2 Overview and Objectives This case study allows students to build and configure a complex network using skills gained throughout the course. This case study is not a trivial task. To complete it as outlined with all required documentation will be a significant accomplishment. The case study scenario describes the project in general terms, and will explain why the network is being built. Following the scenario, the project is broken into a number of phases, each of which has a detailed list of requirements. It is important to read and understand each requirement to make sure that the project is completed accurately. The following tasks are required to complete this case study: Set up the physical layout of the network using the diagram and accompanying narrative Correctly configure multi-area OSPF with MD5 authentication Correctly configure VLANs and 802.1q trunking Correctly configure STP Correctly configure VTP Correctly configure Etherchannel when required Correctly configure HSRP Correctly configure DHCP Correctly configure NAT Create and apply access control lists (ACL S) on the appropriate routers and interfaces Verify/test and document, all devices must operational and functioning according to the scenario guidelines Provide detailed documentation in a prescribed form as listed in the deliverables sections
3 Scenario Galway S0/0 OSPF 10 Area 1 ISP Server /30 G0/ / Hosts Hosts S0/0 DCE / /30 ISP ISP / /30 Nat Outside /26 Nat Inside /20 Cork 100 Hosts S0/1 OSPF 10 area 0 S0/1 DCE Belfast VLANs 900 hosts (total) Belfast2 G0/1 S2 G0/1 Etherchannel VLAN 3 Etherchannel S3 VLAN 4 Belfast1 HSRP S1 Etherchannel G0/1 G0/1 S0/0 Limerick 200 hosts A company needs a network to be designed and implemented; the company has locations in four cities. All of the locations will be connected using leased-line serial links. The company has previously used RIP version 2; however, all four locations will use OSPF routing process. Also, default static route must be used to access the internet. One location, Belfast, has a large and complex LAN. Due to the size and complexity, the company wants to create VLANs to control broadcasts, enhance security, and logically group users. The company also wants to use private addresses throughout the Autonomous System, DHCP over most of the LAN segments, and NAT implemented for Internet connectivity. The company also wishes to limit Internet access to Web traffic while allowing multiple protocols (not all) within its own WAN. Although private addresses (RFC 1918) will be used, the company appreciates efficiency and address conservation in design. To minimize wasted address space, they have requested VLSM to be used when appropriate. You will build and troubleshoot this design (Prototype), first in Packet Tracer, and then using lab equipment when presenting your design on the assigned date.
4 Phase 1: Addressing the WAN & LAN Use the following instructions to complete Phase 1: Use /20 for internal addressing with IP subnet zero enabled. Apply /30 subnets on all serial interfaces, using the last available subnet. Assign an appropriately sized subnet for the Belfast LAN, which has about 900 devices: 1. VLAN 99: 40 devices (Management VLAN) 2. VLAN 2: 120 hosts 3. VLAN 3: 250 hosts 4. VLAN 4: 500 hosts Assign the appropriately sized subnet to the Limerick LAN, which has 200 hosts. Assign an appropriately sized subnet for the Galway s 2 LANs, which have 400 devices. Assign the appropriately sized subnet to the Cork LAN, which has 100 hosts Document all of the addressing in tables. Phase 2: Configuring Default Routes, OSPF Routing and HSRP Use the following instructions to complete Phase 2: Configure each router with a hostname and required passwords. Configure each interface on all routers documented in Phase 1. Configure Multi-area OSPF on Routers (Galway, Cork, Limerick, and Belfast). Configure a summary (type 3) for area 1. Configure a Default on Belfast and redistribute the route into the OSPF process. Configure MD5 authentication between OSPF routers across all WAN links Adjust the Hello timer to 40 sec and Dead timers to 160 sec on the link between Cork and Galway Verify that the Limerick, Belfast, Galway, and Cork routers have connectivity through Layers 1-7. Provide the ability to dynamically recover from the failure of a device acting as a default gateway to ISP. Use first-hop redundancy protocol (HSRP) to provide the mechanism. Also allow for load balancing across the two Internet connections. Phase 3: Configuring VLANs Use the following instructions to complete Phase 3: 1. Apply the basic switch configuration Hostname, MOTD and passwords 2. Configure PVST+ on 3 switches, switch 1 and 2 must be able to do load balancing S1 is the root bridge for VLAN 4, S2 is the backup root bridge for mentioned VLAN. S2 is the root bridge for VLANs 2 and 3, S1 is the backup root bridge for mentioned VLANs 3. VTP must be used to propagate VLAN information to other client switches
5 VTP domain name: CCNA3, password: Ca$e$tudy3 Using VTP, create and name three Data VLANs and one Management VLAN on VTP server: o VLAN 99: Management (Native) o VLAN 2: HR o VLAN 3: R&D o VLAN 4: Production. 4. Configure switches S1, S2 and S3; assign: Gigabit ports 1-4 as trunks (802.1Q) Configure Etherchannel when appropriate. 5. Configure the Belfast s LAN (2 routers and 3 switches) as follows: 6. Configure access layer switch S3; assign: Port 6 to VLAN 99 Ports 7-10 to VLAN 2 Ports to VLAN 3 Ports to VLAN 4 Disable all unused ports Connect G0/1 of the Belfast s 2 routers to G0/1 of S1 and S2 o Configure the appropriate number of sub-interfaces o Associate each sub-interface with a VLAN o Assign sub-interfaces the appropriate IP addresses Configure other router interfaces as shown in the diagram Connect one workstation per VLAN Phase 4: Configuring ACLs Use the following instructions to complete Phase 4: 1. Configure an Extended ACL On the Belfast Routers. The ACL should: Allow IP traffic for TCP and ICMP sessions originating from the inside (established sessions) while denying IP traffic for sessions originating outside the network. 2. Use an ACL to control VTY access to routers ACL to permit Administrators from VLAN 99 VTY access to all routers. Phase 5: Configuring DHCP DHCP Services Configure DHCP services on the Cork router. DHCP should provide services to the following LANs hosts: Belfast s VLAN 2, VLAN 3 and VLAN 4 DHCP should pass the following parameters to the hosts:
6 IP address and Subnet Mask Default Gateway DNS address ( ) The Cork router will perform the DHCP services. Configure Cork using the DHCP pools documented in Phase 1. Configure DHCP services on the Cork router as follows: Phase 6: NAT FG0/1 s sub-interfaces with the first useable address. Exclude the first 10 IP addresses from each pool (to be used for printers and servers) Configure Workstations to obtain its IP address automatically. Have one host connected to on Cork and one host per VLAN connected to VLANs 2-4 on the Belfast s access layer switch. Use the following instructions to complete Phase 6: 1. The Belfast s (2) routers will perform NAT. Configure the routers as follows: Define the NAT pool. The pool consists of public network address /26. Exclude first 10 addresses from this pool (to be use for servers, when required). Define an access control list, which will translate for all internal ( /20) addresses, and deny all other traffic. Establish dynamic source translation, specifying the NAT pool and the ACL defined in the previous steps. Specify the inside and the outside NAT interfaces. Change the default NAT timeout value to 120 seconds. Document NAT configuration in a chart; it will serve as the deliverable item for Phase Connect a Server to the ISP s port to simulate an ISP server. Configure this Server as follows: Configure the IP address and subnet mask as /8. Configure the default gateway to be Configure the server to act as a web server. enable a simple web page that will tell users that they have reached the ISP. Phase 7: Verification and Testing Use the following instructions to complete Phase 7: 1. Verify communication between various hosts in the network. Troubleshoot and fix any problems in the network until it works properly. Document the results of the tests in a table. 2. Capture and save the router configuration files for all four routers. Edit the text files, and include comments at the top of each file documenting the following: Your name
7 The date CCNA3 Case Study Final Router Configuration The router name that corresponds to each file.
8 Case Study Deliverables Once the case study problem has been solved, the network has been successfully designed and the prototype implemented and tested, a final report must be provided to your instructor. This report will include thorough and wellorganized documentation of the process. It is highly recommended that all tables be completed using a spreadsheet program such as Microsoft Excel. Cisco Network Designer, Visio or a paint program can be used for the network diagrams. Some of these tables and outputs should be used in your power point presentation The following items must be included in the final report and presentation: Outline Summary of the Company and Network Requirements Discussion on the implementation of IP address and VLSM Discussion on the implementation of Routing Discussion on the implementation of VLANs, STP, and switches Discussion on the physical layer design and equipment Discussion on testing and verification strategies Recommendations for future network upgrades Logical Diagram Physical Diagram IP Addressing Table Equipment Table including quantity, make and model (Routers & Switches ONLY) Show Commands outputs to verify connectivity: show ip route, show ip ospf neighbors, show spanning-tree, show vlan, ping, telnet, etc. Router Configurations Switch Configuration The documentation should be complete and should contain enough information to allow a third party to properly install, configure and troubleshoot the network without requesting additional information.
Case Study. Routing & Switching. Cisco Networking Academy Routing and Switching: Scaling Network Case Study
Case Study Routing & Switching Cisco Networking Academy Routing and Switching: Scaling Network Case Study Overview and Objectives This case study allows students to build and configure a complex network
More informationCase Study. WANs. Cisco Networking Academy Program CCNA 4: WAN Technologies v3.0
Case Study WANs Cisco Networking Academy Program CCNA 4: WAN Technologies v3.0 Overview and Objectives This final case study shows you how to build and configure a complex network using the skills you
More informationCase Study. Routing. Cisco Networking Academy Program CCNA 2: Routers and Routing Basics v3.1
Case Study Routing Cisco Networking Academy Program CCNA 2: Routers and Routing Basics v3.1 Overview and Objectives This case study allows students to complete a network design, implementation, and troubleshooting
More informationTestOut Routing and Switching Pro - English 6.0.x COURSE OUTLINE. Modified
TestOut Routing and Switching Pro - English 6.0.x COURSE OUTLINE Modified 2017-07-10 TestOut Routing and Switching Pro Outline- English 6.0.x Videos: 133 (15:42:34) Demonstrations: 78 (7:22:19) Simulations:
More informationCase Study. Routing. Cisco Networking Academy Program CCNA 2: Routers and Routing Basics v3.0
Case Study Routing Cisco Networking Academy Program CCNA 2: Routers and Routing Basics v3.0 Overview and Objectives This case study will allow you to complete a network design, implementation, and troubleshooting
More informationCCNA 2: ROUTING PROTOCOLS AND CONCEPTS V4.0 CASE STUDY
Tecnologies de Xarxes D Ordinadors (CCNA) CCNA 2: ROUTING PROTOCOLS AND CONCEPTS V4.0 CASE STUDY Overview and Objectives This case study allows students to complete a network design, implementation, and
More informationPT Activity 8.6.1: CCNA Skills Integration Challenge Topology Diagram
Topology Diagram All contents are Copyright 2008 Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 1 of 7 Addressing Table for HQ Device Interface IP Address Subnet
More informationCCNA Exploration Network Fundamentals
CCNA Exploration 4.0 1. Network Fundamentals The goal of this course is to introduce you to fundamental networking concepts and technologies. These online course materials will assist you in developing
More informationThe primary audience for this course includes Network Administrators, Network Engineers,
CCNA COURSE DESCRIPTION: Cisco Certified Network Associate (CCNA) validates the ability to install, configure, operate, and troubleshoot medium-size route and switched networks, including implementation
More informationLaboration 1 Examine the Topology and Basic Troubleshooting Commands
Laboration 1 Examine the Topology and Basic Troubleshooting Commands Topology All contents are Copyright 1992 2011 Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page
More informationCCNA. Course Catalog
CCNA Course Catalog 2012-2013 This course is intended for the following audience: Network Administrator Network Engineer Systems Engineer CCNA Exam Candidates Cisco Certified Network Associate (CCNA 640-802)
More informationCisco CCNA (ICND1, ICND2) Bootcamp
Cisco CCNA (ICND1, ICND2) Bootcamp Course Duration: 5 Days Course Overview This five-day course covers the essential topics of ICND1 and ICND2 in an intensive Bootcamp format. It teaches students the skills
More informationInterconnecting Cisco Networking Devices Part 1 ( )
Interconnecting Cisco Networking Devices Part 1 (100-101) Exam Description: The 100-101 Interconnecting Cisco Networking Devices Part 1 (ICND1) is a 1.5- hour exam with 50 60 questions. The 100-101 Interconnecting
More informationBook Heading. 2 Configurating Static Routing. 7 Router Security VLAN Network Router Security Network Infrastructure Design
CND 1: Part 1. Navigation and Administration Switch CL EXEC Mode Switch CL Configuration Process Switch CL Configuration Process Router CL EXEC Mode Router CL EXEC Mode Router CL Configuration Process
More informationLab Configuring and Verifying Extended ACLs Topology
Topology 2015 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 8 Addressing Table Objectives Device Interface IP Address Subnet Mask Default Gateway R1 G0/1 192.168.10.1
More informationGoCertify Advanced Cisco CCIE Lab Scenario # 1
GoCertify Advanced Cisco CCIE Lab Scenario # 1 (http://www.gocertify.com) IPexpert, Inc. is a leading provider in on-line Cisco CCNA, CCNP and CCIE training material. For more information please visit
More informationMobile MOUSe ROUTING AND SWITCHING FUNDAMENTALS PART II ONLINE COURSE OUTLINE
Mobile MOUSe ROUTING AND SWITCHING FUNDAMENTALS PART II ONLINE COURSE OUTLINE COURSE TITLE ROUTING AND SWITCHING FUNDAMENTALS PART II COURSE DURATION 10 Hour(s) of Self-Paced Interactive Training COURSE
More informationLab : Challenge OSPF Configuration Lab. Topology Diagram. Addressing Table. Default Gateway. Device Interface IP Address Subnet Mask
Topology Diagram Addressing Table Device Interface IP Address Subnet Mask Default Gateway Fa0/0 HQ S0/0/0 S0/0/1 Lo1 10.10.10.1 255.255.255.252 Fa0/0 Branch1 S0/0/0 S0/0/1 Fa0/0 Branch2 S0/0/0 S0/0/1 PC1
More informationCCNA Routing and Switching (NI )
CCNA Routing and Switching (NI400+401) 150 Hours ` Outline The Cisco Certified Network Associate (CCNA) Routing and Switching composite exam (200-125) is a 90-minute, 50 60 question assessment that is
More informationSkills Assessment (EIGRP) Student Training Exam
Skills Assessment (EIGRP) Student Training Exam Topology 2013 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 16 Addressing Table Assessment Objectives Device
More information"Charting the Course... Interconnecting Cisco Networking Devices Accelerated 3.0 (CCNAX) Course Summary
Description Course Summary The Cisco CCNA curriculum includes a third course, Interconnecting Cisco Networking Devices: Accelerated (CCNAX), consisting of Interconnecting Cisco Networking Devices, Part
More informationInterconnecting Cisco Networking Devices Part 1 (ICND1) Course Overview
Interconnecting Cisco Networking Devices Part 1 (ICND1) Course Overview This course will teach students about building a simple network, establishing internet connectivity, managing network device security,
More informationLab 8.5.2: Troubleshooting Enterprise Networks 2
Lab 8.5.2: Troubleshooting Enterprise Networks 2 Topology Diagram Addressing Table Device Interface IP Address Subnet Mask Default Gateway Fa0/0 192.168.10.1 255.255.255.0 N/A R1 Fa0/1 192.168.11.1 255.255.255.0
More informationSkills Assessment Student Training
Skills Assessment Student Training Topology Assessment Objectives Part 1: Initialize Devices (6 points, 5 minutes) Part 2: Configure Device Basic Settings (33 points, 20 minutes) Part 3: Configure Switch
More informationSkills Assessment (OSPF) Student Training Exam
Skills Assessment (OSPF) Student Training Exam Topology 2013 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 17 Addressing Table Assessment Objectives Device
More informationCCNA Routing and Switching Course Overview
CCNA Routing and Switching Course Overview Course Structure and Sequences Market research and global employers have consistently indicated that the skills gap for general networking skills is shrinking,
More informationScenario Labs NETSIM FOR CCNA LAB MANUAL. Scenario Labs. Boson NetSim for CCNA Lab Manual
NETSIM FOR CCNA LAB MANUAL Welcome to the NetSim. The goal of these labs is to introduce you to the limited number of commands needed to enable a technology, without addressing extra commands that could
More informationLab 1-2Connecting to a Cisco Router or Switch via Console. Lab 1-6Basic Graphic Network Simulator v3 Configuration
MODULE1 GETTING STARTED WITH YOUR CISCO LAB Lab 1-1Identifying Router Components and Accessories Lab 1-2Connecting to a Cisco Router or Switch via Console Lab 1-3Identifying Router & Switch IOS Software
More informationScope and Sequence: CCNA Exploration v4.0
Scope and Sequence: CCNA Exploration v4.0 Last Updated August 30, 2007 The course objectives and outline for the final two CCNA Exploration courses, LAN Switching and Wireless and Accessing the WAN, are
More informationCCNA ROUTING & SWITCHING
CCNA ROUTING & SWITCHING Curriculum Overview The CCNA Routing and Switching curriculum consists of four courses that make up the recommended learning path. Students will be prepared to take the Cisco CCENT
More informationCCNA Boot Camp. Course Description
CCNA Boot Camp Course Description CCNA Boot Camp combines both the Interconnecting Cisco Network Devices Part 1 (ICND1) course and the Interconnecting Cisco Network Devices Part 2 (ICND2) course into one
More informationCisco Certified Network Associate ( )
Cisco Certified Network Associate (200-125) Exam Description: The Cisco Certified Network Associate (CCNA) Routing and Switching composite exam (200-125) is a 90-minute, 50 60 question assessment that
More informationCCNA Routing and Switching ucertify Network Simulator. Course Outline. 30 Oct ( Add-On )
Course Outline CCNA Routing and Switching 200125 ucertify Network 30 Oct 2018 ( Add-On ) Contents 1. Course Objective 2. Expert Instructor-Led Training 3. ADA Compliant & JAWS Compatible Platform 4. State
More informationCCNA. Murlisona App. Hiralal Lane, Ravivar Karanja, Near Pethe High-School, ,
CCNA Cisco Certified Network Associate (200-125) Exam DescrIPtion: The Cisco Certified Network Associate (CCNA) Routing and Switching composite exam (200-125) is a 90-minute, 50 60 question assessment
More informationLab 9.6.2: Challenge EIGRP Configuration Lab
Topology Diagram Addressing Table Device Interface IP Address Subnet Mask Default Gateway HQ BRANCH1 BRANCH2 PC1 PC2 PC3 Fa0/0 S0/0/0 S0/0/1 Lo1 Fa0/0 S0/0/0 S0/0/1 Fa0/0 S0/0/0 S0/0/1 NIC NIC NIC All
More informationInterconnecting Cisco Networking Devices: Accelerated
Interconnecting Cisco Networking Devices: Accelerated CCNAX v3.0; 5 days, Instructor-led Course Description The Cisco CCNA curriculum includes a third course, Interconnecting Cisco Networking Devices:
More informationCOPYRIGHTED MATERIAL. Table of Contents. Assessment Test
10089.book Page xi Monday, July 23, 2007 3:17 PM Introduction Assessment Test xxiii xxxiii Chapter 1 Internetworking 1 Internetworking Basics 4 Internetworking Models 11 The Layered Approach 12 Advantages
More informationSkills Assessment (EIGRP) Student Training Exam
Skills Assessment (EIGRP) Student Training Exam Topology Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 15 Addressing Table Device Interface IP Address Subnet
More informationSeite von 7 05.0.200 Close Window Assessment System Exam Viewer - CCNA Practice Certification Exam # - (Version 4.0) Below you will find the assessment items as presented on the exam as well as the scoring
More informationSkills Assessment (OSPF) Student Training Exam
Skills Assessment (OSPF) Student Training Exam Topology Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 16 Addressing Table Device Interface IP Address Subnet
More informationCCNP SWITCH (22 Hours)
CCNP SWITCH 642-813 (22 Hours) Chapter-1 Enterprise Campus Network Design 1.1 IIN & SONA 1.2 Campus Network 1.3 Enterprise Model 1.4 Nonhierarchical Network Devices Layer-2 Switching, Layer-3 Routing Multilayer
More informationIT245 ROUTING AND SWITCHING I
IT245 ROUTING AND SWITCHING I ***For Classes Delivered Online, please see specific requirements in your online course header located at Course Objectives http://classes.miller motte.edu*** Upon successful
More informationEIGRP Practice Skills Assessment - Packet Tracer
CCNA Routing and Switching Scaling Networks EIGRP Practice Skills Assessment - Packet Tracer A few things to keep in mind while completing this activity: 1. Do not use the browser Back button or close
More informationCCNA 2014 Performance Based Lab. Course Outline. CCNA 2014 Performance Based Lab Sep 2018
Course Outline CCNA 2014 Performance Based Lab 08 Sep 2018 Contents 1. Course Objective 2. Expert Instructor-Led Training 3. ADA Compliant & JAWS Compatible Platform 4. State of the Art Educator Tools
More informationActual4Test. Actual4test - actual test exam dumps-pass for IT exams
Actual4Test http://www.actual4test.com Actual4test - actual test exam dumps-pass for IT exams Exam : 200-125 Title : CCNA Cisco Certified Network Associate CCNA (v3.0) Vendor : Cisco Version : DEMO Get
More informationCCNA Routing & Switching
CCNA Routing & Switching 1.0 LAN Switching Technologies 1. VLANs,Trunk, DTP 2. VLANs, Trunks and DTP Configuration 3. Voice Vlan Configuration 4. VTP 5. VTP - Configuration 6. Spanning-tree 7. STP - PVST+
More informationLab Configuring HSRP and GLBP Topology
Topology 2014 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 9 Addressing Table Objectives Device Interface IP Address Subnet Mask Default Gateway R1 G0/1 192.168.1.1
More informationCertified Cisco Networking Associate v1.1 ( )
Certified Cisco Networking Associate v1.1 (640-802) Exam Description: The Cisco Certified Networking Associate v1.1 640-802 is the composite exam that is associated with Cisco CCNA Routing and Switching
More informationLab 5.6.2: Challenge RIP Configuration
Topology Diagram Addressing Table Device Interface IP Address Subnet Mask Default Gateway BRANCH HQ ISP PC1 PC2 PC3 Fa0/0 S0/0/0 Fa0/0 S0/0/0 S0/0/1 Fa0/0 S0/0/1 NIC NIC NIC Learning Objectives Upon completion
More informationCCNA 4 - Final Exam (B)
CCNA 4 - Final Exam (B) 1. Identify the factors that contribute to congestion on an Ethernet LAN. (Choose three.) improper placement of enterprise level servers addition of hosts to a physical segment
More information3. What could you use if you wanted to reduce unnecessary broadcast, multicast, and flooded unicast packets?
Nguyen The Nhat - Take Exam Exam questions Time remaining: 00: 00: 51 1. Which command will give the user TECH privileged-mode access after authentication with the server? username name privilege level
More informationUniNets CCNA Security LAB MANUAL UNiNets CCNA Cisco Certified Network Associate Security LAB MANUAL UniNets CCNA LAB MANUAL
UNiNets CCNA Cisco Certified Network Associate Security LAB MANUAL Contents: UniNets CCNA Security LAB MANUAL Section 1 Securing Layer 2 Lab 1-1 Configuring Native VLAN on a Trunk Links Lab 1-2 Disabling
More informationICND1 v2.0 Interconnecting Cisco Networking Devices Part 1 CCENT & Part of CCNA Rout/Switch
ICND1 v2.0 Interconnecting Cisco Networking Devices Part 1 CCENT & Part of CCNA Rout/Switch Course Length: 5 days Course Delivery: Traditional Classroom Online Live Course Overview Interconnecting Cisco
More informationCase Study: CCNA Cap Stone
Case Study: CCNA Cap Stone TOPICS COVERED Advanced Routing WAN simulation Frame Relay ISDN PPP DDR CHAP VLANS NAT DHCP Trunking Access Lists Security Copyright 2005 by Lukasz Tomicki PGP
More informationDevice Interface IP Address Subnet Mask Default Gateway. Ports Assignment Network
Felix Rohrer Topology Diagram Addressing Table Device Interface IP Address Subnet Mask Default Gateway S1 VLAN 99 172.17.99.11 255.255.255.0 N/A S2 VLAN 99 172.17.99.12 255.255.255.0 N/A S3 VLAN 99 172.17.99.13
More informationEXAM CERTIFICATION MAPPING
EAM CERTIFICATION MAPPING CCNA 3: SWITCHING BASICS AND INTERMEDIATE ROUTING 1 EAM MAPPING AND EAM TOPICS/AREAS 2 CCNA 3 Certification Exam Mappings Mapping of Cisco Academy CCNA 3 to the One exam certification
More information6.5.1: Packet Tracer Skills Integration Challenge Activity Topology Diagram
6.5.1: Packet Tracer Skills Integration Challenge Activity Topology Diagram All contents are Copyright 1992 2007 Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page
More informationInterconnecting Cisco Networking Devices Part 1 ICND1
Interconnecting Cisco Networking Devices Part 1 ICND1 Course Length: 5 days Course Delivery: Traditional Classroom Online Live Course Overview Interconnecting Cisco Networking Devices, Part 1 (ICND1) v3.0
More informationCourse: CCNA Bootcamp (Intensive CCNA)
Course: CCNA Bootcamp (Intensive CCNA) Duration: 5 Days Description Introduction to Networking course will prepare you for the basic knowledge and in-depth technology of networking design and implementation.
More informationTEXTBOOK MAPPING CISCO COMPANION GUIDES
TestOut Routing and Switching Pro - English 6.0.x TEXTBOOK MAPPING CISCO COMPANION GUIDES Modified 2018-08-20 Objective Mapping: Cisco 100-105 ICND1 Objective to LabSim Section # Exam Objective TestOut
More informationCCNP ROUTING & SWITCHING PRACTICAL LAB WORKBOOK DARE TO CHALLENGE YOUR SKILLS COMPLETE THE TESTS & TAKE YOUR CAREER TO NEXT LEVEL
CCNP ROUTING & SWITCHING PRACTICAL LAB WORKBOOK DARE TO CHALLENGE YOUR SKILLS COMPLETE THE TESTS & TAKE YOUR CAREER TO NEXT LEVEL CONQUER THE CCNP WORK BOOK CHALLENGES & YOU WILL BE READY FOR CCIE Yes,
More informationThis document is exclusive property of Cisco Systems, Inc. Permission is granted to print and copy this document for non-commercial distribution and
This document is exclusive property of Cisco Systems, Inc. Permission is granted to print and copy this document for non-commercial distribution and exclusive use by instructors in the CCNA Exploration:
More informationExam Topics Cross Reference
Appendix R Exam Topics Cross Reference This appendix lists the exam topics associated with the ICND1 100-105 exam and the CCNA 200-125 exam. Cisco lists the exam topics on its website. Even though changes
More informationASM Educational Center (ASM) Est. 1992
Interconnecting Cisco Networking Devices Part 2 (ICND2) Course Overview This course will teach students about implementing scalable medium-sized networks, troubleshooting basic connectivity, implementing
More informationActualtests Q
Actualtests.300-135 55Q Number: 300-135 Passing Score: 800 Time Limit: 120 min File Version: 5.4 http://www.gratisexam.com/ 300-135 Troubleshooting and Maintaining Cisco IP Networks (TSHOOT) Passed today
More informationInterconnecting Cisco Networking Devices Part 2 (ICND2) Course Overview
Interconnecting Cisco Networking Devices Part 2 (ICND2) Course Overview This course will teach students about implementing scalable medium-sized networks, troubleshooting basic connectivity, implementing
More informationCCNA Security 1.0 Student Packet Tracer Manual
1.0 Student Packet Tracer Manual This document is exclusive property of Cisco Systems, Inc. Permission is granted to print and copy this document for non-commercial distribution and exclusive use by instructors
More informationCisco CCNP ROUTE: Implementing Cisco IP Routing (ROUTE) 2.0. Upcoming Dates. Course Description. Course Outline
Cisco CCNP ROUTE: Implementing Cisco IP Routing (ROUTE) 2.0 Implementing Cisco IP Routing (ROUTE) v2.0 is an instructor-led five day training course developed to help students prepare for Cisco CCNP certification.
More informationPass4sures. Latest Exam Guide & Learning Materials
Pass4sures http://www.pass4sures.top/ Latest Exam Guide & Learning Materials Exam : 200-125 Title : CCNA Cisco Certified Network Associate CCNA (v3.0) Vendor : Cisco Version : DEMO Get Latest & Valid 200-125
More informationCh6 Packet Tracer Skills Integration Challenge Topology Diagram
Topology Diagram All contents are Copyright 1992 2007 Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 1 of 7 Addressing Table for R1 Device Interface IP Address
More informationInterconnecting Cisco Networking Devices Part 2 v2.0 (ICND 2)
Interconnecting Cisco Networking Devices Part 2 v2.0 (ICND 2) COURSE OVERVIEW: The Interconnecting Cisco Networking Devices, Part 2 (ICND2) v2.0 course provides entry-level network administrators, network
More informationTroubleshooting, Editing, Port # s
CCNA Commands Summary Page 1 of 23 Troubleshooting, Editing, Port # s show ip interface brief (display interface designations, IP address and status) show ip route (display routing table) show vlan brief
More informationexam. Number: Passing Score: 800 Time Limit: 120 min CISCO Interconnecting Cisco Networking Devices Part 1 (ICND)
100-105.exam Number: 100-105 Passing Score: 800 Time Limit: 120 min CISCO 100-105 Interconnecting Cisco Networking Devices Part 1 (ICND) Exam A QUESTION 1 Which route source code represents the routing
More informationCCNA ROUTING & SWITCHING SECTOR / ENGINEERING TECHNICAL & CERTIFICATE OF ATTENDANCE TRAINING COURSE
SECTOR / ENGINEERING TECHNICAL & CERTIFICATE OF ATTENDANCE TRAINING COURSE Program For Entry-Level Network Engineers That Helps Maximize Your Investment In Foundational Networking Knowledge And Increase
More informationInformation and Network Technology Revised Date 07/26/2012 Implementation Date 08/01/2012
Information and Network Technology Ben Eckart Revised Date 07/26/2012 Implementation Date 08/01/2012 COURSE OUTLINE CRT 286 LAN/WAN Implementation and Support 3 Credit Hours Course Description The focus
More informationLab Configuring and Verifying Standard ACLs Topology
Topology 2013 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 9 Addressing Table Objectives Device Interface IP Address Subnet Mask Default Gateway R1 G0/1 192.168.10.1
More informationChapter 7. IP Addressing Services. IP Addressing Services. Part I
Chapter 7 IP Addressing Services Part I CCNA4-1 Chapter 7-1 IP Addressing Services Dynamic Host Configuration Protocol (DHCP) CCNA4-2 Chapter 7-1 Dynamic Host Configuration Protocol (DHCP) Every device
More informationVendor: Cisco. Exam Code: Exam Name: CCNA Cisco Certified Network Associate CCNA (v3.0) Version: Demo
Vendor: Cisco Exam Code: 200-125 Exam Name: CCNA Cisco Certified Network Associate CCNA (v3.0) Version: Demo DEMO QUESTION 1 A network administrator needs to configure a serial link between the main office
More informationLab Configuring and Verifying Standard IPv4 ACLs Topology
Topology 2016 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public. Page 1 of 10 Addressing Table Objectives Device Interface IP Address Subnet Mask Default Gateway R1 G0/1 192.168.10.1
More informationCisco Implementing Cisco IP Switched Networks (SWITCH v2.0)
Cisco 300-115 Implementing Cisco IP Switched Networks (SWITCH v2.0) http://killexams.com/pass4sure/exam-detail/300-115 Question: 323 An administrator recently configured all ports for rapid transition
More informationManually Configure Default Gateway Cisco Switch 2960
Manually Configure Default Gateway Cisco Switch 2960 Catalyst 2960 and 2960-S Switches Software Configuration Guide, Cisco IOS Release 15.2(1)E. Assigning the Switch IP Address and Default Gateway. A Cisco
More informationLab Configuring Port Address Translation (PAT) Topology
Topology Addressing Table Objectives Device Interface IP Address Subnet Mask Default Gateway Gateway G0/1 192.168.1.1 255.255.255.0 N/A S0/0/1 209.165.201.18 255.255.255.252 N/A ISP S0/0/0 (DCE) 209.165.201.17
More informationCERTIFICATE CCENT + CCNA ROUTING AND SWITCHING INSTRUCTOR: FRANK D WOUTERS JR. CETSR, CSM, MIT, CA
CERTIFICATE CCENT + CCNA ROUTING AND SWITCHING INSTRUCTOR: FRANK D WOUTERS JR. CETSR, CSM, MIT, CA CCENT - Cisco Certified Entry Networking Technician (ICND1) CCNA Routing and Switching (ICND2) Prerequisites:
More informationCCNP (Routing & Switching and T.SHOOT)
CCNP (Routing & Switching and T.SHOOT) Course Content Module -300-101 ROUTE 1.0 Network Principles 1.1 Identify Cisco Express Forwarding concepts 1.1.a FIB 1.1.b Adjacency table 1.2 Explain general network
More informationCCRI LAN Design / Management CNVT 1830
CCRI LAN Design / Management CNVT 1830 Instructor Telephone E-mail Office Hours Class Sections Credit Hours 3 Credit Hours, 2 Lecture Hours & 2 Laboratory Hours per week Instructional Material and Web
More informationTSHOOT v2.0 Troubleshooting and Maintaining Cisco IP Networks 5 days, Instructor-led
TSHOOT v2.0 Troubleshooting and Maintaining Cisco IP Networks 5 days, Instructor-led Course Description TSHOOT v2.0, a five-day ILT course, includes major updates and follows an updated blueprint. (However,
More informationCCNA EXPLORATION V4.0 ROUTING PROTOCOLS AND CONCEPTS
CCNA EXPLORATION V4.0 ACCESSIBLE INSTRUCTOR MATERIALS COMPARISON OF NEW CURRICULA WITH EXISTING CURRICULA Prepared by Cisco Learning Institute June 23, 2008 Routing Protocols and Concepts Summary New CCNA
More informationInterconnecting Cisco Network Devices Part 1 v2.0 (ICND 1)
Interconnecting Cisco Network Devices Part 1 v2.0 (ICND 1) COURSE OVERVIEW: Interconnecting Cisco Networking Devices, Part 1 (ICND1) v2.0 is a five-day, instructor-led training course that teaches learners
More informationTestOut Network Pro - English 5.0.x COURSE OUTLINE. Modified
TestOut Network Pro - English 5.0.x COURSE OUTLINE Modified 2018-03-06 TestOut Network Pro Outline - English 5.0.x Videos: 130 (17:10:31) Demonstrations: 78 (8:46:15) Simulations: 88 Fact Sheets: 136 Exams:
More informationChapter 10 Lab 10-2, Securing VLANs INSTRUCTOR VERSION
CCNPv7.1 SWITCH Chapter 10 Lab 10-2, Securing VLANs INSTRUCTOR VERSION Topology Objectives Background Secure the server farm using private VLANs. Secure the staff VLAN from the student VLAN. Secure the
More informationITDumpsKR. IT 인증시험한방에패스시키는최신버전시험대비덤프
ITDumpsKR http://www.itdumpskr.com IT 인증시험한방에패스시키는최신버전시험대비덤프 Exam : 300-115 Title : Implementing Cisco IP Switched Networks Vendor : Cisco Version : DEMO Get Latest & Valid 300-115 Exam's Question and
More informationBuilding Cisco Multilayer Switched Networks (BCMSN)
Building Cisco Multilayer Switched Networks (BCMSN) Table of Contents Module 1 Defining VLANs Implementing Best Practices for VLAN Topologies Describing Issues in a Poorly Designed Network Grouping Business
More informationCisco Certified Network Professional (CCNP)
Cisco Certified Network Professional (CCNP) MSIT106 / 120 Hours / 12 Months / Self-Paced / Materials Included Course Overview: This CCNP Routing & Switching, Troubleshooting & Maintaining, and Implementing
More informationLab 6.4.2: Challenge Inter-VLAN Routing
Lab 6.4.2: Challenge Inter-VLAN Routing Topology Diagram Addressing Table Device (Hostname) Interface IP Address Subnet Mask Default Gateway S1 VLAN 99 192.168.99.11 255.255.255.0 192.168.99.1 S2 VLAN
More informationStudy Guide. Using ACLs to Secure Networks
CHAPTER 5 ACLs The Study Guide portion of this chapter uses a combination of matching, multiple-choice, and open-ended question exercises to test your knowledge of the various types of access control lists
More informationexamcollection.premium.exam.68q. Exam code: Exam name: Troubleshooting and Maintaining Cisco IP Networks (TSHOOT) Version 15.
300-135.examcollection.premium.exam.68q Number: 300-135 Passing Score: 800 Time Limit: 120 min File Version: 15.0 / Exam code: 300-135 Exam name: Troubleshooting and Maintaining Cisco IP Networks (TSHOOT)
More informationAdvanced Network Administration. 1. Course Description Enabling Communication across Networks Secured Communication using Network Devices
Advanced Network Administration 1. Course Description Enabling Communication across Networks Secured Communication using Network Devices 2. Duration 5 Days 3. Purpose This five day course for L-2 Network
More informationCCNA Semester 3 labs. Part 1 of 1 Labs for chapters 1 8
CCNA Semester 3 labs Part 1 of 1 Labs for chapters 1 8 2.1.2.12 Lab - Building a Switched Network with Redundant Links 2.3.2.3 Lab - Configuring Rapid PVST+, PortFast and BPDU Guard 2.4.3.4 Lab - Configuring
More informationLaboration 2 Troubleshooting Switching and First-Hop Redundancy
Laboration 2 Troubleshooting Switching and First-Hop Redundancy Topology All contents are Copyright 1992 2011 Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 1
More informationImplementing Cisco IP Routing (ROUTE)
Implementing Cisco IP Routing (ROUTE) COURSE OVERVIEW: Implementing Cisco IP Routing (ROUTE) v2.0 is an instructor-led five-day training course developed to help students prepare for Cisco CCNP certification.
More information