YEAR 12 FURTHER MATHS UNIT 4 MODULE 2 NETWORKS AND DECISION MATHEMATICS CRITICAL PATH ANALYSIS
|
|
- Jasmine Woods
- 5 years ago
- Views:
Transcription
1 YEAR 12 FURTHER MATHS UNIT 4 MODULE 2 NETWORKS AND DECISION MATHEMATICS CRITICAL PATH ANALYSIS Directed graphs or digraphs can be used to model situations where an order or direction is implied. For example, in the construction of a building the foundations must be laid before the walls can be erected. Often many activities cannot be started until other activities are completed. Any large scale project consists of many phases. The success of the project depends very much on the quality of the planning, scheduling and controlling of these phases. Example: Drawing Activity Networks from Precedence Tables Activity Immediate (EDGE) predecessor A - B - C D E F G A B B C, D E, F Solution: A and B do not have any predecessors so they form the start and can be done at the same time. Check the precedence table and draw edges for each activity from its predecessor. NOTE: G is not an immediate predecessor of any activity so it is the final edge. Do Ex 15C Page 533 Questions 1 a, b, c
2 Dummy Activities Why have a dummy activity? 1.To avoid multiple arcs between two nodes. Sometimes a list of activities and their predecessors leads to multiple arcs between two particular nodes. It is best to avoid this happening so that you can identify different paths through the network. The solution is to create a dummy or invented activity, used solely to keep the precedence structure and allow unique paths to be seen. Eg. If a project has two activities A and B from the start node that are both predecessors of activity C. The diagram on the left is what we would have with multiple arcs; the diagram on the right is the way it is drawn with a dummy activity. It can be drawn before A or before B. Note: a dummy activity is drawn as a dashed arc and still should have a direction. 2. To avoid logical difficulties. Eg. An activity X, has U and V as predecessors. Another activity Y, has only V as a predecessor. A dummy activity is used to keep the correct logical structure as shown in the diagram below right. Draw X after U, draw Y after V, and to ensure that X cannot start until V has been finished, draw a dotted arrow, indicating a dummy activity, from the end of V to the start of.
3 Do Exercise 15C Page 533 Q1d onwards
4 The Critical path Some activities are more critical than others in the completion of a project. Activities can be delayed if they are not critical. A critical activity is any task that if delayed will also delay the entire project. The critical path is the path that gives the largest total of the weighting. These events must occur on time if the project is not to be held up. It is along the critical path that time on the overall project may be saved. Example: Identify the critical path in this project. Solution: Identify all the paths through the network. The float time (or slack). For each activity that is not on the critical path there will be some slack. Eg. Some activities may be able to start a little later and still not affect the finishing time. Float (or Slack) Time is the amount by which the latest finish time is greater than its earliest start time. Float = LST - EST To find the earliest time of an event occurring. (EST) Add the numbers along the path from the first event. Beside each event a double box is drawn. In the left hand box, enter the earliest event time. Always take the largest value. To find the latest time of an event occurring. (LST) Work backward from the earliest time for the final event, by subtracting the number on the edge. Do Exercise 15D Page 543 All questions
5 Crashing In large projects, once the critical path has been identified, it may be possible to put in extra resources (at extra cost) to reduce the duration of one or more of the critical activities. This will have the effect of reducing the overall project duration, which may result in sufficient cost savings to make the extra resource allocation and cost worthwhile. Reducing the length of (some) critical activities is called crashing. It is along the critical path that reductions in activities reduce the length of the project. The minimum possible time to complete an activity (using maximum resources) is called the crash time. The costs associated with crash time for an activity are called crash costs. NOTE: Sometimes reducing activities along a critical path can produce another new critical path that was not critical before. A simple crashing example: Text Book Page 546
6 Example: a. What is the critical path for this project and the minimum completion time? Also complete the table showing EST and LST. Activity EST LST A B C D E F G H I J
Chapter 6: Activity Planning Part 2
Chapter 6: Activity Planning Part 2 NET481: Project Management Afnan Albahli " Representing Lagged Activities Lag activities: are two activities that will be undertaken in parallel but there is a lag between
More informationSEQUENCING AND SCHEDULING ACTIVITIES
SEQUENCING AND SCHEDULING ACTIVITIES SEQUENCING AND SCHEDULING ACTIVITIES Throughout a project, we will require a schedule that clearly indicates when each of the project s activities is planned to occur
More informationModelling with linear programming
Modelling with linear programming jla@imm.dtu.dk Informatics and Mathematical Modeling Technical University of Denmark 1 Decision models Real world abstraction Model interpretation A model is a carefully
More informationif i is a predecessor of j, and there i is an immediate predecessor (IP) of j is no other job for which i is a predecessor and j a successor. Then j i
8.1 Project management applications Katta G. Murty, IOE 612 Lecture slides 8 Large projects consist of many individual jobs (or activities) with a predecessor ordering among them. Job i is a pre- if j
More informationConstruction Planning & scheduling. Precedence Networks. Precedence networks
Construction Planning & scheduling Precedence Networks Dr. Maha alkasasbeh are the most common type of network schedule in use today Most scheduling software these days require the user to input the information
More informationNetwork Optimization Models. Chapter 10: Hillier and Lieberman Chapter 8: Decision Tools for Agribusiness Dr. Hurley s AGB 328 Course
Network Optimization Models Chapter 10: Hillier and Lieberman Chapter 8: Decision Tools for Agribusiness Dr. Hurley s AGB 328 Course Terms to Know Nodes, Arcs, Directed Arc, Undirected Arc, Links, Directed
More informationDependency Table Example. Task ID Name Predecessors 1 A 2 B 3 C 4 D 1 5 E 1;2 6 F 1;2 7 G 5;6 8 H 4;5
Dependency Table Example Task ID Name Predecessors 1 A 2 B 3 C 4 D 1 5 E 1;2 6 F 1;2 7 G 5;6 8 H 4;5 Dependent tasks Dependency Matrix 1 2 3 4 5 6 7 8 9 10 1 x 2 x x 3 x x 4 x 5 x x 6 x 7 x 8 x 9 x x 10
More informationMATHEMATICS (MEI) 4771 Decision Mathematics 1
ADVANCED SUBSIDIARY GCE MATHEMATICS (MEI) 4771 Decision Mathematics 1 QUESTION PAPER * OCE / 1 3662* Candidates answer on the Printed Answer Book OCR Supplied Materials: Printed Answer Book 4771 MEI Examination
More informationMonday 23 January 2012 Morning
Monday 2 January 202 Morning AS GCE MATHEMATICS (MEI) 477 Decision Mathematics QUESTION PAPER *472202* Candidates answer on the Printed Answer Book. OCR supplied materials: Printed Answer Book 477 MEI
More informationMathematics Success Grade 8
T616 Mathematics Success Grade 8 [OBJECTIVE] The student will explore angle relationships within triangles. [PREREQUISITE SKILLS] angles, congruency, supplementary angles, adjacent angles [MATERIALS] Student
More information2.3.5 Project planning
efinitions:..5 Project planning project consists of a set of m activities with their duration: activity i has duration d i, i = 1,..., m. estimate Some pairs of activities are subject to a precedence constraint:
More informationADMS 3330 FALL 2008 EXAM All Multiple choice Exam (See Answer Key on last page)
MULTIPLE CHOICE. Choose the letter corresponding to the one alternative that best completes the statement or answers the question. 1. Which of the following are assumptions or requirements of the transportation
More informationSubtraction Understand Subtraction on a Number Line Using a number line let s demonstrate the subtraction process using the problem 7 5.
Objective 1 Subtraction Understand Subtraction on a Number Line Using a number line let s demonstrate the subtraction process using the problem 7 5. -7-6 -5-4 -3-2 -1 0 1 2 3 4 5 6 7 Using the number line
More informationCS6704 RESOURCE MANAGEMENT TECHNIQUES TOPIC WISE QUESTION BANK LINEAR PROGRAMMING PROBLEMS 1) What is OR techniques? Where it can be used? 2) What is OR? List out various applications of OR. 3) Explain
More information5.4 Pure Minimal Cost Flow
Pure Minimal Cost Flow Problem. Pure Minimal Cost Flow Networks are especially convenient for modeling because of their simple nonmathematical structure that can be easily portrayed with a graph. This
More informationKey Terms. Writing Algebraic Expressions. Example
Chapter 6 Summary Key Terms variable (6.1) algebraic expression (6.1) evaluate an algebraic expression (6.1) Distributive Property of Multiplication over Addition (6.2) Distributive Property of Multiplication
More informationWe can use square dot paper to draw each view (top, front, and sides) of the three dimensional objects:
Unit Eight Geometry Name: 8.1 Sketching Views of Objects When a photo of an object is not available, the object may be drawn on triangular dot paper. This is called isometric paper. Isometric means equal
More informationMath for Liberal Arts MAT 110: Chapter 13 Notes
Math for Liberal Arts MAT 110: Chapter 13 Notes Graph Theory David J. Gisch Networks and Euler Circuits Network Representation Network: A collection of points or objects that are interconnected in some
More informationChapter 26 Set up Smart Connect for Search and Store DW 6.10
Chapter 26 Set up Smart Connect for Search and Store DW 6.10 The Smart Connect module is designed to have a quick integration to other applications and allow the user to gather information for indexes
More informationMini-Project 1: The Library of Functions and Piecewise-Defined Functions
Name Course Days/Start Time Mini-Project 1: The Library of Functions and Piecewise-Defined Functions Part A: The Library of Functions In your previous math class, you learned to graph equations containing
More informationLesson 5: Identical Triangles
NS COMMON CORE MATHEMATICS CURRICULUM Lesson 5 7 6 Classwork Opening When studying triangles, it is essential to be able to communicate about the parts of a triangle without any confusion. The following
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More informationConnect the Dots NEW! Reveal a picture through your skill at working on a coordinate plane.
NEW! Connect the Dots Reveal a picture through your skill at working on a coordinate plane. Typically in a connect-the-dots puzzle, the dots are already given, but not in the National Math Club s version!
More informationMathematics Success Level E
T877 [OBJECTIVE] The student will classify two-dimensional figures based on properties. [PREREQUISITE SKILLS] Lesson 29, knowledge of basic geometry terminology including: parallel sides, congruent sides,
More informationFind terms of a sequence and say whether it is ascending or descending, finite or infinite Find the next term in a sequence of numbers or shapes
1.1 Sequences Find terms of a sequence and say whether it is ascending or descending, finite or infinite Find the next term in a sequence of numbers or shapes Key words sequence term consecutive infinite
More informationThe following notation will be used in the explanations:
In the following slides some geometry basics will be presented: Finding the center of a circle/arc Construct a circle from three points Finding the min/max distance between a point and circle/arc page
More informationBoxplots. Lecture 17 Section Robb T. Koether. Hampden-Sydney College. Wed, Feb 10, 2010
Boxplots Lecture 17 Section 5.3.3 Robb T. Koether Hampden-Sydney College Wed, Feb 10, 2010 Robb T. Koether (Hampden-Sydney College) Boxplots Wed, Feb 10, 2010 1 / 34 Outline 1 Boxplots TI-83 Boxplots 2
More informationLesson #3. Variables, Operators, and Expressions. 3. Variables, Operators and Expressions - Copyright Denis Hamelin - Ryerson University
Lesson #3 Variables, Operators, and Expressions Variables We already know the three main types of variables in C: int, char, and double. There is also the float type which is similar to double with only
More informationLECTURES 3 and 4: Flows and Matchings
LECTURES 3 and 4: Flows and Matchings 1 Max Flow MAX FLOW (SP). Instance: Directed graph N = (V,A), two nodes s,t V, and capacities on the arcs c : A R +. A flow is a set of numbers on the arcs such that
More informationSimple graph Complete graph K 7. Non- connected graph
A graph G consists of a pair (V; E), where V is the set of vertices and E the set of edges. We write V (G) for the vertices of G and E(G) for the edges of G. If no two edges have the same endpoints we
More informationInDesign Tutorial: Working with InDesign panels. InDesign Tutorial: Working with InDesign panels. The InDesign Tools panel
InDesign Tutorial: Working with InDesign panels What you?ll learn in this InDesign Tutorial: The InDesign CS6 Tools Panel Understanding the InDesign CS6 Workspace This tutorial provides you with a foundation
More informationn Given: n set of resources/machines M := {M 1 n satisfies constraints n minimizes objective function n Single-Stage:
Scheduling Scheduling is the problem of allocating scarce resources to activities over time. [Baker 1974] Typically, planning is deciding what to do, and scheduling is deciding when to do it. Generally,
More informationChapter 3. Planning and Scheduling. Chapter Objectives. Check off these skills when you feel that you have mastered them.
Chapter Objectives Check off these skills when you feel that you have mastered them. State the assumptions for the scheduling model. Compute the lower bound on the completion time for a list of independent
More informationExpressions. Eric McCreath
Expressions Eric McCreath 2 Expressions on integers There is the standard set of interger operators in c. We have: y = 4 + 7; // add y = 7-3; // subtract y = 3 * x; // multiply y = x / 3; // integer divide
More informationChapter 5snow year.notebook March 15, 2018
Chapter 5: Statistical Reasoning Section 5.1 Exploring Data Measures of central tendency (Mean, Median and Mode) attempt to describe a set of data by identifying the central position within a set of data
More informationScheduling. Job Shop Scheduling. Example JSP. JSP (cont.)
Scheduling Scheduling is the problem of allocating scarce resources to activities over time. [Baker 1974] Typically, planning is deciding what to do, and scheduling is deciding when to do it. Generally,
More information12 Abstract Data Types
12 Abstract Data Types 12.1 Foundations of Computer Science Cengage Learning Objectives After studying this chapter, the student should be able to: Define the concept of an abstract data type (ADT). Define
More informationCRITICAL PATH ANALYSIS
UMMRY H IION MH RIIL PH NLYI he main ideas are covered in efore the exam you should know Q dexcel MI OR When you need to use dummy activities. he main ideas in this topic are rawing ctivity or Precedence
More informationHow to Do Word Problems. Building the Foundation
Building the Foundation The notion that Mathematics is a language, is held by many mathematicians and is being expressed on frequent occasions. Mathematics is the language of science. It is unique among
More informationM. Yamuna* et al. /International Journal of Pharmacy & Technology
ISSN: 0975-766X CODEN: IJPTFI Available Online through Research Article www.ijptonline.com FINDING CRITICAL PATH OF A NETWORK USING MODIFIED DIJKSTRA S ALGORITHM Shantan Sawa, Shivangee Sabharwal, Purushottam
More informationSUGGESTED SOLUTION CA FINAL MAY 2017 EXAM
SUGGESTED SOLUTION CA FINAL MAY 2017 EXAM ADVANCED MANAGEMENT ACCOUNTING Test Code - F M J 4 0 1 6 BRANCH - (MULTIPLE) (Date : 11.02.2017) Head Office : Shraddha, 3 rd Floor, Near Chinai College, Andheri
More informationMidterm II CS164, Spring 2006
Midterm II CS164, Spring 2006 April 11, 2006 Please read all instructions (including these) carefully. Write your name, login, SID, and circle the section time. There are 10 pages in this exam and 4 questions,
More informationMATHEMATICS (MEI) 4771 Decision Mathematics 1
DVNCED SUSIDIRY GCE MTHEMTICS (MEI) 4771 Decision Mathematics 1 *OCE/T67883* Candidates answer on the nswer ooklet OCR Supplied Materials: Printed nswer ook MEI Examination Formulae and Tables (MF2) Other
More informationMICROSOFT PROJECT 2010 EXERCISE
MICROSOFT PROJECT 2010 EXERCISE Copyright 2011 University of Warwick MICROSOFT PROJECT 2010 EXERCISE Introduction In MS Project there are typically several possible ways to do each desired action. This
More informationIndustrial Engineering and Ergonomics
Industrial Engineering and Ergonomics Exercise Unit 2 Work organization Fall Winter 207/208 Dr.-Ing. Dr. rer. medic. Dipl.-Inform. Alexander Mertens Chair and Institute of Industrial Engineering and Ergonomics
More informationLearning Log Title: CHAPTER 3: ARITHMETIC PROPERTIES. Date: Lesson: Chapter 3: Arithmetic Properties
Chapter 3: Arithmetic Properties CHAPTER 3: ARITHMETIC PROPERTIES Date: Lesson: Learning Log Title: Date: Lesson: Learning Log Title: Chapter 3: Arithmetic Properties Date: Lesson: Learning Log Title:
More informationChapter 4 Answers. Lesson 4.1. Chapter 4 Answers 1
Chapter 4 Answers Lesson 4.1 1. 2. 3. 4. Chapter 4 Answers 1 5. Answers vary. Sample answer: a. A: 2, none; B: 4, A; C: 3, B; D: 7, C; E: 5, A; F: 10, E; G: 8, A; H: 3, A; I: 4, D, F, G, and H b. c. In
More informationIntroduction to AutoCAD 2010
Page 1 Introduction to AutoCAD 2010 Alf Yarwood Chapter 2 Exercise 1 1. Open AutoCAD 2010 - either with a double-click on its start-up icon in the Windows desktop, or by using the method on the computer
More informationPENTAGON FUZZY NUMBER AND ITS APPLICATION TO FIND FUZZY CRITICAL PATH
Volume 114 No. 5 017, 183-185 ISSN: 1311-8080 (printed version); ISSN: 1314-3395 (on-line version) url: http://www.ijpam.eu PENTAGON FUZZY NUMBER AND ITS APPLICATION TO FIND FUZZY CRITICAL PATH SyedaNaziyaIkram
More information1 Introduction. 1.1 Clicking on any orange box shows the login window. Seatrack Web last updated
Seatrack Web last updated 2016-11-07 1 Introduction Below follow simple screenshots of what to expect when selecting the orange boxes. This is the start page for Seatrack Web located at https://stw-helcom.fcoo.dk/.
More informationMATH 353 Engineering mathematics III
MATH 353 Engineering mathematics III Instructor: Francisco-Javier Pancho Sayas Spring 2014 University of Delaware Instructor: Francisco-Javier Pancho Sayas MATH 353 1 / 20 MEET YOUR COMPUTER Instructor:
More informationClass Notes, 3/21/07, Operating Systems
Class Notes, 3/21/07, Operating Systems Hi, Jane. Thanks again for covering the class. One of the main techniques the students need to how to recognize when there is a cycle in a directed graph. (Not all
More informationBaseline Scheduling with ProTrack
Baseline Scheduling with ProTrack 1.0 (last update: 11/11/08) 1 Baseline Scheduling with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner
More informationENGR (Socolofsky) Week 02 Python scripts
ENGR 102-213 (Socolofsky) Week 02 Python scripts Listing for script.py 1 # data_types.py 2 # 3 # Lecture examples of using various Python data types and string formatting 4 # 5 # ENGR 102-213 6 # Scott
More informationTTS Scratch Controller. Teacher Guide. 1 TTS Scratch Controller - Teacher Guide. Product Code: EL00530
1 TTS Scratch Controller - Teacher Guide Product Code: EL00530 TTS Scratch Controller Teacher Guide www.tts-shopping.com 2 TTS Scratch Controller - Teacher Guide TTS Scratch Controller Using the Scratch
More informationThe Algorithm Design by using programming language Visual Basic for Application on the example of Crithical Path Method (CPM)
The Algorithm Design by using programming language Visual Basic for Application on the example of Crithical Path Method (CPM) Slavomir Vukmirović Economics Faculty University of Rijeka, Croatia vukmirovics@gmail.com,
More informationGraph and Digraph Glossary
1 of 15 31.1.2004 14:45 Graph and Digraph Glossary A B C D E F G H I-J K L M N O P-Q R S T U V W-Z Acyclic Graph A graph is acyclic if it contains no cycles. Adjacency Matrix A 0-1 square matrix whose
More informationAssessment of Programming Skills of First Year CS Students: Problem Set
Assessment of Programming Skills of First Year CS Students: Problem Set Notes to the working group participants. Enclosed in this file are the three problems. They are in ascending order of difficulty.
More informationName Course Days/Start Time
Name Course Days/Start Time Mini-Project : The Library of Functions In your previous math class, you learned to graph equations containing two variables by finding and plotting points. In this class, we
More informationA Theory of Parallel Computation The π-calculus
A Theory of Parallel Computation The π-calculus Background DFAs, NFAs, pushdown automata, Turing machines... All are mathematical entities that model computation. These abstract systems have concrete,
More informationLab 7 - Toaster Oven Commit ID Form:
UNIVERSITY OF CALIFORNIA, SANTA CRUZ BOARD OF STUDIES IN COMPUTER ENGINEERING CMPE-13/L: COMPUTER SYSTEMS AND C PROGRAMMING Lab 7 - Toaster Oven Commit ID Form: http://goo.gl/forms/d2lo0jqhcr Introduction
More informationUnit 7 Day 1. Task Graphs and Critical Paths
Unit 7 Day 1 Task Graphs and ritical Paths Remember that ollege Tour ctivity is due at the beginning of class tomorrow!! Notes Day 1 Task Graphs and ritical Paths GRPH PPLITIONS How does a building contractor
More informationObject Behaviours UML Statecharts
Object Behaviours UML Statecharts Software Requirements and Design CITS 4401 Lecture 5 Based on Ch 5 Lecture Notes by Bruegge & Dutoit Finite state machine flip switch on light off light on flip switch
More informationImage Formation and the Lens: Object Beyond The Focal Point
Image Formation and the Lens: Object Beyond The Focal Point A convex lens is shown below with its focal points displayed (the dots). An object is located to the left of and at a distance of 2f to the lens.
More informationIntroduction to Networks
LESSON 1 Introduction to Networks Exploratory Challenge 1 One classic math puzzle is the Seven Bridges of Königsberg problem which laid the foundation for networks and graph theory. In the 18th century
More informationPrimal Simplex Algorithm for the Pure Minimal Cost Flow Problem
Primal Simplex Algorithm for the Pure Minimal Cost Flow Problem Algorithm This section describes the adaptation of the primal simplex algorithm for solving a pure network flow program; that is, the problem
More informationAn Introduction to Graph Theory
An Introduction to Graph Theory CIS008-2 Logic and Foundations of Mathematics David Goodwin david.goodwin@perisic.com 12:00, Friday 17 th February 2012 Outline 1 Graphs 2 Paths and cycles 3 Graphs and
More informationAutoCAD 2D I. Module 15. Trimming and Extending. IAT Curriculum Unit PREPARED BY. January 2011
AutoCAD 2D I Trimming and Extending PREPARED BY IAT Curriculum Unit January 2011 Institute of Applied Technology, 2011 Auto CAD Self-paced Learning Modules AutoCAD 2D Trimming and Extending Learning Outcomes:
More informationmay be sent to:
B A S I C M A T H A Self-Tutorial by Luis Anthony Ast Professional Mathematics Tutor LESSON 1: NUMBERS Copyright 2005 All rights reserved. No part of this publication may be reproduced or transmitted in
More informationUse of Technology. Perform statistical computations on stored data or entered statistics.
Chapter 1 Introduction Use of Technology Statistics is a field that deals with sets of data. After the data is collected, it needs to be organized and interpreted. There is a limit to how much of the work
More information2.8 An application of Dynamic Programming to machine renewal
ex-.6-. Foundations of Operations Research Prof. E. Amaldi.6 Shortest paths with nonnegative costs Given the following directed graph, find a set of shortest paths from node to all the other nodes, using
More informationIntro to Contemporary Math
Intro to Contemporary Math Conditional Probability Intro Department of Mathematics UK Announcement You have a homework assignment due next Monday. Sequences of Experiments Suppose two experiments are performed,
More informationAustralian Journal of Basic and Applied Sciences. Meeting the Desired Fuzzy Shortest Possible Duration to Complete the Project at Fuzzy Least Cost
Australian Journal of Basic and Applied Sciences, 9(23) July 2, Pages: 36-43 ISSN:99-878 Australian Journal of Basic and Applied Sciences Journal home page: www.ajbasweb.com Meeting the Desired Shortest
More informationComputational Modelling 102 (Scientific Programming) Tutorials
COMO 102 : Scientific Programming, Tutorials 2003 1 Computational Modelling 102 (Scientific Programming) Tutorials Dr J. D. Enlow Last modified August 18, 2003. Contents Tutorial 1 : Introduction 3 Tutorial
More informationCSE 333 Midterm Exam 7/29/13
Name There are 5 questions worth a total of 100 points. Please budget your time so you get to all of the questions. Keep your answers brief and to the point. The exam is closed book, closed notes, closed
More informationGraphs Definitions. Gunnar Gotshalks. GraphDefinitions 1
Graphs Definitions GraphDefinitions 1 Examples of Graphs Street maps» Vertices are the intersections» Edges are the streets Power line network» Vertices are the houses & power stations» Edges are the power
More informationFireplace Mantel in Google SketchUp
Creating the fireplace itself is quite easy: it s just a box with a hole. But creating the mantel around the top requires the fun-to-use Follow Me tool. This project was created in SketchUp 8, but will
More informationUse the Associative Property of Multiplication to find the product.
3-1 1. The Associative Property of Multiplication states factors can be grouped differently and the product remains the same. Changing the grouping of the factors changes the factors that are multiplied
More information8 Optimisation. 8.1 Introduction to Optimisation
8 8.1 Introduction to 8.1 Introduction refers to compiler strategies which result in generated object code which is more efficient, either in terms of speed or memory use. can be performed in two locations:
More informationSubprime Fibonacci sequences
CS 7A - Spring 2015 - Richard Guy s Sub-Fibonacci Sequence. Due 5/21/15 Subprime Fibonacci sequences 0.1 Background Theory Start like the Fibonacci sequence 0, 1, 1, 2, 3, 5,..., but before you write down
More informationFundamentals of Operations Research. Prof. G. Srinivasan. Department of Management Studies. Indian Institute of Technology Madras.
Fundamentals of Operations Research Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras Lecture No # 06 Simplex Algorithm Initialization and Iteration (Refer Slide
More informationCourse Learning Outcomes for Unit I. Reading Assignment. Unit Lesson. UNIT I STUDY GUIDE Number Theory and the Real Number System
UNIT I STUDY GUIDE Number Theory and the Real Number System Course Learning Outcomes for Unit I Upon completion of this unit, students should be able to: 2. Relate number theory, integer computation, and
More informationSTATISTICAL TECHNIQUES. Interpreting Basic Statistical Values
STATISTICAL TECHNIQUES Interpreting Basic Statistical Values INTERPRETING BASIC STATISTICAL VALUES Sample representative How would one represent the average or typical piece of information from a given
More informationGraphs of Increasing Exponential Functions
Section 5 2A: Graphs of Increasing Exponential Functions We want to determine what the graph of an exponential function y = a x looks like for all values of a > We will select a value of a > and examine
More informationMini-Project 1: The Library of Functions and Piecewise-Defined Functions
Name Course Days/Start Time Mini-Project 1: The Library of Functions and Piecewise-Defined Functions Part 2: Piecewise-Defined Functions A piecewise-defined function is two or more functions combined into
More informationTable of Contents. 1. Creating a Microsoft Excel Workbook...1 EVALUATION COPY
Table of Contents Table of Contents 1. Creating a Microsoft Excel Workbook...1 Starting Microsoft Excel...1 Creating a Workbook...2 Saving a Workbook...3 The Status Bar...5 Adding and Deleting Worksheets...6
More informationGraphs of Increasing Exponential Functions
Section 5 2A: Graphs of Increasing Exponential Functions We want to determine what the graph of an exponential function y = a x looks like for all values of a > We will select a value of a > and examine
More informationMatDeck tips. Basic. :=- assignment of variable values; assign value to variable a with code a := value
MatDeck tips Basic :=- assignment of variable values; assign value to variable a with code a := value = - displaying variable value; display value stored in the variable a with code a = Alt continue with
More informationif you have anything on the screen you can clear it by pressing: CLEAR
Graphing Calculators are really very powerful hand held computing devices. The allow mathematics problems to be investigated by those whose learning styles range from the symbolic to the visual to the
More informationMathematics for Business and Economics - I. Chapter7 Linear Inequality Systems and Linear Programming (Lecture11)
Mathematics for Business and Economics - I Chapter7 Linear Inequality Systems and Linear Programming (Lecture11) A linear inequality in two variables is an inequality that can be written in the form Ax
More informationMathematics Concepts 2 Exam 1 Version 4 21 September 2018
Mathematics Concepts 2 Exam 1 Version 4 21 September 2018 Name: Permissible Aides: The small ruler distributed by the proctor Prohibited: Class Notes Class Handouts Study Guides and Materials The Book
More informationDecision Mathematics D1 Advanced/Advanced Subsidiary. Friday 17 May 2013 Morning Time: 1 hour 30 minutes
Paper Reference(s) 6689/01R Edexcel GCE ecision Mathematics 1 Advanced/Advanced Subsidiary Friday 17 May 2013 Morning Time: 1 hour 30 minutes Materials required for examination Nil Items included with
More informationProject Management. Week 5 Microsoft Project 2007 Tutorial
Project Management Week 5 Microsoft Project 2007 Tutorial Project Activities ID TASK NAME DURATION PREDECESSORS 1 A1 CLIENT WORKSHOP 10-2 A2 CASE MODEL 15 1 3 A3 USER REVIEW 10 2 4 B1 Db DEFINITION 10
More informationECE 2030D Computer Engineering Spring problems, 5 pages Exam Two 8 March 2012
Instructions: This is a closed book, closed note exam. Calculators are not permitted. If you have a question, raise your hand and I will come to you. Please work the exam in pencil and do not separate
More informationIntroduction p. 1 Java Features p. 2 Java Expansion p. 4 Getting, Setting Up, and Using Java p. 5 The Java Language p. 5 Java Swing Components p.
Introduction p. 1 Java Features p. 2 Java Expansion p. 4 Getting, Setting Up, and Using Java p. 5 The Java Language p. 5 Java Swing Components p. 6 Components, Containers, and Layour Management p. 6 Checkboxes,
More informationPractical 2: Ray Tracing
2017/2018, 4th quarter INFOGR: Graphics Practical 2: Ray Tracing Author: Jacco Bikker The assignment: The purpose of this assignment is to create a small Whitted-style ray tracer. The renderer should be
More informationExamples of Tasks from Course 1, Unit 4
Examples of Tasks from Course 1, Unit 4 What Solutions are Available? Lesson 1: page 258, Modeling Task 1; page 260, Modeling Task 4; page 261, Organizing Task 1; page 271, Modeling Task 2; page 272, Modeling
More information4 Operations On Data 4.1. Foundations of Computer Science Cengage Learning
4 Operations On Data 4.1 Foundations of Computer Science Cengage Learning Objectives After studying this chapter, the student should be able to: List the three categories of operations performed on data.
More informationPLAY VIDEO. 2. Select Cell Library File menu > New item to display the Create Cell Library dialog.
Chapter 12 Cells PLAY VIDEO INTRODUCTION A cell is a group of elements combined into one complex element and stored in a cell library or in your design file as a shared cell. Any cell can be easily recalled
More informationAdjusting the Schedule
L E S S O N 3 Adjusting the Schedule Suggested lesson time 45-55 minutes Lesson objectives To be able to manage future tasks, you will: a b Adjust future tasks. You will adjust future tasks by changing
More information