Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Seven

Size: px
Start display at page:

Download "Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Seven"

Transcription

1 DISTRICT SEVEN PROJECT OVERVIEW continues to make significant project investments in District Seven. In fiscal years 2014 and 2015, current Turnpike projects total over $141 million within Citrus, Hernando, Hillsborough, Pasco and Pinellas Counties. Summary of Major Project Funding by Project Type: The table below summarizes the funding programmed for the major Turnpike projects in the Tentative Five-Year Work Program (FY 2015/2016 through FY 2019/2020) that are located in District Seven. The project descriptions below this section identify and describe the major projects by county. The following phase abbreviations are used in the project tables: ENV Environmental (Funding Codes: C2, C8) PE Preliminary Engineering (Funding Codes: 31, 32) ROW Right of Way (Funding Codes: 41, 42, 43, 4B) RRU Railroad & Utilities (Funding Codes: 56, 57) CST Construction (Funding Codes: 52, 53, 54, 58, 61, 62) Work Description New Road Construction $253,423,820 $0 $3,280,000 $0 $0 $256,703,820 All-Electronic Tolling Conversion $25,186,775 $10,280,000 $0 $0 $0 $35,466,775 Major Projects Total $278,610,595 $10,280,000 $3,280,000 $0 $0 $292,170,595 Summary of Major Projects by County: The major Turnpike project expenditures by county in the Tentative Five-Year Work Program are shown in the table below. Please note that the funding for AET 6C ($35,466,775), a major regional project in Hillsborough and Hernando Counties, is not included in these totals and is addressed later in this document. County Citrus $216,411,013 $0 $3,280,000 $0 $0 $219,691,013 Hernando $37,012,807 $0 $0 $0 $0 $37,012,807 Total $253,423,820 $0 $3,280,000 $0 $0 $256,703,820 1 As ofjanuary 7, 2015

2 Citrus County Project: Construction of the Suncoast Parkway 2/SR 589 from the Hernando/Citrus County Line to Cardinal Street FPN: This project is the construction of the Suncoast Parkway 2/SR 589 as a four-lane limited access toll facility from the Hernando/Citrus County Line to Cardinal Street. ROW $4,662,000 $0 $0 $0 $0 $4,662,000 CST $64,139,817 $0 $1,640,000 $0 $0 $65,779,817 ENV $145,000 $0 $0 $0 $0 $145,000 Total $68,946,817 $0 $1,640,000 $0 $0 $70,586,817 Construction of the Suncoast Parkway 2/SR 589 from Cardinal Street to SR 44 FPN: This project is the construction of the Suncoast Parkway 2/SR 589 as a four-lane limited access toll facility from Cardinal Street to SR 44. PE $3,700,000 $0 $0 $0 $0 $3,700,000 ROW $39,144,300 $0 $0 $0 $0 $39,144,300 RRU $21,000,000 $0 $0 $0 $0 $21,000,000 CST $83,474,896 $0 $1,640,000 $0 $0 $85,114,896 ENV $145,000 $0 $0 $0 $0 $145,000 Total $147,464,196 $0 $1,640,000 $0 $0 $149,104,196 2 As ofjanuary 7, 2015

3 Hernando County Project: Construction of the Suncoast Parkway 2/SR 589 from US 98 to the Hernando/Citrus County Line FPN: This project is the construction of the Suncoast Parkway 2/SR 589 as a four-lane limited access toll facility from US 98 to the Hernando/Citrus County Line. ROW $232,000 $0 $0 $0 $0 $232,000 RRU $250,000 $0 $0 $0 $0 $250,000 CST $24,530,807 $0 $0 $0 $0 $24,530,807 ENV $12,000,000 $0 $0 $0 $0 $12,000,000 Total $37,012,807 $0 $0 $0 $0 $37,012,807 Regional Projects: Implement All-Electronic Tolling (AET) 6C on the Suncoast Parkway/SR 589 FPN: This project implements 6C of an overall program to convert portions of the Suncoast Parkway/SR 589 to a cashless, all-electronic toll collection system. The limits of 6C begin at Van Dyke Road (MP 14) on the Suncoast Parkway/SR 589 in Hillsborough County and end at US 98 (MP 55) in Hernando County. PE $775,000 $0 $0 $0 $0 $775,000 CST $24,411,775 $10,280,000 $0 $0 $0 $34,691,775 Total $25,186,775 $10,280,000 $0 $0 $0 $35,466,775 3 As ofjanuary 7, 2015

4 Summary of Minor Project Funding by Project Type: The table below summarizes the funding programmed for minor projects (signing/pavement markings, landscaping, environmental, bridge paintings, canal revetment and on-going project phases) for Turnpike roadways throughout the District. Work Description Signing/Pavement Markings $369,000 $1,137,000 $0 $0 $0 $1,506,000 Additonal Speical Use Lane $3,812,000 $0 $0 $0 $0 $3,812,000 Minor Projects Total $4,181,000 $1,137,000 $0 $0 $0 $5,318,000 Summary of All Project Funding: PROJECTS Minor Projects Total $4,181,000 $1,137,000 $0 $0 $0 $5,318,000 Major Projects Total $278,610,595 $10,280,000 $3,280,000 $0 $0 $292,170,595 Total $282,791,595 $11,417,000 $3,280,000 $0 $0 $297,488,595 4 As ofjanuary 7, 2015

5 5 As ofjanuary 7, 2015

Honorable Mayor and Members of the City Council. Memorandum of Understanding: Interstate 80 Integrated Corridor Mobility (I-80 ICM) Project

Honorable Mayor and Members of the City Council. Memorandum of Understanding: Interstate 80 Integrated Corridor Mobility (I-80 ICM) Project Office of the City Manager CONSENT CALENDAR May 1, 2012 To: From: Honorable Mayor and Members of the City Council Christine Daniel, Interim City Manager Submitted by: Andrew Clough, Director, Public Works

More information

Florida Department of Transportation

Florida Department of Transportation Florida s Turnpike Enterprise The Business of Tolling Diane Gutierrez-Scaccetti Executive Director & Chief Executive Officer William Wood Deputy Director of Toll Systems AGENDA Why Tolls? Toll Agency Models

More information

Kansas Division. January 31, 2018

Kansas Division. January 31, 2018 Division January 31, 6111 SW 29 th, Suite 100 Topeka, 66614 (785) 273-2600 (785) 273-2620 (fax) www.fhwa.dot.gov/ksdiv/index.htm Catherine M. Patrick, P.E. State Transportation Engineer Department of Transportation

More information

Using Geographical Information Systems to Enhance Public Finance Analyses

Using Geographical Information Systems to Enhance Public Finance Analyses Using Geographical Information Systems to Enhance Public Finance Analyses Presented by: Tindale-Oliver & Associates, Inc. Presentation Overview 1 2 Introduction City of Tampa Background 3 4 Project Funding

More information

Northwest Needs Improvements Survey

Northwest Needs Improvements Survey PW5 NW 107th Ave One thousand feet N of NW 122nd St Okeechobee Rd Widen bridge over Miami Canal PW6 NW 82nd Ave NW 8th St NW 12th St Construct new 4-lane road PW7 NW 87 Ave NW 36th St NW 58th St Add 2-lanes

More information

City of Tampa Transportation Impact Fee Update Study. Presentation to Mayor Iorio February 23, 2009

City of Tampa Transportation Impact Fee Update Study. Presentation to Mayor Iorio February 23, 2009 City of Tampa Transportation Impact Fee Update Study Presentation to Mayor Iorio February 23, 2009 Presentation Overview ground Overview Impact Fee Districts Population and Employment Growth Transit Service

More information

Gaston County GIS. Interactive Mapping Website

Gaston County GIS. Interactive Mapping Website Gaston County GIS Interactive Mapping Website The Gaston County GIS mapping website optimizes the available window viewing area and has interactive tools, collapsible menus and movable windows. This map

More information

BUILDINGS AND FACILITIES

BUILDINGS AND FACILITIES EB-00-0 Exhibit C Tab Schedule Page of BUILDINGS AND FACILITIES FACILITIES AND ASSET MANAGEMENT OVERALL STRATEGY THESL s buildings and facilities (the facilities ) include operating centers (00 Commissioners,

More information

Corridor Management Committee Meeting. June 4, 2014

Corridor Management Committee Meeting. June 4, 2014 Corridor Management Committee Meeting June 4, 2014 1 Today s Topics Welcome Approval of Minutes Municipal Consent Process Update Public Hearing Schedule City/County Comment Categories Public Outreach Activities

More information

Creating Dallas-Fort Worth s Transportation System: Celebrating Partnerships and Milestones

Creating Dallas-Fort Worth s Transportation System: Celebrating Partnerships and Milestones Creating Dallas-Fort Worth s Transportation System: Celebrating Partnerships and Milestones Presentation to the Texas Transportation Commission August 27, 2014 Presenters Mike Cantrell Commissioner, Dallas

More information

Why is Indiana using P3s?

Why is Indiana using P3s? Why is Indiana using P3s? Project acceleration and job creation P3s allow for projects to be accelerated into earlier years when compared to traditional delivery. This results in jobs being created sooner.

More information

Enclosure: Pasco County Ridge Road Extension Monthly Status Report

Enclosure: Pasco County Ridge Road Extension Monthly Status Report PASC COUNTY FLORIDA --,.. A. June 6, 2018 - -- ------- Mr. Shayne Hayes, Section Chief Pensacola Permits Section US Army Corps Engineers, Jacksonville District 41 North Jefferson Street, Suite 301 Pensacola,

More information

MAJOR PROJECTS STRATEGY

MAJOR PROJECTS STRATEGY MAJOR PROJECTS STRATEGY Texas Transportation Commission October 25, 2017 Outline and Goals Current TexasClearLanes initiatives to mitigate congestion for non-tolled projects Review Unified Transportation

More information

Rapid Incident Scene Clearance (RISC) Annual Report

Rapid Incident Scene Clearance (RISC) Annual Report Rapid Incident Scene Clearance (RISC) Annual Report Fiscal Year 2014/2015 September 2015 Publication of: Florida Department of Transportation Commercial Vehicle Operations and Traffic Incident Management

More information

Dallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office

Dallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office Trinity Parkway Alternative 3C Dallas City Council August 2, 2017 Jody Puckett, Assistant City Manager (I) City Manager s Office Presentation Overview Provide background on Trinity Parkway Alternative

More information

UTILITY MARKING DEVICES. Naples City Council Workshop November 17, 2014 Presented by: Andrew Holland, P.E., Engineering Manager

UTILITY MARKING DEVICES. Naples City Council Workshop November 17, 2014 Presented by: Andrew Holland, P.E., Engineering Manager UTILITY MARKING DEVICES Naples City Council Workshop November 17, 2014 Presented by: Andrew Holland, P.E., Engineering Manager CITY OF NAPLES UTILITIES Reclaimed Water Sewer Force Mains Raw Water Potable

More information

Consumer Services, Division of Forestry; and Florida Department of Environmental Protection.

Consumer Services, Division of Forestry; and Florida Department of Environmental Protection. Consumer Services, Division of Forestry; and Florida Department of Environmental Protection. Any Florida DEO comments and requests should be foiwarded to: Planning and Development Department West Pasco

More information

STATE STREET CORRIDOR

STATE STREET CORRIDOR CITY OF WEST LAFAYETTE AND PURDUE UNIVERSITY STATE STREET CORRIDOR March 11, 2015 1 March 11, 2015 2 STATE STREET CORRIDOR AGENDA STATE STREET CORRIDOR 1. Project Fundamentals Project History Project Goals

More information

REGISTERED LEED GOLD IN STERLING, VA & Woodland Road

REGISTERED LEED GOLD IN STERLING, VA & Woodland Road REGISTERED LEED GOLD IN STERLING, VA 45600 & 45610 Woodland Road GREEN AND GOLD Atlantic Corporate Park is s premier office destination, and the county s first office project to be designated LEED Gold

More information

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM Date of Meeting: # 9 SUBJECT: ELECTION DISTRICTS: STAFF CONTACTS: Public and Private Infrastructure Improvements Adjacent to the Dulles

More information

MOST TRUSTED ADVISER IN THE TOLL INDUSTRY

MOST TRUSTED ADVISER IN THE TOLL INDUSTRY MOST TRUSTED ADVISER IN THE TOLL INDUSTRY The HNTB Companies Infrastructure Solutions HNTB Toll Clients Alamo Regional Mobility Authority Bay Area Toll Authority Burlington County Bridge Commission Cameron

More information

Regional Contracting Opportunities. McGuire AFB, Ft. Dix and NAVFAC Mid-Atlantic plus Fort Drum

Regional Contracting Opportunities. McGuire AFB, Ft. Dix and NAVFAC Mid-Atlantic plus Fort Drum New Jersey Post Society of American Military Engineers Regional Contracting Opportunities McGuire AFB, Ft. Dix and NAVFAC Mid-Atlantic plus Fort Drum 17 April 2007 Check-in at 1100 promptly Enlisted &

More information

County: King List of Amendment Projects: Approved 5/16/2017. Jurisdiction: Enumclaw. Project Number: ENM-6

County: King List of Amendment Projects: Approved 5/16/2017. Jurisdiction: Enumclaw. Project Number: ENM-6 Central Puget Sound Regional 2017-2020 Transportation Improvement Program Amendments and Corrections to be included in the 2017-20 STIP PSRC's Amendment 2017-04 County: King List of 17-04 Amendment Projects:

More information

Florida Regional Domestic Security Task Forces

Florida Regional Domestic Security Task Forces Florida Regional Domestic Security Task Forces North Florida North East Florida North West Florida Tampa Bay Citrus, Sumter, Hernando, Pasco, Pinellas, Hillsborough, Polk and Hardee Counties Central Florida

More information

Transportation & Mobility

Transportation & Mobility Transportation & Mobility October 11, 2017 October 11, 2017 Community Dialogue Series Session 3: Transportation & Mobility YOU ARE NOT STUCK IN TRAFFIC. YOU ARE TRAFFIC. October 11, 2017 Community Dialogue

More information

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT: BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: March 13, 2018 # 7 SUBJECT: ELECTION DISTRICT: Contract Award/Roadway and Civil Design

More information

the City of Palm Bay Brevard County Florida held on November

the City of Palm Bay Brevard County Florida held on November RESOLUTION NO 2018-60 A RESOLUTION OF THE CITY OF PALM BAY, BREVARD COUNTY, FLORIDA, AMENDING RESOLUTION NO 2018-45, ADOPTING RATES, CHARGES, AND FEES, FOR FISCAL YEAR 2018-2019, PURSUANT TO THE CITY OF

More information

Amy Wells Brennan, Esq. Assistant General Counsel (813) x. 4658

Amy Wells Brennan, Esq. Assistant General Counsel (813) x. 4658 From: Amy Brennan To: Kate Zamboni; Jan Burke; Albert A. Gagne; David Sauskojus; Cliff Ondercin; Carolyn Pina; Kim Dymond Cc: Dave Kramer; Steven Lopes Subject: FW: Mid Florida Mine - Palmer Resources

More information

TOLL-FLA ( ) FAX: (U.S. Only)

TOLL-FLA ( ) FAX: (U.S. Only) 1-888-TOLL-FLA (1-888-865-5352) FAX: 1-888-265-1725 (U.S. Only) Call Center Hours of Operation: Monday Friday, 7:00AM 7:00PM Saturday, 8:30AM 5:00PM Closed Sundays www.sunpass.com User Manual Revised January

More information

Rapid Incident Scene Clearance (RISC) Annual Report

Rapid Incident Scene Clearance (RISC) Annual Report Rapid Incident Scene Clearance (RISC) Annual Report Fiscal Year 2015/2016 September 2016 Publication of: Florida Department of Transportation Commercial Vehicle Operations and Traffic Incident Management

More information

2011 Congestion Management Program Update

2011 Congestion Management Program Update PPLC Meeting 06/13/11 Agenda Item 4A Handout 2011 Congestion Management Program Update Presentation to PPLC June 13, 2011 Slide 1 2011 CMP Update Status Update Schedules, Issues, approach approved January

More information

REGULAR MEETING AGENDA

REGULAR MEETING AGENDA November 12, 2017 6:00 PM REGULAR BOARD MEETING Lehigh Acres Municipal Services Improvement District Barrett Room 601 East County Lane Lehigh Acres, FL 33936 This meeting is open to the general public.

More information

Rapid Incident Scene Clearance (RISC) Annual Report

Rapid Incident Scene Clearance (RISC) Annual Report Rapid Incident Scene Clearance (RISC) Annual Report Fiscal Year 2013/2014 September 2014 Publication of: Florida Department of Transportation Commercial Vehicle Operations and Traffic Incident Management

More information

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility

More information

KEEPING DATA ACCURATE WITH THE DUSA APPLICATION

KEEPING DATA ACCURATE WITH THE DUSA APPLICATION KEEPING DATA ACCURATE WITH THE DUSA APPLICATION Jenn Sylvester, Mapping Branch Team Lead Adam Breznicky, Mapping Branch Web Master Transportation Planning & Programming Division (TPP) ESRI International

More information

NON-VDOT ADMINISTERED PROJECTS (NVAP) GUIDE JUNE 2018

NON-VDOT ADMINISTERED PROJECTS (NVAP) GUIDE JUNE 2018 NON-VDOT ADMINISTERED PROJECTS (NVAP) GUIDE JUNE 2018 NON-VDOT ADMINISTERED PROJECTS (NVAP) PORTAL Localities deliver a significant number of the projects in Virginia and any reporting on the status of

More information

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS Commonwealth of Virginia Office of Transportation P3 s Dusty Holcombe, Deputy Director DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS September 20, 2011 Virginia: DT / MT

More information

INDUSTRIAL LAND FOR SALE

INDUSTRIAL LAND FOR SALE INDUSTRIAL LAND FOR SALE INDUSTRIAL LAND & DEVELOPMENT OPPORTUNITIES 150 ACRE INDUSTRIAL BUSINESS PARK LOTS RANGING FROM 5 150 ACRES Property Features Nexus at DIA provides a compelling opportunity for

More information

8/8/2018 Council Approval Presentation. 8/14/2018 MOVEBR Infrastructure Enhancement and Traffic Mitigation Plan 1

8/8/2018 Council Approval Presentation. 8/14/2018 MOVEBR Infrastructure Enhancement and Traffic Mitigation Plan 1 8/8/2018 Council Approval Presentation 8/14/2018 MOVEBR Infrastructure Enhancement and Traffic Mitigation Plan 1 Speaker Panel Jamie Setze Executive Director, Capital Regional Planning Commission Stephen

More information

ALBEMARLE COUNTY SERVICE AUTHORITY

ALBEMARLE COUNTY SERVICE AUTHORITY ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA ITEM EXECUTIVE SUMMARY AGENDA TITLE: FY 2017 CIP Authorizations STAFF CONTACT(S)/PREPARER: Peter C. Gorham, P.E., Director of Engineering AGENDA DATE: March 16,

More information

Baltimore City Department of Public Works

Baltimore City Department of Public Works Baltimore City Department of Public Works Bureau of Water and Wastewater WHEN IT BREAKS, IT POURS January 16, 2014 Presentation Outline Overview of Baltimore Water System Light Street Main Break Asset

More information

I-35 FROM THE RED RIVER TO THE RIO GRANDE

I-35 FROM THE RED RIVER TO THE RIO GRANDE I-35 FROM THE RED RIVER TO THE RIO GRANDE Commission Workshop Oct. 24, 2018 The Story of Congestion Relief Task Force made up of senior leaders of TxDOT challenged with developing a strategic plan to address

More information

HEADLIGHT PROGRAM IMPLEMENTATION

HEADLIGHT PROGRAM IMPLEMENTATION HEADLIGHT PROGRAM IMPLEMENTATION TxDOT Dallas US 75/PGBT Improvements Million Weldemariam, P.E. Jacobs Engineering Group Inc. AGENDA TOPICS 1 US 75 at President George Bush Turnpike Improvements Project

More information

Proposed Increase In Rates In Water, Sewer and Reclaimed. June 9, 2009

Proposed Increase In Rates In Water, Sewer and Reclaimed. June 9, 2009 Proposed Increase In Rates In Water, Sewer and Reclaimed June 9, 2009 1 WATER 2 3 Reclaimed Water Accounts 27,500 25,000 22,500 20,000 17,500 15,000 12,500 10,000 7,500 5,000 2,500 387-24,863 4 FY 96 FY

More information

BRIEFING ON FUTURE TPC AMENDMENTS TO THE TIP AND RTP

BRIEFING ON FUTURE TPC AMENDMENTS TO THE TIP AND RTP TPC Agenda Item 8C Mailout - 03/10/16 BRIEFING ON FUTURE TPC AMENDMENTS TO THE TIP AND RTP Amendment Summary Staff will present eight (8) proposed amendments to the Transportation Improvement Program and

More information

South Central Pennsylvania Regional Operations Plan Candidate Project Listing (DRAFT)

South Central Pennsylvania Regional Operations Plan Candidate Project Listing (DRAFT) South Central Pennsylvania Regional Operations Plan Candidate Project Listing (DRAFT) APPLICABILITY South Central PA ITS Deployment Plan Update Lebanon County ITS deployment Lancaster County ITS deployment

More information

NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance

NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY ITEM: 6B SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance Jacobs Engineering has completed Task 1 with amendment

More information

Florida Statewide Regional Evacuation Study Program

Florida Statewide Regional Evacuation Study Program Florida Statewide Regional Evacuation Study Program Methodology and Support Documentation Volume 8 Florida Division of Emergency Management All Florida Regional Planning Councils Includes Hurricane Evacuation

More information

ELECTRONIC PACKET MARCH 13, 2017 POLICY, FINANCE, & PERSONNEL COMMITTEE MEETING. RELEASED: Monday, March 6, 2017

ELECTRONIC PACKET MARCH 13, 2017 POLICY, FINANCE, & PERSONNEL COMMITTEE MEETING. RELEASED: Monday, March 6, 2017 ELECTRONIC PACKET MARCH 13, 2017 POLICY, FINANCE, & PERSONNEL COMMITTEE MEETING RELEASED: Monday, March 6, 2017 Item 5 COMMISSION FILE NO: 17-030-3 DATE INTRODUCED: March 13, 2017 INTRODUCED BY: REFERRED

More information

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension MOTION NO. M2014-79 Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 Varuna A. Singh August 17, 2018 NHHIP OVERVIEW Project divided into three segments: Segment 1: I-45: from Beltway 8 to I-610 (9 mi) 45 Segment

More information

TEA s Analysis of Compliance

TEA s Analysis of Compliance Maintenance of Effort (MOE) for Special Education: 2016 2017 Preliminary Compliance Review Action Steps Denise Dusek, MPA Federal Funding Specialist Education Service Center, Region 20 April 18, 2018 TEA

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0002, Ashburn Station North Broad Run CRITICAL ACTION DATE: STAFF

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

Rutgers Interactive Lane Closure Application (RILCA) for Work Zone Planning User Manual. New Jersey Highway Authority. Garden State Parkway

Rutgers Interactive Lane Closure Application (RILCA) for Work Zone Planning User Manual. New Jersey Highway Authority. Garden State Parkway Rutgers Interactive Lane Closure Application (RILCA) for Work Zone Planning User Manual Prepared for Garden State Parkway New Jersey Highway Authority April 2007 Developed by: Rutgers University Intelligent

More information

NON-VDOT ADMINISTERED PROJECTS (NVAP) PORTAL

NON-VDOT ADMINISTERED PROJECTS (NVAP) PORTAL NON-VDOT ADMINISTERED PROJECTS (NVAP) USER GUIDE DEC 2018 NON-VDOT ADMINISTERED PROJECTS (NVAP) PORTAL Localities deliver a significant number of the projects in Virginia and any reporting on the status

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The

More information

Our Stakeholders in Transportation Planning From: H. David Jones, Director (806) Fax (806)

Our Stakeholders in Transportation Planning From: H. David Jones, Director (806) Fax (806) Transportation Policy Committee Chair Karen Gibson Mayor Pro Tem Vice Chair Dr. Charles Addington, II Mayor City of Wolffor Glen Robertson Mayor Patti Jones County Commissioner Todd Klein City Council

More information

Florida Courts E-Filing Authority Board. April Readiness Report

Florida Courts E-Filing Authority Board. April Readiness Report Florida Courts E-Filing Authority Board Monday, April 30, 2012 efiling Project Team eportal Usage Statistics January 1, 2011 March 31, 2012: Cases Filed = 116,535 7,769 per month Documents Filed = 136,371

More information

2018 State and Federal Legislative Program

2018 State and Federal Legislative Program 2018 State and Federal Legislative Program STATE TRANSPORTATION FUNDING The passage of HB 2313 (2013) was the result of bipartisan cooperation throughout the Commonwealth. The regional funding provided

More information

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT 16 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 18, 2015 SUBJECT: ACTION: EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF

More information

FOR SALE >> COMMERCIAL LAND >> HWY 287 AT I-45 IN ENNIS, TX

FOR SALE >> COMMERCIAL LAND >> HWY 287 AT I-45 IN ENNIS, TX FOR SALE >> COMMERCIAL LAND >> HWY 287 AT I-45 IN ENNIS, TX Colliers International is pleased to introduce Southgate Industrial Park, 460 acres zoned for Heavy Industrial usage, with Rail Service from

More information

2014 BOND PROGRAM UPDATE

2014 BOND PROGRAM UPDATE 2014 BOND PROGRAM UPDATE Presented to the City Council By the City Manager s Office August 11, 2015 1 Topics Previous Debt Programs 2014 Bond Program o Goals o Funding Commitments o Progress Communication

More information

1.0 PURPOSE AND NEED

1.0 PURPOSE AND NEED 1.0 PURPOSE AND NEED This chapter documents the need for transit improvements in the Northwest Corridor and the purposes that the proposed project is intended to serve. An overview of the study corridor

More information

Intelligent Transportation Systems (ITS)

Intelligent Transportation Systems (ITS) Intelligent Transportation Systems (ITS) Systems Engineering (SE) Requirement Intelligent Transportation Systems (ITS) means electronics, communications, or information processing used singly or in combination

More information

NTTA Professional Services Procurement Process and Vendor Outreach Efforts

NTTA Professional Services Procurement Process and Vendor Outreach Efforts NTTA Professional Services Procurement Process and Vendor Outreach Efforts Anthony Coleman Director of Business Diversity May 1, 2013 Professional Services Procurement Act Chapter 2254 of the Government

More information

NOCoE Sponsored Virtual Peer Exchange- TMC Staffing

NOCoE Sponsored Virtual Peer Exchange- TMC Staffing NOCoE Sponsored Virtual Peer Exchange- TMC Staffing AASHTO TSMO Subcommittee Meeting September 2017 TxDOT- Traffic Operations Division September 2017 TxDOT- Traffic Operations Division September 2017 NOCoE

More information

FY STIP SAN ANTONIO DISTRICT FY TIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY

FY STIP SAN ANTONIO DISTRICT FY TIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY SAN ANTONIO DISTRICT FY 2011-2014 TIP 7-2010 FY 2011-2014 Transportation Improvement Program San Antonio Bexar County Metropolitan

More information

STATE OF FLORIDA CONTRACT NUMBER: ORDERING INSTRUCTIONS

STATE OF FLORIDA CONTRACT NUMBER: ORDERING INSTRUCTIONS ORDERING INSTRUCTIONS COMPANY: TOSHIBA AMERICA BUSINESS SOLUTIONS, INC. FEDERAL IDENTIFICATION NUMBER: 33-0865305 CONTRACT Primary contact person responsible for answering questions regarding the contract

More information

Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008

Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008 Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008 INTRODUCTION The City of Moorhead (City), along with the Fargo-Moorhead Metropolitan Council of Governments (FM

More information

Overview of SAS/GIS Software

Overview of SAS/GIS Software 3 CHAPTER 1 Overview of SAS/GIS Software Introduction to Geographic Information Systems 3 Features of SAS Software 4 Data in SAS/GIS Applications 5 Spatial Data 5 Spatial Data Layers 6 Spatial Data Coverages

More information

Director of Public Works/City Engineer. Secretary. Word Processor. Streets and Facilities Supervisor. Traffic Signal Technician.

Director of Public Works/City Engineer. Secretary. Word Processor. Streets and Facilities Supervisor. Traffic Signal Technician. PUBLIC WORKS ORGANIZATIONAL CHART Director of Public Works/City Engineer Secretary Word Processor Transit Services Manager Fleet Services Supervisor Streets and Facilities Supervisor Principal Principal

More information

Division C Land Development Division

Division C Land Development Division SECTION 1 - Applications Division C Land Development Division A. Atlas Amendment $ 650.00 plus $10.00 per acre B. Appeals Commercial Infill 1. Application to the BOCC $ 600.00 $ 650.00 plus $10.00 per

More information

TxDOT TMS PERFORMANCE MEASURES ITS TEXAS Texas Department of Transportation

TxDOT TMS PERFORMANCE MEASURES ITS TEXAS Texas Department of Transportation TxDOT TMS PERFORMANCE MEASURES ITS TEXAS 2017 Texas Department of Transportation Traffic Management Systems November 2017 TRF-TM Update 1 2 Implementation of TMS Performance Metrics TMS Performance Metrics

More information

STUDY REPORT #1 ADDENDUM

STUDY REPORT #1 ADDENDUM STUDY REPORT #1 ADDENDUM 1.0 PURPOSE OF ADDENDUM This document is an addendum to Study Report #1: Sub-System Planning Alternatives. The purpose of this addendum is to bridge the gap between the initial

More information

TRANSPORTATION DEPARTMENT Business Plan

TRANSPORTATION DEPARTMENT Business Plan TRANSPORTATION DEPARTMENT 2018 Business Plan Today s Agenda Mission Department Overview Planning Initiatives Commission Priorities and 2018 Budget Requests Five-year Plan Department of Transportation Mission

More information

2017 UNIFIED TRANSPORTATION PROGRAM (UTP) UPDATE

2017 UNIFIED TRANSPORTATION PROGRAM (UTP) UPDATE 2017 UNIFIED TRANSPORTATION PROGRAM (UTP) UPDATE Commission Workshop February 22, 2017 Workshop Agenda Introduction and Overview Discussion on Category 4 Corridors Discussion on 2017 March UTP Revision

More information

South Central ROP Projects

South Central ROP Projects Pennsylvania Department of Transportation ROP Overview and Summary South Central ROP Projects November 2007 77 INCIDENT MANAGEMENT (IM) Draft Version 1 July 2007-40 - IM 1: SOUTH CENTRAL PA ITS DEPLOYMENT

More information

65E-9 Licensure Information Residential Treatment Centers and Therapeutic Group Homes (8/2/06)

65E-9 Licensure Information Residential Treatment Centers and Therapeutic Group Homes (8/2/06) District 1 Agency Name Belle Point Mailing Address 1221 West Lakeview Avenue, Pensacola Fl 32501 Phone (850) 432-1222 Contact Craig Woolard or Lee Riley License Expiration 071507 Agency Name Coppenger

More information

FINANCE MANAGER. Accounting Manual Finance Manager.

FINANCE MANAGER. Accounting Manual Finance Manager. FINANCE MANAGER Accounting Manual 2010 Finance Manager Accounting Setup - Table of Contents Start Page... 1 Setup Which Files Should Be Completed First?... S-1 Items... S-2 Item Categories... S-7 Unit

More information

PLANNING COMMISSION WORK SESSION

PLANNING COMMISSION WORK SESSION 1 DEPARTMENT OF BUILDING AND DEVELOPMENT Date of Meeting: STAFF REPORT PLANNING COMMISSION WORK SESSION SUBJECT: ELECTION DISTRICT: FIDP-2016-0001, Broad Run CRITICAL ACTION DATE: STAFF CONTACTS: APPLICANT:

More information

Provo-Orem Bus Rapid Transit

Provo-Orem Bus Rapid Transit Provo-Orem Bus Rapid Transit and Timpanogos Maintenance Facility Expansion Procurements Informational Meeting August 18, 2014 Agenda Topic Presenter Time Introduction of key project personnel Project history

More information

Mobile Mapping Solutions for Ohio s Integrated Transportation Network. Brian Foster, CP

Mobile Mapping Solutions for Ohio s Integrated Transportation Network. Brian Foster, CP Mobile Mapping Solutions for Ohio s Integrated Transportation Network Brian Foster, CP About Woolpert Established in 1911 Over 600 Professionals 25 Offices $12,000,000 invested in new technology in last

More information

Transportation and Road Improvement GO Bond. September 2016 Report

Transportation and Road Improvement GO Bond. September 2016 Report 1 2014 Transportation and Road Improvement GO Bond 2 2014 Transportation and Road Improvement GO Bond Projects Nearing Completion Projects Moving into and is expected to last one year. By Spring 2017,

More information

MACOMB COUNTY DEPARTMENT OF ROADS TRAFFIC OPERATIONS CENTER

MACOMB COUNTY DEPARTMENT OF ROADS TRAFFIC OPERATIONS CENTER MACOMB COUNTY DEPARTMENT OF ROADS TRAFFIC OPERATIONS CENTER To provide and maintain a reliable real-time traffic operations system, in coordination with county stakeholders, that enables a safe, efficient,

More information

Virginia Transit Update

Virginia Transit Update Virginia Transit Update Jennifer Mitchell Agency Director Virginia Transit Association May 24, 2017 1 Key Priorities for Statewide Transit Program Funding Safety and State of Good Repair Expansion 2 Funding

More information

New York Building Congress May 24, Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital

New York Building Congress May 24, Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital New York Building Congress May 24, 2016 Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital Construc@on Agenda 1. East Side Access 2. Second Avenue Subway 3. Penn Access 4. Security Projects

More information

Neutral Host Reimbursable Capital Project

Neutral Host Reimbursable Capital Project Finance & Administration Committee Action Item III-E November 4, 2010 Neutral Host Reimbursable Capital Project Page 37 of 161 Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Lee District Summary Report

Lee District Summary Report oute Lee Summary eport Key: =omplete; =OnSchedule; =Behind Schedule; =hange Since Previous eport; =Schedule oncern; =Funding oncer Key: D=Design; =ight-of-way Acquisition; =tility elocation; =onstruction(includes

More information

Paul DiGiacobbe, PE, DBIA MASER Consulting Ryan Putt, PE HNTB Corporation Kevin Poad, PE HNTB Corporation

Paul DiGiacobbe, PE, DBIA MASER Consulting Ryan Putt, PE HNTB Corporation Kevin Poad, PE HNTB Corporation Paul DiGiacobbe, PE, DBIA MASER Consulting Ryan Putt, PE HNTB Corporation Kevin Poad, PE HNTB Corporation Introduction Using LiDAR to Manage Safety Assets SPEED the acquisition phase is being performed

More information

LiDAR AT PennDOT Michael Loose, C.P. BOPD Photogrammetry and Surveys

LiDAR AT PennDOT Michael Loose, C.P. BOPD Photogrammetry and Surveys LiDAR AT PennDOT Michael Loose, C.P. BOPD Photogrammetry and Surveys 2 I. What is LiDAR? II. Benefits of LiDAR III. PennDOT Case Studies IV. Best Practices/Lessons Learned V. Questions 3 4 LiDAR for Engineering

More information

Recommendation to Board. Final Action

Recommendation to Board. Final Action MOTION NO. M2017-59 City of Seattle Center City Mobility Plan Agreement MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 05/04/2017 05/25/2017 Recommendation

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

Civic Center Station

Civic Center Station Civic Center Station City of Pittsburg Webinar May 21, 2014 Staff: Joe Sbranti, City Manager Tina Olson, Finance Director Maria Aliotti, Development Manager Leigha Schmidt, Planner Special Counsel: David

More information

6.9 Intelligent Transportation Systems

6.9 Intelligent Transportation Systems 6.9 Intelligent Transportation Systems This chapter describes Intelligent Transportation Systems (). The chapter also describes the process that defines how agencies and systems are interconnected through

More information

FY Janette Pell Department Director. Information and Communications Technology. Administration and Finance

FY Janette Pell Department Director. Information and Communications Technology. Administration and Finance FY 2018 19 Janette Pell Department Director Administration and Finance Capital Projects Facilities and Real Estate Management Fleet Operations Information and Communications Technology Purchasing, Surplus

More information

The Piedmont Corridor

The Piedmont Corridor Richard E. Mullinax, PE, PTOE, CPM 27 March 2018 Piedmont Corridor Part of Federal Southeast Corridor 1992 Federal Railroad Administration designated Southeast High Speed Rail Corridor Important Freight

More information

Our Mission: To provide technology resources for the County and set the vision for future technology investments

Our Mission: To provide technology resources for the County and set the vision for future technology investments Jack Belcher, Chief Information Officer 2100 CLARENDON BLVD., SUITE 612, ARLINGTON, VA 22201 703-228-3220 cio@arlingtonva.us Our Mission: To provide technology resources for the County and set the vision

More information

2017 ANNUAL REPORT

2017 ANNUAL REPORT INFRASTRUCTURE UPGRADES ECONOMIC DEVELOPMENT PUBLIC SAFETY IMPROVED APPEARANCE 2017 ANNUAL REPORT www.stonemountaincid.com Stone Mountain Community Improvement District BOARD OF DIRECTORS Chairman Joe

More information

CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION. Ryan Sagar 1196 Grant Street, Suite 313 Denver, CO 80203

CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION. Ryan Sagar 1196 Grant Street, Suite 313 Denver, CO 80203 CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION HEARING DATE: January 11, 2018 PROJECT NAME: FTC Chippers SC CASE NUMBER: PDP #170027 APPLICANT: OWNER: HEARING OFFICER: LRK Consulting

More information