1 Finance & Administration Committee Action Item III-A February 11, 2010 Rosslyn Station New Entrance

2 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: Rosslyn Station New Entrance PURPOSE: To obtain Board approval of: 1) The construction of the new Rosslyn Station entrance by Arlington County; and 2) Authorization for the General Manager to execute the Project Coordination Agreement among Metro, Arlington County and The JBG Companies for two projects at Rosslyn Station: the new entrance by Arlington County and Rosslyn Central Place(RCP) by JBG, all subject to Arlington County approval of the agreement on February 20, DESCRIPTION: The new entrance, known as the Rosslyn Station Access Improvements Project, consists of three new high-speed elevators, an underground station mezzanine and passageway connection, an emergency stairway, and related infrastructure and operating systems. Arlington County is funding the capital costs of the new entrance, including all Metro costs; thus, this is a reimbursable Metro project. On behalf of Arlington County, Metro is designing the new entrance via its on-call consultant, P2D. Subject to availability of funding, which will include federal and state grants, Arlington County will construct the new entrance from Fall 2010 to Spring Metro will own, operate and maintain the new entrance in early FY2013. The purpose of the new entrance is to support the increase in Metrorail customers from new high-density mixed-use developments, particularly RCP by The JBG Companies, which will be built adjacent to the station and integrated with the new entrance. JBG`s RCP Phase 1 will be a new office building of 31 stories and 531,000 square feet, the tallest in the metropolitan region. During construction of the new entrance and RCP, there will be uninterrupted station elevator service, via the one existing elevator or, when completed, the three elevators of the new entrance. After the three new elevators are in service, JBG will remove and abandon the upper part of the one existing elevator during

3 its construction of RCP underground parking. The Project Coordination Agreement among Metro, Arlington County and the JBG Companies addresses the coordinated construction, operations and maintenance of the new entrance and JBG`s RCP. In early February 2010, The JBG Companies will have signed the Project Coordination Agreement. At its February 20, 2010 meeting, the Arlington County Board will be considering approval of the Project Coordination Agreement, including authorization for the Arlington County Manager to execute the agreement. Staff will later request Board approval of a Phase Two Construction Agreement between Metro and Arlington County for the new entrance, which will address the roles and responsibilities of the two parties during the construction phase, will define the Metro procurement and installation of automatic fare collection equipment (AFC) and other equipment, and will establish Arlington County funding of Metro costs, to include AFC equipment, other equipment and Metro consultant costs. A Project Management Plan between Metro and Arlington County will include the project budget of Metro costs during the construction phase. FUNDING IMPACT: Project: Rosslyn Station New Entrance Department of Transit Infrastructure Office: and Engineering Services/Office of Engineering Service Budget: $4,207,000 This Action: $0 Prior Approval: $3,935,696 Remaining Budget: $271,304 No new budget authority is Remarks: requested with this action. (FY2010 Approved Budget Book Page 197) $830,000 in FY2013, offset by Annual Operating Budget Impact: increased revenue due to new development-related ridership RECOMMENDATION: Board approval of: 1) The construction of the new Rosslyn Station entrance by Arlington County; and 2) Authorization for the General Manager to execute the Project Coordination

4 Agreement among Metro, Arlington County and The JBG Companies for two projects at Rosslyn Station: the new entrance by Arlington County and Rosslyn Central Place by JBG, all subject to Arlington County approval of the agreement on February 20, 2010.

5 Rosslyn Station ti New Entrance Finance and Administration Committee February 11, 2010

6 Purpose To obtain Board approval of: 1) Construction of new Rosslyn Station entrance by Arlington County; and 2) Authorization for the General Manager to execute the agreement, all subject to Arlington County approval on February 20, 2010.

7 Background Due to major re-development of Rosslyn: New entrance is integrated with Rosslyn Central Place Metro designed new entrance for Arlington County under reimbursable agreement Arlington County will finance and construct new station entrance Metro will own, operate and maintain entrance, likely l commencing in early FY2013 Rosslyn Central Place

8 New Entrance Profile New entrance has Three elevators Emergency stairway Mezzanine with kiosk Full security systems Small chilled water plant Ele evators Sta airway Existing Station Mezzanine

9 New Entrance Plan at Surface Existing Station Entrance Existing Escalatorway and Elevator N. Moore Street New Entrance Central Place Phase 1 Tower Central Place Phase 2 Tower N. Lynn Street

10 Benefits: New Entrance Justification Replaces one existing elevator with three new ones Satisfies increased demand d for access Provides second emergency stairway Capital costs fully funded by Arlington County Costs: Increases Metro operating staff and costs, but offset by revenues from new development-related ridership New Entrance

11 Recommendation Board Approval of: 1) Construction of new Rosslyn Station entrance by Arlington County; and 2) Authorization for the General Manager to execute the agreement, all subject to Arlington County approval on February 20, 2010.

12 SUBJECT: APPROVE ROSSLYN STATION NEW ENTRANCE AND PROJECT COORDINATION AGREEMENT PROPOSED RESOLUTION OF THE BOARD of DIRECTORS OF THE WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY WHEREAS, Arlington County has approved the plans prepared by The JBG Companies to construct the Rosslyn Central Place development, proximate to and above Rosslyn Station; and WHEREAS, The developer has been required by Arlington County to accommodate a new station entrance to Rosslyn Station within the Rosslyn Central Place development; and WHEREAS, In coordination with the developer project, Arlington County has been and will be funding and managing, and proposes to construct the Rosslyn Station Access Improvements Project for the new station entrance, including three high-speed elevators, an exit stairway and a mezzanine proposed for Metro ownership, operations and maintenance upon their completion and acceptance; and WHEREAS, At the request of Arlington County and on a fully reimbursable basis, Metro with its on-call general architectural engineering services consultant is completing final design and contract documents of the Access Improvements Project for Arlington County; and WHEREAS, Metro, Arlington County, and the developer have negotiated a Project Coordination Agreement to address the coordinated construction, operation and maintenance of the Access Improvements Project for the new station entrance by Arlington County and of the Rosslyn Central Place development by the developer; and WHEREAS, Metro staff will later request Board of Directors approval of a Phase Two Construction Agreement between Metro and Arlington County, which addresses the roles and responsibilities of the two parties during the construction phase for the new station entrance; now, therefore be it RESOL VED/ That the Board of Directors approves Arlington County's construction of the Rosslyn Station Access Improvements Project for the new station entrance; and be it further

13 RESOL VED, That the Board of Directors authorizes the General Manager to execute the Project Coordination Agreement; and be it further RESOLVE~ That this Resolution shall be effective immediately. Reviewed as to form and legal sufficiency, ~rol B. o~v41j General Counsel 2

Approval of Medical Center New Entrance Agreement

Approval of Medical Center New Entrance Agreement Finance & Administration Committee Action Item III-A February 14, 2013 Approval of Medical Center New Entrance Agreement Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Neutral Host Reimbursable Capital Project

Neutral Host Reimbursable Capital Project Finance & Administration Committee Action Item III-E November 4, 2010 Neutral Host Reimbursable Capital Project Page 37 of 161 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Planning, Program Development and Real Estate Committee Item V- B September 11, 2014 Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Washington Metropolitan

More information

Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing

Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing Customer Services, Operations, and Safety Committee Board Information Item III-B September 24, 2009 Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing Washington Metropolitan Area

More information

Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove

Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove Finance, Administration and Oversight Committee Action Item III-J February 14, 2008 Relocation of Track & Structures Systems Maintenance (TSSM) Function from Twinbrook to Shady Grove Washington Metropolitan

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

MOU with Maryland DOT for New Carrollton Metrorail Station Transit-Oriented Development

MOU with Maryland DOT for New Carrollton Metrorail Station Transit-Oriented Development Joint Development and Real Estate Committee Item III-D June 24, 2010 MOU with Maryland DOT for New Carrollton Metrorail Station Transit-Oriented Development Page 33 of 41 Washington Metropolitan Area Transit

More information

Wireless Network (Neutral Host) Request for Proposals Update

Wireless Network (Neutral Host) Request for Proposals Update Finance, Administration and Oversight Committee Action Item III-B March 13, 2008 Wireless Network (Neutral Host) Request for Proposals Update Washington Metropolitan Area Transportation Authority Board

More information

Proposed FY 06 Project Development Program and FY 05 Project Development Program Update

Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Washington Metropolitan Area Transit Authority Proposed FY 06 Project Development Program and FY 05 Project Development Program Update Presented to the Board of Directors: P D E C Planning & Development

More information

Dupont Circle Escalator Replacement

Dupont Circle Escalator Replacement Customer Service and Operations Committee Board Information Item III-B December 1, 2011 Dupont Circle Escalator Replacement Page 46 of 71 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Metrobus 30s Line Enhancements

Metrobus 30s Line Enhancements Customer Service, Operations and Safety Committee Action Item III-C February 14, 2008 Metrobus 30s Line Enhancements Washington Metropolitan Area Transportation Authority Board Action/Information Summary

More information

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17 Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11

More information

BEVRLYRLY STAFF REPORT. Meeting Date: August 4, 2015 Item Number: To: From:

BEVRLYRLY STAFF REPORT. Meeting Date: August 4, 2015 Item Number: To: From: BEVRLYRLY STAFF REPORT Meeting Date: August 4, 215 Item Number: To: From: Honorable Mayor & City Council Mark Cuneo, City Engineer Aaron Kunz, Deputy Director of Transportation Subject: Update on Metro

More information

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary MEAD Number:

Washington Metropolitan Area Transit Authority Board Action/Information Summary MEAD Number: Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 102934 Resolution: Yes No TITLE Incident Communications Panel Discussion PRESENTATION SUMMARY

More information

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM Date of Meeting: # 9 SUBJECT: ELECTION DISTRICTS: STAFF CONTACTS: Public and Private Infrastructure Improvements Adjacent to the Dulles

More information

Metro Police Crime Statistics and Significant Facts

Metro Police Crime Statistics and Significant Facts Customer Services, Operations, and Safety Committee Board Information Item III-B December 17, 2009 Metro Police Crime Statistics and Significant Facts Page 15 of 46 Washington Metropolitan Area Transit

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0002, Ashburn Station North Broad Run CRITICAL ACTION DATE: STAFF

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The

More information

Dallas Streetcar Central Link Locally Preferred Alternative Selection

Dallas Streetcar Central Link Locally Preferred Alternative Selection Dallas Streetcar Central Link Locally Preferred Alternative Selection Mobility Solutions, Infrastructure & Sustainability Committee August 28, 2017 Tanya Brooks, Assistant Director Mobility and Street

More information

A RESOLUTION. WHEREAS, recent organizational changes require the appointment of an

A RESOLUTION. WHEREAS, recent organizational changes require the appointment of an RESOLUTION NO. 2013-76 APPOINTING ARACEL Y ALONSO AS ASSISTANT SECRETARY TO THE METRO BOARD OF DIRECTORS; AND MAKING FINDINGS AND PROVISIONS RELATED TO THE SUBJECT WHEREAS, recent organizational changes

More information

The Board grants site licenses for utilities that do not interfere with the park function.

The Board grants site licenses for utilities that do not interfere with the park function. Date: August 26, 2008 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Rogers Telecommunications Proposal - Hillcrest Park RECOMMENDATION A. THAT the Board enters

More information

Transparent Metro Data Sets

Transparent Metro Data Sets Customer Services, Operations, and Safety Committee Board Information Item IV-D July 8, 2010 Transparent Metro Data Sets Page 106 of 114 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Agenda Item No. AGENDA ITEM BRIEFING

Agenda Item No. AGENDA ITEM BRIEFING AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval to Amend the FY 2016-FY 2020 Texas A&M University

More information

Reston Town Center North Development. Community Update

Reston Town Center North Development. Community Update Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: Security Report - 2nd Quarter 2011 PURPOSE: The Metro Transit Police

More information

Report to the Business Administration Committee

Report to the Business Administration Committee Report to the Business Administration Committee Recommendation to Award a Contract to Replace Wi-Fi Infrastructure Systems at Ronald Reagan Washington National Airport and Washington Dulles International

More information

PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST

PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST THE CENTER THAT NEVER SLEEPS The greater New York metro area is a pulsing capital of industry and finance alive 24 x 7 x 365 with critical transactions

More information

A RESOLUTION. WHEREAS, On January 20, 2017, the inauguration of the 47th President of the United States of

A RESOLUTION. WHEREAS, On January 20, 2017, the inauguration of the 47th President of the United States of RESOLUTION 2016-130 APPROVING AN AGREEMENT WITH WASHINGTON METROPOLITAN TRANSIT AUTHORITY TO PROVIDE UP TO TEN POLICE OFFICERS IN SUPPORT OF SECURITY MEASURES FOR THE 2017 PRESIDENTIAL INAUGURATION; AND

More information

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201697 Resolution: Yes No TITLE: MTPD Security Updates PRESENTATION SUMMARY: The Metro Transit

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting

More information

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT: BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: March 13, 2018 # 7 SUBJECT: ELECTION DISTRICT: Contract Award/Roadway and Civil Design

More information

El Camino Community College El CAPITAL CONSTRUCTION PROJECTS 2013

El Camino Community College El CAPITAL CONSTRUCTION PROJECTS 2013 El Camino Community College CAPITAL CONSTRUCTION PROJECTS 2013 FACILITIES MASTER PLAN 2003 SCIENCE COMPLEX The Science Complex Building Project was completed in Spring 2005 for a total cost of $24,211,755.

More information

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS METRO SHORT RANGE TRANSIT PLAN FY 2010 2014 2014 Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS OVERVIEW Purpose of Metro SRTP Develop multi year strategic plan to improve transit quality,

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: Incident Customer Communications PURPOSE: To provide an update

More information

A RESOLUTION. WHEREAS, METRO is in need of executive search services to assist in its

A RESOLUTION. WHEREAS, METRO is in need of executive search services to assist in its RESOLUTION NO. 2013-40 AUTHORIZING THE PRESIDENT & CEO TO EXECUTE AND DELIVER A CONTRACT WITH KRAUTHAMER & ASSOCIATES FOR EXECUTIVE SEARCH FIRM SERVICES; AND MAKING FINDINGS AND PROVISIONS RELATED TO THE

More information

Traverse City Asset Management Plan

Traverse City Asset Management Plan Utilities and Public Services Larry LaCross, GISP, Asset Management/GIS Analyst Traverse City Department of Public Services Introduction About Traverse City (TC) TC Assets Department of Public Services

More information

Recommendation to Board. Final Action

Recommendation to Board. Final Action MOTION NO. M2017-59 City of Seattle Center City Mobility Plan Agreement MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 05/04/2017 05/25/2017 Recommendation

More information

PROSPECTUS ALTERATION PHILLIP BURTON FEDERAL BUILDING & U.S. COURTHOUSE SAN FRANCISCO, CA

PROSPECTUS ALTERATION PHILLIP BURTON FEDERAL BUILDING & U.S. COURTHOUSE SAN FRANCISCO, CA Prospectus Number: PCA-0154-S F15 FY2015 Project Summary The General Services Administration () proposes a repair and alteration project to upgrade several building systems and reconfigure existing space

More information

MVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014

MVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014 MVTA-Prior Lake-Shakopee Merger SCALE Presentation, October 10, 2014 MVTA Commitment Our Vision The Minnesota Valley Transit Authority is a trusted partner in transportation, serving as an innovative leader

More information

CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT

CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT 35 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net CONSTRUCTION COMMITTEE NOVEMBER 20, 2014 SUBJECT: ACTION: CONSTRUCTION MANAGEMENT CONSULTANT SUPPORT SERVICES CONTRACT INCREASE

More information

7900 HARKINS ROAD Lanham, MD

7900 HARKINS ROAD Lanham, MD 7900 HARKINS ROAD 7900 HARKINS ROAD This rare offering represents the opportunity to acquire a best-in-class office asset with guaranteed NNN cash flow for 12 years at a significant discount to replacement

More information

TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013

TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013 TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013 Introduction The Transport Chapter of the 1818 Society organized a tour of the Washington

More information

Committee Report. Management Committee Meeting date: October 10, Transportation Committee Meeting date: October 17, 2018

Committee Report. Management Committee Meeting date: October 10, Transportation Committee Meeting date: October 17, 2018 Committee Report Management Committee Meeting date: October 10, 2018 Transportation Committee Meeting date: October 17, 2018 That the Metropolitan Council authorizes the Regional Administrator to negotiate

More information

Dulles Area Transportation Association

Dulles Area Transportation Association Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements

More information

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public

More information

Report to: General Committee Date Report Authored: January 18, 2012

Report to: General Committee Date Report Authored: January 18, 2012 SUBJECT: Energy Services Agreement with Markham District Energy Inc. PREPARED BY: Henry Tse, P. Eng., Senior Project Manager, extension 2208 RECOMMENDATION: 1) THAT the report titled Energy Services Agreement

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of September 22, 2018

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of September 22, 2018 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 22, 2018 ATE: September 12, 2018 SUBJECT: Award of Contract ITB-18-273 to Crown Construction Co. for the construction of playground

More information

Our Mission: To provide technology resources for the County and set the vision for future technology investments

Our Mission: To provide technology resources for the County and set the vision for future technology investments Jack Belcher, Chief Information Officer 2100 CLARENDON BLVD., SUITE 612, ARLINGTON, VA 22201 703-228-3220 cio@arlingtonva.us Our Mission: To provide technology resources for the County and set the vision

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline Georgia Institute of Technology Advanced Computing Technology Building Draft Program Vision Program Outline Issued April 2, 2001 I N T R O D U C T I O N Scope This document is a summary of the Vision Session

More information

Washington Metropolitan Area Transit Authority. December 1, 2010

Washington Metropolitan Area Transit Authority. December 1, 2010 Washington Metropolitan Area Transit Authority Elevator/Escalator Assessment Riders Advisory Council December 1, 2010 1 Equipment Audit Findings ELEVATOR/ESCALATOR ASSESSMENT EQUIPMENT AUDIT FINDINGS Review

More information

Los Angeles County One Gateway Plaza 2i3.g Tel Metropolitan Transportation Authority Los Angeles, CA metro.net

Los Angeles County One Gateway Plaza 2i3.g Tel Metropolitan Transportation Authority Los Angeles, CA metro.net Metro Los Angeles County One Gateway Plaza 2i3.g22.2000 Tel Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net PLANNING AND PROGRAMMING COMMITTEE JULY 14,2010 SUBJECT: BUENA VISTA

More information

SITE DESCRIPTION. Vicinity

SITE DESCRIPTION. Vicinity SITE DESCRIPTION Vicinity The Montrose Shopping Center is located in the northeast quadrant of the intersection of Randolph Road and Rockville Pike (MD 355). The existing building (formally known as the

More information

The Blue Line Extension

The Blue Line Extension The Blue Line Extension NORTH CAROLINA JOINT TRANSPORTATION OVERSIGHT COMMITTEE Presented by Carolyn Flowers CATS Chief Executive Officer Raleigh, NC February 10, 2012 Overview Charlotte Area Transit System

More information

City of East Bethel City Council Agenda Special Meeting - 5:30 PM Date: July 10, 2013

City of East Bethel City Council Agenda Special Meeting - 5:30 PM Date: July 10, 2013 City of East Bethel City Council Agenda Special Meeting - 5:30 PM Date: July 10, 2013 Item 5:30 PM 1.0 Call to Order 5:31 PM 2.0 Adopt Agenda 5:32 PM 3.0 Castle Towers/Whispering Aspen 2013 Forcemain Project

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION 1 DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0001, Broad Run CRITICAL ACTION DATE: STAFF CONTACTS: APPLICANT:

More information

ALBEMARLE COUNTY SERVICE AUTHORITY

ALBEMARLE COUNTY SERVICE AUTHORITY ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA ITEM EXECUTIVE SUMMARY AGENDA TITLE: FY 2017 CIP Authorizations STAFF CONTACT(S)/PREPARER: Peter C. Gorham, P.E., Director of Engineering AGENDA DATE: March 16,

More information

Our Mission: To provide technology resources for the County and set the vision for future technology investments

Our Mission: To provide technology resources for the County and set the vision for future technology investments Jack Belcher, Chief Information Officer 2100 CLARENDON BLVD., SUITE 612, ARLINGTON, VA 22201 703-228-3220 cio@arlingtonva.us Our Mission: To provide technology resources for the County and set the vision

More information

ANNUAL ACCESSIBILITY STATUS REPORT

ANNUAL ACCESSIBILITY STATUS REPORT The Ontarians with Disabilities Act, 2001 The Accessibility for Ontarians with Disabilities Act, 2005 ANNUAL ACCESSIBILITY STATUS REPORT 2017 Township Council Accessibility Policy C-PD-03 Administrative

More information

Municipal Broadband Project. City Council Meeting February 4, 2016

Municipal Broadband Project. City Council Meeting February 4, 2016 Municipal Broadband Project City Council Meeting February 4, 2016 Broadband Timeline 12 Months February March 2015 Feasibility Study April May 2015 Business Plan Development June August 2015 Renegotiation

More information

# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report

# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM Date of Meeting: May 2, 2017 # I-2 SUBJECT: Quarterly Metrorail Construction Status Report ELECTION DISTRICTS: Ashburn/Broad Run STAFF CONTACTS: Alan

More information

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension MOTION NO. M2018-30 Task Order 2 with the City of Des Moines for the Federal Way Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 03/08/2018 Final Action Ahmad Fazel, DECM

More information

JOINT DEVELOPMENT. Partnering to Build Complete Communities Near Transit

JOINT DEVELOPMENT. Partnering to Build Complete Communities Near Transit JOINT DEVELOPMENT Partnering to Build Complete Communities Near Transit September 2017 Joint Development Examples of joint development include: Transit systems create value in surrounding real estate.

More information

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m. AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting July 9, 2014 Executive Director Approval

More information

Region of Waterloo Corporate Services Facilities & Fleet Management

Region of Waterloo Corporate Services Facilities & Fleet Management Region of Waterloo Corporate Services Facilities & Fleet Management To: Chair Tom Galloway and Members of the Planning & Works Committee Date: February 14, 2017 File Code: Subject: King-Victoria Transit

More information

THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM

THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM SFMTA s current Central Control Center is severely outdated and under staffed. The lack of proper functional

More information

CITY OF NORTH OLMSTED ORDINANCE NO

CITY OF NORTH OLMSTED ORDINANCE NO CITY OF NORTH OLMSTED ORDINANCE NO. 2011-74 BY: Mayor Kennedy AN ORDINANCE AMENDING SECTION 915.04 OF THE CODIFIED ORDINANCES OF THE CITY OF NORTH OLMSTED TO ESTABLISH REVISED CHARGES FOR THE USE OF THE

More information

Item IV Transfer of On-site Natural Gas Distribution System

Item IV Transfer of On-site Natural Gas Distribution System Item IV Transfer of On-site Natural Gas Distribution System PRESENTED BY Angela M. Poole CPA, Vice President Finance and Administration/CFO and Sameer Kapileshwari P.E., Associate Vice President for Facilities

More information

Bike Sharing Feasibility Study and Implementation Plan 2012

Bike Sharing Feasibility Study and Implementation Plan 2012 Source: Nice Ride (Twin Cities MN) Source: Capital Bikeshare (Washington, DC) City of Cleveland Bike Sharing Feasibility Study and Implementation Plan 2012 November 20, 2013 Toole Design Group BrownFlynn,

More information

REPORT TO THE BUSINESS ADMINISTRATION COMMITTEE

REPORT TO THE BUSINESS ADMINISTRATION COMMITTEE REPORT TO THE BUSINESS ADMINISTRATION COMMITTEE RECOMMENDATION TO AWARD A SOLE SOURCE CONTRACT FOR MAINTENANCE AND TECHNICAL SUPPORT OF THE CENTRAL HEATING AND COOLING PLANT S DISTRIBUTED CONTROL SYSTEM

More information

FAIRFIELD COUNTY S PREMIER TECHNOLOGY CENTER River Bend 2

FAIRFIELD COUNTY S PREMIER TECHNOLOGY CENTER River Bend 2 FAIRFIELD COUNTY S PREMIER TECHNOLOGY CENTER River Bend 2 River Bend 6 River Bend 11 RIVER BEND CENTER OVERVIEW 7 8 6 1 2 12 highly flexible buildings situated on 40 sprawling acres in the Springdale section

More information

S T A F F R E P O R T

S T A F F R E P O R T S T A F F R E P O R T Meeting Date: 04 Jul 2017 To: Prepared By: Reviewed/Approved By: Department Report No: Subject: Corporate Strategic Plan: Mayor and Members of Council Lynn Phillips Tim Blake, Valerie

More information

Rail Division Update. Presented to Joint Appropriations Subcommittee on Transportation. Paul C. Worley, CPM Rail Division Director February 28, 2013

Rail Division Update. Presented to Joint Appropriations Subcommittee on Transportation. Paul C. Worley, CPM Rail Division Director February 28, 2013 Rail Division Update Presented to Joint Appropriations Subcommittee on Transportation Paul C. Worley, CPM Rail Division Director February 28, 2013 0 Rail in North Carolina Over 3,500 miles of rail lines.

More information

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO

More information

Transportation Research Forum

Transportation Research Forum Joseph F. Trainor, P.E., Vice President & Chief Engineer Transportation Research Forum March 23, 2006 Number 7 Subway Line Extension Project Background No. 7 Project Context Far West Midtown Manhattan

More information

Westside Subway Extension of the Metro Purple Line

Westside Subway Extension of the Metro Purple Line metro.net/works Westside Subway Extension of the Metro Purple Line Station Fact Sheet fall 2012 Background Station Overview Work to bring the Metro Purple Line to the Westside is moving forward, with plans

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 11, 2016 SUBJECT: Request to ratify advertisement of public hearings by the Planning Commission and the County

More information

LOUISVILLE UTILITY AND PUBLIC WORKS ADVISORY GROUP UTILITY OPERATIONS REVIEW

LOUISVILLE UTILITY AND PUBLIC WORKS ADVISORY GROUP UTILITY OPERATIONS REVIEW 14 Marrch 2012 LOUISVILLE UTILITY AND PUBLIC WORKS ADVISORY GROUP UTILITY OPERATIONS REVIEW OVERVIEW Introduction Industry Overview Management Best Practices Benchmarking Other Utility Governance Models

More information

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE:

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: MOTION NO. M2014-04 Contract for On-call Sustainability Consulting Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: Operations and Administration Committee PROPOSED ACTION 03/06/14 Final Action

More information

Gigabit West Sussex. Report to Cabinet. Executive Summary. Recommendations. Reasons for Recommendations. Background Papers

Gigabit West Sussex. Report to Cabinet. Executive Summary. Recommendations. Reasons for Recommendations. Background Papers Report to Cabinet 21 st September 2017 By the Cabinet Member for Finance & Assets DECISION REQUIRED Not Exempt Gigabit West Sussex Executive Summary This report explains the reasons why the Council should

More information

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time. TO WHOM IT MAY CONCERN: NOTICE OF RE-SCHEDULED BOARD MEETINGS This is notice that the re-scheduled meetings of the Board of Directors of the New Jersey Transit Corporation, NJ Transit Rail Operations,

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: Security Report PURPOSE: To present to the Board of Directors,

More information

Joint Committee Report

Joint Committee Report J Joint Committee Report Transporation Committee (April 27, 2009) Management Committee (May 13, 2009) For the Metropolitan Council meeting of May 13, 2009 Item: SW 2009-138 Date Prepared: Subject: Cooperative

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT

STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT CURRENT STATE THE C&W WAY College athletic departments throughout the country are spending at an unprecedented pace to develop and renovate facilities

More information

PUBLIC WORKS ORGANIZATIONAL CHART

PUBLIC WORKS ORGANIZATIONAL CHART PUBLIC WORKS ORGANIZATIONAL CHART C-108 Actual 2012-13 Adopted Year-End Estimated 2014-15 2015-16 PROGRAM EXPENSES/REVENUES Salaries & Benefits $ 1,725,030 $ 1,855,980 $ 1,676,130 $ 1,956,510 $ 1,979,470

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

Lease of City-Owned Property at 455 Industrial Ave to United We Can

Lease of City-Owned Property at 455 Industrial Ave to United We Can Lease of City-Owned Property at 455 Industrial Ave to United We Can 1 Kevin McNaney, Assistant Director of Planning Standing Committee on City Finance and Services May 16, 2013 United We Can (UWC) UWC

More information

AGENDA 5. ALBERT ROBLES CENTER (ARC) DESIGN-BUILD PROJECT PROGRESS REPORT 6. ALBERT ROBLES CENTER (ARC) OUTREACH PROGRAMS UPDATE

AGENDA 5. ALBERT ROBLES CENTER (ARC) DESIGN-BUILD PROJECT PROGRESS REPORT 6. ALBERT ROBLES CENTER (ARC) OUTREACH PROGRAMS UPDATE CAPITAL IMPROVEMENT PROJECTS (CIP) COMMITTEE WATER REPLENISHMENT DISTRICT OF SOUTHERN CALIFORNIA 4040 PARAMOUNT BLVD., LAKEWOOD, CA. 90712 11:00 AM, WEDNESDAY, JULY 11, 2018 AGENDA Each item on the agenda,

More information

GOAL 1: To develop an on-campus chilled water generation and distribution system that adequately serves the future campus population needs.

GOAL 1: To develop an on-campus chilled water generation and distribution system that adequately serves the future campus population needs. CHILLED WATER SUB-ELEMENT GOAL 1: To develop an on-campus chilled water generation and distribution system that adequately serves the future campus population needs. OBJECTIVE 1.1: To ensure that there

More information

Metropolitan Council meeting: February 22, 2012

Metropolitan Council meeting: February 22, 2012 Business Item T Transportation Committee Item: 202-29 Meeting date: January 23, 202 REVISED Metropolitan Council meeting: February 22, 202 ADVISORY INFORMATION Date: February 2, 202 Subject: Light Rail

More information

MOTION NO. M Contract Amendment for Technology Software, Hardware, and Related Maintenance Services

MOTION NO. M Contract Amendment for Technology Software, Hardware, and Related Maintenance Services MOTION NO. M2017-67 Contract Amendment for Technology Software, Hardware, and Related Maintenance Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee 05/04/2017

More information

Financing AirRail Projects Jean-Pierre Labuschagne 7 October 2016

Financing AirRail Projects Jean-Pierre Labuschagne 7 October 2016 Financing AirRail Projects Jean-Pierre Labuschagne 7 October 2016 Contents 1. Challenges of passenger rail financing 2. Different models 3. South African ideas 4. Conclusion 2016. For information, contact

More information

Georgia World Congress Center Authority

Georgia World Congress Center Authority Georgia World Congress Center Authority BOARD OF GOVERNORS MEETING August 28, 2018 Authority Financial Facility ACTION ITEM Approval of Minutes July 31, 2018 JULY FINANCIAL UPDATE Janet Arsenault Sr. Director

More information

Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE

Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Achieving Compact & Connected Engaging in a regional transit discussion Pursuing a compact

More information

Annual Accessibility Status Report 2017

Annual Accessibility Status Report 2017 Annual Accessibility Status Report 2017 A summary of Norfolk County s accomplishments towards inclusion in 2016, and looking ahead to 2017. Accessible formats and communication supports available upon

More information

Request For Proposals. Information Technology (IT) Services. General: The City of Bishop requests proposals from consultants to provide IT services.

Request For Proposals. Information Technology (IT) Services. General: The City of Bishop requests proposals from consultants to provide IT services. Release: 10 June 2014 Closes: 27 June 2014 CITY OF BISHOP 377 West Line Street - Bishop, California 93514 Post Office Box 1236 - Bishop, California 93515 760-873-8458 publicworks@ca-bishop.us www.ca-bishop.us

More information

Greater Toronto Area

Greater Toronto Area Greater Toronto Area Transit Fare System Smart Card Alliance Transportation Council Salt Lake City, March 2007 David McIlwraith Ontario Topics GTA Fare System Overview Project Preparation Current Status

More information