1. Project Description

Size: px
Start display at page:

Download "1. Project Description"

Transcription

1 Page No: 1 of Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal Station (TRTS). This Terminal Station will be built for the connection of Macarthur Wind Farm and Tarrone Power Station and associated facilities to the existing Moorabool-Heywood/Alcoa Portland No.1 500kV Line at Tarrone. The development is to provide a combined maximum output limited to 550MW approximately (due to transformer rating limits). 1.2 Expected System Conditions The following expected system conditions are only included to allow the design of the secondary equipment and for the preparation of secondary settings Expected fault levels The fault levels shown in Table apply to the operation of TRTS once constructed. Table identifies X/R ratios that apply at this Terminal Station. Table 1.2.1: Fault Levels Plant Design Fault Level Max Fault Levels ( Note 1) 3 ph (ka) 3ph (ka) 1ph-g (ka) TRTS No.1 500kV Bus 50 TRTS No.2 500kV Bus 50 Table 1.2.2: X/R Ratios Plant X/R at Ultimate Fault Levels X/R at Max Fault Levels ( Note 1) TRTS No1 500kV Bus 35 TRTS No2 500kV Bus 35 Note 1: Maximum fault Level information will be provided by AEMO upon confirmation of final equipment data from the successful Tenderer Expected protection safe loading limits The protection safe loading limits shown in Table apply to the operation of TRTS once constructed and represent peak loading under worst case conditions considering prior outage and next contingency. Table 1.2.3: Protection Safe Loading Limit Plant Load (ka) Scenario 1 / Scenario 2 TRTS-MLTS No.1 500kV Line TRTS-HYTS/APD No.1 500kV Line 500 kv circuit breakers 500kV busbar The successful Tenderer must consult AEMO if proposed secondary equipment imposes thermal or setting limitations lower than primary plant winter ratings.

2 Page No: 2 of Context of Project Other related PCRs For any consequential works at other terminal stations that may arise out of this project, protection and control requirements will be outlined in the terminal station-specific PCRs identified in Table Table 1.3.2: Consequential Works and other related PCRs PCR PCR Description PCR/HYTS/9 Consequential work at Heywood Terminal Station PCR/APD/5 Consequential work at Alcoa Portland PCR/MLTS/14 Consequential work at Moorabool Terminal Station PCR/TRTS/1 Connection asset requirements associated with establishment of TRTS PCR/TRTS/3 Interface work requirements associated with establishment of TRTS 1.4 General Provision of Information AEMO will advise all parties as applicable, generally 3 months prior to service, the following information: Settings for the synchronism-check interlock facilities; Auto-reclose settings; and Settings for all voltage controls and interlocks General Security Requirements If the successful Tenderer provides any of the following facilities, they must be duplicated and be provided with some measure of physical and electrical segregation as far as practicable: Batteries used for protection and communications purposes; Battery chargers; Auxiliary supplies; Protection panels; Circuit breaker trip coils; Control cables containing X and Y protection quantities, including: Trip circuits to CBs; CT and VT secondaries; Communication systems; and Transformer quantities used for protection purposes. The successful Tenderer must ensure that there is no common point of failure between these duplicated facilities. 1.5 Definitions and Glossary The following terms are used throughout this document: Connection Asset Interface CT HSM PCR QOSM ROI RTU The interface between the shared network development and the connection assets Current Transformer High Speed Monitor Protection and Control Requirements Quality of Supply Monitor Remote Operated Isolator Remote Terminal Unit

3 Page No: 3 of 16 Shared Network Asset Interface SPAR TOC TPAR TPI The interface between the shared network development and the existing SPI PowerNet assets Single phase auto reclose Transmission Operations Centre Three phase auto reclose Tap Position Indication 2. Interface and Shared Network Development The successful Tenderer and SPI PowerNet must exchange protection, monitoring and control signals at the interface between the shared transmission network and the connection assets. The physical location of the interface will be defined in the connection agreement between the successful Tenderer and SPI PowerNet. AEMO has specified within this document the functional obligations on either side of the interface. This interface is shown in Figure 1. The Proponent Generator and the successful Tenderer must exchange protection, monitoring and control signals at an interface between the shared transmission network and the connection assets. The physical location of the interface will be defined in the connection agreement between the successful Tenderer and the Proponent Generator. AEMO has specified within this document the functional obligations on either side of the interface. This interface is shown in Figure 1. Existing (SPI PowerNet s) Transmission Assets Shared Network Development (TRTS owner) Proponent Generator Interface nterface Figure 1: Interface arrangement for TRTS Development. 3. Protection Requirements for Shared Network 3.1 General Requirements For the purposes of this section dead zone is defined as that area in a terminal station between a protection zone and a circuit breaker adjacent to that protection zone that is required to open to clear a fault. Table 3.1: Station Protection Requirements Requirement All clearance times (including backup and dead-zone protection) include the circuit breaker operating times (including those required to operate at remote locations). Equipment provided for each protection system shall, where practical, either be of different manufacturer or have different principle of operation. Protection design must be coordinated to prevent CT saturation interfering with differential protection. Any primary protection system implemented to meet obligations detailed in this document must have sufficient redundancy to ensure that it can meet all obligations within the relevant times with any single element (including any communications facility upon which the protection system depends) out of service.

4 Page No: 4 of Primary Protection Station Protection The successful Tenderer must ensure that any 500 kv faults within the successful Tenderer s assets at TRTS are cleared in the times given in Row 1 of Table measured from fault inception. If the clearance of any fault inside of the successful Tenderer s assets requires the operation of connection assets, the successful Tenderer must ensure that protection trip signalling is provided to the Proponent Generator at the interface within the times listed in Row 2 of Table from the initiation of the fault. Table 3.2.1: Protection - Maximum Protection Times Row Protection System Milliseconds 1 Maximum protection clearance time 80 2 Maximum protection signalling time kV Line Protection If a fault occurs on the TRTS-MLTS No.1 500kV Line, the successful Tenderer must ensure that: - the protection system at TRTS detects the fault and all the successful Tenderer s assets, which are needed to clear the fault, do in fact clear the fault within the time listed in Table from the inception of the fault; and - the successful Tenderer s primary protection system at TRTS interacts with SPI PowerNet s protection system at MLTS to allow SPI PowerNet to achieve the fault clearance within the required time listed in Table from the inception of the fault. Table 3.2.2: Main Protection - Maximum Clearance Times Protection System Milliseconds TRTS MLTS No.1 500kV Line (X and Y) 80 If a fault occurs on the TRTS HYTS section of the TRTS HYTS/APD No kv Line, the successful Tenderer must ensure that: - the protection system at TRTS detects the fault and all the successful Tenderer s assets needed to clear the fault clear the fault within the required time listed in Row 1 of Table from the inception of the fault; and - the protection system at TRTS interacts with SPI PowerNet s protection equipment to achieve the clearance times in Row 2 of Table at HYTS. Table 3.2.3: Main Protection - Maximum Clearance Times Row Station Milliseconds 1 TRTS 80 2 HYTS 80 If SPI PowerNet provides a signal indicating a fault has occurred on the HYTS APD section of the TRTS HYTS/APD No kv Line, the successful Tenderer must trip all assets at TRTS required to clear the fault from the network within the time given in Table after receiving a trip signal from SPI PowerNet at the interface. Table 3.2.4: Main Protection - Maximum Clearance Times Station Milliseconds TRTS 50

5 Page No: 5 of Connection Asset Protection If the Proponent Generator provides a signal indicating a fault has occurred within the connection assets, the successful Tenderer must trip all assets at TRTS required to clear the fault from the network within the time given in Table after receiving the trip signal. Table 3.2.5: Main Protection - Maximum Clearance Times Station Milliseconds TRTS kV Reactor Trip Signals On receipt of remote reactor protection trip signals provided by SPI PowerNet at the interface, the successful Tenderer must ensure that all of the successful Tenderer s assets needed to operate to isolate: - the HYTS/APD No.1 500kV Line; or - the MLTS No.1 500kV Line isolate the required 500kV Line within the time given in Table from the receipt of the signal at the Shared Network Interface. Table 3.2.6: Main Protection - Maximum Operating Times Station Milliseconds TRTS Backup/Dead-zone Protection Maximum Clearance and Signal Times Background to this Requirement AEMO requires that backup/dead-zone protection systems must clear a fault, not otherwise cleared by a primary protection system. SPI PowerNet, the successful Tenderer, and the owners of affected terminal stations must work together in order for these clearance times to be achieved. To achieve this, AEMO requires that the successful Tenderer must meet the following obligations set out in Section Operation of backup protection If a fault is detected by any of the successful Tenderer primary protection systems, the successful Tenderer must ensure that that system also initiates a backup/dead-zone protection system Providing a backup/dead-zone protection trip signal If: - the successful Tenderer s primary protection systems fail to clear a fault, or a fault occurs within a dead zone; or - the successful Tenderer s assets fail to clear a fault if initiated by primary protection of Proponent Generator or SPI PowerNet; and - to clear this fault (while isolating the minimum amount of plant necessary to clear the fault) would require the operation of SPI PowerNet assets, or Alcoa Portland assets; the successful Tenderer must provide a backup/dead-zone protection trip signal to SPI PowerNet at the interface for transmission to remote ends within the times listed in Table from the occurrence of a fault.

6 Page No: 6 of 16 Table 3.3.1: Time for the successful Tenderer to provide a backup/dead-zone Protection Signal at TRTS Shared Network Interface Protection System Milliseconds 500kV Fault (initiated by both X and Y protection) 130 If: - the successful Tenderer s primary protection systems fail to clear a fault, or a fault occurs within a dead zone; and - to clear this fault (while isolating the minimum amount of plant necessary to clear the fault) would require the operation of Proponent Generator s assets; the successful Tenderer must provide a backup/dead-zone protection trip signal to the Proponent Generator at the interface within the times listed in Table from the initiation of a fault. Table 3.3.2: Time for the successful Tenderer to provide a backup/dead-zone Protection Signal at TRTS Connection Asset Interface Protection System Milliseconds 500kV Fault (initiated by both X and Y protection) Clearing fault on receipt of backup/dead-zone protection trip signal The successful Tenderer must ensure that, if a backup/dead-zone protection trip signal is received from SPI PowerNet at the interface, all of the successful Tenderer s assets that are needed to clear the fault do in fact clear the fault within the maximum operating time listed in Table from the receipt of the signal. The successful Tenderer must ensure that, if a backup/dead-zone protection trip signal is received from the Proponent Generator at TRTS at the interface, all of the successful Tenderer s assets that are needed to clear the fault do in fact clear the fault within the maximum operating time listed in Table from the receipt of the signal. Table 3.3.5: Maximum Operating Time Protection System Milliseconds 500kV Fault Monitoring and Controls 4.1 Circuit Breakers and ROIs The successful Tenderer must ensure that all circuit breakers and ROIs referred in this PCR meet the requirements outlined in Tables 4.1.1, and 4.1.3: Table 4.1.1: General Control Requirements General Requirements Equipment must be arranged so that failure of local automatic or remote manual controls cannot prevent operation of the local manual switching controls at the TRTS. Table 4.1.2: Circuit Breaker Common Requirements Requirement Local Trip and Close controls Remote Trip controls for all 500 kv CBs from TOC Remote Close control for all 500 kv CBs from TOC Status indications remotely transmitted for all three 500kV CBs

7 Page No: 7 of 16 Alarms as appropriate for the type of CB Phase discrepancy detection and tripping (if required by CB type) Table 4.1.3: ROI Common Requirements Requirement Local Open and Close controls Interlocked appropriately with circuit breaker and earth switch operation Status indications remotely transmitted for all isolators 4.2 Circuit Breaker Controls The successful Tenderer must ensure that the controls in the following Tables 4.2.1, and are implemented: Table 4.2.1: Circuit Breaker Controls Circuit Breaker: HYTS/APD No.1 Line / No.2 Bus CB (Node DD HH; refer to SLD) Control Requirement Setting Manual synchronising Required Remote Manual Synchronism Check Interlock Required - Voltage differential - Angle differential - Frequency differential - Undervoltage Blocking Remote Manual Synchronism Check Required Interlock bypass Three Pole Auto Reclose - Dead time - Reclaim time Synchronism Check for Auto-Reclose - Voltage differential - Angle differential - Frequency differential - Undervoltage Blocking Live Line Lockout Voltage Interlock Single Pole Auto Reclose - Dead time - Reclaim time Phase discrepancy * *if required by CB type Required (initiated by HYTS/APD No.1 500kV Line protection) Required (initiated by HYTS/APD No.1 500kV Line protection) Not Required Not Required Required (initiated by HYTS/APD No.1 500kV Line protection) CB trip on discrepancy Table 4.2.2: Circuit Breaker Controls Circuit Breaker: MLTS No.1 Line / HYTS/APD No.1 Line CB (Node GG HH; refer to SLD) Control Requirement Setting Manual synchronising Required Remote Manual Synchronism Check Interlock Required - Voltage differential - Angle differential - Frequency differential

8 Page No: 8 of 16 Circuit Breaker: MLTS No.1 Line / HYTS/APD No.1 Line CB (Node GG HH; refer to SLD) Control Requirement Setting - Undervoltage Blocking Remote Manual Synchronism Check Required Interlock bypass Three Pole Auto Reclose - Dead time - Reclaim time Synchronism Check for Auto-Reclose - Voltage differential - Angle differential - Frequency differential - Undervoltage Blocking Live Line Lockout Voltage Interlock Single Pole Auto Reclose - Dead time - Reclaim time Phase discrepancy * *if required by CB type Required (initiated by MLTS No.1 500kV Line or HYTS/APD No.1 500kV Line protection) Required (initiated by MLTS No.1 500kV Line protection or HYTS/APD No.1 500kV Line protection) Not Required Not Required Required (initiated by MLTS No.1 500kV Line or HYTS/APD No.1 500kV Line protection) CB trip on discrepancy Table 4.2.3: Circuit Breaker Controls Circuit Breaker: MLTS No.1 Line / No.1 Bus CB (Node AA GG; refer to SLD) Control Requirement Setting Manual synchronising Required Remote Manual Synchronism Check Interlock Required - Voltage differential - Angle differential - Frequency differential - Undervoltage Blocking Remote Manual Synchronism Check Required Interlock bypass Three Pole Auto Reclose - Dead time - Reclaim time Synchronism Check for Auto-Reclose - Voltage differential - Angle differential - Frequency differential - Undervoltage Blocking Live Line Lockout Voltage Interlock Single Pole Auto Reclose - Dead time - Reclaim time Phase discrepancy * 4.3 SF6 Trip Signals Required (initiated by MLTS No.1 500kV Line protection) Required (initiated by MLTS No.1 500kV Line protection) Not Required Not Required Required (initiated by MLTS No.1 500kV Line protection) CB trip on discrepancy If a SF6 Auto De-energisation trip signal is provided by SPI PowerNet, the successful Tenderer must ensure that all of the TRTS assets that are needed to operate to isolate the HYTS/APD No.1 500kV

9 Page No: 9 of 16 Line isolate the HYTS/APD No 1 500kV Line within the time given in Table from the receipt of the signal at the interface. Table 4.3.1: Maximum Operation Times Station Milliseconds TRTS Alarms The successful Tenderer must provide alarms identified in Table 4.3 for all plant located at the TRTS. Table 4.4: Alarms Requirement Alarms relating to protection or devices relating to protection where such protection would impact on power system security Communications (including RTU, if required) Fire (if applicable) any other control and protection alarms in accordance with good electricity industry practice for the types of plant provided in the station 4.5 Instrumentation Accuracy The successful Tenderer must ensure that the overall errors of measurements are less than: 1.0% of range for current and voltage measurements, and 2.0% for other measurements Ranges The successful Tenderer must provide instrumentation (at the Shared Network Interface) as listed in Table 4.5. Table 4.5: Instrumentation ranges Plant Quantity Required ranges No kv Bus Voltage (3-phase) kv Frequency Hz No kv Bus Voltage (3-phase) kv Frequency Hz MLTS No.1 Line Current (3-phase) 0-3 ka Active power TB FB GW Reactive power TB FB GVAr Voltage (3-phase) kv HYTS/APD No.1 Line Current (3-phase) 0-3 ka Active power TB FB GW Reactive power TB FB GVAr Voltage (3-phase) kv MLTS No.1 Line /No.1 Bus 500kV CB Current (3-phase) 0-3 ka HYTS/APD No.1 Line / No.2 Bus 500kV CB Current (3-phase) 0-3 ka MLTS No.1 Line / HYTS/APD No.1 Line 500kV CB Current (3-phase) 0-3 ka

10 Page No: 10 of Voltage sources The successful Tenderer must ensure that voltage representations of each 500kV Line are established. These voltage representations must be provided from two independently supplied voltage sources through automatic potential selection. These voltage sources, selected from appropriate and suitably switched (via CB or ROI or both auxiliary switches) Line, 500kV Busbar and 500kV Gen Transformer, are required for instrumentation, monitoring and control systems. 4.7 High Speed Monitoring (HSM) Facilities The successful Tenderer must transmit all the inputs in relation to the HSM facility, provided by the Proponent Generator at the interface, to SPI PowerNet at the Shared Network Interface. 4.8 Quality of Supply Monitoring (QOSM) Facilities The successful Tenderer must transmit all the inputs in relation to the QOSM facility, provided by the Proponent Generator at the interface, to SPI PowerNet at the Shared Network Interface. 4.9 Auxiliary Supplies AC Supplies for Shared Network Facilities The successful Tenderer must ensure that three independent and appropriately sized AC supplies are available for the Shared Network assets at TRTS. Acceptable sources include: Transformer tertiary windings. Two feeder supplies from different substations. There should not be loss of supply due to a single event. Diesel generator. Portable generators are acceptable provided the portable units can be connected and operated before expiration of battery capability. The successful Tenderer may negotiate with the Proponent Generator at TRTS or with SPI PowerNet for the provision of AC supplies at the interface or otherwise must establish its own AC supplies. The successful Tenderer must submit the AC Supply design to AEMO for approval DC Supplies for Shared Network facilities The successful Tenderer must ensure that two independent and appropriately sized DC supplies are available for the Shared Network assets at TRTS. The successful Tenderer must ensure that these DC auxiliary supplies meet the requirements in Table and Table The successful Tenderer may negotiate with the Proponent Generator at TRTS for the provision of DC supplies at the interface or otherwise must establish its own DC supplies. Table 4.9.1: DC Supply Requirements Requirement DC supplies must be provided from batteries. The batteries are required to be duplicated. Segregation of X and Y supplies to equipment is required. Table 4.9.2: DC Supply battery load life expectancy Battery life expectancy Main Batteries: 8 hours plus 2 open and 1 close operations for each CB including 2 open and 1 close operation for each ROI Communication Supplies: 10 hours

11 Page No: 11 of Over-voltage protection scheme Under certain abnormal operating conditions, the successful Tenderer s asset may be exposed to voltage conditions in excess of those nominated in S5.1.4 of the NER. The successful Tenderer must ensure that a duplicated over-voltage protection scheme is implemented to reduce the TRTS voltage back to the nominal operating level. The over-voltage scheme must detect an over-voltage at TRTS, while the MLTS-TRTS No.1 500kV Line is open at the MLTS end. This condition may result in an over-voltage condition as depicted in Table Table : Maximum Voltage Conditions Voltage Level Duration 580 TRTS No.1 and No kv Bus 30 minutes The successful Tenderer must ensure that the over-voltage protection scheme will trip the MLTS-TRTS No.1 500kV Line CBs at TRTS, if all of the following conditions are satisfied: - MLTS-TRTS No.1 500kV Line CBs detected open at MLTS; - the TRTS 500kV voltage is detected above a threshold (adjustable in the range of 550 kv to 600 kv with a 2.5 kv resolution); and - the over-voltage is detected for a time (adjustable continuously in the range 1 to 30 seconds). Table summarises the over-voltage protection control scheme. Table : Trip signalling requirements Initiated by over-voltage protection scheme at TRTS Initiate Conditions Output 1 MLTS-TRTS No.1 500kV Line open at MLTS end + over-voltage Trip MLTS-TRTS No.1 500kV Line detected at TRTS for a pre-set time (TRTS end only) The successful Tenderer must ensure that conceptual design of the over-voltage scheme is submitted to AEMO for comments. 5. Remote Monitoring and Control from TOC The successful Tenderer must provide or utilise the quantities identified in Table 5.1 at the Shared Network Interface, where they will be communicated between TRTS and TOC by SPI PowerNet. Table 5.1: Remote Monitoring and Control quantities to be communicated to and from TOC Quantities Controls MLTS No.1 Line / HYTS/APD No.1 Line CB open/close; MLTS No.1 Line / HYTS/APD No.1 Line CB ROIs open/close; MLTS No.1 Line / No.1 Bus CB open/close; MLTS No.1 Line / No.1 Bus CB ROIs open/close; HYTS/APD No.1 Line / No.2 Bus CB open/close; HYTS/APD No.1 Line / No.2 Bus CB ROIs open/close. Status Indications All 500 kv CBs open / closed; All 500 kv ROIs open / closed; SPAR On/Off; TPAR On/Off. Instrumentation As per Table 4.5 The successful Tenderer must ensure that any controls, status indications and instrumentation required to be transmitted between the Proponent Generator and TOC are transmitted to the interface.

12 Page No: 12 of Voltage Unbalance Monitoring AEMO requires the installation of permanent equipment to enable the ongoing monitoring of unbalance on the 500 kv transmission corridor between Victoria and South Australia. This section outlines the requirements for installation of unbalance monitoring facilities, consisting of unbalance measuring devices ( Monitors ), auxiliary supplies, voltage sources and current sources, and for provision of measured data to AEMO. 6.1 Services to be provided The successful Tenderer must provide facilities to enable the measurement of unbalance on each 500kV Line section, and must ensure that: 1. the facilities are designed, installed, calibrated and commissioned to monitor positive and negative sequence current and voltage, and voltage and current unbalance 2. Monitors comply with the requirements outlined in Table the facilities are calibrated such that the overall errors of measurement of the facilities are no greater than those specified in Table measured data is provided to AEMO as specified in Table Monitoring requirements The successful Tenderer must ensure that monitoring provided as part of this project complies with the requirements outlined in Table 6.2. Table 6.2: Monitoring requirements Requirement Measures and stores each rms average phase to phase voltage (magnitude and angle) at a minimum sampling rate of 150 Hz Measures and stores each rms average phase current (magnitude and angle) at a minimum sampling rate of 150 Hz Calculates and stores the following instantaneous quantities at a minimum sampling rate of 150 Hz: Voltage unbalance Negative sequence voltage (magnitude and angle) Positive sequence voltage (magnitude and angle) Zero sequence voltage (magnitude and angle) Current unbalance Negative sequence current (magnitude and angle) Positive sequence current (magnitude and angle) Measures or calculates, and stores, voltage magnitude and angle quantities with a resolution sufficient to satisfy the accuracy requirements of Table 6.3 Measures or calculates, and stores, current magnitude and angle quantities with a resolution sufficient to satisfy the accuracy requirements of Table 6.3 Measures or calculates, and stores, angles relative to: R-W phase for voltage measurements R-N phase for sequence voltage calculations R-phase for current measurements or sequence current calculations Time stamps each measurement with a maximum error of ±1 milliseconds Is capable of storing up to five (5) weeks of data 6.3 Accuracy of measurements The successful Tenderer must ensure that the overall errors of measurement of the facilities are not greater than those specified in Table 6.3.

13 Page No: 13 of 16 Table 6.3: Calibration of Facilities (required accuracy of measurement) Quantity Required accuracy Over the range Phase to phase voltage - magnitude ±0.05% of nominal kv (L-L) Phase to phase voltage angle ± kv (L-L) Sequence voltage magnitude ±0.05% of nominal 450/sqrt(3) kv to 550/sqrt(3) kv (L-N) Sequence voltage angle ± /sqrt(3) kv to 550/sqrt(3) kv (L-N) Phase current - magnitude ±0.05% of full scale A Phase current angle ± A Sequence current - magnitude ±0.1% of full scale A Sequence current - angle ± A 6.4 Provision of data to AEMO AEMO requires data at regular intervals to allow assessment of unbalance before and after establishment of new generation Regular provision of data to AEMO The successful Tenderer must provide data to AEMO: a) as identified in Table 6.4.1; b) in a readily usable format such as Excel, or otherwise in a proprietary format, with the proprietary software included in the project delivery; c) at intervals of no longer than five (5) Business Days 1 ; d) via a process that does not require manual intervention; e) via a method of delivery such as or SPI PowerNet communications facilities (B2B process). Table 6.4.1: Data to be provided to AEMO Quantity Phase to phase voltage - magnitude Phase to phase voltage angle (relative to R-W phase to phase voltage) Positive sequence voltage - magnitude Positive sequence voltage angle (relative to R-W phase to phase voltage) Negative sequence voltage - magnitude Negative sequence voltage angle (relative to R-W phase to phase voltage) Phase current - magnitude Phase current angle (relative to R-phase current) Positive sequence current - magnitude Positive sequence current angle (relative to R phase current) Negative sequence current - magnitude Negative sequence current angle (relative to R phase current) Type Measured Measured Calculated Calculated Calculated Calculated Measured Measured Calculated Calculated Calculated Calculated The successful Tenderer must outline its strategy for data delivery in Table Table 6.4.2: Provision of measured data to AEMO Alternatives Period of use 1 As that term will be defined in the proposed Network Services Agreement

14 Page No: 14 of Availability considerations The successful Tenderer must ensure that continuous data records representing measured unbalance on the TRTS MLPS No 1 500kV Line and the TRTS HYTS/APD No 1 500kV Line are available for at least 90% of each month.

15 No kv Bus No kv Bus TRANSMISSION SERVICES Page No: 15 of 16 Attachment 1: A.1.1 Single Line Diagram TRTS connection MCWF EE II BB HYTS/APD No.1 LINE KK JJ MLTS No.1 LINE DD HH GG AA Shared Network Assets SPI works: Existing Shared Transmission Network Assets: Shared Network Assets Successful Tenderer: Connection Assets: Tarrone Terminal Station Proposed 500kV Single Line Diagram

16 Page No: 16 of 16 A.1.2 Single Line Diagram TRTS Connection Assets

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4. Branch Procedure Document No. Issue No. : : CEOP8012 5 Approved By : Specialist Engineering NETWORK : Manager Approval Date Review Date : : 29/06/2018 29/06/2021 (Supersedes CEOP8012, Generation Connection:

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet Reference: ZD23 Version: 1.1 Issue date: 15 May 2014 Contents 1 Scope... 3 2 Deer Park Terminal

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination GSU Phase Overcurrent (51T), GSU Ground Overcurrent (51TG), and Breaker Failure (50BF) Protection System Protection and Control Subcommittee

More information

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V Version: 1 Issued: March 2014 Owner: Electrical Networks Asset

More information

SRAS GUIDELINES FOR SYSTEM RESTART ANCILLARY SERVICES INCORPORATING: SRAS DESCRIPTION SRAS ASSESSMENT GUIDELINES SRAS QUANTITY GUIDELINES

SRAS GUIDELINES FOR SYSTEM RESTART ANCILLARY SERVICES INCORPORATING: SRAS DESCRIPTION SRAS ASSESSMENT GUIDELINES SRAS QUANTITY GUIDELINES FOR SYSTEM RESTART ANCILLARY SERVICES INCORPORATING: SRAS DESCRIPTION SRAS ASSESSMENT GUIDELINES SRAS QUANTITY GUIDELINES BOUNDARIES OF ELECTRICAL SUB-NETWORKS SRAS TENDER GUIDELINES PREPARED BY: System

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Specification Voltage Limiting Device

Specification Voltage Limiting Device Engineering Specification Electrical Networks L1-CHE-SPE-152 Specification Voltage Limiting Device Version: 1 Issued: 20 th April 2018 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering,

More information

RMS Product Presentation

RMS Product Presentation RMS Product Presentation THE RELAY SPECIALISTS relay monitoring systems pty ltd www.rmpl.com.au Relay Monitoring Systems Pty Ltd 6 Anzed Court - Melbourne - Australia Manufacturing in Australia Company

More information

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation 111 Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation Z. Gajić (ABB, Sweden) JP Wang / PW Gong / YS Xu (ABB China) ZX Zhou (CERPI, China) Summary Power utilities

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

STCP 04-3 Issue 005 Real Time Data Provision

STCP 04-3 Issue 005 Real Time Data Provision STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish

More information

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection 1 Process PG&E Order No. 754 Analysis Receive Bus List from Planning that Meet the Criteria in Table A Protection Computes Actual Clearing

More information

PROTECTION REQUIREMENTS OF EMBEDDED GENERATORS < 5 MVA (LV + HV UP TO 22KV)

PROTECTION REQUIREMENTS OF EMBEDDED GENERATORS < 5 MVA (LV + HV UP TO 22KV) PROTECTION REQUIREMENTS OF EMBEDDED GENERATORS < 5 MVA (LV + HV UP TO 22KV) Standard Operating Procedures Document number SOP 11-16 Issue number 3 Status Approver Approved Peter Grove Date of approval

More information

MiCOM Agile P746. Grid Solutions. Key Benefits. Numerical Busbar Protection. A Combination of Speed, Security and Selectivity. About MiCOM P40 Agile

MiCOM Agile P746. Grid Solutions. Key Benefits. Numerical Busbar Protection. A Combination of Speed, Security and Selectivity. About MiCOM P40 Agile GE Grid Solutions MiCOM Agile P746 Numerical Busbar Protection The MiCOM Agile P746 centralized numerical busbar protection provides complete protection for all voltage levels up to extra voltage busbar

More information

POWER SYSTEM DATA COMMUNICATION STANDARD

POWER SYSTEM DATA COMMUNICATION STANDARD POWER SYSTEM DATA COMMUNICATION STANDARD PREPARED BY: AEMO Systems Capability VERSION: 2 EFFECTIVE DATE: 1 December 2017 STATUS: FINAL Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au

More information

IMP/ 001 / 014 Policy for the Protection of Distribution Networks

IMP/ 001 / 014 Policy for the Protection of Distribution Networks Version:- 1.1 Date of Issue:- July 2016 Page 1 of 39 IMP/ 001 / 014 Policy for the Protection of Distribution Networks 1. Purpose The purpose of this document is to detail the network protection philosophy

More information

Substation Automation Products. High impedance differential busbar protection REB650 Relion 650 series

Substation Automation Products. High impedance differential busbar protection REB650 Relion 650 series Substation Automation Products High impedance differential busbar protection REB650 Relion 650 series One IED for a wide range of high impedance differential protection applications ABB introduces a new,

More information

Description of the Application Process for Small Embedded Generators

Description of the Application Process for Small Embedded Generators Description of the Application Process for Small Embedded Generators This document describes the Application Process for Small Embedded Generators (as required under section 5.3.3A of the National Electricity

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series Substation Automation Products Generator protection REG670/650 Relion 670 and 650 series A new protection standard for your valuable assets Based on ABB s extensive experience, REG670 and REG650 IEDs (Intelligent

More information

Bus Protection Application Challenges

Bus Protection Application Challenges Bus Protection Application Challenges KN Dinesh Babu - Megger JC Theron, Lubomir Sevov GE Grid Solutions 2017 Texas A&M Protective Relay Conference Content Introduction Application Challenges Increase

More information

SEL-487B. A Powerful Solution for Busbar Differential Protection. Bus Differential and Breaker Failure Relay

SEL-487B. A Powerful Solution for Busbar Differential Protection. Bus Differential and Breaker Failure Relay Bus Differential and Breaker Failure Relay A Powerful Solution for Busbar Differential Protection Features and Benefits Select the for the differential protection of busbar systems with up to 18 terminals.

More information

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU SOUTHERN REGIONAL POWER COMMITTEE BENGALURU Additional Agenda for the 80 th Meeting of Protection Coordination Sub-Committee of SRPC to be held on 20-21 December, 2018 1. Grid Occurrences Additional Grid

More information

Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014

Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014 Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014 PREPARED BY: Systems Capability DATE: 6 June 2014 STATUS: FINAL

More information

Busbar protection REB 670

Busbar protection REB 670 Gunnar Stranne Busbar protection REB 670 Rio de Janeiro April 23-25, 2006 ABB Power Technologies AB 2 3 4 REB 500 is enabled for use with IEC61850 communication Benefits of REB 670 outstanding features

More information

Mehta Tech, Inc. TRANSCAN IED For Multi-Function, Multi-Speed Recording

Mehta Tech, Inc. TRANSCAN IED For Multi-Function, Multi-Speed Recording Mehta Tech, Inc. TRANSCAN IED For Multi-Function, Multi-Speed Recording Two independent, simultaneously operating recorders in one package Triggering on input quantities and calculated values, such as

More information

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5 Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System

More information

ELECTRICAL, INSTRUMENTATION & CONTROL SYSTEMS

ELECTRICAL, INSTRUMENTATION & CONTROL SYSTEMS ELECTRICAL, INSTRUMENTATION & CONTROL SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017 ELECTRICAL PLANT CONCEPT The electrical equipment, depending

More information

MiCOM P124 T&D. Self and Dual Powered Overcurrent Relays

MiCOM P124 T&D. Self and Dual Powered Overcurrent Relays PROTECTION MiCOM P124 Self and Dual Powered Overcurrent Relays MiCOM P124 are numerical relays designed to offer complete overcurrent protection without requiring any external auxiliary supply. They can

More information

GUIDELINES FOR SHARED TRANSMISSION CONNECTIONS IN VICTORIA

GUIDELINES FOR SHARED TRANSMISSION CONNECTIONS IN VICTORIA GUIDELINES FOR SHARED TRANSMISSION CONNECTIONS IN VICTORIA PREPARED BY: Transmission Services VERSION: 2.0 RELEASE DATE: 14 December 2011 FINAL Version Release History Version Date Approved 1.0 3 Jun 11

More information

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES 1. Introduction Real time monitoring and control is necessary to ensure public and employee safety and to protect the integrity

More information

Substation Automation Products. Line differential protection RED670 Relion 670 series

Substation Automation Products. Line differential protection RED670 Relion 670 series Substation Automation Products Line differential protection RED670 Relion 670 series For maximum reliability of your power system The RED670 IED (Intelligent Electronic Device) is designed for protection,

More information

ELG4125: System Protection

ELG4125: System Protection ELG4125: System Protection System Protection Any power system is prone to 'faults', (also called short-circuits), which occur mostly as a result of insulation failure and sometimes due to external causes.

More information

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field DTRV-EP COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS Application field The DTRV type of complex transformer protection is designed to protect 120 kv / medium voltage transformers,

More information

MiCOM P721 & P723. Numerical High Impedance Differential Relay. Protection Relays. Customer Benefits

MiCOM P721 & P723. Numerical High Impedance Differential Relay. Protection Relays. Customer Benefits 01 MiCOM P721 & P723 Numerical High Impedance Differential Relay The new P72x high impedance differential protection series provides an independent and simple high impedance differential protection solution

More information

SPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS. G. Steynberg

SPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS. G. Steynberg SPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS G. Steynberg Siemens AG; Energy Sector, Energy Automation, Nuremberg 1. INTRODUCTION The breaker-and-a-half configuration

More information

Non-conventional instrument transformers Advanced GIS substations with IEC LE process bus

Non-conventional instrument transformers Advanced GIS substations with IEC LE process bus Non-conventional instrument transformers Advanced GIS substations with IEC 61850-9-2LE process bus Content Towards the digital GIS substations Optimized substation design NCIT for gas-insulated switchgears

More information

Design Guidelines for SCADA & DSA

Design Guidelines for SCADA & DSA Design Guidelines for SCADA & 28 th February 2017 28 FEBRUARY 2017 ISSUE 4 PREPARED BY: PRINCIPAL ENGINEER SCADA & MANAGER AUTHORISED BY: MANAGER SECONDARY SYSTEMS DOCUMENT NUMBER: ISSUE 4 This plan is

More information

Landsnet-Icegrid. Requirements for protection and control systems. Principles for the Icelandic power transmission network.

Landsnet-Icegrid. Requirements for protection and control systems. Principles for the Icelandic power transmission network. Landsnet-Icegrid Requirements for protection and control systems. Principles for the Icelandic power transmission network. Introduction.... 4 System requirements... 6 Validity:... 6 Requirements for protection:...

More information

Sapphire Wind Farm 330/33kV Substation

Sapphire Wind Farm 330/33kV Substation Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire

More information

11 kv Indoor Switchgear - SCADA Controlled

11 kv Indoor Switchgear - SCADA Controlled Specification 11 kv Indoor Switchgear - SCADA Controlled Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network owned or managed by the

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

Using the Bitronics 70 Series to Improve Local Monitoring and Control

Using the Bitronics 70 Series to Improve Local Monitoring and Control Automate a Substation and Preserve the Electromechanical Relay Investment Part Two of Four Using the Bitronics 70 Series to Improve Local Monitoring and Control Paul Grabowski - Bitronics Senior Application

More information

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)] Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected

More information

S&C IntelliRupter PulseCloser Fault Interrupter Overhead Source-Transfer Application

S&C IntelliRupter PulseCloser Fault Interrupter Overhead Source-Transfer Application Overhead Source-Transfer Application Detailed Functional Specification Guide 1.0 GENERAL 1.01 The automated distribution fault-interrupting system shall conform to the following specification. 1.02 The

More information

JEA. Facility Connection Requirements

JEA. Facility Connection Requirements JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities

More information

Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A

Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A Public Table of contents 1 Connection Framework... 3 2 Connection Types...

More information

REAL-TIME MONITORING DATA SPECIFICATION

REAL-TIME MONITORING DATA SPECIFICATION REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...

More information

POWER GRID AUTOMATION. Pág.. n. RMU Automation

POWER GRID AUTOMATION. Pág.. n. RMU Automation POWER GRID AUTOMATION RMU Automation Distribution Network Non-Controlled Secondary Distribution Systems Distribution Network RMU Automation - Levels RMU Automation - RTU / FRTU SMART CONTROLLER Monitoring

More information

Bus Bar Protection Applications Seminar

Bus Bar Protection Applications Seminar Bus Bar Protection Applications Seminar April 3, 2006 College Station TX ZONE 1 23 24 ZONE 2 1 2 11 12 13 22 ZONE 1 ZONE 2 23 24 1 2 3 21 22 Presentation Outline Introduction to Bus Bar Protection Bus

More information

7SG26 Tau Autoreclose and synchronization Answers for energy

7SG26 Tau Autoreclose and synchronization Answers for energy Reyrolle Protection Devices SG Tau Autoreclose and synchronization Answers for energy SG Tau Autoreclose and synchronization Fig 1. Tau relay in size 1 case Description The Tau range of auto-reclosing

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR

More information

TRIP OF CLARE SOUTH TOWNSVILLE SOUTH 132 KV TRANSMISSION LINE ON 24 JUNE 2015

TRIP OF CLARE SOUTH TOWNSVILLE SOUTH 132 KV TRANSMISSION LINE ON 24 JUNE 2015 TRIP OF CLARE SOUTH TOWNSVILLE SOUTH 132 KV TRANSMISSION LINE ON 24 JUNE 2015 AN AEMO POWER SYSTEM OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICTY MARKET Published: October 2015 VERSION RELEASE HISTORY

More information

SIPROTEC 5 Application Note. Breaker-and-a-half solutions. SIP5-APN-002, Edition 2.

SIPROTEC 5 Application Note. Breaker-and-a-half solutions. SIP5-APN-002, Edition 2. -and-a-half solutions SIP5-APN-002, Edition 2 www.siemens.com/protection SIPROTEC 5 Application Note -and-a half solutions SIP5-APN-002, Edition 2 -and-a-half solution Content 1 -and-a-half solutions 3

More information

Application Notes on Generator Protection Schemes

Application Notes on Generator Protection Schemes Application Notes on Generator Protection Schemes Single Line Diagram Examples 1. Introduction The application notes provide selected single line diagrams for the SIPROTEC 4 generator protection device

More information

Substation Automation Products. Transformer protection RET670/650 Relion 670 and 650 series

Substation Automation Products. Transformer protection RET670/650 Relion 670 and 650 series Substation Automation Products Transformer protection RET670/650 Relion 670 and 650 series For reliable protection and control of all types of power transformers and reactors The RET670/650 IEDs (Intelligent

More information

Company Directive ENGINEERING SPECIFICATION EE SPEC: 136

Company Directive ENGINEERING SPECIFICATION EE SPEC: 136 Company Directive ENGINEERING SPECIFICATION EE SPEC: 136 Ancillary Electrical Equipment for Use in Conjunction with Switchgear and Protection/Control Panels NOTE: The current version of this document is

More information

Numerical Protective and Management Relays

Numerical Protective and Management Relays Numerical Protective and Management Relays Presented at: The Institution of Engineers (India) Andaman and Nicobar State Centre Port Blair Dr. H. K. Verma Deputy Director and Professor of Electrical Engineering

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

SACE Emax 2 Specification guide

SACE Emax 2 Specification guide SACE Emax 2 Specification guide Specification Number: 26 01 20.17 Product Name: LOW VOLTAGE POWER CIRCUIT BREAKERS PART 1 GENERAL NOTE: ( ) Indicates option or a selection is to be made for quantity or

More information

SIGMA. Advanced Generator Protection and Control. Short Form Catalogue

SIGMA. Advanced Generator Protection and Control. Short Form Catalogue Short Form Catalogue SIGMA Advanced Generator Protection and Control Generator protection, synchronizing and load sharing Power management system Easy to install and commission Control most governors/avrs

More information

Document C0. Use for:

Document C0. Use for: Date: July 27, 2015 Document C0 Use for: Connection of Electric Generation that will operate with an Open Transition (Category 1) between the Ameren System and the Generator or operate with a Synchronized

More information

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage

More information

High-speed transformer differential protection for up to five terminals

High-speed transformer differential protection for up to five terminals Transformer Protection Relay High-speed transformer differential protection for up to five terminals Advanced differential protection and three restricted earth fault (REF) elements minimize damage and

More information

Substation Automation Products. Bay control REC670/650 Relion 670 and 650 series

Substation Automation Products. Bay control REC670/650 Relion 670 and 650 series Substation Automation Products Bay control REC670/650 Relion 670 and 650 series For optimized control and reliable operation of your switchyard The REC670 and REC650 Bay control IEDs (Intelligent Electronic

More information

Redundant Bus Protection Using High-Impedance Differential Relays. Josh LaBlanc

Redundant Bus Protection Using High-Impedance Differential Relays. Josh LaBlanc Redundant Bus Protection Using High-Impedance Differential Relays Josh LaBlanc Purpose Discuss the configuration of the bus under study, and touch on the needs for redundant protection on the bus. Briefly

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM April 13, 2007 LIPA Facility Connection Requirements TABLE OF CONTENT I. INTRODUCTION...1 II. REFERENCE

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

MiCOM P124. Self and Dual Powered Overcurrent Relays. Protection Relays

MiCOM P124. Self and Dual Powered Overcurrent Relays. Protection Relays 01 Self and Dual Powered Overcurrent Relays are numerical relays designed to offer complete overcurrent protection without requiring any external auxiliary supply. They can be applied to a wide variety

More information

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power 1. Abstract Dinesh Mithanthaya Design Manager, Horizon Power Higher capacity substation power transformers ( 5MVA),are

More information

MiCOM P122C Time-Overcurrent Protection

MiCOM P122C Time-Overcurrent Protection Protection Relays 01 MiCOM P122C Time-Overcurrent Protection Customer Benefits 1A/5A software setting 4 function keys Compact unit for flush and wall-surface mounting Comprehensive measurements Disturbance

More information

DRS-LIGHT. Device Description DRS-LP824. Digital Unit Decoupling Relay Type DRS-LP824. Device Description DIL

DRS-LIGHT. Device Description DRS-LP824. Digital Unit Decoupling Relay Type DRS-LP824. Device Description DIL DRS-LIGHT Digital Unit Decoupling Relay Type DRS-LP824 Device Description Edition:09.05.2008 SLLR_LP824_e.doc Page 1 /10 CAUTION Installing, commissioning and operating of this product may be performed

More information

Chapter 2 State Estimation and Visualization

Chapter 2 State Estimation and Visualization Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation

More information

Awareness of the Situation

Awareness of the Situation 17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog

More information

Overcurrent and Arc Protection by Reyrolle Alexander Erokhin. 21, 2017 I Berlin

Overcurrent and Arc Protection by Reyrolle Alexander Erokhin. 21, 2017 I Berlin Overcurrent and Arc Protection by Reyrolle Alexander Erokhin VAR Partner Day September 20-21, 21, 2017 I Berlin Reyrolle Product Range by SIEMENS Challenges We Meet for our Customers Easy-to-use protection

More information

ICX-CMOS-E-2006 Electrical / I&C Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ICX-CMOS-E-2006 Electrical / I&C Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 102904-ICX-CMOS-E-2006 Electrical / I&C Engineer Holds a B. Sc. in Electronics & Electrical Communications Engineering and has over 9 years hands-on experience working in I&C field. Has extensive experience

More information

DGSZV-EP DIGITAL GALVANIC LONGITUDINAL DIFFERENTIAL PROTECTION. Application field

DGSZV-EP DIGITAL GALVANIC LONGITUDINAL DIFFERENTIAL PROTECTION. Application field DGSZV-EP DIGITAL GALVANIC LONGITUDINAL DIFFERENTIAL PROTECTION The digital galvanic longitudinal differential protection of type DGSZV-EP is part of device family named EuroProt. This short description

More information

ADVANCED. Protection Co-ordination. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

ADVANCED. Protection Co-ordination. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E ADVANCED Protection Co-ordination H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae ictd@ictd.ae Course Introduction: Distribution Networks are designed to serve loads in a

More information

Important Considerations in Testing and Commissioning Digital Relays

Important Considerations in Testing and Commissioning Digital Relays Important Considerations in Testing and Commissioning Digital Relays Drew Welton, Beckwith Electric Co. Inc. Will Knapek, OMICRON electronics Corp. USA Justification Digital technology in protection relays

More information

TECHNICAL SPECIFICATION FOR A 1500V DC SWITCHGEAR ASSEMBLY

TECHNICAL SPECIFICATION FOR A 1500V DC SWITCHGEAR ASSEMBLY Engineering Specification Electrical TECHNICAL SPECIFICATION FOR A 1500V DC SWITCHGEAR ASSEMBLY Version: 2 Issued: October 2017 Owner: Chief Engineer Approved By: Phil Ellingworth Chief Engineer PRINTOUT

More information

MMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A

MMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A AUTOMATION MMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A GRID Note: The technical manual for this device gives instructions for its installation, commissioning,

More information

Siprotec 7ST61 / 7ST63

Siprotec 7ST61 / 7ST63 Siprotec / Numerical overhead contact line protection for AC traction power supply siemens.de/rail-electrification The numerical overhead contact line protection relay Siprotec / is a selective and quick

More information

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68 The Challenges and Opportunities Faced by Utilities using Modern Protection and Control Systems - Paper Unavailable Trends in Protection and Substation Automation Systems and Feed-backs from CIGRE Activities

More information

Power Systems Communications Implementation of IEC61850 in a Substation Environment

Power Systems Communications Implementation of IEC61850 in a Substation Environment Power Systems Communications Implementation of IEC61850 in a Substation Environment 26 October 2009 Reference VEE4700-01 Revision 0 Document Control Document ID: DOCUMENT1 Rev No Date Revision Details

More information

MiCOM P521. Fast Feeder Differential Protection

MiCOM P521. Fast Feeder Differential Protection 01 Fast Feeder Differential Protection The relay provides high-speed two-ended current differential unit protection of overhead lines and underground cables in applications such as ring mains and parallel

More information

Hybrid STATCOM / SVC Workgroup 15 th May 2014

Hybrid STATCOM / SVC Workgroup 15 th May 2014 Hybrid STATCOM / SVC Workgroup 15 th May 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System PUBLIC SERVICE OF NEW HAMPSHIRE Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System September 2013 1.0 Purpose of this document Public Service of New Hampshire

More information

BREAKER FAILURE PROTECTION

BREAKER FAILURE PROTECTION 0 th Annual HANDS-ON RELAY SCHOOL March 11-15, 201 REAKER FAILURE PROTECTION brent.c@relayapplication.com OUTLINE Protection System Failures and reaker Failures Protection versus Relaying Relay Schemes

More information

Configuration and Interoperability Guide for IEC for the SEL-751 Feeder Protection Relay. July 10, 2015

Configuration and Interoperability Guide for IEC for the SEL-751 Feeder Protection Relay. July 10, 2015 Configuration and Interoperability Guide for IEC 60870-5-103 for the SEL-751 Feeder Protection Relay July 10, 2015 Contents 1 Interoperability... 3 1.1 Physical Layer... 3 Electrical Interface... 3 Optical

More information

MESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR

MESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR 22 kv Version: 2 Issued: 19 th December 2016 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering - Electrical

More information

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-0150 LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES LPN This standard provides guidelines for the development of the 33kV distribution

More information

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical Issued for Review Section 26 28 16.01 Air Circuit Breakers Page 1 of 7 PART 1 GENERAL 1.1 GENERAL.1 This specification serves to define requirements for a replacement of low voltage circuit breaker of

More information

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements Introduction to Bus Protection By Matt Horvath, P.E. November 6, 2018 Electrical Buses Physical and Electrical Junction A bus is a critical element of a power system, as it is the point of convergence

More information

MiCOM P521. Fast feeder differential protection

MiCOM P521. Fast feeder differential protection 01 Fast feeder differential protection The relay provides high-speed two-ended current differential unit protection of overhead lines and underground cables in applications such as ring mains and parallel

More information