Large Embedded Generators Register of Completed Projects

Similar documents
PROTECTION REQUIREMENTS OF EMBEDDED GENERATORS < 5 MVA (LV + HV UP TO 22KV)

Description of the Application Process for Small Embedded Generators

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

REQUIREMENTS FOR CONNECTION OF EMBEDDED GENERATORS UP TO 5MW TO THE EVOENERGY NETWORK VERSION SM3201

Standard for Connection of Embedded Generating Systems (>30 kw to 1,500 kw) to a Distributor s LV Network

Standard for Connection of Embedded Generating Systems 5MW and below in the Ergon Energy Distribution Network

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.

Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE

Interconnection Application

Midwest Energy, Inc. Distributed Generation Interconnection Expedited & Standard Process Application

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM. July 2011 UPDATED STANDARDS

Small Generator Interconnection System Impact Study Report. Completed For Q0047

STCP 04-3 Issue 005 Real Time Data Provision

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

IEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES

Applying Intelligent Fast Load Shed Using IEC GOOSE

Power System Network Simulator (PSNsim)

Generation, Transmission, and End User Facilities

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Instructions. Interconnection Customer declares its intention to interconnect with the AEP Distribution System.

INTERCONNECTION FACILITIES STUDY REPORT

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)

Common Departures Interconnecting Facilities Requirements

Major Customer Connections

Mehr Spannungsqualität im Netz mit SVC PLUS. Improvement in Voltage Quality for Power Systems with SVC PLUS

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Karl Iliev, San Diego Gas & Electric Company

Company Directive STANDARD TECHNIQUE: TP18A/1. Application of Connection Control Panels for Soft Intertrip and/or Voltage Constraint Schemes

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

Legal Name of the Customer (or, if an individual, individual's name):

Catching Falling Conductors in Midair Detecting and Tripping Broken Distribution Circuit Conductors at Protection Speeds

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,

The Universe of Possibilities using AF. Copyr i ght 2014 O SIs oft, LLC.

Series 2400 Paralleling Switchgear

POWER GRID AUTOMATION. Pág.. n. RMU Automation

CIM, PI AF and SISCO CIM Adapter Create New Application Opportunities for Utilities

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Generation Interconnection Feasibility Study Report

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL

Feasibility Study on Load Flow and Short Circuit Project

Practical Impact of Very Small Power Producers (VSPP) on Control and Protection System in Distribution Networks

OC IEEE IAS/PES Meeting February 21, 2013

Easy Networking for Power Monitoring. network based MONITORING SOLUTIONS

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

Distributed Generation Interconnection in Illinois

Synchronizing Systems

CenterPoint Energy P O Box 1700 Houston, TX

SCHEDULE 22 COMMON CONNECTION CHARGING METHODOLOGY

Wind Plant Systems Grid Integration Plant and Turbine Controls SCADA

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

PG&E Transmission Interconnection Handbook

Implementation of a Power Line Carrier solution to support anti-islanding protection and reduce interconnection costs for Distributed Generation

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards

IMP/ 001 / 014 Policy for the Protection of Distribution Networks

Interconnection and Transmission

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DEPARTMENT SYSTEM DESIGN SECTION

SDG&E s Accomplishments and Future Plans

TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT

C E R T I F I C A T E O F C O M P L I A N C E

Plats för bild på PST2291 med solpanel och en person

Local Area Studies Update - PACW Kevin Putnam

THE INTERCONNECTION HANDBOOK

COGENERATION INTERCONNECTION REQUIREMENTS. Parallel Operation of Connecting Parties Generation

6 Check that the earth system is complete, undamaged and bonded to earth points ( including capacitor and control).

Power and accuracy. Versatile. One display can monitor up to 32 measuring modules information

ADINE EU DEMONSTRATION

Blueprint Data Center

EOS REMSDAQ CALLISTO NX TYPE E RTU

TRIP OF CLARE SOUTH TOWNSVILLE SOUTH 132 KV TRANSMISSION LINE ON 24 JUNE 2015

Future plans/changes in the grid - Grid4EU. Ilaria Losa - RSE SpA Daniele Stein ENEL SpA Lars Jendernalik RWE SpA Paul Douard - ERDF

Southern Company Smart Grid

Distributed Generation Requirements Update

Hosting Capacity for Distributed Energy Resources on Distribution Feeders A Case Study

Energy Security: A Global Challenge

Load Management of Industrial Facilities Electrical System Using Intelligent Supervision, Control and Monitoring Systems

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

EFASOLAR PVStation Solutions

NEW ERA METER. Installation & Operation Guide NE METER

How customers can benefit from new metering technologies. A business case in Bilbao-Spain. Barcelona, September 20, 2005

D Real-time simulation results of protection and network automation options to improve the stability of DG unit in supplying feeder fault

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

Smart Distribution Technology

A Data Approach to Advanced Distribution Management Systems. L. WILKE, B. WALL POWER Engineers USA

SCADA SYSTEM FOR PEDEEE SYRIA PROJECT

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field

Uncontrolled document when printed. Large Customer Connection Manual

Smart Grid Operations - Combining the Power of Smart Meters and The Control Room ADMS

FACTS and HVDC for Grid Connection of Large Wind Farms

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

Transcription:

Large Embedded Generators Register of Completed Projects This document contains a description of the completed projects relating to the connection of Large Embedded Generators to the TasNetworks distribution network. A Large Embedded Generator is considered to be either: a generator that exports into the distribution network through a single connection point at greater than 5 MW; or a generator that exports into the distribution network through a single connection point at less than 5 MW and which has to be registered with AEMO 1. There have been only two Large Generation connections to the TasNetworks distribution network in the last five years. Details of these are given below. 1 The Australian Energy Market Operator

Embedded Generation Projects complete as at 30 January 2015 Generator 1 Technology of generating unit Maximum power generation capacity of the generating system Maximum contribution to fault level Size and rating of the relevant transformer Renewable, hydro gravity, Leroy Somer, LSA 58 65 / 6p / vertical Synchronous generator. 6,078 kw, 7,150 kva @ rated power factor of 0.85. Up to 2,000 amps maximum at the Connection Point. Generator transformer rating 7.5/6 MVA (22/3.3 kv). Single line diagram of the connection arrangement 2

Protection systems and communication systems Voltage control and reactive power capability Location specific facilities required to support the generator connection Protection systems Site disconnection for faults within private HV network; Anti islanding solution installed to ensure that the generating unit only connects to a network that is in a satisfactory operating state; Generator can only be connected to the distribution network with STATCOM in service. Communications Systems SCADA systems have been installed to provide the network service provider with visibility of: Private CB Status relevant to generator connection; Power flows and voltages at the connection site; and Power flows and voltages at the generator connection. Generating unit operates in Voltage Control mode to 1.02 PU. Power factor maintained between 0.95 and 0.98 lagging (absorbing reactive power). STATCOM installation (network side of the main site connection) required to provide voltage support for the distribution network following loss of generator. Anti islanding solution based on microwave and radio communications installed to prevent generator exporting electricity to an islanded portion of the distribution network. Upstream network augmentation completed to accommodate generator capability. Cogeneration control settings applied to voltage regulating controllers. Joint operating procedure developed between Customer and the Network Service Provider to accommodate operational limitations specific to this installation. 3

Generator 2 Technology of generating unit Maximum power generation capacity of the generating system Maximum contribution to fault level Size and rating of the relevant transformer Synchronous generator manufactured by General Electric Company. Natural gas fired turbine manufactured by Siemens. 7,900 kw. Up to 3,000 amps maximum at the Connection Point. Generator connection is via a 22/11kV, 10 MVA step up transformer to the customers high voltage distribution network. TasNetworks Customer Generator s Anti-Islanding Trip Signal HV Feeder HV Connection Site Main CB Generator Connection Site Single line diagram of the connection arrangement Metering HV Connection Point & PCC LV Distribution Board A LV Distribution Board B Generating Unit 4

Protection systems and communication systems Voltage control and reactive power capability Location specific facilities required to support the generator connection Protection systems Anti islanding systems incorporate Rate of change of frequency (ROCOF) and Vector phase shift (VPS) protection relays for the prevention of embedded generating unit islanded operation; Neutral voltage displacement (NVD) protection has been installed for the detection of distribution network earth faults and the prevention of embedded generating unit islanded operation. Communications systems SCADA based truth table solution implemented to ensure generating unit is only connected to a network in a satisfactory operating state. Power factor at the connection point will be maintained between 0.9 lagging to 0.9 leading. Joint operating procedure developed between Customer and the Network Service Provider to accommodate operational limitations specific to this installation. 5