1 P. O. Box 52025, MS POB100 Phoenix, Arizona (602) Feb 9, 2018 Peter Mackin Chair, WECC Studies Subcommittee Utility System Efficiencies, Inc. Phone: (916) Doug Tucker WECC Technical Staff Western Electricity Coordinating Council 155 North 400 West, Suite 200 Salt Lake City, Utah Subject: Salt River Project 2018 Annual Progress Report Mr. Mackin and Mr. Tucker, Attached is Salt River Project s 2018 Annual Progress Report to WECC in accordance with WECC Progress Report Policies and Procedures. If you have any questions contact me at (602) Sincerely, Philip Augustin, PE STS Representative Principal Electrical Engineer SRP, Transmission Analysis cc: Zack Heim SRP, Michael Jones SRP Eldin Dizdarevic

2 Transmission Additions and Changes 2018 Annual Progress Report to WECC Salt River Project The following projects will be reported in the 2018 Existing Generation and Significant Additions and Changes to System Facilities report in accordance with section five of the WECC Project Coordination, Path Rating and Progress Report Processes guideline. Transmission Additions and Changes - Waiver of Significant Transmission Project Status Request As of February 9 th SRP does not have any new projects seeking a waiver of Significant Transmission Project status. 2

3 Transmission Additions and Changes Projects Granted a Waiver of Significant Transmission Project Status The following transmission additions and changes received a waiver of Significant Transmission Project status in Browning Corbell 230kV & Santan Rogers 230kV Line Reconfiguration Estimated date of operation: 2019 Browning 230kV Substation and Santan 230kV Substation None Corbell 230kV Substation and Rogers 230kV Substation Approximately 13 miles The purpose of the project is to create a third 230kV circuit serving the Corbell 230/69kV substation and prevent the loss of the Corbell 69kV area in the event of multiple 230kV line outages. This is a reliability driven project and is not triggered by rising system load levels forecasted in the next ten years. The Browning Corbell line reconfiguration will follow the current route of the Browning Santan and Santan Corbell 230kV lines. Reconfiguration of the line will be done in tandem with reconfiguration of Santan Rogers 230kV line. 2. Price Road Corridor Estimated date of operation: 2021 Knox 230kV Substation New Henshaw 230kV Substation Approximately 7 miles The purpose of the project is to serve growing industrial and commercial customer loads along the Price Road Corridor, adjacent to Price Road in south Tempe and Chandler. Line routes will be determined through the CEC process. The project will consist of a new 230kV Henshaw Substation will be located in the southern portion of the Price Road Corridor, The project will consist a new double circuit Knox Henshaw 230kV line. 3

4 3. Abel Pfister - Ball 230kV line Estimated date of operation: 2021-TBD Santan - Schrader 230kV line (near existing Moody 69kV Substation and future Ball (RS17) 230kV Substation) New Pfister (RS24) 230kV Substation Abel 230kV Substation Approximately 20 miles Estimated in-service dates are: Abel Santan 230kV line Abel - Schrader 230kV line TBD - Pfister Substation TBD Ball Substation The purpose of the project is to accommodate near term new generation resources in the Abel area. This is a reliability driven project and is not triggered by rising system load levels forecasted in the next ten years. The project is a double circuit 230kV line and a new 230kV substation that connects to the existing Santan - Schrader 230kV line. The new double circuit 230kV line will be routed generally south and east from a point on the Santan - Schrader 230kV line near the existing Moody 69kV Substation and future Ball (RS-17) 230kV Substation to the new Pfister (RS-24) 230kV Substation in the southeastern portion of the town of Queen Creek. From Pfister 230kV Substation, the 230kV line will continue south and east to the Abel 230kV Substation. 4. Copper Crossing Abel 230kV Estimated date of operation: 2023 New Copper Crossing 230kV Substation Abel 230kV Substation Less than 1 mile The purpose of this project is to accommodate near term new generation resources connecting in the Abel area. This is a reliability driven project and is not triggered by rising system load levels forecasted in the next ten years. The project is a double circuit 230kV line and a new 230kV switchyard. 4

5 5. Southeast Power Link Estimated date of operation: 2024 Intermediate Points Section of Santan Browning 230kV Line RS kV and RS kV substations Section of Abel Pfister Ball 230kV Line To meet potential growing customer loads in the southeast valley. Analysis indicates that adding one or two new 230kV substations and a connection between the existing Santan Browning corridor to the future Abel Pfister Ball corridor would provide the greatest benefit to the area. The location of the 230kV substations and any new lines will be determined by the public siting process and load growth in the area. 6. Hassayampa Pinal West #2 500kV line Estimated date of operation: 2024 Hassayampa 500kV Substation Jojoba 500kV Substation Pinal West 500kV Substation Approximately 51 miles The Central Arizona Transmission System Study identified a number of system additions to accommodate load growth and access to energy sources in western or central Arizona. This project is needed to fulfill Arizona s Implementation Plan resulting from the EPA s ruling on Section 111(d) of the Clean Air Act. This is a reliability driven project and is not triggered by rising system load levels forecasted in the next ten years. The route is south and east of the Hassayampa Switchyard along the existing Hassayampa Jojoba Kyrene 500kV line to a point where the gas pipeline splits from the transmission line, then generally along the pipeline (except in the Maricopa County Mobile Planning Area) to the Pinal West Substation. 5

6 7. Silver King New Oak Flat New Superior 230kV line Estimated date of operation: 2026 Silver King 230kV Substation New Oak Flat 230kV Substation New Superior 230kV Substation Approximately 6.5 miles The purpose of the project is to serve growing customer loads at Oak Flat and Superior. The line starts at the Silver King Receiving Station, heading south and then turning southwest into the New Oak Flat 230kV Substation. The alignment will then traverse to the west into the New Superior 230kV Substation. The location of the New Oak Flat and the New Superior sites are still being determined. 6

SRP Ten Year Transmission Plan

SRP Ten Year Transmission Plan 2018 SRP Ten Year Transmission Plan 2018-2027 Prepared for the Arizona Corporation Commission January 2018 Docket No. E-00000D-17-0001 Page1 Page1 Table of Contents 1. Introduction... 1 2. Planning Organizations...

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D (.laps Lisa Malagon Leader Federal and State Compliance Mail Station 9704 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250- 5671 Elisa.Malagon@aps.com January 31, 2014 Docket Control Arizona Corporation

More information

February 25, Subject: Southern California Edison 2015 Annual Progress Report

February 25, Subject: Southern California Edison 2015 Annual Progress Report February 25, 2015 Mr. Tracy Rolstad, Chair WECC Technical Studies Subcommittee Avista Corp. 1411 East Mission Avenue Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff Salt Lake City, UT 84103-1114

More information

TUCSON ELECTRIC POWER COMPANY TEN YEAR PLAN FOR YEARS

TUCSON ELECTRIC POWER COMPANY TEN YEAR PLAN FOR YEARS TEN YEAR PLAN FOR YEARS 2012-2021 SUBMITTED TO THE ARIZONA CORPORATION COMMISSION JANUARY 2012 DOCKET NO: E-00000D-11-0017 CONTENTS INTRODUCTION... 3 Tortolita 500/138kV Transformer T3... 13 Vail 345/138kV

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

TransWest Express and Gateway South

TransWest Express and Gateway South TransWest Express and Gateway South Co-developed by four leading entities: Arizona Public Service PacifiCorp National Grid Wyoming Infrastructure Authority Regional Stakeholder Meeting January 23, 2008

More information

Executive Summary. City of Goodyear. Prepared for: Prepared by: November, 2008 Copyright 2008, Kimley-Horn and Associates, Inc.

Executive Summary. City of Goodyear. Prepared for: Prepared by: November, 2008 Copyright 2008, Kimley-Horn and Associates, Inc. Goodyear Intelligent Transportation Systems Strategic Plan Executive Summary Prepared for: City of Goodyear Prepared by: 191376000 Copyright 2008, Kimley-Horn and Associates, Inc. I. INTRODUCTION The City

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

Presentation to Local/State/Federal Agency Mtg November 10, 2015

Presentation to Local/State/Federal Agency Mtg November 10, 2015 Presentation to Local/State/Federal Agency Mtg November 10, 2015 Summary Proposed 114 mile 500 kv transmission project that will connect with Delaney Substation near Palo Verde Nuclear Generating Station,

More information

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011 Western DSW Planning Stakeholder Meeting (Western OATT Attachment P) June 9, 2011 Agenda: 1. Welcome and Introductions of Attendees 2. Planning Process 3. Interconnection Requests 4. Comments/questions

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

Municipal Service Park 3 December Consolidation of City services to one centralized complex

Municipal Service Park 3 December Consolidation of City services to one centralized complex Municipal Service Park 3 December 2010 Consolidation of City services to one centralized complex Overview: Operational Challenges and Opportunities South East Connector impacts Opportunities: The South

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE Prepared by

CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE Prepared by CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE 2445 Prepared by BC HYDRO AUGUST 2008 Table of Contents Background... 2 Ductbank on South West... 3 Ampacities at Maximum... 3 at Recent Maximum Demands...

More information

Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays

Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays Prepared by the System Protection and Control Task Force of

More information

2055 E TECHNOLOGY CIRCLE

2055 E TECHNOLOGY CIRCLE 2055 E TECHNOLOGY CIRCLE TEMPE, ARIZONA PROPERTY SPECIFICATIONS 2055 E Technology Circle, Tempe Location Within the Arizona State University Research Park, Tempe s largest corporate campus Building Description

More information

Discussion Guide. Benvoulin Substation Project.

Discussion Guide. Benvoulin Substation Project. Discussion Guide Benvoulin Substation Project A Growing Region South Central Kelowna has experienced substantial growth over the last ten years. FortisBC is enhancing the electrical power supply system

More information

Flexible Grant Program- Innovative Approaches to Provide Broadband Service to Unserved Towns NOFA No MBI-01 Response from:

Flexible Grant Program- Innovative Approaches to Provide Broadband Service to Unserved Towns NOFA No MBI-01 Response from: Flexible Grant Program- Innovative Approaches to Provide Broadband Service to Unserved Towns NOFA No. 2018-MBI-01 Response from: Massachusetts Technology Collaborative 75 North Drive Westborough, MA 01581-3340

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

Planning for the Future

Planning for the Future Gas/Electric Partnership Conference Planning for the Future February 1, 2018 Entergy Texas, Inc. Entergy Texas, Inc. Staci Meyer Manager, Resource Planning Jeff Dicharry Manager, Transmission Planning

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

We invite your input and appreciate your cooperation. If you have any questions please feel free to contact me or your Land Rights Management Agent.

We invite your input and appreciate your cooperation. If you have any questions please feel free to contact me or your Land Rights Management Agent. Conflict Review Requestor/Customer: Thank you for considering the impact of your project upon the operation and maintenance of SRP facilities. In order to accommodate your needs in a responsible manner

More information

PREMIER DATA CENTER OPPORTUNITY ±64.31 ACRES OF LAND ENGLER BLVD AND HWY 212 Chaska, MN 55318

PREMIER DATA CENTER OPPORTUNITY ±64.31 ACRES OF LAND ENGLER BLVD AND HWY 212 Chaska, MN 55318 -$2.50/GROSS SF CLOVER PRESERVE DR PROPERTY HIGHLIGHTS + + Preliminary plat approved. Data center site, shovel ready + + 25MW service to the site via adjacent, double-ended substation with multiple feeds

More information

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax: B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: 0-- E-mail: janet.fraser@bctc.com October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street,

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

Data Center Site Assessment and Tiered Designation Program. Northport Industrial Park North Mankato, MN Executive Site Summary

Data Center Site Assessment and Tiered Designation Program. Northport Industrial Park North Mankato, MN Executive Site Summary Data Center Site Assessment and Tiered Designation Program Northport Industrial Park North Mankato, MN Executive Site Summary Northport Industrial Park North Mankato, MN Econdev.greatriverenergy.com Summary

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

RE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line

RE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line Dominion Energy P.O. Box 26666, Richmond, VA 23261 DominionEnergy.com David J. DePippo Senior Counsel Direct: (804) 819-2411 Facsimile: (804) 819-2183 david.j.depippo@dominionenergy.com Via Email Ms. Anna

More information

Washington City. September Capital Facilities Plan- Electrical

Washington City. September Capital Facilities Plan- Electrical Washington City Capital Facilities Plan- Electrical September 2007 Intermountain Consumer Professional Engineers, Inc. 1145 East South Union Avenue Midvale, Utah 84047 (801) 255-1111 TABLE OF CONTENTS

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

Increasing Operational Efficiency with the PI System at SRP USERS GROUP

Increasing Operational Efficiency with the PI System at SRP USERS GROUP Increasing Operational Efficiency with the PI System at SRP Presented by Cory Fisher, EMS Engineer Agenda About SRP The Necessity of Historical Data PI System Value, Out-of-the-Box Homebrew PI Applications

More information

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT 16 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 18, 2015 SUBJECT: ACTION: EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF

More information

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group SUNZIA SOUTHWEST TRANSMISSION PROJECT David Getts General Manager SouthWestern Power Group PROJECT UPDATE NEW MEXICO RETA 8.22.12 SouthWestern Power Group Independent developer of utility-scale generation

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Increasing Operational Efficiency with the PI System at SRP

Increasing Operational Efficiency with the PI System at SRP Increasing Operational Efficiency with the PI System at SRP Presented by Cory Fisher 1 Agenda About SRP The Necessity of Historical Data PI System Value, Out-of-the-Box Homebrew PI System Applications

More information

Appendix F Notices

Appendix F  Notices Appendix F Email Notices 2015 2016 Scoping Period From: Sent: To: Subject: CoSu Line Project on behalf of CoSu Line Project Friday, December

More information

WON Security Guideline

WON Security Guideline WON Security Guideline Data Exchange Work Group October 7, 2015 155 rth 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WON Security Guideline 1 Table of Contents Purpose... 1 Background... 1 Security

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC Order 1000, 2018-19 Biennial Planning Cycle Quarter 2 Meeting June 14, 2018 PAGE 2 Agenda Pacific Time Topic Presenter 9:00 9:05 Greetings and

More information

CC Docket Notice of Detariffing of Common Carrier Wireline Broadband Internet Access Transmission Service

CC Docket Notice of Detariffing of Common Carrier Wireline Broadband Internet Access Transmission Service South Central COMMUNICATIONS P.O. BOX 555 ESCALANTE, UTAH 84726 (435) 826-4211 Marlene H. Dortch, Secretary Federal Communications Commission 445 lih Street, SW Washington, D.C. 20554 Re: CC Docket 02-33

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Background Power Grid has evolved from a vertically integrated

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

Preliminary 2010 Revenue Requirements. Appendix D. O&M Savings Report

Preliminary 2010 Revenue Requirements. Appendix D. O&M Savings Report O&M Savings Report 0 0 Implementation of different projects within the capital plan can result in an increase, decrease or have little to no effect on operating costs depending on the nature of the work

More information

Appendix A Existing Surface Utilities

Appendix A Existing Surface Utilities Appendix A Existing Surface Utilities PRELIMINARY INFRASTRUCTURE STUDY PROPOSED DUSEL SITE GILES COUNTY, VIRGINIA Prepared for: Kimballton Deep Underground Science and Engineering Laboratory Kimballton

More information

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019 ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019 Introduction Throughout 2015 and 2016 the structure of committees in the Western Electricity

More information

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014 I-20 EAST TEXAS CORRIDOR STUDY TxDOT Planning Conference, Corpus Christi June 4 th, 2014 Table of Contents 1 Introduction 3-5 2 I-20 East Texas Corridor Advisory Committee 6-10 3 Study Schedule 11-12 4

More information

Western Interconnection

Western Interconnection Transmission Planning in the Western Interconnection Supporting Resource Development NWCC/NCSL Transmission Policy Institute Byron Woertz, Senior Project Manager Denver, CO June 17, 2010 Overview A Few

More information

Memorandum. To: Federal Communications Commission (FCC) Staff. From: Fall River Rural Electric Cooperative, Inc. Date: 3/6/2014

Memorandum. To: Federal Communications Commission (FCC) Staff. From: Fall River Rural Electric Cooperative, Inc. Date: 3/6/2014 Memorandum To: Federal Communications Commission (FCC) Staff From: Fall River Rural Electric Cooperative, Inc. Date: 3/6/2014 Re: Expression of Interest Rural Trials Docket No. 10-90 Background Fall River

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Year Assessment Preliminary Solutions

Year Assessment Preliminary Solutions 2016 10-Year Assessment Preliminary Solutions Stakeholder and Customer Presentation May 26, 2016 Jeremy Voigt Purpose Summarize Asset Renewal Solution Identification Process Summarize Preliminary Changes

More information

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works Item 7.3.5 Meeting date: August 13, 2018 Department: Prepared by: Reviewed by: SUBJECT: Engineering & Public Works COUNCIL REPORT George Elliott, P.Eng., Director of Engineering & Public Works Greg McClinchey,

More information

Seattle ITS Resiliency Project. ITS California Jason Cambridge September 19th, 2017

Seattle ITS Resiliency Project. ITS California Jason Cambridge September 19th, 2017 Seattle ITS Resiliency Project ITS California Jason Cambridge September 19th, 2017 1 Our mission, vision, and core values Mission: deliver a high-quality transportation system for Seattle Vision: connected

More information

37 SOUTH LAKESIDE OFFICE PARK

37 SOUTH LAKESIDE OFFICE PARK 4705 S. Old Hwy 37, Lakeland, Fl 33813 PROPERTY HIGHLIGHTS FREESTANDING OFFICES SOUTH LAKELAND 5,000 SF AVAILABLE RECENTLY REMODELED MATURE, SERENE LANDSCAPING AMPLE ON-SITE PARKING SIX ACRE OFFICE PARK

More information

Assimilating GIS-Based Voter Districting Processes in Maricopa County, Arizona

Assimilating GIS-Based Voter Districting Processes in Maricopa County, Arizona Assimilating GIS-Based Voter Districting Processes in Maricopa County, Arizona Tim Johnson Geographic Information Systems Manager Maricopa County Recorder/Elections Department Abstract Accurate district

More information

NERC History, Mission and Current Issues Southern States Energy Board. October 16, 2011

NERC History, Mission and Current Issues Southern States Energy Board. October 16, 2011 NERC History, Mission and Current Issues Southern States Energy Board October 16, 2011 Electricity Vital to America 2 RELIABILITY ACCOUNTABILITY Risk Curve with Actual Events Severity ( Log Base 10) 2003

More information

APPENDIX C SOURCES & REFERENCES CITED

APPENDIX C SOURCES & REFERENCES CITED APPENDIX C SOURCES & REFERENCES CITED Sources & References Cited Chapter 1 City of Minneapolis. 2007. Access Minneapolis Ten Year Transportation Action Plan. Connetics Transportation Group. 2012. Transit

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

Transit Development Plan/Transportation Demand. Chuck Steigerwald Director of Strategic Planning. Management Plan

Transit Development Plan/Transportation Demand. Chuck Steigerwald Director of Strategic Planning. Management Plan Transit Development Plan/Transportation Demand Chuck Steigerwald Director of Strategic Planning Management Plan OmniRide Strategic Plan Phase III TDP/TDMP Recommended service changes Ten-year plan Final

More information

TRIBAL WATER AND WASTEWATER OPERATOR CERTIFICATION PROGRAM TRAINING ANNOUNCEMENT WATER DISTRIBUTION LEVEL 2 TRAINING AND CERTIFICATION EXAM FOR WATER

TRIBAL WATER AND WASTEWATER OPERATOR CERTIFICATION PROGRAM TRAINING ANNOUNCEMENT WATER DISTRIBUTION LEVEL 2 TRAINING AND CERTIFICATION EXAM FOR WATER TRIBAL WATER AND WASTEWATER OPERATOR CERTIFICATION PROGRAM TRAINING ANNOUNCEMENT WATER DISTRIBUTION LEVEL 2 TRAINING AND CERTIFICATION EXAM FOR WATER OPERATORS Hosted by the Salt River Pima-Maricopa Indian

More information

Multiple Listing Service of Southern Arizona Monthly Statistics December 2018

Multiple Listing Service of Southern Arizona Monthly Statistics December 2018 For Immediate Release: January, 9 CONTACT: Cheryl Terpening MLSSAZ President (5) 97-7 Sean Murphy Executive Vice President (5) -79 Randy Rogers CEO, MLSSAZ (5) 7- Multiple Listing Service of Southern Arizona

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES PROOF OF SERVICE NOTICE TO COMMUNITY ORGANIZATIONS PUBLIC NOTICE NOTICE IN UTILITY BILLS NOTICE OF OWNERS OF PROPERTY

More information

NEW TxDOT CONGESTION RELIEF PROGRAM

NEW TxDOT CONGESTION RELIEF PROGRAM NEW TxDOT CONGESTION RELIEF PROGRAM REGIONAL TRANSPORTATION COUNCIL January 14, 2016 BACKGROUND Expedite congestion relief projects TxDOT to allocate $1.0 billion -$1.3 billion statewide Need early construction

More information

Decision on the 2012/2013 ISO Transmission Plan

Decision on the 2012/2013 ISO Transmission Plan Decision on the 2012/2013 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 20-21, 2013 Approving the plan means approving

More information

Local Area Studies Update - PACW Kevin Putnam

Local Area Studies Update - PACW Kevin Putnam Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network

More information

GIS Based Tools for County Road Management Crash Data Analysis Application. January 12, 2012

GIS Based Tools for County Road Management Crash Data Analysis Application. January 12, 2012 GIS Based Tools for County Road Management Crash Data Analysis Application January 12, 2012 Good News: Crash Rates for All Types of Crashes in Unincorporated Maricopa County Are Declining 2,000 Crashes

More information

SWLRT Community Advisory Committee Meeting. June 27, 2013

SWLRT Community Advisory Committee Meeting. June 27, 2013 SWLRT Community Advisory Committee Meeting June 27, 2013 Today s Topics Welcome and Introductions Hennepin County Works Update: TSAAP Open House Summary Mind-Mixer Demonstration Focus Group Outreach Technical

More information

StonePointe Corporate Center 2525 N. 12th Street, Reading, PA 19605

StonePointe Corporate Center 2525 N. 12th Street, Reading, PA 19605 For Lease up to 150,000 SF Industrial Flex Space StonePointe Corporate Center 2525 N. 12th Street, 19605 Property Features Open Floor Plans Low Operating Costs Heavy Infrastructure Plug and Play capabilities

More information

Information Technology Community Involvement

Information Technology Community Involvement Information Technology Community Involvement Tom Hoover Associate Vice Chancellor Helping students achieve through technology Information Technology at the University of Tennessee Chattanooga is focused

More information

Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE

Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Making Mobility Better, Together JANUARY 31, 2013 AUSTIN CITY COUNCIL PROJECT CONNECT REGIONAL TRANSIT UPDATE Achieving Compact & Connected Engaging in a regional transit discussion Pursuing a compact

More information

ENHANCED PARKWAY STUDY: PHASE 3 REFINED MLT INTERSECTION ANALYSIS

ENHANCED PARKWAY STUDY: PHASE 3 REFINED MLT INTERSECTION ANALYSIS ENHANCED PARKWAY STUDY: PHASE 3 REFINED MLT INTERSECTION ANALYSIS Final Report Prepared for Maricopa County Department of Transportation Prepared by TABLE OF CONTENTS Page EXECUTIVE SUMMARY ES-1 STUDY

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

TOWN HALL MEETING February 5, 2014

TOWN HALL MEETING February 5, 2014 TOWN HALL MEETING February 5, 2014 A.J. ROBINSON President Central Atlanta Progress Atlanta Downtown Improvement District DR. RISA PALM Georgia State Provost and Senior Vice President for Academic Affairs

More information

Welcome to the 2009 General Assembly

Welcome to the 2009 General Assembly Welcome to the 2009 General Assembly Development Excellence : Illustrated Issues Facing the Region Transportation Air Quality Water Supply Environment Mission Statement: Center of Development Excellence

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

Dominion Supplemental Projects

Dominion Supplemental Projects Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer

More information

2011 Winter Outage Southern Arizona. WRGC Workshop Tempe, Az.

2011 Winter Outage Southern Arizona. WRGC Workshop Tempe, Az. 2011 Winter Outage Southern Arizona WRGC Workshop Tempe, Az. August 24, 2011 OUTLINE Southwest Gas overview Factors leading up to the outage Managing the outage Lessons learned Future challenges SWG Service

More information

(801) Spanish Fork Power. 860 East 4500 South Suite 312 Salt Lake City, UT 84107

(801) Spanish Fork Power. 860 East 4500 South Suite 312 Salt Lake City, UT 84107 (801) 288-4033 info@comlinkls.com Spanish Fork Power 860 East 4500 South Suite 312 Salt Lake City, UT 84107 S P A N I S H F O R K C I T Y Municipal Power Substation Siting & Capital Project Study October

More information

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project Welcome Metro North Transmission Project Vancouver Community Information Open House March 9, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

Transit Oriented Development Best Practices Seminar Series

Transit Oriented Development Best Practices Seminar Series Transit Oriented Development Best Practices Seminar Series January 22, 2007 Presented by Jim Prost, AICP, Principal Basile Baumann Prost Cole & Associates 177 Defense Highway, Suite 10 Annapolis, Maryland

More information

Valley-Ivyglen and Alberhill Transmission Line Projects

Valley-Ivyglen and Alberhill Transmission Line Projects Valley-Ivyglen and Alberhill Transmission Line Projects Final Environmental Impact Report City Council Meeting May 23, 2017 Valley-Ivyglen Project Construction of a new, single-circuit 115-kV subtransmission

More information

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace.

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace. Power delivery Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace. Forward-thinking power grid design This evolution has

More information

Year Assessment Preliminary Needs

Year Assessment Preliminary Needs 2018 10-Year Assessment Preliminary Needs Stakeholder and Customer Presentation March 1, 2018 Jeremy Voigt Purpose Key Study Assumptions Reminder Summarize Preliminary Changes to Needs Solicit Input on

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

F O R S A L E 2 Acre Outparcel Four Lane Exposure Gateway Corridor to Downtown 0 Kathleen Road, Lakeland, Florida 33801

F O R S A L E 2 Acre Outparcel Four Lane Exposure Gateway Corridor to Downtown 0 Kathleen Road, Lakeland, Florida 33801 0 Kathleen Road, Lakeland, Florida 33801 Property: This is a 2 acre out parcel. Site is level and serviced by a master water retention system. Adjacent to the south is the newly built Storeright Self Storage

More information

Exhibit 25.A. June 2, [First Name] [Last Name] [Suffix] [Address_1] [Address_2] [City], [State] [Zip]

Exhibit 25.A. June 2, [First Name] [Last Name] [Suffix] [Address_1] [Address_2] [City], [State] [Zip] June 2, 2017 [First Name] [Last Name] [Suffix] [Address_1] [Address_2] [City], [State] [Zip] Application of Pedernales Electric Cooperative, Inc. to Amend its Certificate of Convenience and Necessity for

More information