Free Standing Emergency Department DGL Project No SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY PART 1 - GENERAL

Similar documents
1. Coordination of series-rated devices is permitted where indicated on Drawings.

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

POWER SYSTEMS STUDY: SIGNIFICANT (OR TOTAL) DELETION OF EXISTING TEXT

1510 MOTOR CONTROLLERS

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

The City of Winnipeg Dry Type Transformers up to 600 V Primary Section Bid Opportunity No Page 1 of 2

A. Operation and Maintenance Data: For the overcurrent protective devices to include in emergency, operation, and maintenance manuals.

SECTION DISCONNECT SWITCHES

SECTION ELECTRIC METERING

SECTION SWITCHGEAR

SECTION (16410) - ENCLOSED SWITCHES AND CIRCUIT BREAKERS

1. Section Lightning Protection for lightning protection system. D. The installation shall be in conformance with NEC Article 285.

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

SECTION 16450: NON-AUTOMATIC TRANSFER SWITCH / QUICK CONNECT GENERATOR SWITCHBOARD <S> <OM>

SECTION TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

Contractor to provide a draft and final power study report to be reviewed by the Engineer.

UL 508 A standard-compliant design of industrial control panel

SECTION SURGE PROTECTION DEVICES. A. Section includes Surge Protection Devices for low-voltage power, control, and communication equipment.

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

30-Cycle Rated Switchboards - Selectivity Tradeoffs

SECTION PANELBOARDS. A. NECA (National Electrical Contractors Association) -Standard of Installation

SECTION SURGE PROTECTIVE DEVICES

Equipment Short-Circuit Current Rating and Available Fault Current

SECTION PANELBOARDS

SECTION ( ) LIGHTING CONTROL PANELBOARD

Certification Exams. Detailed Content Outlines Level 2 Certified Assistant Technician Level 3 Certified Technician Level 4 Certified Senior Technician

Understanding SCCR. THE BEST ELECTRICAL CONTROLS BUSINESS ON THE PLANET! Unmatched Service Superior Product Quality Advantage Pricing

Applying branch circuit breakers and supplementary protectors in North America

SECTION DISTRIBUTION SWITCHBOARDS

3a. IEM Indoor Metal Clad Medium Voltage Switchgear 25KV a. Section INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

RELT Reduced Energy Let Thru 2018

PLT. Breaker-based transfer switch open, closed or soft transition amps. Specification sheet

I-Line Panelboards. Innovative design, smart bus technology, and simple installation

System Protection and Control Subcommittee

Electrical Plan Review

C C CIRCUIT-BREAKERS Moulded-case (MCCB), general. 1. Introduction. 2. General description

SECTION VARIABLE FREQUENCY MOTOR CONTROLLERS (VFD)

Siemens Dynamic Arc Flash Reduction System and its application in motor control centers

Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services.

SECTION 16496E ATS MOLDED CASE WITH ATC 900 CONTROLLER

Short-Circuit Calculation Methods

TECHNICAL SPECIFICATION FOR MEDIUM VOLTAGE METAL-CLAD SWITCHGEAR (15 KV)

Applying branch circuit breakers and supplementary protectors in North America

Mitigating Arc Flash Hazards

Document C0. Use for:

Tmax molded case circuit breakers Specification guide

FORM FOR PROPOSAL FOR 2014 NATIONAL ELECTRICAL CODE

SECTION IDENTIFICATION FOR ELECTRICAL SYSTEMS

SECTION SWITCHBOARDS

Dynamic Arc Flash Reduction System

Spectra RMS Circuit Breakers with microentelliguard Trip Units

ASCO 920 Remote Control (RC) Switches

Interconnection Application

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers. 4. Electronic-grade panelboards.


NEMA Standards Publication AB Establishing Levels of Selective Coordination for Low Voltage Circuit Breakers

SERIES RATED COMBINATIONS

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)

DIVISION 16 SECTION Surge Protective Device Submittal (SPD)

Midwest Energy, Inc. Distributed Generation Interconnection Expedited & Standard Process Application

SECTION WIRING DEVICES PART 1 - GENERAL. A. Drawings and Division 1 Specification Sections, apply to this Section.

920 Remote Control (RC) Switches

TRI-SERVICE ELECTRICAL WORKING GROUP (TSEWG) 07/16/08 TSEWG TP-3: SURGE PROTECTOR PERFORMANCE AND EVALUATION CRITERIA

(1986; Rev. 1989) Molded Case Circuit Breakers and Molded Case Switches. (1985; Rev. 1988) Enclosures for Electrical Equipment (1000 Volts Maximum)

National Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

SECTION PANELBOARDS

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

GE Energy Industrial Solutions. GE Overcurrent Device Instantaneous Selectivity Tables

Power-Style QED-2, Series 2 Low Voltage Switchboards

24973 Circuit Breaker MINIATURE CIRCUIT BREAKER, 440VAC, 10A, CIRCUIT BREAKER TYPE: STANDARD

Entry Level Assessment Blueprint Electrical Occupations

Quick Start Guide TS A

Bulletin 1489 Circuit Breakers. Selection Guide

PowerFlex 400 AC Drive Guide Specification

Industrial Control Panels Tested product combinations to meet NEC Article 409 and UL 508A Standard

SENTRON. Protective devices Selectivity for 3VA molded case circuit breakers. Introduction. Selectivity - terms and definitions

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

SECTION ELECTRICAL CONTROL DEVICES

JCK, JCK-A, JCK-B, JCH, JCL, JCL-A, JCL-B, JCG, JCR-A, & JCR-B. R-Rated Fuses For Motor Circuit Protection Medium Voltage.

Installation, Operation and Maintenance Manual

Document Owner: Name: Phil Langlois Department: Lead Electrical Engineer

Eaton s Innovative Technology Surge Suppression Guideform Specification High Exposure DIVISION 16 SECTION 16289

Eaton s Innovative Technology Surge Suppression Guideform Specification Low Exposure DIVISION 16 SECTION 16289

White Paper. UL Standards for Power Control System Equipment

Power System Protection Training

Application Techniques CENTERLINE 2100 Motor Control Centers

PowerPact Q-Frame Molded Case Circuit Breakers and Switches (Types QB, QD, QG and QJ)

LOW VOLTAGE BYPASS/ISOLATION BREAKER BASED AUTOMATIC TRANSFER SWITCHES SECTION 16496D

4.3. Switchboards. Contents Description Pow-R-Line Drawout Molded Case Circuit Breaker Switchboards Product Selection...

Ground Fault Current Protection Devices Prevent Costly Production Shutdowns

GENERAL UL th EDITION BID SPEC: SURGE PROTECTIVE DEVICES Prepared by THOR SYSTEMS, INC.

UL 508A Industrial Control Panels Eaton. All Rights Reserved.

TSC Schneider-PDI Agenda

SURE TRIP RETRO KITS With RMS CURRENT MEASUREMENT

C E R T I F I C A T E O F C O M P L I A N C E

Medium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks

Enabling a Solid State Circuit Breaker

PRC Coordination of Protection Systems for Performance During Faults

Transcription:

SECTION 26 05 73 1.1 SUMMARY OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY PART 1 - GENERAL A. This Section includes the following: 1. Requirements for computer-based, fault-current and overcurrent protective device coordination studies. Protective devices shall be set based on Engineer s review of submitted results of the protective device coordination study. a. Coordination of series rated devices is not permitted. 2. Delegated Design Requirements for Arc Flash Hazard Analysis. B. Related Sections include the following: 1. Division 26 Section "Common Work Results for Electrical" for Arc Flash Training Requirements. 1.2 PERFORMANCE REQUIREMENTS A. Overcurrent Protective Device Coordination: All overcurrent protective devices proposed for inclusion in the Work shall be selected to be selectively coordinated with the overcurrent protective devices installed on their supply side such that an overcurrent event (overload, short-circuit, or ground-fault) occurring at the lowest level in the system (branch circuit) cannot cause the feeder protective device supplying the branch circuit panelboard to open. This coordination shall be carried through each level of distribution for all branches of normal and emergency power. B. Arc Flash Hazard Analysis Delegated Design: Prepare computerized Arc Flash protection study per the requirements set forth in NPA 70E Standard for Electrical Safety in the Workplace and according to IEEE 1548 to obtain information required for Arc Flash Warning and Instructions labels specified under PART 2 of Section 16 26 Identification for Electrical Systems. 1.3 SUBMITTALS A. Submit product data and shop drawings in accordance with Division 01 and Division 26 Section Common Work Results for Electrical for products specified under PART 2 - PRODUCTS. B. Simultaneous Action Submittals: The following action submittals shall be made in conjunction with the approval process for system protective devices specified in other Division 26 Sections. The following submittals shall be in digital form: 1. Coordination-study input data, including completed computer program input data sheets. 2. Study and Equipment Evaluation Reports. 3. Coordination-Study Report. OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-1

4. Arc Flash Hazard Analysis Report. C. Product Data: For computer software program to be used for studies. D. Product Certificates: For coordination-study and fault-current-study computer software programs, certifying compliance with IEEE 399. E. Qualification Data: For coordination-study specialist and Arc Flash Hazard Analysis. F. Report shall include the following sections: 1. Executive Summary 2. Descriptions, purpose, basis and scope of the study. 3. Tabulations of circuit breaker, fuse, and other protective device ratings versus calculated short circuit duties. 4. Protective device time versus current coordination curves, tabulations of relay and circuit breaker trip unit settings, and fuse selection. 5. Fault current calculations including a definition of terms and guide for interpretation of the computer printout. 6. Details of the incident energy and flash protection boundary calculations. 7. Recommendations for system improvements, where needed. 8. One line diagram. 9. Equipment specific Arc Flash Hazard labels. 1.4 QUALITY ASSURANCE A. Studies shall use computer programs that are distributed nationally and are in wide use. Software algorithms shall comply with requirements of standards and guides specified in this Section. Manual calculations are not acceptable. B. Coordination-Study Specialist Qualifications: An entity experienced in the application of computer software used for studies, having performed successful studies of similar magnitude on electrical distribution systems using similar devices. 1. Study to be performed by a professional engineer or personnel trained, employed, and supervised by a registered professional engineer. 2. Registered professional engineer shall be a full-time employee of the electrical equipment manufacturer or a professional engineering firm. 3. Registered professional engineer shall have a minimum of five (5) years of experience in performing power system studies. C. Comply with IEEE 242 for short-circuit currents and coordination time intervals. D. Comply with IEEE 399 for general study procedures. E. Arc Fault Hazard Analysis Qualifications: Comprehensive engineering analysis by a qualified professional engineer or personnel trained and employed by the equipment manufacturer in required calculation methodology. 1. Analysis to be performed by a professional engineer or personnel trained, employed, and supervised by a registered professional engineer. 2. Registered professional engineer shall be a full-time employee of the electrical equipment manufacturer or a professional engineering firm. OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-2

3. Registered professional engineer shall have a minimum of five (5) years of experience in performing power system studies. F. Comply with IEEE 1584 for performing Arc Flash Hazard Calculations. 2.1 OVERCURRENT PROTECTIVE DEVICES PART 2 - PRODUCTS A. Basis-of-Design Product: The overcurrent protective device (OCPD) types indicated on the Drawings correspond to products produced by Square D; Schneider Electric. Subject to compliance with the requirements, produce Overcurrent Protective Device Coordination Study based on the exact equipment proposed for inclusion in the Work by the basis-ofdesign manufacturer as base bid. Provide alternate pricing in accordance with Division 01 Section "Alternates" for a comparable product by one of the following: 1. Cutler-Hammer, Inc.; Eaton Corporation. 2. General Electric Co.; Electrical Distribution & Protection Div. 3. Siemens Energy & Automation, Inc. 2.2 COMPUTER SOFTWARE DEVELOPERS A. Computer Software Developers: Subject to compliance with requirements, provide products by the following: 1. SKM Systems Analysis, Inc. 2.3 COMPUTER SOFTWARE PROGRAM REQUIREMENTS A. Comply with IEEE 399. B. Analytical features of fault-current-study computer software program shall include "mandatory," "very desirable," and "desirable" features as listed in IEEE 399. C. Computer software program shall be capable of plotting and diagramming time-currentcharacteristic curves as part of its output. Computer software program shall report device settings and ratings of all overcurrent protective devices and shall demonstrate coordination by computer-generated, time-current coordination plots. 3.1 EXAMINATION PART 3 - EXECUTION A. Examine Project overcurrent protective device submittals for compliance with electrical distribution system coordination requirements and other conditions affecting performance. 1. Proceed with coordination study only after relevant equipment submittals have been assembled, but prior to their submission to the Architect. Coordination study shall accompany submission of relevant equipment submittals. 3.2 POWER SYSTEM DATA A. Engineer performing the short-circuit, protective device coordination study, and arc flash hazard analysis shall furnish the Contractor with a list of required data immediately after OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-3

award of the contract. Contractor shall expedite collection of the data to ensure completion of the study and analysis as required. B. Engineer performing the study and analysis shall make at least one job-site visit before completion of the final studies to familiarize himself/herself with the project to ensure that the provided data is accurate. C. Source combination shall include present and future motors and generators indicated in the documents. D. Load data utilized shall include existing and proposed loads obtained from Contract Documents provided by Owner, or Contractor. E. If applicable, include fault contribution of existing motors in the study and analysis. The Contractor shall obtain required existing equipment data, if necessary, to satisfy the study requirements. F. Gather and tabulate the following input data to support coordination study: 1. Product Data for overcurrent protective devices specified in other Division 26 Sections and involved in overcurrent protective device coordination studies. Use equipment designation tags that are consistent with electrical distribution system diagrams, overcurrent protective device submittals, input and output data, and recommended device settings. 2. Impedance of utility service entrance. 3. Electrical Distribution System Diagram: In hard-copy and electronic-copy formats, showing the following: a. Circuit-breaker and fuse-current ratings and types. b. Relays and associated power and current transformer ratings and ratios. c. Transformer kilovolt amperes, primary and secondary voltages, connection type, impedance, and X/R ratios. d. Generator kilovolt amperes, size, voltage, and source impedance. e. Cables: Indicate conduit material, sizes of conductors, conductor material, insulation, and length. f. Busway ampacity and impedance. g. Motor horsepower and code letter designation according to NEMA MG 1. 4. Data sheets to supplement electrical distribution system diagram, cross-referenced with tag numbers on diagram, showing the following: a. Special load considerations, including starting inrush currents and frequent starting and stopping. b. Transformer characteristics, including primary protective device, magnetic inrush current, and overload capability. c. Motor full-load current, locked rotor current, service factor, starting time, type of start, and thermal-damage curve. d. Generator thermal-damage curve. e. Ratings, types, and settings of utility company's overcurrent protective devices. f. Time-current-characteristic curves of devices. g. Manufacturer, frame size, interrupting rating in amperes rms symmetrical, ampere or current sensor rating, long-time adjustment range, short-time adjustment range, and instantaneous adjustment range for circuit breakers. OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-4

h. Manufacturer and type, ampere-tap adjustment range, time-delay adjustment range, instantaneous attachment adjustment range, and current transformer ratio for overcurrent relays. i. Panelboards, switchboards, motor-control center ampacity, and interrupting rating in amperes rms symmetrical. 3.3 FAULT-CURRENT STUDY A. A short-circuit current ratings indicated in the Contract Documents are based on Fault- Current study prepared by the Engineer during design and are based on available information and anticipated feeder lengths. Calculate the maximum available short-circuit current in amperes rms symmetrical at circuit-breaker positions of the electrical power distribution system based on proposed feeder routing. The calculation shall be for a current immediately after initiation and for a three-phase bolted short circuit at each of the following: 1. Motor-control center. 2. Distribution panelboard. 3. Branch circuit panelboard. 4. Transfer Switch. 5. Enclosed Fused Switch. 6. Enclosed Circuit Breaker. 7. Enclosed Bus Assembly. B. Study electrical distribution system from normal and alternate power sources throughout electrical distribution system for Project. Include studies of system-switching configurations and alternate operations that could result in maximum fault conditions. C. Calculate momentary and interrupting duties on the basis of maximum available fault current. D. Calculations to verify interrupting ratings of overcurrent protective devices shall comply with IEEE 241 and IEEE 242. 1. Transformers, as appropriate for transformers included in the Work: a. ANSI C57.12.10. b. ANSI C57.12.22. c. ANSI C57.12.40. d. IEEE C57.12.00. e. IEEE C57.96. 2. Low-Voltage Circuit Breakers: IEEE 1015 and IEEE C37.20.1. 3. Low-Voltage Fuses: IEEE C37.46. E. Study Report: 1. Show calculated X/R ratios and equipment interrupting rating (1/2-cycle) fault currents on electrical distribution system diagram. F. Equipment Evaluation Report: 1. For 600-V overcurrent protective devices, ensure that interrupting ratings are equal to or higher than calculated 1/2-cycle symmetrical fault current. 2. For devices and equipment rated for asymmetrical fault current, apply multiplication factors listed in the standards to 1/2-cycle symmetrical fault current. OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-5

3. Verify adequacy of phase conductors at maximum three-phase bolted fault currents; verify adequacy of equipment grounding conductors and grounding electrode conductors at maximum ground-fault currents. Ensure that short-circuit withstand ratings are equal to or higher than calculated 1/2-cycle symmetrical fault current. 4. Notify Architect/Engineer, in writing, of any existing circuit protective devices improperly rated for the calculated available fault current. 3.4 COORDINATION STUDY A. Perform coordination study using approved computer software program. Prepare a written report using results of fault-current study. Comply with IEEE 399. 1. Calculate the maximum and minimum 1/2-cycle short-circuit currents. 2. Calculate the maximum and minimum ground-fault currents. B. Comply with IEEE 241 and IEEE 242 recommendations for fault currents and time intervals. C. Transformer Primary Overcurrent Protective Devices: 1. Device shall not operate in response to the following: a. Inrush current when first energized. b. Self-cooled, full-load current or forced-air-cooled, full-load current, whichever is specified for that transformer. c. Permissible transformer overloads according to IEEE C57.96 if required by unusual loading or emergency conditions. 2. Device settings shall protect transformers according to IEEE C57.12.00, for fault currents. D. Conductor Protection: Protect cables against damage from fault currents according to ICEA P-32-382, ICEA P-45-482, and conductor melting curves in IEEE 242. Demonstrate that equipment withstands the maximum short-circuit current for a time equivalent to the tripping time of the primary relay protection or total clearing time of the fuse. To determine temperatures that damage insulation, use curves from cable manufacturers or from listed standards indicating conductor size and short-circuit current. E. Coordination-Study Report: Prepare a written report indicating the following results of coordination study: 1. Tabular Format of Settings Selected for Overcurrent Protective Devices: a. Device tag. b. Relay-current transformer ratios; and tap, time-dial, and instantaneous-pickup values. c. Circuit-breaker sensor rating; and long-time, short-time, and instantaneous settings. d. Fuse-current rating and type. e. Ground-fault relay-pickup and time-delay settings. 2. Coordination Curves: Prepared to determine settings of overcurrent protective devices to achieve selective coordination. Graphically illustrate that adequate time separation exists between devices installed in series, including power utility company's upstream devices. Prepare separate sets of curves for the switching schemes and for emergency periods where the power source is local generation. Show the following information: a. Electric Utility's overcurrent protective device. OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-6

b. Device tag. c. Voltage and current ratio for curves. d. Three-phase and single-phase damage points for each transformer. e. No damage, melting, and clearing curves for fuses. f. Transformer inrush points value set to 8. g. Maximum fault-current cutoff point. h. Motor starting characteristics, damage points and overload relay. i. Generator short-circuit decrement curve and damage point. F. Completed data sheets for setting of overcurrent protective devices. G. Complete Schedule of breaker settings to summarize information contained on data sheets. Sample schedule has been included at the end of this section for preferred format. 3.5 ARC FLASH HAZARD ANALYSIS A. Comply with IEEE 1584 for arc flash hazard analysis. B. The flash protection boundary and the incident energy shall be calculated at all significant locations in the electrical distribution system where work could be performed on energized parts including, but not limited to, the following: 1. Disconnect switches. 2. Emergency system boxes and enclosures. 3. Enclosed circuit breakers. 4. Meter Sockets and assemblies. 5. Motor starter. 6. Panelboards. 7. Power transfer equipment. (ATS) 8. Transformers. C. When appropriate, the short circuit calculations and the clearing times of the phase overcurrent devices will be retrieved from the short-circuit and coordination strudy model. Ground overcurrent protection relays should not be taken into consideration when determining the clearing time when performing incident energy calculations. D. Short-circuit calculations and the corresponding incident energy calculations for multiple system scenarios to be compared and the greatest incident energy to be uniquely reported for each equipment location. Calculations to be performed to represent the maximum and minimum contributions of fault current magnitude for all normal and emergency operating conditions. 1. The minimum calculation will assume that the utility contribution is at a minimum and will assume a minimum motor contribution (all motors off). 2. The maximum calculation will assume a maximum contribution from the utility and will assume the maximum amount of mtors to be operating. Calculations shall take into consideration the parallel operation of synchronous generators with the electric utility, where applicable. E. Incident energy calculations shall consider the accumulation of energy over time when performing arc flash calculations on buses with multiple sources. Iterative calculations must take into account the changing current contributions, as the sources are interrupted OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-7

or decremented with time. Fault contribution from motors and generators to be decremented as follows: 1. Fault contribution from induction motors should not be considered beyond 3-5 cycles. 2. Fault contribution from synchronous motors and generators should be decayed to match the actual decrement of each as closely as possible. F. For each equipment location with a separately enclosed main device, calculations for incident energy and flash protection boundary shall include both the line and load side of the main breaker. 1. When performing incident energy calculations on the line side of a main breaker, the line side and load side contributions must be included in the fault calculation. G. Mis-coordination should be checked amongst all devices within the branch containing the immediate protective device to compute the incident energy for the corresponding location. H. Arc Flash calculations shall be based on actual overcurrent protective device clearing time. Maximum clearing time will be capped at 2 seconds based on IEEE 1584 section B.1.2. Where it is not physically possible to move outside of the flash protection boundary in less than 2 seconds during an arc flash even, a maximum clearing time based on the specific location shall be utilized. I. Complete Arc Flash report to be used for the preparation of Arc Flash Warning labels for electrical equipment. Refer to Division 26 Section Identification for Electrical Systems for requirements of Arc Flash Study and labels. J. Correct Deficiencies, Re-calculate and Report: 1. After Engineer s initial review, correct unsatisfactory conditions and recalculate to demonstrate compliance; resubmit overcurrent protective devices as required to bring system into compliance. 2. Revise and Resubmit report multiple times as necessary to demonstrate compliance with requirements. END OF SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-8

SENSOR 4000 250 100 400 PLUG LTPU (%) 1 1 LTPU 4000 400 SAMPLE CIRCUIT BREAKER COORDINATION SCHEDULE FRAME 4000 250 100 1200 BREAKER TYPE MASTERPACT NW KI FI POWERPACT PJ BREAKER MAUNFACTURER SQUARE D SQUARE D SQUARE D SQUARE D LOAD/DEVICE DESCRIPTION MSCPA MAIN DIST PANEL CPEQH VIA AT PANEL CPLSH VIA ATS PANEL CPH DEVICE TYPE SST TM TM SST DEVICE PD-MSCPA PD-CPEQ PD-CPLS PD-CPH LEGEND SST = STATIC TRIP ELECTRONIC CIRCUIT BREAKER = NOT APPLICABLE TM = THERMAL MAGNETIC LTD 2 0.5 STPU 4 5 STPU 16000 2000 STD 0.1 0.1 INST 15 10 FIXED 6 INST 60000 2500 FIXED 2400 GFPU C A GFPU 720 120 GFD 0.2 0 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-9

THIS PAGE INTENTIONALLY LEFT BLANK OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 26 05 73-10