1 Prepared by: D. R. Duckworth, Corporate Services and Community Safety Director Improvements_BUS_1.docx

2 Executive Summary This business case seeks approval for additional funding of $1,000,000 for capital and maintenance upgrades to the RCMP Main Detachment at 560 Battle Street and the North Shore Community Policing Office (NSCPO) at 917 7th Street. Staff recommend using the 2016 RCMP budget surplus to fund this business case request. The Main Detachment houses 80% of the RCMP members and the majority of City RCMP support staff. Since 2006, there have been no significant renovations at this location; however, the number of members and staff has grown by 15%. Corporate Services and Community Safety (CSCS), RCMP Departmental Security Section (DSS), and RCMP Senior Management have identified a number of safety/statutory deficiencies, as well as several critical building maintenance work issues. It is recommended that these deficiencies and issues be addressed at the same time. The NSCPO houses 20% of the local RCMP members, however, 44% of all RCMP calls come from the North Shore area. Therefore, it makes sense to increase the number of RCMP resources at the NSCPO. Upon review, staff recommend moving the Police Dog Section (PDS) from the Main Detachment to the NSCPO, as 50% of all RCMP calls for service related to the PDS are located on the North Shore. Accordingly, staff are requesting funding to renovate NSCPO garage bay areas to accommodate the PDS. It is recommended that these improvements be completed over the 2017 and 2018 fiscal years. Class D cost estimates have been prepared for capital expenditures and maintenance upgrades and CSCS will work with the Capital Projects Division to complete the work. Situational Overview (Terms of Reference) Main Detachment The Main Detachment was constructed in 1989 and currently houses 106 RCMP members and 55 municipal support staff. Since 2006, there have been no significant renovations at this location, but the number of RCMP members and support staff has grown by more than 15%. In addition to the growth of the Main Detachment, the DSS completed a physical security review of the Main Detachment in October The objective of this review was to assess the overall physical security of the Main Detachment, identify security deficiencies, and provide remedies to ensure the Main Detachment meets statutory security requirements. The City is required to implement the recommendations generated from this review to improve any identified security deficiencies. The DSS security review identified a number of Main Detachment safety/statutory deficiencies, as outlined in the following table. Additionally, staff have identified several critical building maintenance items that are recommended to proceed at the same time as the safety/statutory deficiency upgrades. Improvements_BUS_1.docx 1

3 Project Description Project Category Cost Estimate Regulatory Requirements Statutory and Safety $305,000 Inventory Office Metal door thresholds File room wall construction IT room wall construction CCVE cameras install in additional rooms Replacement of locksets Gas line regulator Parking lot signage Safe box installation Security grills Electric strike Door locksets Window removal Furniture mounting Replace viewports Replace prisoner/visitor windows Cellblock toilet replacements Change to vehicle bay for storage Handicap access for parking lot Ventilation for exhibit lockers Forensic lab shower and eyewash station Emergency shut off for laser equipment Stainless steel counter for forensic lab Sink/processing area upgrade Building maintenance Generator HVAC leaking tiles Front entrance vestibule Window film replacement Window sealing Refinish cracked concrete walls Civilian fingerprint renovation Relocation of waste bins and installation of gated enclosure Front counter area renovation Garage door replacement Building paint Toilet replacement Flooring/baseboards Cellblock paint Cellblock fingerprint room renovation Parking lot lines Shower upgrades Cellblock kitchen renovation Cellblock washing machine and dryer Maintenance of Existing Infrastructure $270,000 Improvements_BUS_1.docx 2

4 North Shore Community Policing Office (NSCPO) In 2013, Council approved the purchase and renovation of the old KIA dealership located at 915 7th Street for the new NSCPO. When compared to the construction of a new police station, renovating this building for the NSCPO was more cost-effective, it is situated in an ideal location, and the site allows for future growth. There are currently 24 members and 3 municipal staff at this location. RCMP calls for service on the North Shore account for 44% of all RCMP calls, yet only 18% of police resources are located on the North Shore at the NSCPO. To provide further presence on the North Shore, and to alleviate some of the congestion at the Main Detachment, the RCMP has asked the City to consider moving the PDS to the NSCPO. This move would meet Council s strategic goal of enhancing the sense of safety/security in all areas of the City, especially in the downtown core and the North Shore. Approximately 50% of all RCMP calls for service related to the PDS unit are located on the North Shore; therefore, this move would increase the unit s current level of service and response time. Additional benefits of moving the PDS unit include the following: a bay to keep dogs out of the elements a dog wash facility better office space for members the current PDS office could be used to house RCMP inventory The cost associated with moving the PDS unit to the NSCPO is shown in the following table. In addition to moving the PDS unit to the NSCPO, the RCMP is also requesting the following other minor improvements to the NSCPO: Description Project Category Cost Estimate Renovate garage bay to include: Forensic Unit identification bay Mechanic bay Storage area Locker room Office space Bathroom Improvements $400,000 Rear compound storage Improvements $25,000 City staff and the RCMP have been working with the Capital Projects Division on the scope and costs for these proposed capital expenditures. At this time, the Capital Projects Division has only completed a Class D (+/- 40%) cost estimate for the capital improvements, DSS requirements, and maintenance items. The Capital Projects Division will work with the RCMP to manage the projects, complete detailed design, and control the scope of work. If the capital improvements are lower than the projected $1,000,000 estimate, the actual amount of funds transferred from the RCMP Reserve Fund will be adjusted accordingly. If the cost to complete the improvements at both locations is higher than anticipated, staff will reprioritize some of the projects and eliminate some of the work. Improvements_BUS_1.docx 3

5 Options (Alternatives) Considered Do not proceed with any of the work identified. Risk Analysis Public Works and Utilities Department staff will provide project management and construction supervision services. Conclusion/Recommendation That Council authorize staff to add a new project to the Capital Plan to facilitate capital and maintenance upgrades to the RCMP Main Detachment and North Shore Community Policing Office at a cost of $1,000,000, funded from the 2016 RCMP contract surplus. Main Detachment Cost Summary Regulatory Requirements $305,000 Building Maintenance $270,000 North Shore Community Policing Office Cost Summary Renovate Garage Bay $400,000 Rear Compound Storage $25,000 Total Costs $1,000,000 Improvements_BUS_1.docx 4

Mountain Lakes Infrastructure Projects and Investments. January 2017

Mountain Lakes Infrastructure Projects and Investments. January 2017 Mountain Lakes Infrastructure Projects and Investments January 2017 Presentation & Discussion of: Birchwood & Island Beach Renovations Sunset Lake Dam Restoration/Rehabilitation Project Borough Hall Administrative

More information

BUILDINGS AND FACILITIES

BUILDINGS AND FACILITIES EB-00-0 Exhibit C Tab Schedule Page of BUILDINGS AND FACILITIES FACILITIES AND ASSET MANAGEMENT OVERALL STRATEGY THESL s buildings and facilities (the facilities ) include operating centers (00 Commissioners,

More information

Guelph Police Service

Guelph Police Service Guelph Police Service The Guelph Police Service provides policing services to the City of Guelph and has an authorized complement of 196.5 police officers and 89.42 civilians. We serve our community by

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

Redmond Facilities Strategic Management Plan Overview

Redmond Facilities Strategic Management Plan Overview Redmond Facilities Strategic Management Plan Overview Project Purpose + Provide guidance on how to best operate, maintain, and upgrade facilities now and in the future + Optimize maintenance staffing and

More information

CNM Master Plan. Total Project Budget Section A - Proposed Facilities and IT Maintenance Projects for FY18

CNM Master Plan. Total Project Budget Section A - Proposed Facilities and IT Maintenance Projects for FY18 CNM Master Plan Line # Master Plan Project Title Description Total Project Budget Section A - Proposed Facilities and IT Maintenance Projects for FY18 Projected spending for FY18 Potential Funding Source

More information

PUBLIC WORKS ORGANIZATIONAL CHART

PUBLIC WORKS ORGANIZATIONAL CHART PUBLIC WORKS ORGANIZATIONAL CHART C-108 Actual 2012-13 Adopted Year-End Estimated 2014-15 2015-16 PROGRAM EXPENSES/REVENUES Salaries & Benefits $ 1,725,030 $ 1,855,980 $ 1,676,130 $ 1,956,510 $ 1,979,470

More information

EVANSTON PUBLIC LIBRARY BOARD OF TRUSTEES FACILITIES COMMITTEE

EVANSTON PUBLIC LIBRARY BOARD OF TRUSTEES FACILITIES COMMITTEE EVANSTON PUBLIC LIBRARY BOARD OF TRUSTEES FACILITIES COMMITTEE Wednesday, July 19, 2017 5:30 P.M. Evanston Public Library, Community Meeting Room, 1703 Orrington Ave. 1. CALL TO ORDER 2. NEW BUSINESS AGENDA

More information

Critical Maintenance for Community Colleges bonded Health and Safety bonded Facilities Preservation bonded

Critical Maintenance for Community Colleges bonded Health and Safety bonded Facilities Preservation bonded Section Contents Five-Year Capital Plan FY 2017-18 through FY 2021-22 Project Funding Type Five-Year Plan Total ($ 000s) Critical Maintenance for Community Colleges bonded $235,000 Health and Safety bonded

More information

Five-Year Capital Plan Request FY through FY

Five-Year Capital Plan Request FY through FY Section Contents Five-Year Capital Plan Request FY 2015-16 through FY 2019-20 Project Funding Type Total ($ 000s) Critical Maintenance Seniors bonded $690,706 Health and Safety bonded Facilities Preservation

More information

Report to the Board. Steve Dickinson, Assistant Superintendent Administrative Services

Report to the Board. Steve Dickinson, Assistant Superintendent Administrative Services Report to the Board TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent Steve Dickinson, Assistant Superintendent Administrative Services 2016-2017 Routine Restricted Maintenance

More information

Appendix 2. Capital Funding Source Summary Table of Contents

Appendix 2. Capital Funding Source Summary Table of Contents Capital Source Summary Table of Contents 2016 Corporate Services APP 2-3 Mayor and Council APP 2-5 Office of the Chief Administrative Officer APP 2-5 Office of the Chief Operating Officer APP 2-5 Planning

More information

Facilities Department Town of Duxbury, MA

Facilities Department Town of Duxbury, MA Facilities Department Town of Duxbury, MA FY18 Capital Project Request Presentation To The Board of Selectmen, Finance, & Fiscal Advisory Committee s Duxbury Senior Center November 14, 2016 Prepared and

More information

Western Illinois University Quad Cities FACILITIES. FY17 Planning and Accomplishments. Submitted by: William Brewer Director of Facilities Quad Cities

Western Illinois University Quad Cities FACILITIES. FY17 Planning and Accomplishments. Submitted by: William Brewer Director of Facilities Quad Cities Western Illinois University Quad Cities FACILITIES FY17 Planning and Accomplishments Submitted by: William Brewer Director of Facilities Quad Cities I. Accomplishments and Productivity for FY17 WIU-QC

More information

Director of Public Works/City Engineer. Secretary. Word Processor. Streets and Facilities Supervisor. Traffic Signal Technician.

Director of Public Works/City Engineer. Secretary. Word Processor. Streets and Facilities Supervisor. Traffic Signal Technician. PUBLIC WORKS ORGANIZATIONAL CHART Director of Public Works/City Engineer Secretary Word Processor Transit Services Manager Fleet Services Supervisor Streets and Facilities Supervisor Principal Principal

More information

FY Janette Pell Department Director. Information and Communications Technology. Administration and Finance

FY Janette Pell Department Director. Information and Communications Technology. Administration and Finance FY 2018 19 Janette Pell Department Director Administration and Finance Capital Projects Facilities and Real Estate Management Fleet Operations Information and Communications Technology Purchasing, Surplus

More information

CITY OF WINSTON-SALEM, NORTH CAROLINA Public Safety Needs Assessment Study Phase One EXECUTIVE SUMMARY

CITY OF WINSTON-SALEM, NORTH CAROLINA Public Safety Needs Assessment Study Phase One EXECUTIVE SUMMARY EXECUTIVE SUMMARY I. Documentation and Current Conditions Establishment Process II. Existing Public Safety Facilities Analysis III. Space Allocation, Co-Location and Potential Site Location Analysis IV.

More information

2019 Capital Improvement Plan 2018 Adopted vs 2019 Request Executive CIP 2017 Adopted CIP

2019 Capital Improvement Plan 2018 Adopted vs 2019 Request Executive CIP 2017 Adopted CIP Police Department Capital Improvement Plan Project Summary Agency Priority # Light Bar Replacement Project 1 45,000 47,225 - - - - # North Police Station 4-100,000 - - - - # Police Building Improvements

More information

C H Group Building Surveyors, BCA 9c and Age Care Certification Consultants

C H Group Building Surveyors, BCA 9c and Age Care Certification Consultants Agenda for Today s Presentation Introduction BCA Classifications BCA 9c Provisions Conversion of Class 3 to 9c Summary Introduction Prior to 1997 RCI Nursing Home funding PCAI Hostel funding Post 1997

More information

Facilities Strategic Planning. Community Centers Stakeholder Group October 16, 2017 Jeanne Justice

Facilities Strategic Planning. Community Centers Stakeholder Group October 16, 2017 Jeanne Justice Facilities Strategic Planning Community Centers Stakeholder Group October 16, 2017 Jeanne Justice Agenda Review facilities prioritization criteria Co-location examples Co-location exercise Coming Up: 10/17

More information

S T A F F R E P O R T

S T A F F R E P O R T S T A F F R E P O R T Meeting Date: 04 Jul 2017 To: Prepared By: Reviewed/Approved By: Department Report No: Subject: Corporate Strategic Plan: Mayor and Members of Council Lynn Phillips Tim Blake, Valerie

More information

Corporate Security & Emergency Management Summary of Submitted 2015 Budget From Rates

Corporate Security & Emergency Management Summary of Submitted 2015 Budget From Rates Corporate Security & Emergency Management Summary of Submitted 2015 From Rates Service Expense 2014 2015 Revised Non Tax Revenue Net Tax Supported Expense Draft Non Tax Revenue Net Tax Supported Increase

More information

Business Opportunities with VISN 23 Capital Assets Management. Cynthia A. Doolittle, PE Capital Assets Manager Eagan, MN (VISN 23)

Business Opportunities with VISN 23 Capital Assets Management. Cynthia A. Doolittle, PE Capital Assets Manager Eagan, MN (VISN 23) Business Opportunities with VISN 23 Capital Assets Management Cynthia A. Doolittle, PE Capital Assets Manager Eagan, MN (VISN 23) Overview VISN 23 Capital Assets Manager Veterans Health Administration,

More information

OUTSOURCED FACILITIES MANAGEMENT SERVICES CAPE TOWN

OUTSOURCED FACILITIES MANAGEMENT SERVICES CAPE TOWN OUTSOURCED FACILITIES MANAGEMENT SERVICES CAPE TOWN LOCATION OF SERVICE REQUIRED 141 Voortrekker road Parow Cape Town Areas: Offices Entrance foyers Balcony Toilets Basements Conference rooms Store rooms

More information

MEMORANDUM. Board Members Alaska Industrial Development and Export Authority

MEMORANDUM. Board Members Alaska Industrial Development and Export Authority MEMORANDUM To: From: Board Members Alaska Industrial Development and Export Authority John Springsteen CEO/Executive Director Date: January 9, 2019 Subject: Information Technology Capital Request Resolution

More information

M E M O R A N D U M. To: California State Lottery Commission Date: October 16, Item 9(c): Approval to Hire Project Management Consultant

M E M O R A N D U M. To: California State Lottery Commission Date: October 16, Item 9(c): Approval to Hire Project Management Consultant M E M O R A N D U M To: California State Lottery Commission Date: From: Joan M. Borucki Director Prepared By: Linh Nguyen Chief Deputy Director Subject: Item 9(c): Approval to Hire Project Management Consultant

More information

CITY COUNCIL AGENDA REPORT

CITY COUNCIL AGENDA REPORT K.5 CITY COUNCIL AGENDA REPORT TYPE OF ITEM: Info/Consent AGENDA ITEM NO.: 5 DATE: December 6, 2016 TO: City Council THROUGH: Greg Nyhoff City Manager FROM: SUBJECT: Darwin Base Fire Chief Additional Appropriation

More information

ATTACHMENT 3 ZAB Page 1 of 8. The police department feels that the expanded use and hours are okay with the recommended security upgrades.

ATTACHMENT 3 ZAB Page 1 of 8. The police department feels that the expanded use and hours are okay with the recommended security upgrades. Page 1 of 8 From: White, Byron E. Sent: Wednesday, April 24, 2013 8:28 AM To: Greene, Elizabeth Subject: Re: 1799 University comments The police department feels that the expanded use and hours are okay

More information

RCMP Support / Bylaw Services Department

RCMP Support / Bylaw Services Department RCMP Support / Bylaw Services Department business plan 2012-2014 TABLE OF CONTENTS 1. Our Services 1.1 Our Mandate 1.2 Lines of Business 2. Accomplishments 3. Implementing Sustainability 3.1 Strategy 1

More information

Facilities Space Needs

Facilities Space Needs Facilities Space Needs Presented by Chief Eric Girt D/Chief Ken Weatherill Fleet and Facilities Manager Dan Bowman September 21, 2016 Space Needs Overview 1. Chronology 2. Options - Future Needs 3. Current

More information

City of St. Louis. Treasurer's Office

City of St. Louis. Treasurer's Office City of St. Louis Treasurer's Office Request for Proposals Parking and Revenue Control System Proposals due no later than 3:00 p.m., September 4, 2015 1 1) Opening Statement The City of St. Louis Treasurer

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting

More information

2018 Capital Improvement Budget Library Department

2018 Capital Improvement Budget Library Department 2018 Capital Improvement Budget Library Department (in thousands) Projects s State Federal Other Total Chugiak-Eagle River Library Facility Improvements 90 - - - 90 Loussac Library Planning and Video Surveillance

More information

ANNUAL ACCESSIBILITY STATUS REPORT

ANNUAL ACCESSIBILITY STATUS REPORT The Ontarians with Disabilities Act, 2001 The Accessibility for Ontarians with Disabilities Act, 2005 ANNUAL ACCESSIBILITY STATUS REPORT 2017 Township Council Accessibility Policy C-PD-03 Administrative

More information

The Engineering Department recommends that Council: 1. Receive this Corporate Report for information purposes.

The Engineering Department recommends that Council: 1. Receive this Corporate Report for information purposes. Corporate NO: R038 Report COUNCIL DATE: MARCH 12, 2007 REGULAR COUNCIL TO: Mayor & Council DATE: March 8, 2007 FROM: General Manager, Engineering FILE: 5420-00 SUBJECT: Street Lighting Copper Wire Theft

More information

Centre Lionel E. Lalonde Centre (Emergency & Protective Services Centre)

Centre Lionel E. Lalonde Centre (Emergency & Protective Services Centre) (Emergency & Protective Services Centre) Priorities Committee Meeting Wednesday, March 21 st 2007 Presented By: Tim P. Beadman Acting General Manager of Emergency Services - and - Richard Dixon Facilities

More information

City Reso-A Requests FY 2018 (City Council and Borough Presidents)

City Reso-A Requests FY 2018 (City Council and Borough Presidents) Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2017-18 through FY 2021-22 Project Funding Type Five-Year Plan Total ($ 000s) Replacement of Unit Ventilation

More information

2018 Capital Budget Presentation

2018 Capital Budget Presentation 2018 Capital Budget Presentation 2018 General Capital Budget Expenditures Asset Type 2018 Capital Projects Police 1,431,200 Fire 1,200,000 Finance 37,000 Transportation 8,231,900 Drainage 7,356,000 Parks

More information

City of Kingston Report to Council Report Number

City of Kingston Report to Council Report Number To: From: Resource Staff: City of Kingston Report to Council Report Number 15-171 Mayor and Members of Council Denis Leger, Commissioner, Transportation, Facilities and Emergency Services Desiree Kennedy,

More information

Bicycle Access & Parking Plan Project List Review

Bicycle Access & Parking Plan Project List Review Bicycle Access & Parking Plan Project List Review Bicycle Advisory Committee September 19th, 2013 Strategy Overview New Bicycle Issues and Ideas (BAC, staff, public) Funding External Agency Lead BAPP s

More information

DATE: June 16, 2014 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

DATE: June 16, 2014 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration PUBLIC WORKS COMMISSION DATE: June 16, 2014 REPORT NO. PW2014-053 TO: FROM: Chair and Members Committee of the Whole Operations and Administration Geoff Rae, MBA, P.Eng. General Manager, Public Works Commission

More information

PROGRESS REPORT of TECHNOLOGY PLAN 2016 INITIATIVES AS OF FEBRUARY 28, 2013

PROGRESS REPORT of TECHNOLOGY PLAN 2016 INITIATIVES AS OF FEBRUARY 28, 2013 PROGRESS REPORT of TECHNOLOGY PLAN 2016 INITIATIVES AS OF FEBRUARY 28, 2013 The Tier 1 Initiatives were tied to Strategic Plan 2013 and the Program Review & Planning process. They offered desirable benefits

More information

U. S. Postal Service National Delivery Planning Standards A Guide for Builders and Developers

U. S. Postal Service National Delivery Planning Standards A Guide for Builders and Developers U. S. Postal Service National Delivery Planning Standards A Guide for Builders and Developers Table of Contents 1 Introduction... 3 2 Finding Your Growth Manager and USPS Online Resources... 4 2.1 Find

More information

Supplemental Details - Capital Funding Source Summary Cap Fund Cap Fund Cap Fund - 21

Supplemental Details - Capital Funding Source Summary Cap Fund Cap Fund Cap Fund - 21 Supplemental Details - Capital Source Summary 2018 Cap Fund - 2 2019 Cap Fund - 12 2020 Cap Fund - 21 Brampton Public Library Automation Software & Hardware Upgrades Brampton Library - 4 Corners BramWest

More information

College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY through FY

College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY through FY Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY 2013-14 through FY 2017-18 Project Funding Type Total ($ 000s) Replacement of Unit Ventilation System

More information

ORA DATA REQUEST ORA-SCG-122-LMW SOCALGAS 2019 GRC A SOCALGAS RESPONSE DATE RECEIVED: FEBRUARY 6, 2018 DATE RESPONDED: FEBRUARY 23, 2018

ORA DATA REQUEST ORA-SCG-122-LMW SOCALGAS 2019 GRC A SOCALGAS RESPONSE DATE RECEIVED: FEBRUARY 6, 2018 DATE RESPONDED: FEBRUARY 23, 2018 Exhibit Reference: SCG-23 - Capital SCG Witness: Herrera Subject: Fleet Services & Facilities Please provide the following: ORA DATA REQUEST 1. In response to data request ORA-SCG-037-LMW Q4f, SCG provided

More information

Mathematical and Statistical Sciences

Mathematical and Statistical Sciences Technology Enhanced Facilities Mathematical and Statistical Sciences CAB & BioSci Project Charter University of Alberta Academic Information and Communication Technologies (AICT Labs) 20 April 2006 TABLE

More information

CIP # Category Bldg. / Room CIP15 PROJECTS as approved by the College Governing Council, September 2014 GOVERNMENT DESCRIPTION Estimated Cost 15.01 Safety & Security Building B [RENOVATIN] To improve Student

More information

Stryker Center Concept

Stryker Center Concept Stryker Center Concept 1/13 Background Information Evolution of Williamsburg s City Square (See Figure I) City government offices moved to N. Boundary St. from S. England Street in the early 1930s to make

More information

COUNTY OF LOS ANGELES DEPARTMENT OF AUDITOR-CONTROLLER

COUNTY OF LOS ANGELES DEPARTMENT OF AUDITOR-CONTROLLER COUNTY OF LOS ANGELES DEPARTMENT OF AUDITOR-CONTROLLER J. TYLER McCAULEY AUDITOR-CONTROLLER KENNETH HAHN HALL OF ADMINISTRATION 500 WEST TEMPLE STREET, ROOM 525 LOS ANGELES, CALIFORNIA 90012-2766 PHONE:

More information

Platte County Courthouse Remodel Phase I Project

Platte County Courthouse Remodel Phase I Project Platte County Courthouse Remodel Phase I Project 1 Background The courthouse is in its 100th year of use and is in need of updates and space re-purposing to take us through another 100 years of serving

More information

BLUE RIBBON Facilities

BLUE RIBBON Facilities BLUE RIBBON 2015 Facilities FACILITY PRIORITIES Police Administration Addition $4,484,864 Relocation of Fire Station 3 $4,829,683 (Does not include land purchase) City Hall Basement/Conference/Training/Emergency

More information

ROYAL CANADIAN MOUNTED POLICE (RCMP) - NORTH VANCOUVER DETACHMENT

ROYAL CANADIAN MOUNTED POLICE (RCMP) - NORTH VANCOUVER DETACHMENT ROYAL CANADIAN MOUNTED POLICE (RCMP) - NORTH VANCOUVER DETACHMENT Mission The RCMP is Canada s national police service. Proud of our traditions and confi dent in meeting future challenges, we commit to

More information

2017 Capital Improvement Budget Police Department

2017 Capital Improvement Budget Police Department 2017 Capital Improvement Budget Police Department (in thousands) Projects Bonds State Federal Other Total APD Headquarters Campus Perimeter Security Project 500 - - - 500 APD Investigation Interview Room

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 4.0 2.0 0.59 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 4.0 3.0 0.89 Parking and Access

More information

Hurricane Florence Response and Recovery. October 18, 2018 Miles Lackey, Vice Chancellor of Business Affairs & CFO

Hurricane Florence Response and Recovery. October 18, 2018 Miles Lackey, Vice Chancellor of Business Affairs & CFO Hurricane Florence Response and Recovery October 18, 2018 Miles Lackey, Vice Chancellor of Business Affairs & CFO Event Impact Campus Grounds Approximately 400 downed trees Light poles Power lines Page

More information

THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM

THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM THE SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY S CENTRAL CONTROL & COMMUNICATIONS (C3) PROGRAM SFMTA s current Central Control Center is severely outdated and under staffed. The lack of proper functional

More information

CHAPTER TWELVE SECURITY. Oakland Alive

CHAPTER TWELVE SECURITY. Oakland Alive CHAPTER TWELVE SECURITY Oakland Alive 165 SECURITY Importance Oakland is a site full of landmark buildings, elaborate grave art, and extensive infrastructure. A comprehensive security system supported

More information

Metropolitan Council. Transportation Division Proposed Transit Capital Program

Metropolitan Council. Transportation Division Proposed Transit Capital Program Metropolitan Council Transportation Division Proposed 2015-2020 Transit Capital Program Transportation Committee October 27, 2014 Goals of the 2015 Capital Program Simplify the process Standardize the

More information

The Corporation of the TOWN OF MILTON

The Corporation of the TOWN OF MILTON The Corporation of the TOWN OF MILTON Report to: From: Chair & Members of the Community Services Standing Committee Jennifer Reynolds, Director, Community Services Date: March 7, 2011 Report No. COMS-016-11

More information

Technology Incubation Center. High Tech Cleanroom Laboratory & Production Facility.

Technology Incubation Center. High Tech Cleanroom Laboratory & Production Facility. High Tech Cleanroom Laboratory & Production Facility www.technologyincubationcenter.com Jay Chmieleski 612 275 3775 mobile Dan Friedner FOR SALE OR LEASE Technology Incubation Center VADNAIS HEIGHTS, MINNESOTA

More information

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension MOTION NO. M2018-30 Task Order 2 with the City of Des Moines for the Federal Way Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 03/08/2018 Final Action Ahmad Fazel, DECM

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline Georgia Institute of Technology Advanced Computing Technology Building Draft Program Vision Program Outline Issued April 2, 2001 I N T R O D U C T I O N Scope This document is a summary of the Vision Session

More information

Extract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017

Extract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017 Extract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017 Agenda Item 10.1 Scheduled Business 7. Funding for The Richmond Hill Centre for High-Tech Business Development (Staff

More information

çbevrlyrly STAFF REPORT Meeting Date: October 17, 2017 To:

çbevrlyrly STAFF REPORT Meeting Date: October 17, 2017 To: çbevrlyrly STAFF REPORT Meeting Date: October 17, 2017 To: Honorable Mayor & City Council From: Sandra Spagnoli, Chief of Police Subject: Police Department Upgrades Project Attachments: 1. Executive Summary

More information

To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Assistant GM Customer Resources. From: Meredith Owens Approved by: /s/

To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Assistant GM Customer Resources. From: Meredith Owens Approved by: /s/ AGENDA ITEM NO.: 5.B.1 MEETING DATE: 12/14/2015 ADMINISTRATIVE REPORT NO.: 2016-49 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Assistant GM Customer Resources From: Meredith Owens

More information

Agenda Item No. AGENDA ITEM BRIEFING

Agenda Item No. AGENDA ITEM BRIEFING AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval to Amend the FY 2016-FY 2020 Texas A&M University

More information

Technology Services. FY Budget Presentation

Technology Services. FY Budget Presentation FY 2018-19 Budget Presentation Goals and Accomplishments Overall, completed 74 projects, fulfilled 8,676 service/incident requests, and held uptime of 99.96% Application Consolidation/Reduction initiative-

More information

Cisco & Sprint Smart City Venture. Stephanie Steele Cisco Systems - Connected City Venture August 2015

Cisco & Sprint Smart City Venture. Stephanie Steele Cisco Systems - Connected City Venture August 2015 Cisco & Sprint Smart City Venture Stephanie Steele Cisco Systems - Connected City Venture August 2015 Agenda Introductions Sprint Strategic Direction Cisco Strategic Direction Venture Overview Kansas City

More information

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket Clause 5 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 28, 2018. 5 Servicing Capacity Assignment

More information

Deferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M

Deferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M Landscape 1,340 acres, 66 miles of sidewalks, 20 miles of roads Irrigation state of the art central control system; 70 systems, 8 fountains, 4 underground storage systems Stormwater management 119 sites,

More information

NASA Policy Directive

NASA Policy Directive NASA Policy Directive NPD 8820.2D Effective Date: July 02, 2013 Expiration Date: July 02, 2018 COMPLIANCE IS MANDATORY Subject: Design and Construction of Facilities Responsible Office: Facilities Engineering

More information

Request for Proposals. Information Technology Consultant and Network & Information Technology Support Services

Request for Proposals. Information Technology Consultant and Network & Information Technology Support Services Request for Proposals Information Technology Consultant and Network & Information Technology Support Services July 18, 2018 General Description The City of Greenville is looking to select a qualified firm

More information

Pipe Replacement & DIMP. Omni Hotel, Fort Worth, TX September 12, 2011

Pipe Replacement & DIMP. Omni Hotel, Fort Worth, TX September 12, 2011 Pipe Replacement & DIMP AGA Management of Vintage Pipelines Workshop Omni Hotel, Fort Worth, TX September 12, 2011 Company Overview Atmos Energy serves 3.2 million customers in 12 States Atmos Energy provides

More information

Department of Infrastructure Maintenance & Operations23 Equipment Services Division Plan Highlight Vehicle and Equipment Replacement Project Cost: Fun

Department of Infrastructure Maintenance & Operations23 Equipment Services Division Plan Highlight Vehicle and Equipment Replacement Project Cost: Fun Department of Infrastructure Maintenance & Operations23 Equipment Services Division Mission: To establish and maintain delivery of fleet services by departments with safe, reliable, economical, environmentallysound

More information

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS METRO SHORT RANGE TRANSIT PLAN FY 2010 2014 2014 Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS OVERVIEW Purpose of Metro SRTP Develop multi year strategic plan to improve transit quality,

More information

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time. TO WHOM IT MAY CONCERN: NOTICE OF RE-SCHEDULED BOARD MEETINGS This is notice that the re-scheduled meetings of the Board of Directors of the New Jersey Transit Corporation, NJ Transit Rail Operations,

More information

Hamlet Board Meeting. August 27/18. 3:00 pm RM office

Hamlet Board Meeting. August 27/18. 3:00 pm RM office Hamlet Board Meeting August 27/18 3:00 pm RM office Present: Larry Bedel, Jim Toth, Carla Taylor, Dan Dukart (arrived 3:45), Nicole Keith (excused at 4:00) 1. Call to Order Larry at 3:04 pm 2. Approval

More information

El Camino Community College El CAPITAL CONSTRUCTION PROJECTS 2013

El Camino Community College El CAPITAL CONSTRUCTION PROJECTS 2013 El Camino Community College CAPITAL CONSTRUCTION PROJECTS 2013 FACILITIES MASTER PLAN 2003 SCIENCE COMPLEX The Science Complex Building Project was completed in Spring 2005 for a total cost of $24,211,755.

More information

Schematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones

Schematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones Schematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones Public Safety & Security Secure parking and access for Police, Sheriff, Judge Secure & segregated

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

Facilities Master Plan Toronto Public Library Board Consultation

Facilities Master Plan Toronto Public Library Board Consultation STAFF REPORT INFORMATION ONLY Facilities Master Plan Toronto Public Library Board Consultation Date: May 28, 2018 20. To: From: Toronto Public Library Board City Librarian SUMMARY The purpose of this report

More information

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works Item 7.3.5 Meeting date: August 13, 2018 Department: Prepared by: Reviewed by: SUBJECT: Engineering & Public Works COUNCIL REPORT George Elliott, P.Eng., Director of Engineering & Public Works Greg McClinchey,

More information

Energy Action Plan 2015

Energy Action Plan 2015 Energy Action Plan 2015 Purpose: In support of the Texas A&M University Vision 2020: Creating a Culture of Excellence and Action 2015: Education First Strategic Plan, the Energy Action Plan (EAP) 2015

More information

MillTZreek WASHIN GTUN

MillTZreek WASHIN GTUN i_ CITY OF MillTZreek WASHIN GTUN CITY COUNCIL MINUTES February 2, 2016 15728 Main Street, Mill Creek, WA 98012 # 425-745-1891 Pam Pruitt, Mayor Brian Holtzclaw, Mayor Pro Tern Sean Kelly Donna Michelson

More information

PROGRAM 1 MANAGEMENT, COMMUNICATION & OPERATIONS ACTION STEPS RESPONSIBLE FREQUENCY per year

PROGRAM 1 MANAGEMENT, COMMUNICATION & OPERATIONS ACTION STEPS RESPONSIBLE FREQUENCY per year VREDEKLOOF COMMUNITY IMPROVEMENT DISTRICT 5 YEAR IMPLEMENTATION PLAN 1st July 2018 to 30th June 2019 PROGRAM 1 MANAGEMENT, COMMUNICATION & OPERATIONS 1. Successful day-to-day management and operations

More information

STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT

STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT CURRENT STATE THE C&W WAY College athletic departments throughout the country are spending at an unprecedented pace to develop and renovate facilities

More information

AN EMERGENCY OPERATIONS CENTER FIELD STUDY HENRICO COUNTY, VIRGINIA. by Anna M. McRay

AN EMERGENCY OPERATIONS CENTER FIELD STUDY HENRICO COUNTY, VIRGINIA. by Anna M. McRay Notes on the Science of Extreme Situations, Paper No. 2 AN EMERGENCY OPERATIONS CENTER FIELD STUDY HENRICO COUNTY, VIRGINIA by Anna M. McRay Copyright 2002 by Anna M. McRay. All rights reserved. Permission

More information

Our portfolio of equipment includes 1,027 pieces of leased equipment and 9,963 of owned equipment for a total equipment count of 10,990.

Our portfolio of equipment includes 1,027 pieces of leased equipment and 9,963 of owned equipment for a total equipment count of 10,990. Department of Fleet and Facility Management 2017 Budget Statement to the City Council Commissioner David J. Reynolds Good morning, Vice Chairman Ervin, and members of the City Council. Thank you for allowing

More information

City of Toronto Accessibility Design Guidelines 2015

City of Toronto Accessibility Design Guidelines 2015 RE: DI3.2 City of Toronto Accessibility Design Guidelines 2015 Update to Disability Issues Committee Presented By: Facilities Management Division June 2 nd, 2015 Presenters: Sunil Sharma, General Manager,

More information

Case Study Structured Services the FM Framework

Case Study Structured Services the FM Framework Case Study Structured Services the FM Framework Estates Services Strategic Facilities Management Quality Compliance ' FM was an obscure acronym to most members of the University five years ago, but now

More information

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ]

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] DATE: April 8, 2013 REPORT NO. CD2013-040 TO: FROM: Chair and Members Committee of the Whole Community Services Gregory Dworak, General Manager Community Services 1.0 TYPE OF REPORT CONSENT ITEM [ ] ITEM

More information

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for

More information

Proposed Five Year Capital Improvement Plan

Proposed Five Year Capital Improvement Plan Proposed Five Year Capital Improvement Plan July 1, 2015-June 30, 2020 Overview FY 2016 Total FY16 CIP $39,451,538 Presenters: Brian Cason Capital Projects Manager Steve Davidek IT Manager Ron Korman Public

More information

154th SESSION OF THE EXECUTIVE COMMITTEE Washington, D.C., USA, June 2014

154th SESSION OF THE EXECUTIVE COMMITTEE Washington, D.C., USA, June 2014 154th SESSION OF THE EXECUTIVE COMMITTEE Washington, D.C., USA, 16-20 June 2014 Provisional Agenda Item 5.7 CE154/26 28 April 2014 Original: English MASTER CAPITAL INVESTMENT PLAN Periodic Report on the

More information

Feasibility of Establishing a Toner Cartridge Refilling Station

Feasibility of Establishing a Toner Cartridge Refilling Station STAFF REPORT August 8, 2005 To: From: Subject: Administration Committee Treasurer Feasibility of Establishing a Toner Cartridge Refilling Station Purpose: The purpose of this report is to respond to the

More information

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public

More information

Facilities Department Town of Duxbury, MA

Facilities Department Town of Duxbury, MA Facilities Department Town of Duxbury, MA FY19 Capital Project Request Presentation To The Board of Selectmen, Finance & Fiscal Advisory Committee s Duxbury Senior Center January 8, 2018 Prepared and Maintained

More information

Vantage 70 Frederick s Most Visible Location

Vantage 70 Frederick s Most Visible Location Vantage 70 Frederick s Most Visible Location The Vantage70 Advantage Located at the intersection of Interstates 70 and 270 just minutes from Frederick, MD s historic downtown, Vantage70 is the most visible

More information

Request For Proposals. Information Technology (IT) Services. General: The City of Bishop requests proposals from consultants to provide IT services.

Request For Proposals. Information Technology (IT) Services. General: The City of Bishop requests proposals from consultants to provide IT services. Release: 10 June 2014 Closes: 27 June 2014 CITY OF BISHOP 377 West Line Street - Bishop, California 93514 Post Office Box 1236 - Bishop, California 93515 760-873-8458 publicworks@ca-bishop.us www.ca-bishop.us

More information