Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013
|
|
- Nancy Boyd
- 5 years ago
- Views:
Transcription
1 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013
2 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility for bus transfer activities Improve pedestrian safety and connections by consolidating existing dispersed bus stops in one central location Create a sense of place in the community Provide a secure, comfortable waiting area for passengers Minimize impacts to shopping center operations Accommodate the future Purple Line 2
3 Takoma Langley Transit Center Status Project is fully funded Design has been completed. Property has been acquired Notice to proceed issued in July 2013 Utility relocation is underway Project to be completed in Fall 2015 WMATA to assume operation and maintenance 3
4 Takoma Langley Transit Center Project description The Transit Center will serve 11 bus routes and will have capacity for more than 60 buses during the peak hours. Prince George s County, Montgomery County, WMATA and University of Maryland will be running buses into the Transit Center Existing bus stops will be relocated into the Transit Center The Transit Center will include a ticket sales office, an indoor waiting area and public restrooms. Solar panels will generate all the energy needed for the building. A rainwater harvesting system will irrigate the landscaping. The transit center would be directly across from the Purple Line light rail station. 4
5 Takoma Langley Transit Center Project Cost and Funding Budget Planning $.48 Million Engineering $ 2.97 Million Right-of-way $ Million Construction $ Million Total $ Million Funding WMATA $ 7.31 Million Montgomery County $ 2.50 Million Prince George s County $ 2.50 Million Maryland $ 9.80 Million Federal Grant $.82 Million TIGER Grant $ Million Total $ Million 5
6 Takoma Langley Transit Center 6
7 7
8 Purple Line 16 mile east-west light rail line between Bethesda in Montgomery County and New Carrollton in Prince George s County. Operates mostly on the surface with 21 stations. 8
9 Corridor Description Washington region s inner, older suburbs in Maryland s densest two counties Well developed corridor in which the project is being inserted into the existing built-up environment Involves trade-offs among operating performance, costs and impacts Construction staging and maintenance of traffic will be challenging 9
10 Alignment Characteristics - West Bethesda Silver Spring 3 miles along former railroad ROW with adjacent Trail 1 mile along side of CSX/Metrorail ROW 5 stations 2 Metrorail connections Highest ridership market Exclusive operating environment Primary Vehicle Storage Facility 10
11 Bethesda Terminal with South Metro Entrance Purple Line Level 11
12 Purple Line Station at Bethesda Bethesda Station (under existing office building) Before 12
13 Silver Spring Transit Center Station 13
14 Alignment Characteristics Middle Silver Spring University Boulevard 3.7 miles in street running 1 mile shared traffic operations 1200 ft tunnel 4 stations Street car type operating environment Silver Spring Library Station 14
15 Alignment Characteristics East University Boulevard New Carrollton (approx.10 miles) Approx 2.5 miles in dedicated median lanes Many at grade intersection crossings Direct link to Takoma Langley Transit Center Through University of Maryland Campus share lanes with existing bus services 1+ mile of shared traffic operations Remainder largely dedicated/reserved alignment along roadways 12 stations 2 Metrorail connections Primary Maintenance Facility 15
16 University of Maryland Characteristics University of Maryland College Park Flagship Campus 37,000 Students 14,000 Faculty/Staff Visitors Major Athletic and Cultural Events University of Maryland University College Academic/Conference Center Purple Line operating along main roadway though center of campus Three Purple Line stations: West Campus, Main Campus and East Campus Also serves existing UM/College Park Metrorail station and M Square Research Center 16
17 Case for the Project Linking the Washington D.C. Capital Region by improving: Travel Times Travel within the corridor Major activity centers Adjacent communities Travel from the corridor to areas outside Feeding to and distributing passengers from radial corridors via Metrorail/MARC Especially to DC Travel to the corridor from areas outside Especially north and east of corridor Along Metrorail lines and major arterials 17
18 Case for the Project Intermodal Connections 4 Metro lines 3 MARC lines Amtrak Northeast Corridor Regional and Local Bus Services 18
19 Case for the Project Connections to Major Activity Centers 19
20 Case for the Project Reliability of Travel Times and Shorter Trips 58,200daily users at 2020 opening 64,500 daily users in 2030 Trains every 6 minutes in peak period; minutes in off-peak period 1/3 of users will also use Washington Metrorail for part of their trip 20
21 Purple Line Interface in Local Land Use and Development Project team working closely with jurisdictions that have land use/development responsibilities Goals: Preserve current land use character Integrate with adjoining development Reinforce development at Metrorail stations Help create development opportunities Encourage Transit Oriented Development 21
22 Financial Plan Submitted to FTA on August 16, 2013 and based on Federal, State and local funds Based on current Purple Line cost of $2.245 Billion plus $126 Million financing costs Seeks $900 Million Federal New Starts Funds Includes TIFIA Loan to be held by P3 Concessionaire Reflects State of Maryland Revenue Increases 22
23 FEIS Status Final Environmental Impact Statement (FEIS) distributed for review September 6, 2013 Close of Review and Comment Period October 21, 2013 Responses to comments and mitigation commitments included in Record of Decision (ROD) FTA Record of Decision (ROD) to be issued December,
24 New Starts Status Completed Preliminary Engineering (30% Design) plans. Submitted all Entry into Engineering (next phase) plans and reports by September 13 Approval is awaiting NEPA Record of Decision FFY15 New Starts Criteria Annual Update submitted September 13 Seeking Full Funding Grant Agreement recommendation in January 2014 Annual New Starts Report 24
25 Public Involvement Extensive public involvement program including: Focus Groups and Neighborhood Work Group meetings Close coordination with both counties, WMATA, and State Agencies Meetings with various community associations Meetings with property owners/developers, elected officials and local businesses Attendance at large community events 25
26 Public Outreach Business Outreach Plan Develop and sustain relationships with the businesses: Short-Term Identify and engage community business leaders and business advocates Door to door business canvassing to provide updates on Purple Line project Distribute FOCUS-ON Business brochure Continually update business database Interviews with businesses along the alignment for the ongoing Relocation Assistance Program 26
27 Public Outreach Business Outreach Plan Long-Term Implement industry best practices for mitigation during construction Distribute FOCUS-ON Business brochure throughout life of the project Schedule business outreach meetings throughout the corridor Continue to identify and support potentially impacted businesses Continue to engage County, State, business and economic development agencies and other stakeholders 27
28 Public Outreach Focused Hispanic Community Outreach Bi-lingual staff members Newsletter articles featuring Hispanic businesses Dedicated phone line Translated website and publications Neighborhood events located in Hispanic communities Coordinating with special interest groups 28
29 Public Outreach Construction Phase Outreach Transportation Management Plan Field Office Best practices from other construction project experiences Media & community outreach Business support (such as advertising and promotion) Ongoing engagement with county Department of Economic Development agencies 29
30 3 Months Ahead - Major Activities Prepare and Get Signed ROD Responses to Comment Record of Decision December 2013 Advance P3 process Continue coordination and outreach activities with the Public and Stakeholders New Starts Response to Comments on Request to Enter Engineering and FFY15 Annual Update Submissions Approval to Enter Engineering - December 2013/January 2014 Continue Agreement Development with Key Stakeholders Progress Right-of-Way Acquisition 30
31 Contact Us Questions? Please contact Public Outreach at: Línea telefónica en español: Michael D. Madden Project Manager Phone
The Blue Line Extension
The Blue Line Extension NORTH CAROLINA JOINT TRANSPORTATION OVERSIGHT COMMITTEE Presented by Carolyn Flowers CATS Chief Executive Officer Raleigh, NC February 10, 2012 Overview Charlotte Area Transit System
More informationBill Jackson Asst. Statewide Utility Engineer, Office of Construction MDOT SHA
Jeff Ensor TDD Chief of Staff Director of Project Development & Delivery MDOT MTA Purple Line Judy Freedman Breckon Director of Property Acquisition MDOT MTA Purple Line Brian Horn Purple Line Real Estate
More informationProposed FY 06 Project Development Program and FY 05 Project Development Program Update
Washington Metropolitan Area Transit Authority Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Presented to the Board of Directors: P D E C Planning & Development
More informationMOU with Maryland DOT for New Carrollton Metrorail Station Transit-Oriented Development
Joint Development and Real Estate Committee Item III-D June 24, 2010 MOU with Maryland DOT for New Carrollton Metrorail Station Transit-Oriented Development Page 33 of 41 Washington Metropolitan Area Transit
More informationSECTION 106 ACTIVITIES ANNUAL REPORT
SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The
More informationApproval of Medical Center New Entrance Agreement
Finance & Administration Committee Action Item III-A February 14, 2013 Approval of Medical Center New Entrance Agreement Washington Metropolitan Area Transit Authority Board Action/Information Summary
More informationSECTION 106 ACTIVITIES ANNUAL REPORT
SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The
More informationApproval of Navy Yard Chiller Joint Development Agreement
Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information
More informationDowntown Boise Multimodal Center
Treasure Valley High Capacity Transit Study Downtown Boise Multimodal Center Environmental Assessment June 2009 Prepared by the Federal Transit Administration and Valley Regional Transit. U.S. Department
More informationNorthern Virginia Transportation Authority
IV Northern Virginia Transportation Authority March 23, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation 66 Outside the Beltway Project Scope Multimodal improvements to
More information7900 HARKINS ROAD Lanham, MD
7900 HARKINS ROAD 7900 HARKINS ROAD This rare offering represents the opportunity to acquire a best-in-class office asset with guaranteed NNN cash flow for 12 years at a significant discount to replacement
More informationContinual Innovation Through Diverse Funding Sources. Paul Comfort, Esq. CEO, Maryland Transit Administration
Continual Innovation Through Diverse Funding Sources Paul Comfort, Esq. CEO, Maryland Transit Administration Problem Statement and Solution Issue: Funding continues to dry up Declining Federal Formula
More informationVeirs Mill Road Metrobus Improvements Request to Conduct Public Hearing
Customer Services, Operations, and Safety Committee Board Information Item III-B September 24, 2009 Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing Washington Metropolitan Area
More informationProvo-Orem Bus Rapid Transit
Provo-Orem Bus Rapid Transit and Timpanogos Maintenance Facility Expansion Procurements Informational Meeting August 18, 2014 Agenda Topic Presenter Time Introduction of key project personnel Project history
More informationThe Maryland Transit Administration. A Plan to Connect Baltimore
The Maryland Transit Administration A Plan to Connect Baltimore 1 What We ve Heard Over 1,100 stakeholder comments submitted through the Bus Network Improvement Project (BNIP) Six workshops, three pop-up
More informationMETRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS
METRO SHORT RANGE TRANSIT PLAN FY 2010 2014 2014 Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS OVERVIEW Purpose of Metro SRTP Develop multi year strategic plan to improve transit quality,
More informationMVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014
MVTA-Prior Lake-Shakopee Merger SCALE Presentation, October 10, 2014 MVTA Commitment Our Vision The Minnesota Valley Transit Authority is a trusted partner in transportation, serving as an innovative leader
More informationClick to edit Master title style Click to edit Master title style
Southwest Chief & Front Range Passenger Rail Commission Overview for Transportation Legislative Review Committee November 2, 2017 Presented by: Sal Pace Jacob Riger, AICP November 2, 2017 FIRST WE WERE
More informationMARTA BOARD OF DIRECTORS OCTOBER 4, 2018
MARTA BOARD OF DIRECTORS OCTOBER 4, 2018 TODAY S AGENDA o Key driver of the program o Recommended plan o Project summaries o Next steps 2 KEY DRIVER: PUBLIC INPUT o Atlanta City Design o Atlanta s Transportation
More informationNorth Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009
North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings December 9 & 10, 2009 1 Welcome & Introductions 2 3 What Are We Doing Here Tonight? Public Hearing for RTD North Metro Corridor
More informationSystem Expansion Implementation Plan. Board Meeting, April 2017
System Expansion Implementation Plan Board Meeting, April 2017 2016: A record-breaking year Opened 3 new light rail stations. Completed tunneling for 3 more. Broke ground on our longest extension to date.
More informationCorridor Management Committee. January 12, 2017
Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major
More informationVTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association
VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for
More informationDulles Area Transportation Association
Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements
More informationEngaging Maryland toward CAV advancements Christine Nizer, Administrator
Engaging Maryland toward CAV advancements Christine Nizer, Administrator Maryland Department of Transportation Motor Vehicle Administration Maryland CAV activities Overall goal: Maryland is open for business
More informationS-03-SegB: South Federal Way to Fife LRT
Project Number S-03-SegB Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 4.0 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE
More informationNovember 28, 2012 ALTERNATIVES ANALYSIS PUBLIC MEETING
November 28, 2012 ALTERNATIVES ANALYSIS PUBLIC MEETING Project Background Description of the Project Alternatives Analysis Process Project Progress Activity Stations Comments Adjourn 2 VIA spent 2 years
More informationPROJECT TIMELINE. Next steps. Plan. Start of Service
PROJECT TIMELINE 2018 2019 2020 2021 2022 2023 WE ARE HERE Plan Develop Build Develop design options for termini, station locations, and transit operations Conduct environmental research Assess funding
More informationGATEWAY PROGRAM OVERVIEW AND UPDATE
January 12, 2017 GATEWAY PROGRAM OVERVIEW AND UPDATE John D. Porcari, Interim Executive Director Gateway Program Development Corporation 1 GATEWAY PROGRAM DEVELOPMENT CORPORATION» Incorporated in the state
More informationMaking Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE
Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Achieving Compact & Connected Engaging in a regional transit discussion Pursuing a compact
More informationMetrobus 30s Line Enhancements
Customer Service, Operations and Safety Committee Action Item III-C February 14, 2008 Metrobus 30s Line Enhancements Washington Metropolitan Area Transportation Authority Board Action/Information Summary
More informationDallas Streetcar Central Link Locally Preferred Alternative Selection
Dallas Streetcar Central Link Locally Preferred Alternative Selection Mobility Solutions, Infrastructure & Sustainability Committee August 28, 2017 Tanya Brooks, Assistant Director Mobility and Street
More informationBus Rapid Transit in Montgomery County
Bus Rapid Transit in Montgomery County Presentation to the Transportation Planning Board Technical Committee June 1, 2018 Item #8 Agenda What is Bus Rapid Transit (BRT)? Montgomery County s BRT Network
More informationDowntown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary
north, lrt, light, transit, rail, track, line, closure, close, road, interuption, partial, lane, construction, bulletin, NAIT, line, motorist, pedestrian, map, metro, line,downtown to NAIT LRT Concept
More informationRail Division Update. Presented to Joint Appropriations Subcommittee on Transportation. Paul C. Worley, CPM Rail Division Director February 28, 2013
Rail Division Update Presented to Joint Appropriations Subcommittee on Transportation Paul C. Worley, CPM Rail Division Director February 28, 2013 0 Rail in North Carolina Over 3,500 miles of rail lines.
More informationPublic Outreach Overview Tuesday, September 27. COTA William J. Lhota Building 33 N. High St. Columbus, OH 43215
Public Outreach Overview Tuesday, September 27 COTA William J. Lhota Building 33 N. High St. Columbus, OH 43215 Project Overview Goals and Overview Create a community vision for the future of public transportation
More informationMeeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.
TO WHOM IT MAY CONCERN: NOTICE OF RE-SCHEDULED BOARD MEETINGS This is notice that the re-scheduled meetings of the Board of Directors of the New Jersey Transit Corporation, NJ Transit Rail Operations,
More informationFeasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008
Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008 INTRODUCTION The City of Moorhead (City), along with the Fargo-Moorhead Metropolitan Council of Governments (FM
More information2018 State and Federal Legislative Program
2018 State and Federal Legislative Program STATE TRANSPORTATION FUNDING The passage of HB 2313 (2013) was the result of bipartisan cooperation throughout the Commonwealth. The regional funding provided
More informationStation Location Feasibility Study
Station Location Feasibility Study Gateway Cities Gateway Cities Service Council Meeting May 11, 2017 Gateway Cities Service Council Meeting May 11, 2017 1 Meeting Purpose Introduce and present the Metrolink
More informationMetropolitan Council. Transportation Division Proposed Transit Capital Program
Metropolitan Council Transportation Division Proposed 2015-2020 Transit Capital Program Transportation Committee October 27, 2014 Goals of the 2015 Capital Program Simplify the process Standardize the
More informationvision42
vision42 www.vision42.org vision4 auto-free light rail 2 boulevard for 42nd Street Roxanne Warren, AIA, Chair George Haikalis, ASCE, Co-Chair Institute for Rational Urban Mobility,Inc. www.vision42.org
More informationWashington Metropolitan Area Transit Authority Board Action/Information Summary
Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201697 Resolution: Yes No TITLE: MTPD Security Updates PRESENTATION SUMMARY: The Metro Transit
More informationOregon House Transportation & Economic Development Committee
Oregon House Transportation & Economic Development Committee Ron Pate Cascades Corridor Director WSDOT Rail Director May 6, 2015 Pacific Northwest High-Speed Rail Corridor Passenger Rail Amtrak Cascades
More informationCorridor Management Committee. January 14, 2016
Corridor Management Committee January 14, 2016 1 Today s Topics 2 Regional METRO System Overview 2016 Project Overview: Key Activities and Milestones Municipal Consent Schedule Design Resolution Schedule
More informationTOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013
TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013 Introduction The Transport Chapter of the 1818 Society organized a tour of the Washington
More informationWashington Metropolitan Area Transit Authority Board Action/Information Summary
Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 200972 Resolution: Yes No TITLE: MTPD 2014 Part I Crime Report, January - June PRESENTATION
More informationFigure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended
Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public
More informationRedesigning the Baltimore Transit Network
Redesigning the Baltimore Transit Network Paul W. Comfort, Esq., Administrator and CEO Route 5: Reimagining Your Agency s Transit Services APTA Bus and Para-transit Conference Charlotte, North Carolina
More informationMunicipal Service Park 3 December Consolidation of City services to one centralized complex
Municipal Service Park 3 December 2010 Consolidation of City services to one centralized complex Overview: Operational Challenges and Opportunities South East Connector impacts Opportunities: The South
More informationBusiness Advisory Committee. October 1, 2013
Business Advisory Committee October 1, 2013 1 Today s Topics Hennepin County Community Works Update Project Development Update Ridership Next Steps Success Measures Update Member and Committee Reports/Public
More informationEvolution of TOC. Joint Development Program TOD Land Use/Planning Grants Transit Supportive Toolkit Union Station Redevelopment
Transit Oriented Communities October 12, 2018 Evolution of TOC Joint Development Program TOD Land Use/Planning Grants Transit Supportive Toolkit Union Station Redevelopment First/Last Mile Strategy Systemwide
More informationApproval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development
Planning, Program Development and Real Estate Committee Item V- B September 11, 2014 Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Washington Metropolitan
More informationCommunity Advisory Committee. June 5, 2017
Community Advisory Committee June 5, 2017 1 Today s Topics Call to Order/Introductions Approval of Minutes Project Overview Traffic Signal Coordination 60% Plans Update Advanced Construction: Bassett Creek
More informationRecommendation to Board. Final Action
MOTION NO. M2017-59 City of Seattle Center City Mobility Plan Agreement MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 05/04/2017 05/25/2017 Recommendation
More information1.0 PURPOSE AND NEED
1.0 PURPOSE AND NEED This chapter documents the need for transit improvements in the Northwest Corridor and the purposes that the proposed project is intended to serve. An overview of the study corridor
More informationCentral Corridor. - Central Corridor. Management Committee, Light Rail Transit. Rail-Volution - Weaving Transit into Existing Communities
- Central Corridor Rail-Volution - Weaving Transit into Existing Communities Management Committee, October 31, 2009 June Improving 11, 2008 mobility Easing congestion Strengthening our communities Twin
More informationPresentation to the Maryland Competitiveness Coalition. Michele L. Whelley, President & CEO June 19, 2013
Presentation to the Maryland Competitiveness Coalition Michele L. Whelley, President & CEO June 19, 2013 Transportation is the Future of Business Education Healthcare Biotech Manufacturing Advocacy with
More informationTRANSPORTATION DEPARTMENT Business Plan
TRANSPORTATION DEPARTMENT 2018 Business Plan Today s Agenda Mission Department Overview Planning Initiatives Commission Priorities and 2018 Budget Requests Five-year Plan Department of Transportation Mission
More informationDupont Circle Escalator Replacement
Customer Service and Operations Committee Board Information Item III-B December 1, 2011 Dupont Circle Escalator Replacement Page 46 of 71 Washington Metropolitan Area Transit Authority Board Action/Information
More informationDelivering Maryland s TRANSPORTATION. Maryland s New Starts Projects Jamie Kendrick, Maryland Transit Administration
Delivering Maryland s TRANSPORTATION INVESTMENT Public Private Private Partnerships for Maryland s New Starts Projects Jamie Kendrick, Maryland Transit Administration February, 2014 MTA is an Agency of
More informationMaximizing Asset ROI for Self & Clients in a Public Sector Setting. July 16 th San Diego
Maximizing Asset ROI for Self & Clients in a Public Sector Setting July 16 th San Diego State of Washington Population: 7.53 M Area: 71,303 Sq. Miles Population density: 107 population/mi² Puget Sound
More informationCLAYTON COUNTY TRANSIT INITIATIVE. Technical Advisory Committee/ Stakeholder Advisory Committee Webinar August 29, 2017
CLAYTON COUNTY TRANSIT INITIATIVE Technical Advisory Committee/ Stakeholder Advisory Committee Webinar August 29, 2017 AGENDA Welcome! Introduction of Speakers Webinar Housekeeping Project Overview & Status
More informationAppendix D Supportive Transportation Materials
Appendix D Supportive Transportation Materials D.1. Stakeholder Input and Coordination As noted in Section 1.7 of the main Master Plan document, there have been several opportunities for stakeholders to
More informationBEVRLYRLY STAFF REPORT. Meeting Date: August 4, 2015 Item Number: To: From:
BEVRLYRLY STAFF REPORT Meeting Date: August 4, 215 Item Number: To: From: Honorable Mayor & City Council Mark Cuneo, City Engineer Aaron Kunz, Deputy Director of Transportation Subject: Update on Metro
More informationVirginia Transit Update
Virginia Transit Update Jennifer Mitchell Agency Director Virginia Transit Association May 24, 2017 1 Key Priorities for Statewide Transit Program Funding Safety and State of Good Repair Expansion 2 Funding
More informationWashington Metropolitan Area Transit Authority Board Action/Information Summary. MEAD Number:
Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 102948 Resolution: Yes No TITLE Metro Transit Police Department Third Quarter Security Report
More informationRecord of Public Comment on Central Corridor SDEIS
Executive Summary Page 1 Executive Summary Project Background The Ramsey County Regional Rail Authority (RCRRA) initiated the Central Corridor scoping process in 2001 and conducted the Alternatives Analysis
More informationMinistry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)
nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Welcome Thank you for attending this community engagement on the Trans- Canada Highway 1 West Project, part of the Highway
More informationNCTCOG MTP Policy Bundle Application for TXDOT
MTP Policy Application Acknowledgement I hereby certify that all information provided and contained herein is complete, accurate, and true. I am authorized to provide information on behalf of my agency.
More informationStakeholder Engagement Summary Report
Stakeholder Engagement Summary Report South Shore Corridor Project 1. INTRODUCTION 1.1 Project Overview Port Metro Vancouver s South Shore Trade Area is of critical importance to Canadian trade. One of
More informationWireless Network (Neutral Host) Request for Proposals Update
Finance, Administration and Oversight Committee Action Item III-B March 13, 2008 Wireless Network (Neutral Host) Request for Proposals Update Washington Metropolitan Area Transportation Authority Board
More informationCommunity Update. May 31, 2011
Community Update May 31, 2011 Presented to: Leaside Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough
More informationSubject YRRTC Accomplishments and Highlights
Date May 17, 2018 To Members of York Region Council From Mary-Frances Turner, York Region Rapid Transit Corporation, President Subject 2014-2018 YRRTC Accomplishments and Highlights Ref: Edocs #8410552
More informationFairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development Plan Board Transportation Committee December 1, 2015 Randy White Stuart Boggs Fairfax County County of Fairfax, Virginia Overview Background
More informationBOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM
BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM Date of Meeting: # 9 SUBJECT: ELECTION DISTRICTS: STAFF CONTACTS: Public and Private Infrastructure Improvements Adjacent to the Dulles
More informationLooking Ahead. A Context for the Next Twenty Year Needs Assessment. July 2013
Looking Ahead A Context for the Next Twenty Year Needs Assessment July 2013 A Larger Context for Twenty Year Needs Growing transit demand and complexity of travel paths and times Growing economy changing
More informationBoard of Directors April 25, BART The Next 40 Years BART Metro Vision Update Enhancing Service, Capacity and Coverage
Board of Directors April 25, 2013 BART The Next 40 Years BART Metro Vision Update Enhancing Service, Capacity and Coverage Agenda Project background Update on progress of study Review evaluation process
More informationBus Circulator Feasibility Study Scope of Work March 12, 2018
The City of Hyattsville Comprehensive Transportation and Infrastructure Study Bus Circulator Feasibility Study Scope of Work March 12, 2018 Project Approach At the request of the City of Hyattsville, Toole
More informationHigh Speed Rail Update
Update Mobility Solutions, Infrastructure and Sustainability Committee October 8, 2018 Brady Redwine Vice President Texas Central Molly Carroll Executive Director Project City of Dallas 1 Presentation
More informationBremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY
May 19, 2011 Community Meeting Metro Toronto Convention Centre North Building, Room 203B May 19 th, 2011, 4:30 p.m. to 7:30 p.m. Please sign in and complete a comment sheet Project team members are available
More informationCITY OF VANCOUVER ADMINISTRATIVE REPORT
CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting
More informationWestside Subway Extension of the Metro Purple Line
metro.net/works Westside Subway Extension of the Metro Purple Line Station Fact Sheet fall 2012 Background Station Overview Work to bring the Metro Purple Line to the Westside is moving forward, with plans
More information# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:
BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: March 13, 2018 # 7 SUBJECT: ELECTION DISTRICT: Contract Award/Roadway and Civil Design
More informationOpportunity: BaltimoreLink
Opportunity: BaltimoreLink Cities and Transit: Reimagined, Redesigned, and Reborn Rail~Volution October 11, 2016 Joshua B Diamond 51 Monroe St, Suite 1103 Rockville, MD 20850 301-774-4566 X 410 jdiamond@foursquareitp.com
More informationGirard Siding Environmental Assessment (EA) Public Meeting. May 23, 2013
Girard Siding Environmental Assessment (EA) Public Meeting May 23, 2013 1 Agenda» Program Overview» Girard Siding Project EA» Auburn to Shipman Track Improvement Project» Public Involvement Opportunities
More informationEXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT
16 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 18, 2015 SUBJECT: ACTION: EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF
More informationLos Angeles County One Gateway Plaza 2i3.g Tel Metropolitan Transportation Authority Los Angeles, CA metro.net
Metro Los Angeles County One Gateway Plaza 2i3.g22.2000 Tel Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net PLANNING AND PROGRAMMING COMMITTEE JULY 14,2010 SUBJECT: BUENA VISTA
More informationSITE DESCRIPTION. Vicinity
SITE DESCRIPTION Vicinity The Montrose Shopping Center is located in the northeast quadrant of the intersection of Randolph Road and Rockville Pike (MD 355). The existing building (formally known as the
More informationCITY OF VANCOUVER ADMINISTRATIVE REPORT
CITY OF VANCOUVER A11 ADMINISTRATIVE REPORT Report Date: May 3, 2007 Author: Dale Bracewell Phone No.: 604.871.6440 RTS No.: 06720 VanRIMS No.: 03-1200-11 Meeting Date: May 15. 2007 TO: FROM: SUBJECT:
More informationCommunity Update. June 8, 2011
Community Update June 8, 2011 Presented to: Scarborough Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough
More informationTHE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9
THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental
More informationTHE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9
THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental
More informationBOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM
BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: January 18, 2018 # 8 SUBJECT: ELECTION DISTRICT: Response to Board Member Initiative: Traffic Analysis and Safety Study of Waxpool Road
More informationU.S. System Summary: OHIO HUB
U.S. System Summary: OHIO HUB Ohio Hub High-Speed Rail System (Source: Ohio Hub Study, 2007) The Ohio Hub high-speed rail system is a system of proposed routes containing 864 miles in four segments with
More informationGirard Siding Environmental Assessment (EA) Public Meeting. May 23, 2013
Girard Siding Environmental Assessment (EA) Public Meeting May 23, 2013 1 Agenda» Program Overview» Girard Siding Project EA» Auburn to Shipman Track Improvement Project» Public Involvement Opportunities
More informationNORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3
NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 Varuna A. Singh August 17, 2018 NHHIP OVERVIEW Project divided into three segments: Segment 1: I-45: from Beltway 8 to I-610 (9 mi) 45 Segment
More informationPublic-Private Partnerships in Transit
Public-Private Partnerships in Transit Kristine Leiphart Deputy Associate Administrator Budget & Policy October, 2007 Outline of Presentation Federal Transit Administration (FTA) Role Public Private Partnership
More informationRelocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove
Finance, Administration and Oversight Committee Action Item III-J February 14, 2008 Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove Washington Metropolitan
More information# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report
BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM Date of Meeting: May 2, 2017 # I-2 SUBJECT: Quarterly Metrorail Construction Status Report ELECTION DISTRICTS: Ashburn/Broad Run STAFF CONTACTS: Alan
More information