CHAPTER 4 INCREASE IN CRITICAL CLEARING TIME USING SVC AND STATCOM IN TNEB

Size: px
Start display at page:

Download "CHAPTER 4 INCREASE IN CRITICAL CLEARING TIME USING SVC AND STATCOM IN TNEB"

Transcription

1 80 CHAPTER 4 INCREASE IN CRITICAL CLEARING TIME USING SVC AND STATCOM IN TNEB 4.1 INTRODUCTION The preliminary study conducted to evaluate the potential due to the application of SVC and STATCOM on the TNEB 400 kv transmission network, generators and their respective step-up transformers directly connected to 400 kv substations in Tamil Nadu and nearby 400 kv substations (Trivendrum, Chittoor etc.,) is presented in this chapter. The study compares the results and effectiveness of SVC and STATCOM for enhancing the transient stability of the system through the critical clearing time using MiPower simulation software. The fault clearing time is increased up to the critical clearing time to test the robustness of the system and the effectiveness of the SVC and STATCOM. 4.2 LITERATURE REVIEW An occurrence of three phase fault on the bus and clearance of the fault within a short period of time (up to 100 ms) does not represent a large risk to the power system in terms of transient stability. For this reason, it is necessary to ensure that generators operating in the electric power system have a critical clearing time higher than 100 ms. The electric power system instability can be interpreted using various methods depending on the system configuration and operational

2 81 status. Traditionally, the question of stability has been connected to maintain synchronous operations. The production of electricity is secured primarily using synchronous generators. For this reason, it is important to secure their synchronism and therefore the question of stability has mainly hinged on the transient stability of synchronous machinery and on the relationship between the active power and the rotor angle of the generator. Electric power system instability can also appear even if synchronous operation of the generators is not interrupted (Eleschova et al 2010). On 1st July 1957, TNEB came into being and has remained as the energy provider and distributor all these years. During the period, the Government has extended the electrical network to all villages and towns throughout the state. After fifty three years of journey, on 1st November 2010, TNEB restructured itself into TNEB Limited, Tamil Nadu Generation and Distribution Corporation (TANGEDCO) Limited and Tamil Nadu Transmission Corporation (TANTRANSCO) Limited. Ministry of Power, Government of India, has planned to supply Power for all by To achieve this, TANGEDCO Limited is making progress in generation and distribution sector. TNEB limited has completed the electrification of all villages and towns. To satisfy the energy needs of the state, TANGEDCO Limited has installed generating stations of capacity 10, 214 MW which includes state, central share and independent power producers. Besides, the state has installations in renewable energy sources like windmill up to 5400 MW. Due to the astronomical increase in the energy demand in future, the state has proposed new generation projects for the next five years. TANTRANSCO Limited has a total of 1309 substations with HT(High Tension) and EHT(Extra High Tension) lines to a length of 1.69 lakh km. The voltage levels in use in TANTRANSCO Limited are 400 kv,

3 kv, 110 kv and 66 kv. In order to evacuate bulk power from one region to another region, there is more scope for enhancing the transmission capability to 765 kv level and setting up of 800 kv High Voltage DC system. The Government of India has approved nondiscriminatory open access for the transmission system. The Government of Tamil Nadu has also permitted third party sale of power produced by independent power producer (IPPs), captive power plants (CPPs) and other private power producers through short term intra-state open access to HT consumers within Tamil Nadu. TANGEDCO has a consumer base of about lakh consumers. 100% rural electrification has been achieved. Per Capita consumption of Tamil Nadu is 1080 Units. To achieve reliable and quality power supply, and to minimize the loss of energy, Ministry of Power, Government of India, has launched the restructured APDRP (Accelerated Power Development and Reform Program) scheme under the eleventh five year plan ( power_scenario.pdf.). 4.3 PROBLEM STATEMENT Load growth, equipment outage, unplanned maintenance, aging of substation equipment and increasing stress on grid leads poor voltage profile, network overloading, increase in losses and thermal damage of the equipment. A better method to improve the utilization ratio of the existing electric network is expected. As the awareness of environmental protection is increasing, it becomes critical that the existing transmission and distribution resources can be fully utilized. As the system network grows in complexity and load consumption continues to increase, interface loading conditions are expected to worsen, resulting in more acute transient problem and may lead to disasters and blackouts, which have not only huge commercial loss, but also needs high restoring time. Here, Tamil Nadu 400 kv transmission network

4 83 and nearby interconnected 400 kv substations (Trivendrum, Chittoor etc.) are considered for the study. This has prompted the need to consider broad utilization of FACTS technology, including SVC and STATCOM. SVC and STATCOM can be inserted independently in the TNEB system to achieve control function including enhancement of the transient stability using MiPower simulation software. 4.4 GENERAL REPRESENTATION OF SVC AND STATCOM The representation of both SVC and STATCOM are discussed in sections 2.5 and 3.4 respectively. The SVC and STATCOM model used here is shown in Figures 4.1 and 3.2 respectively. 4.5 TNEB 400 kv TRANSMISSION NETWORK Tamil Nadu 400 kv transmission network and nearby interconnected substations (Trivendrum, Chittoor etc.) are considered for the purpose of identifying the critical clearing time at all 400 kv buses to ensure rapid fault clearance and thereby maintaining the transient stability. The system model includes the representation of thirty four 400 kv buses, eleven generators, eleven transformers etc. Transmission network (only 400 kv) of TNEB is modeled using MiPower. Transmission line parameters of various conductors (Moose and Zeebra) are used as per manufacturer s standard. Line length and type of conductor are considered as per information available in the Power Grid and Ministry of Power website. The generators directly connected to TNEB 400 kv transmission network are modeled along with the generator step-up transformers. The generator, AVR, TG and transformer data are given in the Tables 4.1 to 4.4 respectively. The block diagrams of type1 AVR and TG are depicted in Figures 4.2 and 4.3 respectively.

5 Vref[1] Max=0.529 T=0.2 T=0.003 Max=1 N[5] N[6] N[12] N[2] N[13] N[4] N[8] N[9] K=2.23 Min=-1 K = 1.04 Min= SVC Q Supply N[3] K = 1 N[7] T=0.003 N[10] Figure 4.1 Modeling of SVC 84

6 Table 4.1 Generator data in TNEB 400 kv transmission network Generator Name Rated MVA AVR Type TG No. Model type Rated Voltage(kV) P Schedule Q min Q max Neyveli Neyveli-Ext Kudamkulam Tuticorin-ST Tuticorin Ind-Bharath Coastal Ene Mettur Chennai JV North Chennai North Chennai ABAN Droop Constant 85

7 - - - Figure 4.2 Block diagram of type1 AVR 86

8 87 Table 4.2 Type1 AVR data in TNEB 400 kv transmission network Variable Description Data T rec Input rectifier time constant in s 0.05 K a Amplifier gain 200 T a Amplifier time constant in s 0.1 K e Exciter gain T e Exciter time constant in s 0.5 K f Regulator stabilizing circuit gain 0.05 T f Regulator stabilizing circuit time constant 0.5 V se1 Saturation function at 0.75 times maximum field voltage 0.06 V se2 Saturation function at maximum field voltage 0.3 V rmax Maximum amplifier voltage 1 V rmin Minimum amplifier voltage -1 E fdmax Maximum field voltage 4.3 E fdmin Minimum field voltage 0

9 - - Figure 4.3 Block diagram of TG 88

10 89 Table 4.3 TG data in TNEB 400 kv transmission network Variable Description Data Droop 0.04 P max Maximum power limit 1.1 P min Minimum power limit 0 C max Rate of valve opening 0.1 C min Rate of valve closing - 1 K 1 K 2 Power extraction at HP turbine K 3 K 4 Power extraction at IP turbine K 5 K 6 Power extraction at LP turbine 0.4 T 1 Phase compensation T 2 Phase compensation T 3 Servo time Constant 0.4 T hp HP section Time constant in s 0.26 T rh Reheat section Time constant in s 10 T lp LP section Time constant in s 999 T ip IP section Time constant (including reheater) in s 0.5

11 90 Table 4.4 Transformer data in TNEB 400 kv transmission network Sl. No. Bus Name MVA Rating Primary Voltage (kv) Secondary Voltage (kv) Zp.u. Taps(Min and Max) OCTC (Taps) 1 Neyveli and 9 OCTC(5) 2 Neyveli-Ext and 9 OCTC(5) 3 Kudamkulam and 9 OCTC(5) 4 Tuticorin- ST and 9 OCTC(5) 5 Tuticorin and 9 OCTC(5) 6 Ind-Bharath and 9 OCTC(5) 7 Coastal Ene and 9 OCTC(5) 8 Mettur and 9 OCTC(5) 9 Chennai JV and 9 OCTC(5) North Chennai North Chennai ABAN and 9 OCTC(5) and 9 OCTC(5) Single line diagram of the TNEB 400 kv transmission network system is shown in Figure A 1.2.

12 RESULTS WITH DISCUSSIONS Critical clearing time is the principal criterion for the assessment of transient stability. Fault should be cleared well within the critical clearing time to maintain the transient stability of the power system, even while critical clearing time is not the sufficient criterion to evaluate the transient stability when considering various scenarios of severe fault occurrence in the power system. The oscillation of generators is basically measured with respect to infinite bus / grid which are represented as slack bus. The oscillation level of the generator depends on the disturbance severity and its time duration. If the generator oscillation goes beyond 180 degrees, the generator loses its synchronism and will not be able to regain the steady state. That is, the generator will not be synchronous with rest of the system. Hence, 180 degrees is standardized as the transient stability limit. Since a severe fault (three phase fault) is assumed, the ability of the generator to remain in synchronism depends on the fault clearing time. The time to clear the fault is slowly increased up to the critical clearing time with the help of SVC and STATCOM. The effect of SVC and STATCOM on the transient stability of the power system is analyzed by creating three phase to ground fault at various buses using MiPower through the critical clearing time. By placing the SVC and STATCOM independently at Sholinganallur, Neyveli, Karaikudi and Salem 400 kv substations, the fault clearing time is increased up to the critical clearing time. Critical clearing time for the various buses with SVC at the 400 kv substations, are tabulated in Table 4.5 and compared with critical clearing time without SVC.

13 92 Table 4.5 Critical clearing time of various 400 kv buses with and without SVC Bus No. Bus Name Bus Description Without SVC Critical clearing time in ms SVC at Neyveli SVC at Sholinganallur SVC at Karaikudi SVC at Salem 402 ALAM_4 Alamanthi SVC_4 SVC MLKTYR Malekuttaiyur SHLGNR Sholinganallur PONDI_4 Pondicherry TRCHY_4 Trichy KARKDI Karaikudi MDRAI_4 Madurai KYTHR_4 Kaythar TM_WND TM_Wind TRNVL_4 Tirunelveli TRNDRM Trivandrum TRVLM_4 Tiruvelam SNGRPT Singarpet PGLR_4 Pugalur SALEM_4 Salem UDMLPT Udumalpet ARSR_4 Arasur KRMDI_4 Karmadai MVTPHA Muvattupuzha N_TRCHR N_Trichur HOSUR_4 Hosur Total Critical clearing time for the various buses with STATCOM at the 400 kv substations, are tabulated in Table 4.6 and compared with critical clearing time without STATCOM.

14 93 Table 4.6 Critical clearing time of various 400 kv buses with and without STATCOM Bus No. Bus Name Bus Description Without STATCOM Critical clearing time in ms STATCOM STATCOM at at Sholinganallur Neyveli STATCOM at Karaikudi STATCOM at Salem 402 ALAM_4 Alamanthi SVC_4 SVC MLKTYR Malekuttaiyur SHLGNR Sholinganallur PONDI_4 Pondicherry TRCHY_4 Trichy KARKDI Karaikudi MDRAI_4 Madurai KYTHR_4 Kaythar TM_WND TM_Wind TRNVL_4 Tirunelveli TRNDRM Trivandrum TRVLM_4 Tiruvelam SNGRPT Singarpet PGLR_4 Pugalur SALEM_4 Salem UDMLPT Udumalpet ARSR_4 Arasur KRMDI_4 Karmadai MVTPHA Muvattupuzha N_TRCHR N_Trichur HOSUR_4 Hosur Total Impact of FACTS device on the transient stability enhancement is analyzed with the help of critical clearing time. Critical clearing time at Alamanthi 400 kv substation without FACTS is 120 ms. Considering the relay delay time (40 ms) and circuit breaker opening time (30 ms) in the Alamanthi substation, the relay and circuit breaker fails to isolate the fault during N-1 contingency ( i.e during struck breaker operation - after struck breaker, all other breaker should open to isolate the fault) within the critical clearing time. However, with FACTS installation at various buses, the critical

15 94 clearing time is increased from 120 ms to around 150 ms. This increased cushion of 30 ms (1.5 cycle) will maintain the stability for three phase fault at Alamanthi even for N-1 contingency. The swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4 for a three phase fault at Alamanthi 400 kv substation with and without SVC are presented here. Figure 4.4 Swing curves of generators without SVC The swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4 for 120 ms duration of a three phase fault at Alamanthi 400 kv substation without SVC are shown in Figure 4.4. If the

16 95 fault clearing time exceeds 120 ms, the oscillations of generators exceed 180 degrees. Figure 4.5 Swing curves of generators with SVC at Sholinganallur SVC at Sholinganallur, increases the critical clearing time from 120 ms to 148 ms for a three phase fault at Alamanthi 400 kv substation. The swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4 for 148 ms duration of a three phase fault at Alamanthi 400 kv substation with SVC at Sholinganallur are shown in Figure 4.5. If the fault clearing time exceeds 148 ms, the oscillations of generators exceed 180 degrees.

17 96 Figure 4.6 Swing curves of generators with SVC at Neyveli SVC at Neyveli, increases the critical clearing time from 120 ms to 145 ms for a three phase fault at Alamanthi 400 kv substation. The swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4 for 145 ms duration of a three phase fault at Alamanthi 400 kv substation with SVC at Neyveli are shown in Figure 4.6. If the fault clearing time exceeds 145 ms, the oscillations of generators exceed 180 degrees.

18 97 Figure 4.7 Swing curves of generators with SVC at Karaikudi SVC at Karaikudi, increases the critical clearing time from 120 ms to 149 ms for a three phase fault at Alamanthi 400 kv substation. The swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4 for 149 ms duration of a three phase fault at Alamanthi 400 kv substation with SVC at Karaikudi are shown in Figure 4.7. If the fault clearing time exceeds 149 ms, the oscillations of generators exceed 180 degrees.

19 98 Figure 4.8 Swing curves of generators with SVC at Salem SVC at Salem, increases the critical clearing time from 120 ms to 149 ms for a three phase fault at Alamanthi 400 kv substation. The swing curves of generators in Neyveli-1, Neyveli-Ext, Kudamkulam, Tuticorin-ST4 for 149 ms duration of a three phase fault at Alamanthi 400 kv substation with SVC at Salem are shown in Figure 4.8. If the fault clearing time exceeds 149 ms, the oscillations of generators exceed 180 degrees. Without FACTS, the critical clearing time at Trichy 400 kv substation is 250 ms. With FACTS, this is improved to around 300 ms. This

20 99 will be certainly helpful to maintain the stability, when the backup protection isolates the fault due to primary relay failure. Similarly at all other buses, with FACTS devices the critical clearing time has increased or maintained for three phase to ground faults. The total critical clearing time of the system has significantly improved with the help of FACTS devices. 4.7 CONCLUSION The TNEB 400 kv transmission network is modeled using MiPower. The critical clearing time is found at various 400 kv buses of TNEB system and is tabulated. The proposed SVC and STATCOM model is placed independently at Sholinganallur, Neyveli, Karaikudi and Salem 400 kv substations to identify the critical clearing time of various 400 kv buses to ensure the rapid fault clearance and thereby maintaining the transient stability. The critical clearing time increases appreciably after placing the SVC and STATCOM independently in the TNEB 400 kv transmission network. This is shown in Tables 4.5 and 4.6. It is evidenced that the transient stability of the system has improved. The result obtained in the TNEB system is valid only for the present scenario. The study should be repeated as and when the considerable capacity of new generation (> 500 MW) is added.

Tamil Nadu: Current Power scenario and projects in pipeline

Tamil Nadu: Current Power scenario and projects in pipeline Tamil Nadu: Current Power scenario and projects in pipeline 1. Tamil Nadu per capita consumption is over 1000 Units, which is as against 11 th plan national target of 1000 units. Presently, the national

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Comparison of Shunt Facts Devices for the Improvement of Transient Stability of Two Machine

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1 Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms May 22, 2009 Slide 1 FACTS Applications Flexible AC Transmission Systems May 22, 2009 Slide 4 System Studies - Grid Codes

More information

Transient Stability Improvement of Long Transmission Line System by Using SVC

Transient Stability Improvement of Long Transmission Line System by Using SVC Transient Stability Improvement of Long Transmission Line System by Using SVC Dr.Tarlochan Kaur 1 and Sandeep Kakran 2 1 Associate Professor, EED, PEC University of Technology, Chandigarh, India 2 Assistant

More information

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC Rathnasagar Rangu 1, Poonam Upadhyay 2 1 PG Student, VNR VJIET, Hyderabad, India 2 Professor, VNR VJIET, Hyderabad, India Abstract

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

USE CASE 14 CONTROLLED ISLANDING

USE CASE 14 CONTROLLED ISLANDING I USE CASE 14 CONTROLLED ISLANDING Use Case Title Centralized application separates grid into islands to prevent blackout Use Case Summary Controlled islanding is a method that can significantly improve

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI 621213 EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL TWO MARKS: 1. What are the sources of reactive power? How it is

More information

RELAY CO-ORDINATION IN A 11KV SUBSTATION USING ETAP

RELAY CO-ORDINATION IN A 11KV SUBSTATION USING ETAP International Journal of Recent Innovation in Engineering and Research Scientific Journal Impact Factor - 3.605 by SJIF e- ISSN: 2456 2084 RELAY CO-ORDINATION IN A 11KV SUBSTATION USING ETAP Ms. Serene

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Power Stability and Oscillation Damping Analysis of a Three Machine Nine Bus System

Power Stability and Oscillation Damping Analysis of a Three Machine Nine Bus System Power Stability and Oscillation Damping Analysis of a Three Machine Nine Bus System Suraj Kumar, Priyajit Dash M.Tech Student, Department of EEE, BRCM College of Engineering, Behal, Bhiwani Haryana, India

More information

ABB static var compensator stabilizes Namibian grid voltage

ABB static var compensator stabilizes Namibian grid voltage Power ABB static var compensator stabilizes Namibian grid voltage factor! Rolf Grünbaum, Mikael Halonen, Staffan Rudin The spectacular dune landscapes of Namibia are a key factor in the country s booming

More information

Advanced SIPS using PMU and SCADA data

Advanced SIPS using PMU and SCADA data Advanced SIPS using and SCADA data June 3, 2013 Yutaka Kokai Hitachi America, Ltd. Hitachi, Ltd. 2013. All rights reserved. Hitachi Group s Industry Segments Copy Right Hitachi, Ltd. 2013. All rights reserved.

More information

SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality,

SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality, SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality, integrity, and innovation. Our mission is to offer the safest,

More information

POWER SYSTEM SECURITY CONCEPTS

POWER SYSTEM SECURITY CONCEPTS POWER SYSTEM SECURITY CONCEPTS 1.1 INTRODUCTION The Power System needs to be operationally secure, i.e. with minimal probability of blackout and equipment damage. An important component of power system

More information

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage

More information

ELG4125: System Protection

ELG4125: System Protection ELG4125: System Protection System Protection Any power system is prone to 'faults', (also called short-circuits), which occur mostly as a result of insulation failure and sometimes due to external causes.

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION Exercise 2 Single Bus Scheme EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with electric power substations using the single bus scheme with bus section circuit breakers.

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

Transient Stability Analysis with PowerWorld Simulator

Transient Stability Analysis with PowerWorld Simulator Transient Stability Analysis with PowerWorld Simulator T14: Large-Scale Simulation Examples 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com

More information

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68 The Challenges and Opportunities Faced by Utilities using Modern Protection and Control Systems - Paper Unavailable Trends in Protection and Substation Automation Systems and Feed-backs from CIGRE Activities

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

The various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control

The various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control ENERGY CONTROL CENTERS To generated, Transmission and Distribution system, Number of customers and Total investment. Installed capacity in India exceeds 206 GW with annual energy generated energy exceeding

More information

Real Time Digital Simulator Testing of an On Line Integrated Stability Control System

Real Time Digital Simulator Testing of an On Line Integrated Stability Control System Real Time Digital Simulator Testing of an On Line Integrated Stability Control System R.P. Wierckx, M. Kawasaki, N. Saito, K. Anzai, S.C. Verma Abstract The paper describes the testing of an on line integrated

More information

TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD. ADMINISTRATIVE BRANCH. Letter No /G.39/G.393/2018-1, dated

TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD. ADMINISTRATIVE BRANCH. Letter No /G.39/G.393/2018-1, dated REMINDER-III: TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD. ADMINISTRATIVE BRANCH From Er. A. ASHOK KUMAR, B.E., Chief Engineer/ Personnel, 144, Anna Salai, Chennai 600 002. To The Superintending

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

FACTS and HVDC for Grid Connection of Large Wind Farms

FACTS and HVDC for Grid Connection of Large Wind Farms David Larsson Power-Gen Europe 2005 Milan, Italy FACTS and HVDC for Grid Connection of Large Wind Farms www.abb.com/facts FACTS Agenda Wind Generators Response to Grid Faults PICTURE JPG-FORMAT WEB OPTIMIZED

More information

Solutions for transmission network management

Solutions for transmission network management EM SG SOLutions Solutions for transmission network management Energy Management Smart Grid Solutions Solutions for Transmission Network Management Overview Operator Training Simulator Blackout Prevention

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

Final Report. Mini Project TET Group nr 7 - Project nr 4. Students: Hans Lavoll Halvorson, NTNU

Final Report. Mini Project TET Group nr 7 - Project nr 4. Students: Hans Lavoll Halvorson, NTNU Final Report Mini Project TET4190 28.10.2010 Optimal Distance for connection of offshore wind farm with AC cable with SVC or STATCOM To increase the distance compensation technologies such as SVC and STATCOM

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Agenda for the Meeting of Southern Region constituents regarding Connectivity/LTA Applications of IPPs in SR received during November & December, 2016

Agenda for the Meeting of Southern Region constituents regarding Connectivity/LTA Applications of IPPs in SR received during November & December, 2016 Agenda for the Meeting of Southern Region constituents regarding Connectivity/LTA Applications of IPPs in SR received during November & December, 2016 (To be discussed along with Agenda for Follow up Meeting

More information

The current state of the electrical grid And the technologies that will enable its transformation

The current state of the electrical grid And the technologies that will enable its transformation ABB POWER GRIDS The current state of the electrical grid And the technologies that will enable its transformation IEEE POWER & ENERGY SOCIETY - SUBSTATIONS COMMITTEE May 7-11 th Agenda State of the Industry

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

Blackstart Hardware-in-the-loop Relay Testing Platform

Blackstart Hardware-in-the-loop Relay Testing Platform 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Blackstart Hardware-in-the-loop Relay Testing Platform R. LIU R. SUN M. TANIA Washington

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

Geomagnetic Disturbances

Geomagnetic Disturbances Geomagnetic Disturbances Managing Risk to the North American Power Grid Mark Olson, Reliability Standards Developer Worcester Polytechnic Institute Energy Symposium September 25, 2013 About NERC The North

More information

Simulation and Analysis of Static Var Compensator with Matlab

Simulation and Analysis of Static Var Compensator with Matlab The International Journal Of Engineering And Science (IJES) Volume 4 Issue 12 Pages PP -07-11 2015 ISSN (e): 2319 1813 ISSN (p): 2319 1805 Simulation and Analysis of Static Var Compensator with Matlab

More information

HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM

HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM A. Valenti* I Bel ** S. Lee *EDF **EPRI E2I ConEdison France USA USA arnaud.valenti@edf.fr

More information

Disturbance Monitoring and

Disturbance Monitoring and PRC-002-2 R1 Notification Disturbance Monitoring and Reporting Requirements Compliance Spring Workshop May 10, 2017 Objectives This presentation will discuss: Requirement R1 Part 1.2 notifications Definition

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Achieving Smarter Grid Operation With On-Line DSA Technology

Achieving Smarter Grid Operation With On-Line DSA Technology Achieving Smarter Grid Operation With On-Line DSA Technology Powercon 2014 October 20-22, 2014, Chengdu, China Lei Wang Powertech Labs Inc. 12388 88 th Avenue Surrey, BC, Canada A very simple version of

More information

RTDMS CAISO TRAINING SESSION

RTDMS CAISO TRAINING SESSION Consortium for Electric Reliability Technology Solutions Real-Time Dynamics Monitoring System (RTDMS ) RTDMS CAISO TRAINING SESSION January 31, 2006 Manu Parashar & Jim Dyer Electric Power Group (EPG)

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

System Studies for American Transmission Co. s Benson Lake SVC Project

System Studies for American Transmission Co. s Benson Lake SVC Project Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC Outline Introduction

More information

Transient stability of 11-bus system using SVC and improvement of voltage profile in transmission line using series compensator

Transient stability of 11-bus system using SVC and improvement of voltage profile in transmission line using series compensator American Journal of Electrical Power and Energy Systems 2014; 3(4): 76-85 Published online August 30, 2014 (http://www.sciencepublishinggroup.com/j/epes) doi: 10.11648/j.epes.20140304.12 ISSN: 2326-912X

More information

Real Time Monitoring of

Real Time Monitoring of Real Time Monitoring of Cascading Events Mladen Kezunovic Nan Zhang, Hongbiao Song Texas A&M University Tele-Seminar, March 28, 2006 Project Reports (S-19) M. Kezunovic, H. Song and N. Zhang, Detection,

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination GSU Phase Overcurrent (51T), GSU Ground Overcurrent (51TG), and Breaker Failure (50BF) Protection System Protection and Control Subcommittee

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

Transient stability improvement using svc and pss

Transient stability improvement using svc and pss Transient stability improvement using svc and pss N. Anil kumar 1, K. Ramesh 2 1M.Tech Student,Department ofeee,bapatla Engineering College,Bapatla 2Asisstant Professor,Department of EEE,Bapatla Engineering

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

POWER SYSTEM DATA COMMUNICATION STANDARD

POWER SYSTEM DATA COMMUNICATION STANDARD POWER SYSTEM DATA COMMUNICATION STANDARD PREPARED BY: AEMO Systems Capability VERSION: 2 EFFECTIVE DATE: 1 December 2017 STATUS: FINAL Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au

More information

1. Project Description

1. Project Description Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal

More information

Geomagnetic Induced Current (GIC) Mitigation System Summary for the White Paper

Geomagnetic Induced Current (GIC) Mitigation System Summary for the White Paper Geomagnetic Induced Current (GIC) Mitigation System Summary for the White Paper Grounding of power grids provides benefits to improve AC operation and to optimize the economics of transmission network

More information

Québec Interconnection Approach to BES

Québec Interconnection Approach to BES Québec Interconnection Approach to BES Placer une photo ici s il y a lieu NPCC Governmental/Regulatory Affairs Advisory Group Sylvain Clermont November 27, 2012 Introduction: HQT Our mission HQT operates

More information

Power System Enterprise Solution

Power System Enterprise Solution Power System Enterprise Solution ETAP is the most comprehensive analysis platform for the design, simulation, operation, control, optimization, and automation of generation, transmission, distribution,

More information

Local Area Studies Update - PACW Kevin Putnam

Local Area Studies Update - PACW Kevin Putnam Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton

More information

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines 1 B.T.RAMAKRISHNA RAO, 2 N.GAYATRI, 3 P.BALAJI, 4 K.SINDHU 1 Associate Professor, Department

More information

Bus Protection Application Challenges

Bus Protection Application Challenges Bus Protection Application Challenges KN Dinesh Babu - Megger JC Theron, Lubomir Sevov GE Grid Solutions 2017 Texas A&M Protective Relay Conference Content Introduction Application Challenges Increase

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

Facility Connection Requirements

Facility Connection Requirements SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...

More information

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU SOUTHERN REGIONAL POWER COMMITTEE BENGALURU Additional Agenda for the 80 th Meeting of Protection Coordination Sub-Committee of SRPC to be held on 20-21 December, 2018 1. Grid Occurrences Additional Grid

More information

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC September 21, 2018 Penelec Transmission Zone Need Number: PN-2018-001 Consider upgrading transmission line equipment (switches, conductor, splices,

More information

Chapter 3 MODELING OF SHUNT FACTS DEVICES. The Shunt FACTS Devices are used for voltage control and

Chapter 3 MODELING OF SHUNT FACTS DEVICES. The Shunt FACTS Devices are used for voltage control and 44 Chapter 3 MODELING OF SHUNT FACTS DEVICES 3.0 Introduction The Shunt FACTS Devices are used for voltage control and power flow control, but these are good at for voltage control. These are not in a

More information

Effective Management of Transformer Inrush during Restoration of a Typical Industrial Power System

Effective Management of Transformer Inrush during Restoration of a Typical Industrial Power System Effective Management of Transformer Inrush during Restoration of a Typical Industrial Power System Dr. J. K. Das 1, Debnil Chakraborty 2 Professor& Head, Dept. of EL, Guru Nanak Institute of Technology,

More information

ISO New England Data Modeling Requirements

ISO New England Data Modeling Requirements A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

HYDRO HIPASE SIMPLIFY YOUR SOLUTION

HYDRO HIPASE SIMPLIFY YOUR SOLUTION HYDRO HIPASE SIMPLIFY YOUR SOLUTION The new generation of integration ANDRITZ has extensive long-term experience in the areas of excitation, electrical protection, synchronization, and automation of hydropower

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

INCREASING electrical network interconnection is

INCREASING electrical network interconnection is Blair, Steven Macpherson and Booth, Campbell and Turner, Paul and Turnham, Victoria (2013) Analysis and quantification of the benefits of interconnected distribution system operation. In: 5th International

More information

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are

More information

HVDC in CSG Challenges and Solutions

HVDC in CSG Challenges and Solutions HVDC in CSG Challenges and Solutions LI, Licheng lilc@csg.cn LI, Peng lipeng@csg.cn China Southern Power Grid Co., Ltd June 2013 1 Outline I. Overview of CSG II. Overview of HVDC&UHVDC in CSG III. Challenges

More information

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents

More information

GUIDELINES FOR THE CLASSIFICATION OF GRID DISTURBANCES ABOVE 100 kv

GUIDELINES FOR THE CLASSIFICATION OF GRID DISTURBANCES ABOVE 100 kv GUIDELINES FOR THE CLASSIFICATION OF GRID DISTURBANCES ABOVE 100 kv 13.04.2017 1 INTRODUCTION... 4 2 PURPOSE OF THE GUIDELINES... 4 3 SCOPE AND LIMITATIONS OF THE STATISTICS... 5 4 DEFINITIONS... 6 4.1

More information

An Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems

An Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems An Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems By Eng. Sameh Moustafa Mohamed Abd Elgowad Elbana A thesis submitted to The Faculty

More information

SIGMA. Advanced Generator Protection and Control. Short Form Catalogue

SIGMA. Advanced Generator Protection and Control. Short Form Catalogue Short Form Catalogue SIGMA Advanced Generator Protection and Control Generator protection, synchronizing and load sharing Power management system Easy to install and commission Control most governors/avrs

More information

Synchrophasor-Based Monitoring, Analysis, and Control

Synchrophasor-Based Monitoring, Analysis, and Control Synchrophasor-Based Monitoring, Analysis, and Control Roy Moxley Schweitzer Engineering Laboratories, Inc. Presented at the GCC Power 2008 Conference & Exhibition Manama, Bahrain November 10 12, 2008 Also

More information

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation 111 Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation Z. Gajić (ABB, Sweden) JP Wang / PW Gong / YS Xu (ABB China) ZX Zhou (CERPI, China) Summary Power utilities

More information

Implementing the protection and control of future DC Grids

Implementing the protection and control of future DC Grids Implementing the protection and control of future DC Grids Hengxu Ha, Sankara Subramanian Innovation and Technology Department, SAS, Alstom Grid 1. The challenge of the DC Grid protection 1 High speed

More information

Real-time Power System Operation. Energy Management Systems. Introduction

Real-time Power System Operation. Energy Management Systems. Introduction 1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern

More information

CASE STUDY : Transient Stability Simulation Package

CASE STUDY : Transient Stability Simulation Package CASE STUDY : Transient Stability Simulation Package CLIENT NAME : A major T&D solutions provider in the world END CUSTOMER : A public T&D utility in one of the SAARC nations PROJECT TITLE : Customized

More information

Smart Power Flow Monitoring and Control

Smart Power Flow Monitoring and Control IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 10 April 2016 ISSN (online): 2349-784X John Richardson. J Mathivathani. N Karthikeyan. K Preethi. PA Vivekanandhan. C Vice

More information

Artificial Neural Network Controller With Static VAR Compensator to Improve Transient Stability for A Grid Connected Distributed Generation System

Artificial Neural Network Controller With Static VAR Compensator to Improve Transient Stability for A Grid Connected Distributed Generation System nternational Journal of Applied Sciences, Engineering and Management SSN 2320 3439, Vol. 07, No. 02, March 2018, pp. 01 05 Artificial Neural Network Controller With Static VAR Compensator to mprove Transient

More information

SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE PLANT

SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE PLANT International Telecommunication Union ITU-T L.1200 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (05/2012) SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE

More information