PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

Size: px
Start display at page:

Download "PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System"

Transcription

1 PUBLIC SERVICE OF NEW HAMPSHIRE Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System September 2013

2 1.0 Purpose of this document Public Service of New Hampshire s (PSNH) Supplemental Energy Sources Department (SESD) has established an administrative process for dealing with all types and sizes of Non Utility Generation (NUG) installations. As the level of Developer interest advances beyond the initial enquiry phase, a formal review process takes place in which the potential impact of a given site on the PSNH electrical grid is reviewed. Except for certain inverter-interfaced Net Metered installations (see section 5.B. of this document), this review includes the execution of a formal Interconnection Study (the Study ) and the production of a formal Interconnection Report (the Report ) in which general and specific requirements for certain design aspects of the facility will be defined. These requirements typically include electrical protection and control design and configuration, interface transformer configuration, required upgrades to local PSNH facilities, metering and supervisory control and data acquisition (SCADA) requirements, and in some cases operating constraints for the proposed generation. Depending on the level of general NUG activity at the time, the process can be time consuming as all proposed installations are placed in a queue and are addressed on a first-come, firstserved basis. In an effort to provide potential NUG Developers with an understanding of typical PSNH interface design requirements, this document (the Guidelines ) was developed and is supplied to all potential NUG Developers at the time of initial contact. The information contained within the Guidelines is intended to help those who are attempting to define conceptual designs to better understand the general nature and extent of typical PSNH requirements for installations of various types and electrical size. Such an understanding will generally allow more accurate estimates for the cost and scope of such designs to be produced. Where the Developer has design flexibility, such advance information may also allow choices to be made which will minimize the duration of the PSNH review and approval path, as well as to limit the overall cost of the installation. It should be understood that no attempt has been made to identify all potential PSNH requirements for each and every possible type of NUG source, technology, size and/or configuration. It should also be noted that generic PSNH metering and SCADA requirements are not included in the Guidelines, other than by reference (see section 4.B.2). All such detail will be defined in the Interconnection Report produced for the site. 2.0 Disclaimer It is very important to understand that the Guidelines are in no way a substitute for the formal Interconnection Report which may be required for a given site. SESD will be able to advise the Developer at the time of initial contact as to whether or not such a report will be required. Where such a report is required, materials purchased and engineering performed to address PSNH requirements must be based on the details contained within the Report. Any commitments which are made by a Developer on the basis of the content of the Guidelines are made entirely at the Developer s risk. 2

3 3.0 Why are NUG Interconnection Studies required by PSNH? The PSNH grid is designed to transmit electrical energy from generating sources to end users in a safe, reliable, efficient manner. As such, provisions must be made to ensure that electrical problems of any type (e.g. overloads, short circuits, high voltage, low voltage, etc) are quickly detected and reliably isolated while leaving the healthy portions of the system intact and maintaining the safety of other PSNH customers and PSNH employees. Additionally, the system must be designed in such a way that normal maintenance may be safely performed while maintaining the integrity and reliability of the balance of the interconnected network. In order to simultaneously meet all of these concerns, the impact of any proposed new source of generation must be carefully evaluated and the electrical configuration of such sources properly structured. While proposed sites of large installed capacity tend to have a greater impact than the smaller sites, even the smaller sites can have a profound impact on system performance and operating safety when not properly configured. It is the goal of the interconnection study/interconnection report process to ensure that all interface issues are properly identified and addressed such that the proper system performance is maintained. 4.0 Technical Requirements The following requirements are generally applicable to all NUGs except for those with inverter interfaces. The inverters approved for installation at "Net Metered" sites (see Section 5.B. of this document) either inherently meet the intent of these requirements or the nature of such systems makes these requirements inapplicable. At this time, the general requirements for other inverterbased NUG interfaces are handled on an individual basis. A. Safety Considerations 1. The connection of the facility to the PSNH system must not compromise the safety of PSNH s customers, personnel, or the owner s personnel. 2. The generating facility must not have the capability of energizing a de-energized PSNH circuit. To this end, the electrically controlled primary element(s) configured to enforce this requirement must have all mechanical close features removed and prominently placarded against reinstallation per PSNH. 3. Emergency shutdown and isolation provisions. a. Unless waived by PSNH, an emergency shutdown switch with facility status indicator lights must be made available for unrestricted use by PSNH personnel. 3

4 The shutdown switch shall be installed in a PSNH padlock-lockable enclosure at a location acceptable to PSNH operating personnel. The operation of the switch shall cause all of the facility s generation to be disconnected from the PSNH system, and shall block all manual and automatic reconnection of generation to the PSNH system until the switch is reset. The status lights, mounted with the shutdown switch, shall be located outdoors at a position acceptable to PSNH Operating Division personnel. Red and green lights are to be visible from the road. A red light shall indicate that the facility has generation connected to the PSNH system. A green light shall indicate that all generation is disconnected from the PSNH system. The red and green lights shall be driven by interrupting device auxiliary switches. b. Unless waived by PSNH, a PSNH padlock-lockable load break device with visible contacts must be made available for unrestricted use by PSNH personnel. The device shall be installed at a location acceptable to PSNH operating personnel. The device must be electrically located to interrupt all facility generation output and must be rated by the manufacturer to do so. 4. Protection systems included to address PSNH requirements must utilize utility grade components as approved by PSNH. This requirement includes protective relays as well as auxiliary tripping relays. 5. All PSNH-required voltage relaying applied to three-phase energy sources must be applied on a three-phase basis. 6. All devices utilized to supply PSNH-required protective functions must be equipped with provisions to aid in the post-mortem analysis of their operation. In the case of singlefunction protective elements, these provisions will include properly configured targets. In the case of multifunction numerical devices, these provisions will include properly configured event recording facilities as well as targets. 7. Dedicated relays must be reserved for PSNH required functions. These relays will provide no functions except for PSNH required functions. PSNH will determine, at the Developer s expense, the generic set points for the PSNH-required protective functions. In the case of numerical relays, depending on PSNH s familiarity with the relays being utilized, the Developer may be responsible for developing the balance of the settings (logic, etc.) in these relays, along with the actual electronic settings files themselves. 8. Any relay failure contacts on PSNH-required protective devices shall be wired to (1) trip the site generation and (2) initiate an alarm when the contacts indicate relay malfunction. 9. Under frequency protection on NUGs 1 MW and greater will be set with due regard for the NPCC under frequency load shedding program. NPCC Document Directory # 12 sets forth the requirements for automatic under frequency load shedding and automatic under frequency load shedding associated with generator under frequency tripping. NPCC Document B-07 presents relay application and testing requirements necessary to 4

5 accomplish the objectives of Directory # 12. Note that where a NUG is unable to accommodate the NPCC program settings due to turbine or other issues, additional compensating under frequency protection will be required to account for the lost generation. Any costs associated with obtaining the compensating load shedding will be the responsibility of the NUG. 10. A PSNH approved testing company will be required to verify the proper functioning of those protective systems required by PSNH. This work will be performed at the Developer s expense. 11. The generating facility has full responsibility for ensuring that the protective system and the associated devices are maintained in reliable operating condition. PSNH reserves the right to inspect and test all protective equipment at the generator site whenever it is considered necessary. This inspection may include tripping of the breakers. 12. The short circuit interrupting device(s) must have sufficient interrupting capacity for all faults that might exist. The PSNH system impedance at the facility will be supplied on request. 13. All protection systems utilized for synchronous generator protection must utilize a battery power source. AC-powered inverters are not an acceptable DC supply. The battery must be equipped with appropriate charging and monitoring facilities. The monitoring facilities must annunciate battery high voltage, battery low voltage, and battery grounds. Interrupting devices associated with PSNH-required protection and supplied power from the DC battery must be equipped with facilities configured to trip the associated generator interrupting device with an alternate supply immediately on loss of DC system trip capability. Direct AC trip and capacitor trip devices are acceptable for this backup function 14. Any protection scheme utilizing AC control power must be designed in a fail-safe mode. That is, all protective components must utilize contacts which are closed during normal operating conditions, but which open during abnormal conditions or when control power is lost to de-energize the generator contactor coil. These schemes may be utilized only with non-latching contactors and may not be used with synchronous generators. 15. A protection one line diagram and a complete set of AC and DC schematic (a.k.a. elementary) diagrams showing the implementation of all systems required by PSNH must be supplied for PSNH review. These drawings should be supplied as soon as possible so that any non-conforming items may be corrected by the Developer without impacting the scheduled completion date of the facility. 16. All voltage transformers driving PSNH-required protection systems must be formally rated by the manufacturer as to accuracy class, and must be capable of driving their connected burdens with an error not exceeding 1.2 percent. The NUG is responsible for supplying PSNH with VT manufacturer s documentation supporting VT performance and any 5

6 additional information (e.g. relay manufacturer s data) required by PSNH to verify scheme adequacy. 17. All current transformers driving PSNH-required protection systems must be rated by the manufacturer as to accuracy class and must be capable of driving their connected burdens with an error not exceeding 10 percent under worst-case fault conditions. The NUG is responsible for supplying PSNH with CT manufacturer s documentation supporting CT performance and any additional information (e.g. relay manufacturer s data, cable lengths, etc.) required by PSNH to verify scheme adequacy. 18. The secondary windings of instrument transformers feeding PSNH-required protection equipment will be grounded at one point, and one point only. 19. All PSNH-required protective relays and auxiliary tripping relays must be equipped with test facilities which allow secondary quantity injection and input contact and output contact isolation while the protective relays remain in their cases 20. All PSNH-required tripping and associated logic must be hard wired from protective relays to the interrupting device(s). Tripping and or/logic derived from programmable logic controllers (PLCs), computers, or other similar devices is not acceptable for PSNHrequired protection. 21. It is not the policy of PSNH to maintain a stock of protective relays for resale to facility Developers. Since many protective devices have delivery times of several months, Developers are strongly advised to order them as soon as possible after PSNH typeapproval is received. 22. Protection of the generating facility equipment for problems and/or disturbances which might occur internal or external to the facility is the responsibility of the Developer. Any fault located within the NUG should be detected and interrupted by NUG equipment at the NUG facility. The settings for such equipment whose failure to perform properly during such a fault could result in loss of service to PSNH customers will typically be developed by the NUG and reviewed by PSNH. PSNH s involvement with such equipment is limited to ensuring that coordination exists with upstream PSNH devices, and that the critical interrupting device is capable of interrupting the PSNH fault duty which exists at the point of application. 23. No operation of the facility s generation is allowed until all PSNH requirements have been met, all related systems, are in place, calibrated, and proven functional, and the Developer has received formal signoff from SESD. This requirement may be waived by PSNH for a given system if generation is required to demonstrate the proper functioning of that system. 6

7 B. Service Quality Considerations 1. The connection of the facility to the PSNH system must not reduce the quality of service currently existing on the PSNH system. Voltage fluctuations, flicker, and excessive voltage and current harmonic content are among the service quality considerations. Harmonic limitations should conform to the latest IEEE guidelines and/or ANSI standards. 2. In general, induction generators must be accelerated to synchronous speed prior to connection to the PSNH system to reduce the magnitude and duration of accelerating current and resulting voltage drop to PSNH customers to acceptable levels. 3. In general, synchronous generators may not use the pull-in method of synchronizing due to excessive voltage drops to PSNH customers. 4. Power factor correction capacitors may be required for some facilities either at the time of initial installation, or, at some later date. The installation will normally be done by the Developer at his expense. 5. Automatic reclosing of the PSNH circuit after a tripping operation may occur after an appropriate time delay. If additional voltage blocking of automatic reclosing is required, it will be added at the Developer s expense. C. Metering Considerations 1. Except for protection/control and metering voltage sensing and generator and/or capacitor contactor supply voltage, no unmetered station service AC shall be taken from the station service transformers. D. SCADA and Other Considerations 1. The Electric System Control Center (ESCC) requires the logging of all generator trips caused by relay action, as well as the time and the associated relay targets, for system operation analysis. 2. All NUGs must comply with the requirements of OP-0045 NH-LCC Minimum Interconnection Requirements of Merchant Generators. OP-0045 outlines the minimum metering, telemetering and voice communications requirements. 5.0 Special Considerations 7

8 The following sections describe several interface issues of significance arising from the technical characteristics of certain types and/or electrical sizes of NUG installations. Where the Developer has a choice of configurations, interface technologies, and/or sources, he/she may wish to choose a design approach which offers the least complexity, associated costs, and potential study delay. A. Closed-transition automatic transfer schemes Closed-transition automatic transfer schemes, sometimes referred to as no-break transfer schemes, are typically designed to automatically transfer a load between the PSNH grid and another source, usually a generator, without any interruption of power to the load. As a consequence, there will be a period of time where the two sources are connected together. The duration of time that the sources are tied together during the transfer has a major impact on PSNH requirements for the schemes. 1. Transfer schemes involving PSNH grid-generator paralleling times of 0.5 seconds or less usually require relatively modest supplementary circuitry to that supplied by the manufacturer of such equipment. Such an approach minimizes the associated additional costs, complexity, and PSNH engineering review efforts. 2. Transfer schemes involving PSNH grid-generator paralleling times of greater than 0.5 seconds will require full NUG interface protection. Such an approach will typically result in significant additional cost as well as substantial PSNH engineering review effort. B. NUG Sites Configured for Net Metering The State of New Hampshire has adopted Administrative Rule Puc 900 NET METERING FOR CUSTOMER-OWNED RENEWABLE ENERGY GENERATION RESOURCES. The rule defines the administrative process as well as the minimum technical requirements for the interface of NUGs utilizing renewable resources (wind, water, solar, etc.) having an installed capacity of 100 kilowatts or less. Such installations do not sell their output to the host utility, but are allowed to reduce their energy use with their generation. If they generate more energy than they use, the excess generation delivered to the host utility will be metered and can be used to offset their future energy use. The full text of this rule is available on-line at the State of New Hampshire Public Utilities Commission website ( and anyone contemplating the installation of such facilities should review the document in its entirety. While all details of the Rule will not be repeated here, it is particularly important to note that there are two primary interface types commonly utilized for such facilities, and the chosen method will have a major impact on the complexity of the interface, the extent of PSNH technical requirements, and the amount of time the entire application/approval process will typically take. 1. Net Metering inverter interfaces An inverter is a device which converts direct current (DC) energy into alternating current (AC) energy. Such devices are normally utilized where the NUG energy source consists of solar panels, certain wind mills, or any other DC source. Modern inverters are static 8

9 devices with few if any moving parts. The fundamental nature of inverters makes it very easy and desirable to integrate control and protection into one box. Further, recent efforts in the industry have resulted in certain design standards which, assuming the inverters conform to those standards, may require nothing in the way of additional interface protection in order to be acceptable in New Hampshire Net Metering installations. As would be expected, the review/approval process for Net Metering NUGs utilizing static inverters which are under 100 kilowatts and are certified to meet the standards as defined in Puc 900 will normally be much shorter than those sites utilizing conventional (non-inverter) interfaces (see next section). PSNH reserves the right to require supplemental protection and control equipment for facilities with inverters rated > 100 kilowatts or at sites utilizing multiple inverters that are each <100 kilowatts. 2. Net Metering conventional (non-inverter) interfaces Conventional generation interfaces are typically applied at those sites utilizing energy production equipment designed to generate 60 hertz alternating current (AC). In conventional interfaces, system protection functions of detection and isolation are separate and distinct from system control functions and must be separately engineered, separately purchased, separately wired, and separately tested. Consequently, non-inverter designs must be extensively reviewed for acceptability by PSNH. As would be expected, the review/approval process for Net Metering NUGs utilizing conventional interfaces will normally be substantially longer that those sites utilizing inverter interfaces. C. NUG sites with conventional (non-inverter) interfaces and installed capacity of less than 1 megawatt 1. Induction generation. a. The following protection functions are always required i. Time overvoltage (59) ii. Time undervoltage (27) iii. Time overfrequency (81O) iv. Time underfrequency (81U) v. Reverse power (32) if generator motoring is not revenue metered by PSNH. b. The following electrical configuration requirements exist for the site. i. The site may not be configured as a source of ground current to the PSNH grid. ii. Generator step-up transformer (GSU) configurations which are prone to ferro-resonance may not be used. 2. Synchronous generation a. The following protection functions are always required 9

10 i. Time overvoltage (59) ii. Time undervoltage (27) iii. Time overfrequency (81O) iv. Time underfrequency (81U) v. Reverse power (32) if generator motoring is not revenue metered by PSNH. vi. Voltage-controlled (not voltage-restrained) time overcurrent (51V) with appropriate phase angle correction to control voltage. vii. Ground overvoltage protection with instantaneous and time elements (59N). The associated voltage transformer primary windings must be rated to withstand phase-to-phase voltage. b. The following electrical configuration requirements exist for the site. i. The site may not be configured as a source of ground current to the PSNH grid. ii. GSU configurations which are prone to ferro-resonance may not be used. D. NUG sites with conventional (non-inverter) interfaces and installed capacity of 1 megawatt or more 1. Synchronous generation and induction generation. a. The following protection functions are always required and are in addition to those defined for sites with installed capacity of less than 1 megawatt. i. Ground time overcurrent (51N). This function will receive operating current from the neutral current transformer of the grounding element described in section 5.D.1.b., below. It will be configured to trip the high voltage side three phase interrupting device described in section 5.D.1.b., below. ii. Long-term system time overvoltage protection (59L). This device requires a very high dropout/pickup ratio and will be configured to trip all site generation. iii. Transfer trip from each remote three phase automatic sectionalizing device will be required if the NUG aggregate capacity (including existing NUGs) is more than 1/3 of the minimum local electric power system (EPS) load. In addition, sites with installed capacity of 5 megawatts or more will require transfer trip from each remote three phase automatic sectionalizing device. The transfer trip equipment shall cause all site generation to be tripped. b. The following electrical configuration requirements exist for the site. i. The site must be configured as a reactance-grounded limited source of ground current to PSNH. This configuration typically requires a neutral grounding reactor in addition to a grounded wye (PSNH side) - delta (NUG side) GSU. The necessary electrical parameters of the neutral grounding reactor will be supplied by PSNH. Depending on several factors, other reactance-grounded 10

11 ii. limited ground source configurations may be acceptable but must be reviewed and approved by PSNH. A three phase fully rated fault interrupting device must be included on the high voltage side of the site between the site and the PSNH grid. 6.0 Protection requirements at locations remote from the NUG. Some NUG installations may require additions and enhancements to the PSNH grid itself due to loading, interrupting duty, protection sensitivity, protection coordination, stability, or other issues. The necessity for any such modifications will be identified in the site Interconnection Report. These enhancements will be the financial responsibility of the NUG Developer and may include but not necessarily be limited to one or more of the following: New substations Line replacements or additions Recloser replacements or additions Circuit breaker replacements or additions Protective relay replacements or additions 7.0 Special Studies Some proposed NUG installations may require additional special studies (e.g. stability) in order to determine their potential impact on the PSNH grid. The need for and the estimated costs of any such studies will be detailed to the Developer along with the estimated cost of the Interconnection Study itself after receipt by SESD of the completed Interconnection Request form. 11

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5 Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System

More information

Document C0. Use for:

Document C0. Use for: Date: July 27, 2015 Document C0 Use for: Connection of Electric Generation that will operate with an Open Transition (Category 1) between the Ameren System and the Generator or operate with a Synchronized

More information

ELG4125: System Protection

ELG4125: System Protection ELG4125: System Protection System Protection Any power system is prone to 'faults', (also called short-circuits), which occur mostly as a result of insulation failure and sometimes due to external causes.

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS STATE OF MINNESOTA DISTRIBUTED GENERATION INTERCONNECTION TABLE OF CONTENTS Foreword 2 1. Introduction 3 2. References 6 3. Types of Interconnections 7 4. Interconnection Issues and Technical Requirements

More information

INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM. July 2011 UPDATED STANDARDS

INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM. July 2011 UPDATED STANDARDS INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM July 2011 UPDATED STANDARDS Rev 9.0 July 2011 2 TABLE OF CONTENTS 1.0 SCOPE AND GENERAL REQUIREMENTS...5

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL DISTRIBUTION SYSTEM Revised and Issued March 2003 I.

More information

Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards

Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards Attachment H: Small Generator (10 MW and below) Technical Requirements and Standards Scope Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards The PJM Small Generator Interconnection

More information

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017

More information

WN U-60 Original Sheet No. 152

WN U-60 Original Sheet No. 152 WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H

More information

Power System Network Simulator (PSNsim)

Power System Network Simulator (PSNsim) The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination GSU Phase Overcurrent (51T), GSU Ground Overcurrent (51TG), and Breaker Failure (50BF) Protection System Protection and Control Subcommittee

More information

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES 1. Introduction Real time monitoring and control is necessary to ensure public and employee safety and to protect the integrity

More information

THE INTERCONNECTION HANDBOOK

THE INTERCONNECTION HANDBOOK THE INTERCONNECTION HANDBOOK Southern California Edison Company Rev. 8 This document is controlled by the originating SCE T&D organization. When downloaded and printed, this document becomes UNCONTROLLED,

More information

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011 Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 INTERCONNECTION APPLICATION FOR ALL BUT UL1741 CERTIFIED INVERTER BASED SYSTEMS LESS THAN 10 KW In addition to the information provided below, a complete

More information

MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS

MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS Table of Contents I. Introduction... 5 A. Authority... 5 B. Objectives... 5 C. Interconnection

More information

PGR-4700 MANUAL SENSITIVE GROUND-FAULT RELAY

PGR-4700 MANUAL SENSITIVE GROUND-FAULT RELAY Tel: +1-800-832-3873 E-mail: techline@littelfuse.com www.littelfuse.com/pgr-4700 PGR-4700 MANUAL SENSITIVE GROUND-FAULT RELAY REVISION 2-B-032218 Copyright 2018 by Littelfuse, Inc. All rights reserved.

More information

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V Version: 1 Issued: March 2014 Owner: Electrical Networks Asset

More information

PUBLICLY AVAILABLE SPECIFICATION

PUBLICLY AVAILABLE SPECIFICATION IEC/IEEE/PAS 63547 PUBLICLY AVAILABLE SPECIFICATION Edition 1.0 2011-09 Interconnecting distributed resources with electric power systems INTERNATIONAL ELECTROTECHNICAL COMMISSION PRICE CODE V ICS 29.240.99

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

1. Project Description

1. Project Description Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

PRC System Protection Coordination Supplementary Reference

PRC System Protection Coordination Supplementary Reference PRC-001-2 System Protection Coordination Supplementary Reference Contents: Disclaimer... 2 Generator Protection Devices or Elements that May Require Coordination with Transmission or Distribution Protective

More information

Interconnection Application

Interconnection Application Interconnection Application Member interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &

More information

Technical Guideline For Interconnection Of Generators To The Distribution System

Technical Guideline For Interconnection Of Generators To The Distribution System Technical Guideline For Interconnection Of Generators To The Distribution System May 22, 2002 EDTI acknowledges the use of other utility industry and industry committee developed documents as the framework

More information

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011 Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 2. Initial Technical Review a. The following flowchart provides, for illustrative purposes, the major steps in the Initial Technical Review process:

More information

Bulletin Installation of solar photovoltaic systems Rules , , , , and

Bulletin Installation of solar photovoltaic systems Rules , , , , and Bulletin 64-5-0 Installation of solar photovoltaic systems Rules 64-060, 64-200, 64-214, 84-020, 84-024 and 84-030 Scope (1) Introduction (2) Disconnecting means (a) Disconnecting means for solar photovoltaic

More information

Glencoe Light and Power

Glencoe Light and Power Glencoe Light and Power REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS 1 Table of Contents Page I. INTRODUCTION...5 A. Authority... 5 B. Objectives...5 C. Interconnection

More information

PGR-6101 MANUAL GROUND-FAULT & INSULATION MONITOR

PGR-6101 MANUAL GROUND-FAULT & INSULATION MONITOR Tel: +1-800-832-3873 E-mail: techline@littelfuse.com www.littelfuse.com PGR-6101 MANUAL GROUND-FAULT & INSULATION MONITOR Revision 0-C-041918 Copyright 2018 by Littelfuse, Inc. All rights reserved. Document

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

White Paper Surge Protective Devices in Automatic Transfer Switches

White Paper Surge Protective Devices in Automatic Transfer Switches White Paper Surge Protective Devices in Automatic Transfer Switches Standby power systems provide emergency power, legally required power, or optional standby AC power during utility outages. Standby AC

More information

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION Exercise 2 Single Bus Scheme EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with electric power substations using the single bus scheme with bus section circuit breakers.

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

Oncor Application for Interconnection of Distributed Generation

Oncor Application for Interconnection of Distributed Generation Oncor Application for Interconnection of Distributed Generation Operating Mode: Parallel Operation Longer than 100 milliseconds (07/11/2018) This application is for generator systems that synchronously

More information

Energy Storage Systems Utilizing the SunDial Plus 30PV+S Inverter

Energy Storage Systems Utilizing the SunDial Plus 30PV+S Inverter APPLICATION NOTE 601 Energy Storage Systems Utilizing the SunDial Plus 30PV+S Inverter CONTENTS 1.0 Purpose and Scope.... 1 2.0 Disclaimer.... 1 3.0 Overall Energy Storage System... 1 4.0 Electrical Interfaces...

More information

Medium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks

Medium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks General NEPSI's activar, Medium

More information

SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016

SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016 SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016 BY H S W Karunaratne Assistant Director - Engineering Sri Lanka Standards Institution. 1 DEFINITIONS Ac module:

More information

Using the Bitronics 70 Series to Improve Local Monitoring and Control

Using the Bitronics 70 Series to Improve Local Monitoring and Control Automate a Substation and Preserve the Electromechanical Relay Investment Part Two of Four Using the Bitronics 70 Series to Improve Local Monitoring and Control Paul Grabowski - Bitronics Senior Application

More information

Certification Exams. Detailed Content Outlines Level 2 Certified Assistant Technician Level 3 Certified Technician Level 4 Certified Senior Technician

Certification Exams. Detailed Content Outlines Level 2 Certified Assistant Technician Level 3 Certified Technician Level 4 Certified Senior Technician Detailed Content Outlines Level 2 Certified Assistant Technician Level 3 Certified Technician Level 4 Certified Senior Technician Certification Exams How to Use the Detailed Content Outlines These Detailed

More information

CenterPoint Energy P O Box 1700 Houston, TX

CenterPoint Energy P O Box 1700 Houston, TX CenterPoint Energy P O Box 1700 Houston, TX 77251-1700 IF YOU ARE APPLYING FOR DISTRIBUTED GENERATION, PLEASE FOLLOW THE INSTRUCTIONS IN THE PARAGRAPHS BELOW. YOU WILL NEED TO COMPLETE AND SIGN AND THEN

More information

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

PLT. Breaker-based transfer switch open, closed or soft transition amps. Specification sheet

PLT. Breaker-based transfer switch open, closed or soft transition amps. Specification sheet Specification sheet PLT Breaker-based transfer switch open, closed or soft transition 800 3000 amps Description PLT breaker-based transfer switches are designed for operation and switching of electrical

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

Commission Testing Methods for Protection Systems

Commission Testing Methods for Protection Systems Commission Testing Methods for Protection Systems Tom Ernst GE Grid Solutions Ken Sletten Minnesota Power Abstract Commission testing should be designed to assure that the protection system is set and

More information

C C CIRCUIT-BREAKERS Moulded-case (MCCB), general. 1. Introduction. 2. General description

C C CIRCUIT-BREAKERS Moulded-case (MCCB), general. 1. Introduction. 2. General description CIRCUIT-BREAKERS C C81-21 CIRCUIT-BREAKERS - Contents 1. Introduction 2. General description 3. Rated voltages 3.1 Rated operational voltage (U e ) 3.2 Rated impulse withstand voltage (U imp ) 3.3 Rated

More information

Medium Voltage Metal-Enclosed Harmonic Filter Systems

Medium Voltage Metal-Enclosed Harmonic Filter Systems 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Harmonic Filter Systems General NEPSI s armorvar, medium voltage metal-enclosed

More information

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4. Branch Procedure Document No. Issue No. : : CEOP8012 5 Approved By : Specialist Engineering NETWORK : Manager Approval Date Review Date : : 29/06/2018 29/06/2021 (Supersedes CEOP8012, Generation Connection:

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

INSTRUCTION MANUAL FOR VAR/POWER FACTOR CONTROLLER SCP

INSTRUCTION MANUAL FOR VAR/POWER FACTOR CONTROLLER SCP INSTRUCTION MANUAL FOR VAR/POWER FACTOR CONTROLLER SCP 250 Publication: 9 1100 00 99Y Revision: S 04/04 INTRODUCTION This instruction manual provides information about the operation and installation of

More information

JEA. Facility Connection Requirements

JEA. Facility Connection Requirements JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities

More information

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM April 13, 2007 LIPA Facility Connection Requirements TABLE OF CONTENT I. INTRODUCTION...1 II. REFERENCE

More information

SECTION DISCONNECT SWITCHES

SECTION DISCONNECT SWITCHES SECTION 16440 DISCONNECT SWITCHES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage

More information

Source-Transfer Application Guide

Source-Transfer Application Guide S&C Model 6802 Automatic Switch Control Source-Transfer Application Guide Table of Contents Section Page Section Page Introduction Qualified Persons.... 2 Read this Instruction Sheet.... 2 Retain this

More information

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Power Quality of Commercial Buildings - Advanced

Power Quality of Commercial Buildings - Advanced Buildings - Advanced Hartford Steam Boiler One State Street P.O. Box 5024 Hartford, CT 06102-5024 Tel: (800) 472-1866 www.munichre.com/hsb May 2017 Background Power quality is a general term used to describe

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

SECTION SOLID-STATE REDUCED VOLTAGE STARTERS

SECTION SOLID-STATE REDUCED VOLTAGE STARTERS SECTION 26 29 13.16 PART 1 - GENERAL 1.1 THE REQUIREMENT A. General: The CONTRACTOR shall provide solid-state reduced voltage motor starters, complete and operable, in accordance with the Contract Documents.

More information

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...

More information

(1986; Rev. 1989) Molded Case Circuit Breakers and Molded Case Switches. (1985; Rev. 1988) Enclosures for Electrical Equipment (1000 Volts Maximum)

(1986; Rev. 1989) Molded Case Circuit Breakers and Molded Case Switches. (1985; Rev. 1988) Enclosures for Electrical Equipment (1000 Volts Maximum) Section 16306 50/60-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER Index PART 1 GENERAL PART 2 PRODUCTS 1.1 References 2.1 Frequency Converters 1.2 Factory Tests 2.2 Conduit and Fittings 1.3 Submittals 2.3

More information

Medium Voltage Metal-Enclosed Power Capacitor Banks

Medium Voltage Metal-Enclosed Power Capacitor Banks 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Power Capacitor Banks General Northeast Power System s (NEPSI's) medium

More information

Application Notes on Generator Protection Schemes

Application Notes on Generator Protection Schemes Application Notes on Generator Protection Schemes Single Line Diagram Examples 1. Introduction The application notes provide selected single line diagrams for the SIPROTEC 4 generator protection device

More information

Description of Optional MEMORY AND TIME DELAY P-C BOARD. Part Number

Description of Optional MEMORY AND TIME DELAY P-C BOARD. Part Number TO-210 121090 Revised Description of Optional MEMORY AND TIME DELAY P-C BOARD Part Number 282308 HOBART BROTHERS COMPANY Airport Systems Group Troy, Ohio 45373 U.S.A. This page intentionally left blank.

More information

Application Techniques CENTERLINE 2100 Motor Control Centers

Application Techniques CENTERLINE 2100 Motor Control Centers POWER SYSTEM CONSIDERATIONS FOR PRODUCT SELECTION Application Techniques CENTERLINE 2100 Motor Control Centers Power System Considerations for Product Selection i Power System Considerations for Product

More information

SECTION ELECTRIC METERING

SECTION ELECTRIC METERING SECTION 26 27 13 ELECTRIC METERING SPEC WRITER NOTES: Use this section only for NCA projects Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable

More information

Advanced Line Differential Protection, Automation, and Control System. Combine subcycle line protection with traveling-wave fault locating

Advanced Line Differential Protection, Automation, and Control System. Combine subcycle line protection with traveling-wave fault locating Advanced Line Differential Protection, Automation, and Control System Combine subcycle line protection with traveling-wave fault locating Subcycle differential and distance protection minimizes damage

More information

Flexible High-Speed Load Shedding Using a Crosspoint Switch

Flexible High-Speed Load Shedding Using a Crosspoint Switch Flexible High-Speed Load Shedding Using a Crosspoint Switch Will Allen and Tony Lee Schweitzer Engineering Laboratories, Inc. Published in Wide-Area Protection and Control Systems: A Collection of Technical

More information

SECTION VARIABLE FREQUENCY DRIVES

SECTION VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 DESCRIPTION This specification section establishes the requirements for variable frequency motor drives. The associated motor(s) shall be specified separate from the drive and listed

More information

Power Systems Communications Implementation of IEC61850 in a Substation Environment

Power Systems Communications Implementation of IEC61850 in a Substation Environment Power Systems Communications Implementation of IEC61850 in a Substation Environment 26 October 2009 Reference VEE4700-01 Revision 0 Document Control Document ID: DOCUMENT1 Rev No Date Revision Details

More information

TRANSMISSION FACILITIES INTERCONNECTION REQUIREMENTS

TRANSMISSION FACILITIES INTERCONNECTION REQUIREMENTS TRANSMISSION FACILITIES INTERCONNECTION REQUIREMENTS Corresponds to NERC Standard FAC-001-1 Developed By CPP Engineering Department May 1, 2015 Prepared by: Raymond O Neill, P.E. Version 3 INDEX CPP Transmission

More information

An Urgent Bulletin from CSA Group

An Urgent Bulletin from CSA Group An Urgent Bulletin from CSA Group Photovoltaic Equipment No. 5 Date: September 21, 2015 See Attachment 1 for Effective Dates. See Attachment 1 for Application Due Dates Announcing: Publication of List

More information

Smart Power Flow Monitoring and Control

Smart Power Flow Monitoring and Control IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 10 April 2016 ISSN (online): 2349-784X John Richardson. J Mathivathani. N Karthikeyan. K Preethi. PA Vivekanandhan. C Vice

More information

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical Issued for Review Section 26 28 16.01 Air Circuit Breakers Page 1 of 7 PART 1 GENERAL 1.1 GENERAL.1 This specification serves to define requirements for a replacement of low voltage circuit breaker of

More information

STANDARD SUBMITTAL PACKAGE

STANDARD SUBMITTAL PACKAGE STANDARD SUBMITTAL PACKAGE SBP1000-51( ) FTA1000 Full Voltage Starting Electric Fire Pump Controllers Product Description Description Firetrol FTA1000 Full Voltage Fire Pump Controllers are intended for

More information

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series Substation Automation Products Generator protection REG670/650 Relion 670 and 650 series A new protection standard for your valuable assets Based on ABB s extensive experience, REG670 and REG650 IEDs (Intelligent

More information

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015 Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee

More information

U.S. Virgin Islands Water and Power Authority

U.S. Virgin Islands Water and Power Authority U.S. Virgin Islands Water and Power Authority REQUIREMENTS AND PROCEDURES FOR INTERCONNECTION OF SOLAR PHOTOVOLTAIC GENERATION TO THE ELECTRICAL DISTRIBUTION SYSTEM Request for Proposals from Independent

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form) Attachment 2 Transmission Provider: SMALL GENERATOR INTERCONNECTION REQUEST Designated Contact Person: Address: Telephone Number: (Application Form) An Interconnection Request is considered complete when

More information

GREAT RIVER ENERGY. May 2014 GREAT RIVER ENERGY

GREAT RIVER ENERGY. May 2014 GREAT RIVER ENERGY GREAT RIVER ENERGY GUIDELINES FOR TIE-LINE AND SUBSTATION INTERCONNECTIONS May 2014 GREAT RIVER ENERGY NOTE: Revision numbers were not formally tracked before June 2013 revisions; according to available

More information

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS

More information

APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS. for GENERATION & INTERCONNECTION FACILITIES

APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS. for GENERATION & INTERCONNECTION FACILITIES APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS for GENERATION & INTERCONNECTION FACILITIES Revision: 4.0 12/28/2011 Page 1 of 40 DEFINITIONS TABLE OF CONTENTS A. Scope 1. Generation Connection and Operating

More information

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Metering Devices, Protective Relays, Software and Connectivity. Pre-Wired Control Power, Voltage and CT Inputs

Metering Devices, Protective Relays, Software and Connectivity. Pre-Wired Control Power, Voltage and CT Inputs .3 Features and Benefits Saves installation time and cost One part number to order; no need to worry that any part has been left out Pick the meter or meters you need as it is designed to fit various Eaton

More information

Electrical Demand Specification (Reference SOP: )

Electrical Demand Specification (Reference SOP: ) Project: Equipment Description: Location: Equipment No.: Project No: Protocol No.: Content Index 1. GENERAL...3 Design Standards...3 1.1. Standards...3 2. DESIGN...3 2.1. Safety...3 2.2. Circuit protection...3

More information

As a minimum, the scope of work shall include: 1.12 GPA will install the new drive control equipment per contractor supplied elementary drawings.

As a minimum, the scope of work shall include: 1.12 GPA will install the new drive control equipment per contractor supplied elementary drawings. Requisition # 10093128- Page 6 of 15 1.0 GENERAL REQUIREMENTS: 1.1 Scope Of Work: 1.11 Work includes, but is not limited to, providing all materials and technical direction required to replace the existing

More information

NPW800R RETROFITTING. Power and Volatge Protection Relay

NPW800R RETROFITTING. Power and Volatge Protection Relay RETROFITTING Power and Volatge Protection Relay NPW800R (R3 case) is dedicated to the refurbishment of CEE WTG 7000 relays (R3 case) providing the measurement of apparent (S), active (P) and reactive (Q)

More information

SR489 SR489. Generator Management Relay. Economical protection, metering, and monitoring functions for small and medium sized generators.

SR489 SR489. Generator Management Relay. Economical protection, metering, and monitoring functions for small and medium sized generators. SR489 Generator Management Relay Economical protection, metering, and monitoring functions for small and medium sized generators. 1 Product Highlights Inputs / Outputs Generator Protection Power Metering

More information

Title Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP)

Title Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title Reference Number POP 07 - (RIC Standard: EP 99 00 00 04 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

PGR-6100 MANUAL GROUND-FAULT & INSULATION MONITOR

PGR-6100 MANUAL GROUND-FAULT & INSULATION MONITOR Tel: +1-800-832-3873 E-mail: techline@littelfuse.com www.littelfuse.com/pgr-6100 PGR-6100 MANUAL GROUND-FAULT & INSULATION MONITOR Revision 2-C-050818 Copyright 2018 Littelfuse All rights reserved. Document

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Electrical Company: PacifiCorp For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Designated Contact Person: Robin Moore Address

More information