an overview of the life cycle of an

More information

HANDLING CHALLENGING PROJECT SITUATION

HANDLING CHALLENGING PROJECT SITUATION PMI-PMP CERTIFICATION (You Initiate, We Close) HANDLING CHALLENGING PROJECT SITUATION Lets start with a project definition It's a temporary endeavor undertaken to create a unique product, service or result.

More information

Solutions Technology, Inc. (STI) Corporate Capability Brief

Solutions Technology, Inc. (STI) Corporate Capability Brief Solutions Technology, Inc. (STI) Corporate Capability Brief STI CORPORATE OVERVIEW Located in the metropolitan area of Washington, District of Columbia (D.C.), Solutions Technology Inc. (STI), women owned

More information

gistec Service Delivery Program (SDP)

gistec Service Delivery Program (SDP) gistec Service Delivery Program (SDP) Specifications & Terms and Conditions V4.0 Dated 18 March 2018 gistec Service Delivery Program (SDP) provides a flexible and cost-effective vehicle to engage gistec

More information

Cisco Data Center Accelerated Deployment Service for Nexus 9000 (ASF-DCV1-NEX-ADS)

Cisco Data Center Accelerated Deployment Service for Nexus 9000 (ASF-DCV1-NEX-ADS) Page 1 of 6 Service Description: Advanced Services Fixed Price Cisco Data Center Accelerated Deployment Service for Nexus 9000 (ASF-DCV1-NEX-ADS) This document describes Advanced Services Fixed Price:

More information

HPE 3PAR StoreServ Data Migration Service

HPE 3PAR StoreServ Data Migration Service Data sheet HPE 3PAR StoreServ Data Migration Service HPE Consulting and Integration Services Data migration simplified Available in convenient packaged offerings, HP Enterprise 3PAR StoreServ Data Migration

More information

Security In A Box. Modular Security Services Offering - BFSI. A new concept to Security Services Delivery.

Security In A Box. Modular Security Services Offering - BFSI. A new concept to Security Services Delivery. Modular Security Services Offering - BFSI Security In A Box A new concept to Security Services Delivery. 2017 Skillmine Technology Consulting Pvt. Ltd. The information in this document is the property

More information

Service Description: Software Support

Service Description: Software Support Page 1 of 6 Service Description: Software Support This document describes the service offers under Cisco Software Support. This includes Software Support Service (SWSS), Software Support Basic, Software

More information

PUTTING THE CUSTOMER FIRST: USER CENTERED DESIGN

PUTTING THE CUSTOMER FIRST: USER CENTERED DESIGN PUTTING THE CUSTOMER FIRST: USER CENTERED DESIGN icidigital.com 1 Case Study DEFINE icidigital was chosen as a trusted creative partner to design a forward-thinking suite of sites for AICPA, one of the

More information

IT SECURITY OFFICER. Department: Information Technology. Pay Range: Professional 18

IT SECURITY OFFICER. Department: Information Technology. Pay Range: Professional 18 Pierce County Classification Description IT SECURITY OFFICER Department: Information Technology Job Class #: 634900 Pay Range: Professional 18 FLSA: Exempt Represented: No Classification descriptions are

More information

IASA CONTINUING EDUCATION UNITS

IASA CONTINUING EDUCATION UNITS IASA CONTINUING EDUCATION UNITS This manual serves to outline the requirements, reporting structure, and options for earning your continuing education units. CONTENTS Overview... 2 Requirements... 2 Reporting...

More information

ANZSCO Descriptions The following list contains example descriptions of ICT units and employment duties for each nominated occupation ANZSCO code. And

ANZSCO Descriptions The following list contains example descriptions of ICT units and employment duties for each nominated occupation ANZSCO code. And ANZSCO Descriptions The following list contains example descriptions of ICT units and employment duties for each nominated occupation ANZSCO code. Content 261311 - Analyst Programmer... 2 135111 - Chief

More information

On-site Time and Material Rates for Equipment Not Covered under an HP Service Contract

On-site Time and Material Rates for Equipment Not Covered under an HP Service Contract HPE Per Event U.S. On-Site Services Rate Schedule On-site Time and Material Rates for Equipment Not Covered under an HP Service Contract Equipment Type Enterprise Servers, Associated Storage, Network,

More information

EUROPEAN ICT PROFESSIONAL ROLE PROFILES VERSION 2 CWA 16458:2018 LOGFILE

EUROPEAN ICT PROFESSIONAL ROLE PROFILES VERSION 2 CWA 16458:2018 LOGFILE EUROPEAN ICT PROFESSIONAL ROLE PROFILES VERSION 2 CWA 16458:2018 LOGFILE Overview all ICT Profile changes in title, summary, mission and from version 1 to version 2 Versions Version 1 Version 2 Role Profile

More information

Foundation. Become a ITIL Foundation Certified Professional from our exclusive 2 full day. conducted by authorized faculties from APMG.

Foundation. Become a ITIL Foundation Certified Professional from our exclusive 2 full day. conducted by authorized faculties from APMG. Certified ITIL Foundation Become a ITIL Foundation Certified Professional from our exclusive 2 full day training Certified program conducted by authorized faculties from APMG. Exclusive Classroom Training

More information

Cisco Director Class SAN Planning and Design Service

Cisco Director Class SAN Planning and Design Service Cisco Director Class SAN Planning and Design Service Rapidly Plan and Deploy a Cisco Director Class MDS Solution for More Efficient Storage Networking Service Overview Cisco s intelligent storage networking

More information

NORTH CAROLINA NC MRITE. Nominating Category: Enterprise IT Management Initiatives

NORTH CAROLINA NC MRITE. Nominating Category: Enterprise IT Management Initiatives NORTH CAROLINA MANAGING RISK IN THE INFORMATION TECHNOLOGY ENTERPRISE NC MRITE Nominating Category: Nominator: Ann V. Garrett Chief Security and Risk Officer State of North Carolina Office of Information

More information

How Cisco Expedites IT Integration of an Acquisition

How Cisco Expedites IT Integration of an Acquisition How Cisco Expedites IT Integration of an Acquisition Streamlined, cross-functional processes accelerate how new employees work productively and minimize the transition impact on customers Cisco IT Case

More information

SERVICE TRANSITION ITIL INTERMEDIATE TRAINING & CERTIFICATION

SERVICE TRANSITION ITIL INTERMEDIATE TRAINING & CERTIFICATION SERVICE TRANSITION ITIL INTERMEDIATE TRAINING & CERTIFICATION WHAT IS ITIL ST? The intermediate level of ITIL offers a role based hands-on experience and in-depth coverage of the contents. Successful implementation

More information

Service Description: Advanced Services Fixed Price Cisco WebEx Advise and Implement Service (0-5,000 Users) (ASF- WBXS-UC-PDIBSE)

Service Description: Advanced Services Fixed Price Cisco WebEx Advise and Implement Service (0-5,000 Users) (ASF- WBXS-UC-PDIBSE) Page 1 of 9 Service Description: Advanced Services Fixed Price Cisco WebEx Advise and Implement Service (0-5,000 Users) (ASF- WBXS-UC-PDIBSE) This document describes Advanced Services Fixed Price Cisco

More information

How can you purchase the Appway Academy services?

How can you purchase the Appway Academy services? Education Catalogue How can you purchase the Appway Academy services? Education Catalogue Buy individual training, certifications attempt or coaching sessions. Academy Credits Packages Optimize your Education

More information

Magento Enterprise Edition Customer Support Guide

Magento Enterprise Edition Customer Support Guide Magento Enterprise Edition Customer Support Guide April 2017 magento.com/support 2017 Magento, Inc. All rights reserved. Thank You for using Magento Enterprise Edition Customer support is a vital part

More information

Metadata Framework for Resource Discovery

Metadata Framework for Resource Discovery Submitted by: Metadata Strategy Catalytic Initiative 2006-05-01 Page 1 Section 1 Metadata Framework for Resource Discovery Overview We must find new ways to organize and describe our extraordinary information

More information

Use of Mobile Devices on Voice and Data Networks Policy

Use of Mobile Devices on Voice and Data Networks Policy World Agroforestry Centre Policy Series MG/C/4/2012 Use of Mobile Devices on Voice and Data Networks Policy One of the policies on information security and business continuity which will be audited by

More information

ISO/IEC overview

ISO/IEC overview ISO/IEC 20000 overview Overview 1. What is ISO/IEC 20000? 2. ISO/IEC 20000 and ITIL 2 BS 15000 BS15000 started in UK and first launched on July 1, 2003. Which was replaced by ISO/IEC 20000 after formal

More information

Dell helps you simplify IT

Dell helps you simplify IT Dell helps you simplify IT Workshops the first step. Reduce desktop and data center complexity. Improve productivity. Innovate. Dell IT Consulting Services New Edition 2011 Introduction Are you spending

More information

What is the Joint Application Development (JAD) Process?

What is the Joint Application Development (JAD) Process? What is the Joint Application Development (JAD) Process? By Joy Matthews, Vice President, Pierson Requirements Group, Inc. jmatthews@piersonrequirementsgroup.com JAD is an Important Technique for Software

More information

Symantec Data Center Migration Service

Symantec Data Center Migration Service Avoid unplanned downtime to critical business applications while controlling your costs and schedule The Symantec Data Center Migration Service helps you manage the risks and complexity of a migration

More information

PM029: Project Management Professional (Preparation)

PM029: Project Management Professional (Preparation) PM029: Project Management Professional (Preparation) PM029 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: The overall aim of this course is to prepare participants for the Project Management

More information

SEGUE DISCOVERY PARTICIPATION IN DISCOVERY DISCOVERY DELIVERABLES. Discovery

SEGUE DISCOVERY PARTICIPATION IN DISCOVERY DISCOVERY DELIVERABLES.   Discovery SEGUE DISCOVERY An initial engagement with Segue begins with a Phase where our experienced team works directly with our customer to define the vision, scope, and high-level requirements for the project.

More information

Request for Quotations

Request for Quotations AFRICAN UNION UNION AFRICAINE UNIÃO AFRICANA P. O. Box 3243, Addis Ababa, ETHIOPIA Tel.: (251-11) 5517700 Fax: (251-11) 5517844 www.au.int Request for Quotations Consultancy for Provision of Training Service

More information

PMP Exam Preparation Workshop Setting expectations for the PMP Review

PMP Exam Preparation Workshop Setting expectations for the PMP Review PMP Exam Preparation Workshop Setting expectations for the PMP Review Copyright 2016 PMI SOC 1 Contact Information Bobby Kapoor, PMP PMP Prep Session Coordinator Email: bobby_kapoor@hotmail.com Paolo Treves,

More information

INFORMATION TECHNOLOGY NETWORK ADMINISTRATOR ANALYST Series Specification Information Technology Network Administrator Analyst II

INFORMATION TECHNOLOGY NETWORK ADMINISTRATOR ANALYST Series Specification Information Technology Network Administrator Analyst II Adopted: July 2000 Revised : April 2004; August 2009; June 2014; February 2018 INFORMATION TECHNOLOGY NETWORK ADMINISTRATOR ANALYST Series Specification Information Technology Network Administrator Analyst

More information

MIS Systems & Infrastructure Lifecycle Management 1. Week 12 April 7, 2016

MIS Systems & Infrastructure Lifecycle Management 1. Week 12 April 7, 2016 MIS 5203 Lifecycle Management 1 Week 12 April 7, 2016 Study Objectives Systems Implementation Data Migration Change Over 2 Phase 1 Feasibility Phase 2 Requirements Which ones of these activities are part

More information

for TOGAF Practitioners Hands-on training to deliver an Architecture Project using the TOGAF Architecture Development Method

for TOGAF Practitioners Hands-on training to deliver an Architecture Project using the TOGAF Architecture Development Method Course Syllabus for 3 days Expert led Enterprise Architect hands-on training "An Architect, in the subtlest application of the word, describes one able to engage and arrange all elements of an environment

More information

Project Management Professional (PMP) Exam Prep Boot Camp - Brochure

Project Management Professional (PMP) Exam Prep Boot Camp - Brochure Project Management Professional (PMP) Exam Prep Boot Camp - Brochure Accelerate your Project Management Career with a Globally-recognized Credential Course Name : PMP Version : INVL_PMP_BR_02_019_1.2 Course

More information

Government Resolution No of February 15, Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security

Government Resolution No of February 15, Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security Government Resolution No. 2443 of February 15, 2015 33 rd Government of Israel Benjamin Netanyahu Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security It is hereby resolved:

More information

CAPM & PMP Exam Preparation Boot Camp

CAPM & PMP Exam Preparation Boot Camp CAPM & PMP Exam Preparation Boot Camp About This Course In this course, you will gain the essential knowledge and preparation needed to pass either the Certified Associate in Project Management (CAPM)

More information

IT Audit Process Prof. Liang Yao Week Six IT Audit Planning

IT Audit Process Prof. Liang Yao Week Six IT Audit Planning Week Six IT Audit Planning IT Audit Planning Process Institute of Internal Audit Standards - Section 2010: Planning The chief audit executive must establish a risk-based plan to determine the priorities

More information

COURSE BROCHURE. ITIL - Intermediate Service Transition. Training & Certification

COURSE BROCHURE. ITIL - Intermediate Service Transition. Training & Certification COURSE BROCHURE ITIL - Intermediate Service Transition. Training & Certification What is ITIL ST? The intermediate level of ITIL offers a role based hands-on experience and in-depth coverage of the contents.

More information

ITIL Service Transition Lifecycle

ITIL Service Transition Lifecycle ITIL Service Transition Lifecycle Certificate: ITIL Service Transition Lifecycle Duration: 3 days Course Delivery: Classroom, Virtual Classroom, Exam, ebook Course ID: ITL9337 Language: English Credits:

More information

Copyright protected. Use is for Single Users only via a VHP Approved License. For information and printed versions please see

Copyright protected. Use is for Single Users only via a VHP Approved License. For information and printed versions please see TOGAF 9 Certified Study Guide 4th Edition The Open Group Publications available from Van Haren Publishing The TOGAF Series: The TOGAF Standard, Version 9.2 The TOGAF Standard Version 9.2 A Pocket Guide

More information

Quality Assurance and IT Risk Management

Quality Assurance and IT Risk Management Quality Assurance and IT Risk Deutsche Bank s QA and Testing Transformation Journey Michael Venditti Head of Enterprise Testing Services, Deutsche Bank IT RISK - REGULATORY GOVERNANCE Major shifts in the

More information

WHO SHOULD ATTEND COURSE OUTLINE. Course Outline :: PROJECT MANAGEMENT PROFESSIONAL (PMP) EXAMINATION PREPARATORY COURSE::

WHO SHOULD ATTEND COURSE OUTLINE. Course Outline :: PROJECT MANAGEMENT PROFESSIONAL (PMP) EXAMINATION PREPARATORY COURSE:: Module Title Duration : PROJECT MANAGEMENT PROFESSIONAL (PMP) EXAMINATION PREPARATORY COURSE : 5 days INTRODUCTION The Project Management Professional (PMP ) is an acclaimed professional certification

More information

Step: 9 Conduct Data Standardization

Step: 9 Conduct Data Standardization Step: 9 Conduct Data Standardization Version 1.0, February 2005 1 Step Description/Objectives: Step 9, Conduct Data Standardization, is intended to reduce the life cycle cost of data through data integration,

More information

Service Description of Advanced Services: Focused Technical Support and Network Optimization Support

Service Description of Advanced Services: Focused Technical Support and Network Optimization Support Back to Table of Contents Service Description of Advanced Services: Focused Technical Support and Network Optimization Support This document describes Focused Technical Support (FTS) and Network Optimization

More information

CA Services Partner. Implementation Enablement. Eugene Banks FY18

CA Services Partner. Implementation Enablement. Eugene Banks FY18 CA Services Partner Implementation Enablement Eugene Banks FY18 Without partners, CA Services and Education would be unable to scale to meet the growing demands of the business. If our strategy is effective,

More information

FIVE BEST PRACTICES FOR ENSURING A SUCCESSFUL SQL SERVER MIGRATION

FIVE BEST PRACTICES FOR ENSURING A SUCCESSFUL SQL SERVER MIGRATION FIVE BEST PRACTICES FOR ENSURING A SUCCESSFUL SQL SERVER MIGRATION The process of planning and executing SQL Server migrations can be complex and risk-prone. This is a case where the right approach and

More information

PROJECT MANAGEMENT PROFESSIONAL (PMP)

PROJECT MANAGEMENT PROFESSIONAL (PMP) PROJECT MANAGEMENT PROFESSIONAL (PMP) EXAM PREPARATION TRAINING WHAT IS PMP? Government, commercial and other organizations employ PMP certified project managers in an attempt to improve the success rate

More information

Commercial Catalog & Pricelist. Effective Date: January 1, 2019

Commercial Catalog & Pricelist. Effective Date: January 1, 2019 Commercial Catalog & Pricelist Effective Date: January 1, 2019 TABLE OF CONTENTS Table of Contents... 2 Introduction to Edaptive Computing, Inc.,... 3 Corporate History & Purpose... 3 Principal Officers

More information

CompTIA Project+ (2009 Edition) Certification Examination Objectives

CompTIA Project+ (2009 Edition) Certification Examination Objectives CompTIA Project+ (2009 Edition) Certification Examination Objectives DRAFT INTRODUCTION The Project + examination is designed for business professionals involved with projects. This exam will certify that

More information

Project Management Pre-Implementation Project status reporting Post Implementation Assessment Phase Solidify Project Scope

Project Management Pre-Implementation Project status reporting Post Implementation Assessment Phase Solidify Project Scope Project Management 321 days 10/22/01 01/30/03 Pre-Implementation 14 days 10/22/01 11/08/01 Detailed Scope / Deliverable definition 5 days 10/22/01 10/26/01 Complete Work Breakdown Structure 1 day 10/22/01

More information

Project Management Professional (PMP) Certificate

Project Management Professional (PMP) Certificate Project Management Professional (PMP) Certificate www.hr-pulse.org What is PMP Certificate HR Pulse has the Learning Solutions to Empower Your People & Grow Your Business Project Management is a professional

More information

When Recognition Matters WHITEPAPER ISO SUPPLY CHAIN SECURITY MANAGEMENT SYSTEMS.

When Recognition Matters WHITEPAPER ISO SUPPLY CHAIN SECURITY MANAGEMENT SYSTEMS. When Recognition Matters WHITEPAPER ISO 28000 SUPPLY CHAIN SECURITY MANAGEMENT SYSTEMS www.pecb.com CONTENT 3 4 4 4 4 5 6 6 7 7 7 8 9 10 11 12 Introduction An overview of ISO 28000:2007 Key clauses of

More information

How Cisco IT Improved Development Processes with a New Operating Model

How Cisco IT Improved Development Processes with a New Operating Model How Cisco IT Improved Development Processes with a New Operating Model New way to manage IT investments supports innovation, improved architecture, and stronger process standards for Cisco IT By Patrick

More information

SERVICE DESCRIPTION MANAGED BACKUP & RECOVERY

SERVICE DESCRIPTION MANAGED BACKUP & RECOVERY Contents Service Overview.... 3 Key Features... 3 Implementation... 4 Validation... 4 Implementation Process.... 4 Internal Kick-Off... 4 Customer Kick-Off... 5 Provisioning & Testing.... 5 Billing....

More information

REPORT 2015/149 INTERNAL AUDIT DIVISION

REPORT 2015/149 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2015/149 Audit of the information and communications technology operations in the Investment Management Division of the United Nations Joint Staff Pension Fund Overall results

More information

The ITIL Foundation Examination

The ITIL Foundation Examination The ITIL Foundation Examination Sample Paper A, version 5.1 Multiple Choice Instructions 1. All 40 questions should be attempted. 2. All answers are to be marked on the answer grid provided. 3. You have

More information

TIPA Lead Assessor for ITIL

TIPA Lead Assessor for ITIL TIPA Lead Assessor for ITIL Course Syllabus Fifalde Consulting Inc. +1-613-699-3005 ITIL is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries 2017 Fifalde

More information

Cisco Collaborative Professional Services Unified Computing System Technical Consulting Accelerator Service (ASF-CPSC-UCST)

Cisco Collaborative Professional Services Unified Computing System Technical Consulting Accelerator Service (ASF-CPSC-UCST) Page 1 of 1 Service : Advanced Services Fixed Price Cisco Collaborative Professional Services Unified Computing System Technical Consulting Accelerator Service (ASF-CPSC-UCST) This document describes Advanced

More information

Cisco QuickStart Implementation Service for Tetration Analytics Medium

Cisco QuickStart Implementation Service for Tetration Analytics Medium Page 1 of 9 Service Description: Advanced Services Fixed Price Cisco QuickStart Implementation Service for Tetration Analytics Medium (ASF-DCV1-TA-QS-M) This document describes Advanced Services Fixed

More information

Data Governance Quick Start

Data Governance Quick Start Service Offering Data Governance Quick Start Congratulations! You ve been named the Data Governance Leader Now What? Benefits Accelerate the initiation of your Data Governance program with an industry

More information

PREPARE FOR TAKE OFF. Accelerate your organisation s journey to the Cloud.

PREPARE FOR TAKE OFF. Accelerate your organisation s journey to the Cloud. PREPARE FOR TAKE OFF Accelerate your organisation s journey to the Cloud. cloud. Contents Introduction Program & Governance BJSS Cloud Readiness Assessment: Intro Platforms & Development BJSS Cloud Readiness

More information

Education Brochure. Education. Accelerate your path to business discovery. qlik.com

Education Brochure. Education. Accelerate your path to business discovery. qlik.com Education Education Brochure Accelerate your path to business discovery Qlik Education Services offers expertly designed coursework, tools, and programs to give your organization the knowledge and skills

More information

Certified Information Security Manager (CISM) Course Overview

Certified Information Security Manager (CISM) Course Overview Certified Information Security Manager (CISM) Course Overview This course teaches students about information security governance, information risk management, information security program development,

More information

NC Education Cloud Feasibility Report

NC Education Cloud Feasibility Report 1 NC Education Cloud Feasibility Report 1. Problem Definition and rationale North Carolina districts are generally ill-equipped to manage production server infrastructure. Server infrastructure is most

More information

Managing Projects Using PMI s Standards facilitated by: Mr. Andreas Solomou

Managing Projects Using PMI s Standards facilitated by: Mr. Andreas Solomou 1 Managing Projects Using PMI s Standards facilitated by: Mr. Andreas Solomou 05, 12, 19 April 2019 03, 07 May 2019 Time: 08:30 17:00 Venue: CIIM Nicosia, 21 Akademias Avenue, 2151 Aglandjia Language of

More information

EXAM PREPARATION GUIDE

EXAM PREPARATION GUIDE EXAM PREPARATION GUIDE PECB Certified ISO 21500 Lead Project Manager The objective of the PECB Certified ISO 21500 Lead Project Manager examination is to ensure that the candidate has the knowledge and

More information

Service Description: Identity Services Engine Implementation-Subscription Service

Service Description: Identity Services Engine Implementation-Subscription Service Page 1 of 6 Service Description: Identity Services Engine Implementation-Subscription Service Services Summary This document describes the Identity Services Engine Implementation. Subscription Service.

More information

HRSD Position Description: UNIX Systems Administrator

HRSD Position Description: UNIX Systems Administrator HRSD Position Description: UNIX Systems Administrator Section I. Section II. Section III. Position Reference Information a. Department Finance and Administration b. Division Information Technology c. Position

More information

ISO Information Security Management Systems Implementation Road Map

ISO Information Security Management Systems Implementation Road Map www.uaeiso.com ISO 27001 Information Security Management Systems Implementation Road Map 10 Step Approach to ISO 27001 Certification Awareness Training Information Security Policy and Objectives Finalization

More information

ITIL Intermediate Service Design (SD) Certification Boot Camp - Brochure

ITIL Intermediate Service Design (SD) Certification Boot Camp - Brochure ITIL Intermediate Service Design (SD) Certification Boot Camp - Brochure Get a Management-level overview of Service Design to advance in your Career Course Name : ITIL SD Version : INVL_ITILSD_BR_02_033_1.2

More information

BCM Program Development

BCM Program Development BCM Program Development Course Description: The BCM Program Development course provides you with knowledge to develop an auditable and actionable business continuity program for your organization. This

More information

AUDIT UNITED NATIONS VOLUNTEERS PROGRAMME INFORMATION AND COMMUNICATION TECHNOLOGY. Report No Issue Date: 8 January 2014

AUDIT UNITED NATIONS VOLUNTEERS PROGRAMME INFORMATION AND COMMUNICATION TECHNOLOGY. Report No Issue Date: 8 January 2014 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNITED NATIONS VOLUNTEERS PROGRAMME INFORMATION AND COMMUNICATION TECHNOLOGY Report No. 1173 Issue Date: 8 January 2014 Table of Contents Executive Summary

More information

Managed Security Services - Endpoint Managed Security on Cloud

Managed Security Services - Endpoint Managed Security on Cloud Services Description Managed Security Services - Endpoint Managed Security on Cloud The services described herein are governed by the terms and conditions of the agreement specified in the Order Document

More information

ITSM20F_Umang. Number: ITSM20F Passing Score: 800 Time Limit: 120 min File Version: 4.0. Exin ITSM20F

ITSM20F_Umang.   Number: ITSM20F Passing Score: 800 Time Limit: 120 min File Version: 4.0. Exin ITSM20F ITSM20F_Umang Number: ITSM20F Passing Score: 800 Time Limit: 120 min File Version: 4.0 http://www.gratisexam.com/ Exin ITSM20F IT Service Management Foundation based on ISO/IEC 20000 (ITSM20F.EN) Version:

More information

SPACE for SDGs a Global Partnership

SPACE for SDGs a Global Partnership SPACE for SDGs a Global Partnership for the Coordination of the Development, Operation and Utilization of Space related Infrastructure, Data, Information and Services in support of the 2030 Development

More information

Identity Assurance Framework: Realizing The Identity Opportunity With Consistency And Definition

Identity Assurance Framework: Realizing The Identity Opportunity With Consistency And Definition Identity Assurance Framework: Realizing The Identity Opportunity With Consistency And Definition Sept. 8, 2008 Liberty Alliance 1 Welcome! Introduction of speakers Introduction of attendees Your organization

More information

During each cycle of three years every installer must accumulate CPD Points to qualify for designation renewal of his/her registration.

During each cycle of three years every installer must accumulate CPD Points to qualify for designation renewal of his/her registration. CPD POLICY The Flooring Industry Training Association has applied for official recognition by the South African Qualifications authority (SAQA) as the professional body for the flooring industry in South

More information