1 Pennsylvania Safety Transportation and Research Track (PennSTART) August 2018 Feasibility Study Executive Summary Pennsylvania Turnpike Commission In partnership with: Pennsylvania Department of Transportation Pennsylvania State University
2 Pennsylvania Safety Transportation and Research Track The Pennsylvania Turnpike Commission, Pennsylvania Department of Transportation, and Pennsylvania State University are partnering to advance PennSTART: a state-of-the-art high-speed test track to address the safety and operational needs of the Mid-Atlantic Region and beyond. PennSTART PennSTART is a proposed high-speed test track and transportation facility for research, testing, and training that is designed to accelerate innovation in the areas of: 1) safety testing and training for traffic incident management (TIM), work zones, railways, and aircraft; 2) connected and autonomous vehicle (CAV) testing; and 3) tolling and intelligent transportation systems (ITS) technology testing. PennSTART s business model will target private and public-sector end-users to form a collaborative environment that drives emerging innovation from three cornerstones: 1) public-sector testing and training; 2) private sector research and testing; and 3) academic research As a unique collaboration between PTC, PennDOT, and Penn State, the $23,380,628 project will be funded by the three organizations and will be located near Penn State s main campus in State College, Pennsylvania. Upon completion of the Systems Engineering process, it is envisioned that Penn State will own and operate the facility under the Thomas D. Larson Pennsylvania Transportation Institute, which operates the existing federally designated automated vehicle (AV) Proving Ground test track at Penn State. testing laboratory. As proposed, PennSTART will be capable of testing over 75 percent of the US DOT connected vehicle technology applications. A preferred conceptual design was developed to encompass a 110- acre site near State College, PA. This concept design provides the minimum land area parameters to accommodate PennSTART s proposed concept of operations and supporting facility elements, which were formulated using stakeholder input and due diligence conducted throughout the feasibility study planning process. The project is currently proceeding under the FHWA s Systems Engineering process for intelligent transportation systems (ITS) projects. PennSTART will be located on a 110-acre site and will feature a 1.5-mile high-speed oval test track. The 80-acre infield portion of the oval track will feature an advanced testing and training environment and a future academic research and technology
3 Conceptual Facility Design
4 Benefits and Targeted End-Users
5 Cost Estimate A preliminary cost estimate was prepared by the PTC based on the site specifications. In total, the Phase 1 track engineering and construction, plus land acquisition equals $23,380,628. Subsequent phases will include the engineering and construction of PennSTART s supporting training and academic building, plus the proposed aircraft rescue and training simulator. Track Construction High Speed Track $ 3,309,106 Infield including CAV Technology $ 7,436,215 Infield Parking Area $ 2,596,781 Site Preparation and Drainage $ 863,345 Lighting $ 197,932 Utilities $ 185,000 Sub-Total $ 14,588,379 Mobilization (5%) $ 729,419 Engineering / Design (20%) $ 3,063,560 Sub-Total $ 18,381,357 Contingency (20%) $ 3,676,271 Total Track Construction Cost $ 22,057,628 Other Costs Training/Academic Building $ 10,000,000 Sub-Total Track and Building Construction $ 32,057,628 Site Land Acquisition or Donation $ 1,323,000 Total Project Cost $ 33,380,628 Optional Addition: Aircraft Rescue and Firefighting Training Simulator $ 3,500,000 Total Project Cost with Additions $ 36,880,628
6 Implementation Phases and Schedule Upon completion of the Concept of Operations, System Requirements, and Business Plan in July 2019, Preliminary Engineering and Plans, Specifications, and Estimates are scheduled to begin in August 2019 and will take 10 months to finalize with completion scheduled for May The project will be competitively procured in summer 2020 with a construction contract awarded by November 30, Construction is estimated to take 18 months, beginning in December 2020 and concluded by May Upon completion of construction, the Parties will undertake a 4-month evaluation and testing phase to ensure the facility s technology features are validated and ready for use.
7 Acknowledgements Technical Team Joseph W. Sutor, P.E., Pennsylvania Turnpike Commission Mark Kopko, Pennsylvania Department of Transportation Eric Donnell, Ph.D., P.E., Pennsylvania State University Troy D. Truax, AICP, Michael Baker International, Inc. Work Advisory Group Tony Mento, Federal Highway Administration James Paral, Federal Highway Administration Roger Ryder, Federal Highway Administration Mark Compton, Pennsylvania Turnpike Commission Craig Shuey, Pennsylvania Turnpike Commission Bob Taylor, P.E., Pennsylvania Turnpike Commission Tim Scanlon, P.E., Pennsylvania Turnpike Commission Todd Leiss, Pennsylvania Turnpike Commission Jon Fleming, Pennsylvania Department of Transportation Eric Sponsler, Pennsylvania Department of Transportation Jeff Thomas, Pennsylvania Emergency Management Agency Randy Padfield, Pennsylvania Emergency Management Agency Brent Zechman, Pennsylvania State Police Brian Ianuzzi, Pennsylvania State Police Brian St. John, P.E., McCormick Taylor, Inc. William Capone, McCormick Taylor, Inc. Dave Wolfe, Drive Engineering Prepared for The Pennsylvania Turnpike Commission by McCormick Taylor (Prime Consultant) and Michael Baker International (Lead Technical Consultant) [Contract No , Project EN , Purchase Order No. SAP PO# ]. If you are interested in more information on the facility, partnering with the facility, providing feedback on the facility or just contacting us, please use the contact information below. Joseph Joe W. Sutor, P.E. Planning Manager and Environmental Manager Pennsylvania Turnpike Commission (717) Mark Kopko Manager, Advanced Vehicle Technology Pennsylvania Department of Transportation (717) Also, please visit Funded by the Pennsylvania Turnpike Commission and the Pennsylvania State Transportation Innovation Council (STIC).
Pennsylvania Safety Transportation and Research Track (PennSTART)
Pennsylvania Safety Transportation and Research Track (PennSTART) IBTTA Maintenance and Roadway Operations Workshop June 25, 2018 1 Purpose and Need 2014 PA Transportation Advisory Committee TIM Study
More informationMid-Atlantic Traffic Incident Management Training Facility Feasibility Study
TIM TRAINING FACILITY Mid-Atlantic Traffic Incident Management Training Facility Feasibility Study 2017 Transportation Engineering & Safety Conference December 8, 2017 Troy D. Truax, AICP Michael Baker
More informationPennsylvania Safety Transportation and Research Track (PennSTART) April 10, 2018
Pennsylvania Safety Transportation and Research Track April 10, 2018 1 Purpose and Need Evaluate the need and demand for a PA-based, Mid-Atlantic TIM Training Facility Centrally located facility offering:
More informationDAVID WOLFE TMC Operations & Incident Management Specialist
DAVID WOLFE TMC Operations & Incident Management Specialist Professional Background Education Temple University, B.A. - Communications Licenses/Certificates FEMA NIMS: ICS-100 ICS-200 ICS-300 ICS-400 IS-700
More informationEngaging Maryland toward CAV advancements Christine Nizer, Administrator
Engaging Maryland toward CAV advancements Christine Nizer, Administrator Maryland Department of Transportation Motor Vehicle Administration Maryland CAV activities Overall goal: Maryland is open for business
More informationDulles Area Transportation Association
Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements
More informationRailroad-DOT Mitigation Strategies (R16) An Overview. March 2016
Railroad-DOT Mitigation Strategies (R16) An Overview March 2016 Agenda Railroad-DOT Mitigation Strategies Key Issues Product description How It Works Examples of Railroad-DOT Innovations Benefits States
More informationMobile Communications for Transit
Mobile Communications for Transit Barry Einsig Chair APTA Wireless Communications Subcommittee Chair Joint Council on Transit Wireless Communications and Market Director Harris Corporation, Washington,
More informationCAR Management Briefing Seminar
CAR Management Briefing Seminar John Maddox President & CEO American Center for Mobility July 31, 2017 Connected & Automated Vehicles (CAV) Technology is moving fast Significant technical and policy challenges
More informationFIBER OPTIC RESOURCE SHARING IN VIRGINIA
FIBER OPTIC RESOURCE SHARING IN VIRGINIA Commonwealth Transportation Board Innovation & Technology Subcommittee Dean Gustafson, P.E., PTOE February 20, 2018 Why Fiber? Enormous bandwidth available to support
More informationRegional Operations Traffic Signals Task Force Meeting #1 February 13, 2007
South Central Pennsylvania Regional Operations Traffic Signals Task Force Meeting #1 PennDOT Executive Goal # 6 Effectively and efficiently operate the transportation system Agenda Introductions Purpose
More informationA Pennsylvania Plan for Safe Work Zones PRESENTED BY: LARRY BANKERT, ASSOCIATE V.P., TOLL SERVICES MICHAEL BAKER INTERNATIONAL
A Pennsylvania Plan for Safe Work Zones PRESENTED BY: LARRY BANKERT, ASSOCIATE V.P., TOLL SERVICES MICHAEL BAKER INTERNATIONAL Introduction A Pennsylvania Plan for Safe Work Zones presents a framework
More informationCITY OF VANCOUVER ADMINISTRATIVE REPORT
CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting
More informationGDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010
GDOT PowerPoint Title Page MMPT Technical Committee April 6, 2010 Introduction Senate Bill 200, enacted in May2009, revamped existing P3 enabling legislation This new legislative direction provides an
More informationArizona Emergency VII (E-VII) Program Overview and Focus Areas
Arizona Emergency VII (E-VII) Program Overview and Focus Areas February 2008 The Arizona E-VII Initiative is Underway The Arizona DOT, Maricopa County DOT, FHWA and partners from the academic and private
More informationIntelligent Transportation Systems (ITS)
Intelligent Transportation Systems (ITS) Systems Engineering (SE) Requirement Intelligent Transportation Systems (ITS) means electronics, communications, or information processing used singly or in combination
More informationSouth Central ROP Projects
Pennsylvania Department of Transportation ROP Overview and Summary South Central ROP Projects November 2007 77 INCIDENT MANAGEMENT (IM) Draft Version 1 July 2007-40 - IM 1: SOUTH CENTRAL PA ITS DEPLOYMENT
More informationChattanooga Regional ITS Architecture Update Project Overview. January 7, 2014
Chattanooga Regional ITS Architecture Update Project Overview January 7, 2014 Project Overview Update of the 2010 Chattanooga Regional ITS Architecture and Deployment Plan Provides a long range plan for
More informationIMPROVING CYBERSECURITY AND RESILIENCE THROUGH ACQUISITION
IMPROVING CYBERSECURITY AND RESILIENCE THROUGH ACQUISITION Briefing for OFPP Working Group 19 Feb 2015 Emile Monette GSA Office of Governmentwide Policy emile.monette@gsa.gov Cybersecurity Threats are
More informationSTATE STREET CORRIDOR
CITY OF WEST LAFAYETTE AND PURDUE UNIVERSITY STATE STREET CORRIDOR March 11, 2015 1 March 11, 2015 2 STATE STREET CORRIDOR AGENDA STATE STREET CORRIDOR 1. Project Fundamentals Project History Project Goals
More informationConnected & Automated Vehicle Activities
MDOT State Highway Administration Connected & Automated Vehicle Activities National Rural ITS Conference October 2018 MDOT s CAV Working Group MDOT s CAV Working Group Open discussions on CAV with TBUs,
More informationReston Town Center North Development. Community Update
Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive
More informationPlanning for Resiliency. June 20, 2017 Richard Tetreault, PE WSP USA Office Lead VT, NH, and ME
Planning for Resiliency June 20, 2017 Richard Tetreault, PE WSP USA Office Lead VT, NH, and ME 23,000 years ago there would have been more than 8,000 feet of glacier over our heads 2 Provide for the safe
More informationStockton Aviation Research & Technology Park
Stockton Aviation Research & Technology Park Overview Joseph M. Sheairs, Sr. Executive Director Introduction Industry, Academia, and Government collaboration dedicated to the advancement of aviation sciences,
More informationNational Operations Center of Excellence. Douglas W. Wiersig, P.E. Director of Transportation and Public Works, City of Fort Worth, Texas
National Operations Center of Excellence Douglas W. Wiersig, P.E. Director of Transportation and Public Works, City of Fort Worth, Texas 1 Our Vision & Mission Vision: Provide exceptional services to the
More informationMountain Corridor Incident Management Program
Mountain Corridor Incident Management Program Colorado Department of Transportation Background The I- Incident Management study was initiated in response to CDOT s I- MIS. The resulting program was the
More informationPerformance Measurement, Data and Decision Making: A Matter of Alignment. Mark F. Muriello Assistant Director Tunnels, Bridges & Terminals
Performance Measurement, Data and Decision Making: A Matter of Mark F. Muriello Assistant Director Tunnels, Bridges & Terminals The Port Authority of NY & NJ: Delivering Vital Connections Tunnels and Bridges
More informationKansas City s Metropolitan Emergency Information System (MEIS)
Information- Sharing Interagency Cooperation Resources Management Law Enforcement Fire Emergency Medical Services Public Health Private Sector Kansas City s Metropolitan Emergency Information System (MEIS)
More informationPROJECT TIMELINE. Next steps. Plan. Start of Service
PROJECT TIMELINE 2018 2019 2020 2021 2022 2023 WE ARE HERE Plan Develop Build Develop design options for termini, station locations, and transit operations Conduct environmental research Assess funding
More informationNCHRP Project Impacts of Connected Vehicles and Automated Vehicles on State and Local Transportation Agencies
NCHRP Project 20-102 Impacts of Connected Vehicles and Automated Vehicles on State and Local Transportation Agencies Announcement of New Tasks, August 2016 The National Cooperative Highway Research Program
More informationINNOVATION AT THE VIRGINIA DEPARTMENT OF TRANSPORTATION. Robert H. Cary, PE, LS, Chief Deputy Commissioner 10/2/2018
INNOVATION AT THE VIRGINIA DEPARTMENT OF TRANSPORTATION Robert H. Cary, PE, LS, Chief Deputy Commissioner 10/2/2018 Virginia is Innovating 2 VDOT has Established an Office of Strategic Innovation Office
More informationDISTRICT 6-0 REGIONAL OPERATIONS PLAN PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 6-0
MINUTES OF MEETING (FINAL) PROJECT: PURPOSE OF MEETING: LOCATION: PENNDOT Agreement E00229 Open-end Agreement for ITS, Traffic and Highway Safety Engineering Services Work Order 016 - District 6-0 Regional
More informationRegional TSM&O Vision and ITS Architecture Update
Regional TSM&O Vision and ITS Architecture Update Progress Update Transportation Coordinating Committee April 5, 2019 Task List (2018 2020) 1. Develop a Regional TSM&O Vision 2. Document Current TSM&O
More informationCommercial transformation, procurement and R&D
Commercial transformation, procurement and R&D Purpose For discussion and direction. Summary As part of the fire reform agenda the Home Office is keen for the fire and rescue sector to deliver greater
More informationJSC THE JUSTICE & SAFETY CENTER. Snapshot 2014
JSC THE JUSTICE & SAFETY CENTER Snapshot 2014 The Justice & Safety Center (JSC) is comprised of a team of faculty and staff professionals at Eastern Kentucky University (EKU) dedicated to strengthening
More informationDeploying High Efficiency Outdoor Lighting: Regional Streetlight Procurement Program (RSLPP)
Deploying High Efficiency Outdoor Lighting: Regional Streetlight Procurement Program (RSLPP) Michael Fuller President, Keystone Lighting Solutions RSLPP Technical Advisor and Owner s Agent August 21 st,
More informationPage 7. Page 8. (MDSS)) Pilot Phase. Page 9. Page 6. Vision. Mission. of Program. Optimizing the. complimentary. Page 1 of 9
Inte ligent Transportation Program Direcry of Active Projects In This Edition: Project background and expected benefits for the followingg projects: 511 Pennsylvania Page 2 Video Sharing Solution Page
More informationNorth Central Superpave Center. Marketing Plan and Strategy
North Central Superpave Center Marketing Plan and Strategy North Central Superpave Center (NCSC) Marketing Committee Chairman Michael Heitzman Iowa Department of Transportation Marketing Committee Members
More informationFeasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008
Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008 INTRODUCTION The City of Moorhead (City), along with the Fargo-Moorhead Metropolitan Council of Governments (FM
More informationPREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT
PREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT HOUSE TRANSPORTATION & INFRASTRUCTURE SUBCOMMITTEE ON RAILROADS Oversight Hearing on Railroad Security
More informationDenver s Future. City Club of Denver
Denver s Future City Club of Denver Post-Recession Challenges Building Trades hit hard Aging population Neglected/unfunded infrastructure Constrained federal and state budgets Affordable housing (construction
More informationMOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension
MOTION NO. M2018-30 Task Order 2 with the City of Des Moines for the Federal Way Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 03/08/2018 Final Action Ahmad Fazel, DECM
More information2017 SICOP Meeting/ SCOM Annual Meeting
AASHTO Subcommittee on Transportation Systems Management and Operations (STSMO) 2017 SICOP Meeting/ SCOM Annual Meeting Providence, RI Galen McGill, P.E. System Operations & ITS Manager, Oregon Dept. of
More informationConnecticut Department of Department of Administrative Services and the Broadband Technology Opportunity Program (BTOP) 8/20/2012 1
Connecticut Department of Department of Administrative Services and the Broadband Technology Opportunity Program (BTOP) 8/20/2012 1 Presentation Overview What is BTOP? Making BTOP work for our state What
More informationNORTHWEST PA REGIONAL OPERATIONS PLAN PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 1-0
MINUTES OF MEETING (FINAL) PROJECT: PURPOSE OF MEETING: LOCATION: PENNDOT Agreement E00229 Open-end Agreement for ITS, Traffic and Highway Safety Engineering Services Work Order 015- District 1-0 Regional
More informationNACE/AACE Western Regional Conference Laughlin, Nevada November 3, 2011
NACE/AACE Western Regional Conference Laughlin, Nevada November 3, 2011 Tim Psomas Chairman of the Board, ISI Institute for Sustainable Infrastructure Outline Background Development Features of Envision
More informationDeveloping Consistency in ITS Safety Solutions: Intersection Conflict Warning Systems E N T E R P R I S E
Developing Consistency in ITS Safety Solutions: Intersection Conflict Warning Systems E N T E R P R I S E ITS Canada 2012 Annual Conference and General Meeting June 13, 2012 Agenda Intersection Conflict
More informationDOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS
Commonwealth of Virginia Office of Transportation P3 s Dusty Holcombe, Deputy Director DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS September 20, 2011 Virginia: DT / MT
More informationJLCIMT. OSCIO Broadband Initiative. 11 May 2017
JLCIMT. OSCIO Broadband Initiative 11 May 2017 A Plan to Work Together where we are today 2 Leverage economies of scale to get more for our current funding 700 sites on the planned network statewide, 585
More informationSECTION 106 ACTIVITIES ANNUAL REPORT
SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The
More informationMINNEAPOLIS PARK & RECREATION BOARD COMMUNITY ENGAGEMENT PLAN
Board Plan Approval/Review Date: 9/19/2017 Last Plan Revision Date: 9/5/2017 MINNEAPOLIS PARK & RECREATION BOARD COMMUNITY ENGAGEMENT PLAN Project Title: MPRB Division: Planning Project Manager: Dana Murdoch
More informationCouncil of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013
Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility
More informationNJ Energy Master Plan. NJ Energy Master Plan Energy Efficiency Strategy: Draft Procurement Structure. Presented to: Energy Efficiency Stakeholders
NJ Energy Master Plan Energy Efficiency Strategy: Draft Procurement Structure Presented to: NJ Energy Master Plan Energy Efficiency Stakeholders By: Susan Coakley, NEEP Executive Director Blair Hamilton,
More informationTHE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9
THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental
More informationTHE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9
THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental
More informationMARTA BOARD OF DIRECTORS OCTOBER 4, 2018
MARTA BOARD OF DIRECTORS OCTOBER 4, 2018 TODAY S AGENDA o Key driver of the program o Recommended plan o Project summaries o Next steps 2 KEY DRIVER: PUBLIC INPUT o Atlanta City Design o Atlanta s Transportation
More informationTxDOT TMS PERFORMANCE MEASURES ITS TEXAS Texas Department of Transportation
TxDOT TMS PERFORMANCE MEASURES ITS TEXAS 2017 Texas Department of Transportation Traffic Management Systems November 2017 TRF-TM Update 1 2 Implementation of TMS Performance Metrics TMS Performance Metrics
More informationSouth Central Pennsylvania Regional Operations Plan Candidate Project Listing (DRAFT)
South Central Pennsylvania Regional Operations Plan Candidate Project Listing (DRAFT) APPLICABILITY South Central PA ITS Deployment Plan Update Lebanon County ITS deployment Lancaster County ITS deployment
More informationSchematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones
Schematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones Public Safety & Security Secure parking and access for Police, Sheriff, Judge Secure & segregated
More informationCity Hall Space Selection 15 Market Square. November 27, 2017
City Hall Space Selection 15 Market Square November 27, 2017 Future City Hall Space Recommendation Recommendation Committee of the Whole recommends that Common Council approve the Offer to Amending Existing
More informationGreat Lakes Regional Transportation Operations Coalition (GLRTOC) Multistate Corridor Operations and Management (MCOM) Program
Transportation Operations Coalition (GLRTOC) Multistate Corridor Operations and Management (MCOM) Program National Rural ITS Conference August 2013 Megaregions GLRTOC Partners & Mission Founded in 2010
More informationNORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3
NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 Varuna A. Singh August 17, 2018 NHHIP OVERVIEW Project divided into three segments: Segment 1: I-45: from Beltway 8 to I-610 (9 mi) 45 Segment
More informationEvolution of Canadian
Evolution of Canadian Defence Procurement US U.S. UK Canada Tri-Lateral Symposium 2 October 2009 John Neri Director General International and Industry Programs Department of National Defence Outline The
More informationSituation and Outlook of PPP Infrastructure Development in Indonesia
Situation and Outlook of PPP Infrastructure Development in Indonesia Dedy S. Priatna, PhD Deputy Minister for Infrastructure National Development Planning Agency (Bappenas) PPP Infrastructure Investment
More informationArizona State Troopers Highway Patrol Division Sergeant John Paul Cartier
Arizona State Troopers Highway Patrol Division Sergeant John Paul Cartier Average Annual Number of Responders Struck and Killed Nationally 12 Law Enforcement Officers 5 Fire and Rescue Personnel 60 Towing
More informationTechnology Committee Video Quality in Public Safety/Video Technology Advisory Group
Technology Committee Video Quality in Public Safety/Video Technology Advisory Group John Contestabile Johns Hopkins University/Applied Physics Lab john.contestabile@jhuapl.edu NPSTC is a federation of
More informationDallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office
Trinity Parkway Alternative 3C Dallas City Council August 2, 2017 Jody Puckett, Assistant City Manager (I) City Manager s Office Presentation Overview Provide background on Trinity Parkway Alternative
More informationTransportation System Cybersecurity Framework
Transportation System Cybersecurity Framework August 24, 2016 Patrick Zelinski, AASHTO Background Growing issue of cybersecurity and its impact on the highway environment has highlighted safety and operational
More informationCentre Lionel E. Lalonde Centre (Emergency & Protective Services Centre)
(Emergency & Protective Services Centre) Priorities Committee Meeting Wednesday, March 21 st 2007 Presented By: Tim P. Beadman Acting General Manager of Emergency Services - and - Richard Dixon Facilities
More informationACE Corporate Plan. Mission. Vision
ACE Corporate Plan 2017 2019 Mission ACE promotes the interests of over 450 UK consultancy and engineering companies delivering professional services in the natural and built environment employing over
More information6 July Moving Britain Ahead OFFICIAL. Presentation Title (edit this in Insert > Header and Footer, then click 'Apply to All') 1
Gary Crockford - A2/M2 Connected Vehicle Corridor, Programme Coordinator InterCor ITS-G5 TESTFEST Workshop, Thursday, Dordrecht, Netherlands Moving Britain Ahead OFFICIAL Presentation Title (edit this
More informationThe Final Rule on Work Zone Safety and Mobility
Federal Highway Administration, USDOT The Final Rule on Work Zone Safety and Mobility Updates to 23 CFR Section 630, Subpart J Presented by Tracy Scriba, Federal Highway Administration Talking Operations
More informationThe Center of Innovation: Creating an Innovation
The Center of Innovation: Creating an Innovation Ecosystem Driven by Public-Private Partnerships for the Benefit of the Homeland Security Enterprise Randel L. Zeller Director, Interagency Office Terry
More informationSEAWALL EARTHQUAKE SAFETY & DISASTER PREVENTION PROGRAM
SEAWALL EARTHQUAKE SAFETY & DISASTER PREVENTION PROGRAM Port Jurisdiction Historic shoreline Presentation to the Port Commission March 13, 2018 Photo Michael Macor SEAWALL EARTHQUAKE SAFETY & DISASTER
More informationInfrastructure PA Stephen Lecce
PA Stephen Lecce Ministry of Stephen Lecce, Parliamentary Assistant Meeting: Topics: Topics: PA Stephen Lecce, MPP Monday, August 20, 2018 9:15 am 9:45 am Shaw Centre, Room 107, Level 1 National Centre
More informationKIPDA ITS Architecture Update Kick-off Meeting
KIPDA ITS Architecture Update Kick-off Meeting September 8. 2016 Agenda Overview Intelligent Transportation Systems ITS Architectures Purpose & Limits Development Tasks Review of Current Architecture-
More informationSTRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT
STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT CURRENT STATE THE C&W WAY College athletic departments throughout the country are spending at an unprecedented pace to develop and renovate facilities
More informationAlliant Energy Center Comprehensive Master Plan O v e r s i g h t C o m m i t t e e
Alliant Energy Center Comprehensive Master Plan O v e r s i g h t C o m m i t t e e C O M P R EJ ah ne un as ri y V E 2 2 M, A2S 0T 1E 8R P L A N Today s Agenda 1. Status Update of Master Plan RFP 2. Status
More informationTHE REGIONAL MUNICIPALITY OF YORK
THE REGIONAL MUNICIPALITY OF YORK Committee of the Whole Report of the Executive Director, Corporate and Strategic Planning ECONOMIC DEVELOPMENT ACTION PLAN UPDATE - YORK REGION BROADBAND STRATEGY PROGRESS
More informationEnergy Report. AEE Central PA Chapter April 8th Meeting Announcement APRIL MEETING NOTICE
Energy Report Newsletter for the Central Pennsylvania Chapter of The Association of Energy Engineers About the Central PA Chapter: Local Chapter meetings held throughout the year (except July & August).
More informationMDCSystems. MICHAEL A. BAKER, P.E., M.S.E.M. Consulting Engineer
MDCSystems Providing Expert Solutions for Projects Worldwide MICHAEL A. BAKER, P.E., M.S.E.M. Consulting Engineer Education Drexel University, M.S., Engineering Management, Technology Assessment Brown
More informationFederal Law Enforcement Training Center
Federal Law Enforcement Training Center Industry Day - November 7, 2007 Cheltenham Charleston Artesia Glynco FLETC Mission Statement We Train Those Who Protect The Homeland. FY 07 & FY 08 Training Numbers
More informationTraffic Signal Improvement Plan. Franklin County Metropolitan Planning Organization May 20, 2015
Traffic Signal Improvement Plan Franklin County Metropolitan Planning Organization May 20, 2015 PLAN GOALS Secure Congestion Mitigation and Air Quality (CMAQ) Improvement Program funds to upgrade Borough-managed
More informationMeeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.
TO WHOM IT MAY CONCERN: NOTICE OF RE-SCHEDULED BOARD MEETINGS This is notice that the re-scheduled meetings of the Board of Directors of the New Jersey Transit Corporation, NJ Transit Rail Operations,
More informationVTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association
VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for
More information86 th Annual Short Course Al Alonzi, FHWA October 2012
86 th Annual Short Course Al Alonzi, FHWA October 2012 Solicitation Process Deployment Short List Process Every Day Counts Two Year Cycle Innovation Summits Selection FHWA Training Schedule January 15,
More informationI-95 Corridor Coalition. Multi-State VMT-Based Road-User Fee Initiative. Mark F. Muriello
I-95 Corridor Coalition Multi-State VMT-Based Road-User Fee Initiative Mark F. Muriello Assistant Director Tunnels, Bridges and Terminals The Port Authority of NY & NJ Co-Chair Policy & Strategic Planning
More informationBuilding strong relationships within a jurisdiction by utilizing Geographic Information
Page 1 1. Program Overview Building strong relationships within a jurisdiction by utilizing Geographic Information Systems (GIS) resources is of obvious importance and essential. Relying upon those resources
More informationAccelerating solutions for highway safety, renewal, reliability, and capacity. Connected Vehicles and the Future of Transportation
Accelerating solutions for highway safety, renewal, reliability, and capacity Regional Operations Forums Connected Vehicles and the Future of Transportation ti Session Overview What are connected and automated
More informationI. City of Virginia Beach Intelligent Transportation Systems Workshop, November 2 and 3, 2011
November -2011 I. City of Virginia Beach Intelligent Transportation Systems Workshop, November 2 and 3, 2011 The City of Virginia Beach Intelligent Transportation Systems (ITS) Workshop was organized and
More informationIT Disaster Recovery Services Program
Q4-2017 ISAC Update v.20171107 IT Disaster Recovery Strategy Implementation 2008 Data Center Strategic Plan Part 1 Part 2 Disaster Recovery Strategic Plan Part 1 Part 2 2016 2019 Implementation Goals Decouple
More informationPennDOT Planning Services and Implementation Regional Operations Plan for the Southern Alleghenies Region. Task Force #1.
PennDOT Planning Services and Implementation Regional Operations Plan for the Southern Alleghenies Region Task Force #1 Meeting Notes Foundational Issues Traveler Information Incident Management Communication
More informationSystem Expansion Implementation Plan. Board Meeting, April 2017
System Expansion Implementation Plan Board Meeting, April 2017 2016: A record-breaking year Opened 3 new light rail stations. Completed tunneling for 3 more. Broke ground on our longest extension to date.
More informationUAE Nuclear Energy Program Overview
UAE Nuclear Energy Program Overview Workshop on Nuclear Power Newcomers and International Cooperative Actions November 3 rd,2009 Ambassador Hamad Al Kaabi Permanent Representative of the UAE to the IAEA
More informationAnnual Report for the Utility Savings Initiative
Report to the North Carolina General Assembly Annual Report for the Utility Savings Initiative July 1, 2016 June 30, 2017 NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY http://portal.ncdenr.org Page
More information2014 NASCIO Recognition Award Nomination
2014 NASCIO Recognition Award Nomination TITLE: Network Communication Partnerships for Public Safety and Economic Opportunity CATEGORY: Cross Boundary Collaboration and Partnerships CONTACT: Shannon Barnes
More informationPIPELINE SECURITY An Overview of TSA Programs
PIPELINE SECURITY An Overview of TSA Programs Jack Fox Pipeline Industry Engagement Manager Surface Division Office of Security Policy & Industry Engagement May 5, 2014 TSA and Pipeline Security As the
More informationI 95 CORRIDOR COALITION EXECUTIVE BOARD & STEERING COMMITTEE MEETING Chicago, Illinois September 25, 2015
I 95 CORRIDOR COALITION EXECUTIVE BOARD & STEERING COMMITTEE MEETING Chicago, Illinois September 25, 2015 Agenda ***Important Note: The meeting is in Chicago, Central Time (Eastern Time is noted in parenthesis
More informationUtility Energy Service Contracts (UESCs)
Session: Third Party Funding Options Utility Energy Service Contracts (UESCs) Karen Thomas National Renewable Energy Laboratory (NREL) August 11, 2016 Rhode Island Convention Center Providence, Rhode Island
More informationDeferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M
Landscape 1,340 acres, 66 miles of sidewalks, 20 miles of roads Irrigation state of the art central control system; 70 systems, 8 fountains, 4 underground storage systems Stormwater management 119 sites,
More information