MONTHLY REPORT Issue No. R12-17 December 2017

Similar documents
MONTHLY REPORT March 2017 Issue No. R03-17

MONTHLY REPORT May 2015 Issue No. R05-15

Eng. Desire Nzayanga, Power Program Officer Nile Basin Initiative/NELSAP. 11 th EAPIC, Dar es Salaam, TANZANIA

TERMS OF REFERENCE. Scaling-up Renewable Energy Program (SREP) Joint Mission. Lesotho

AFRICA CLIMATE CHANGE FUND SUPPORTING AFRICAN COUNTRIES TO ACCESS INTERNATIONAL CLIMATE FINANCE

EASTERN AFRICA POWER POOL EAPP Presentation to Afsec, Standardization needs for Integration of Power Pools of Africa August, 2010, South Africa By Jas

Regional Interconnectivity & Cross Border Trade Networks: An EAPP Update. Eng. David M. Mwangi Independent Energy Consultant Kenya

Enhancing synergies towards climate action and sustainable development on the ground

NEPAD ICT BROADBAND INFRASTRUCTURE PROGRAMME

COORDINATED BORDER MANAGEMENT in Southern Africa. May 16, 2013 WCO IT Conference Godwin Punungwe Director, Trade Facilitation

KGRTC was established in 1989 by SADC Energy Ministers to offer specialized training in hydropower and related engineering disciplines.

Dr. Daniel-Alexander Schroth SE4All Africa Hub Coordinator

RESOLUTIONS Review and Status of Implementation

Meeting of PPCR Pilot Countries and Regions May 1-3, 2013 Washington D.C., United States. Progress Updates from PPCR Pilots

Minutes of the Board Meeting

Financing resilience at the subnational 22 JUNE 2014 STANDING COMMITTEE ON FINANCE FORUM, MONTEGO BAY, JAMAICA

1/8. Note by the Chair. Executive Summary. 24 th Senior Officials Meeting of the Environment Management Group. EMGSOM.24(a)_4_Work Plan_2019

E-Strategies in Africa

Multiplying Environmental Action

TERMS OF REFERENCE Scaling-up Renewable Energy Program in Ghana Scoping Mission

OIE Sub-Regional Training Seminar on Veterinary Legislation Botswana National Veterinary Laboratory, Sebele, Gaborone (Botswana)

SME License Order Working Group Update - Webinar #3 Call in number:

Title of presentation

Global Infrastructure Hub Update. G20 Infrastructure Working Group, January 2019

Report on the activities of the Independent Integrity Unit, November 2016 to September 2017

The GCC Interconnection Grid

13174/15 AT/tl 1 DGE 2B

Presentation to PPC Cost to communicate (2) 7 November 2014

Dr. Daniel-Alexander Schroth SEforALL Africa Hub Coordinator

South Africa Bureau of Standards IPAP Commitments. SABS Executive Team. Date : 24 May 2012

The Power of the SE4All Action Agenda and Investment Prospectus

Pilot Program for Climate Resilience in Tajikistan. Coordination Mechanism

Mocuba The First Utility Scale PV Project in Mozambique

Strengthening telecommunications infrastructure for economic growth and security: A case for Zambia

The United Republic of Tanzania. Domestication of Sustainable Development Goals. Progress Report. March, 2017

EASTERN AFRICA AFRICA POWER POWER POOL POOL

TERMS OF REFERENCE FOR: REGIONAL CLIMATE AND GREEN GROWTH CONSULTANT EASTERN AFRICA

CABINET PLANNING SYSTEM PROCUREMENT

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Business Model for Global Platform for Big Data for Official Statistics in support of the 2030 Agenda for Sustainable Development

Innovative Climate Finance Mechanisms for Financial Institutions in Fiji, Pakistan, Indonesia and Sri Lanka

NEPAD ICT Broadband Infrastructure Programme: Interconnection via Umojanet

PIDA WEEK 2018 Concept Note

Flexible power solutions enabling mining growth

Integrated Resource Planning April 20, 2010

Global Infrastructure Connectivity Alliance Initiative

A BUSINESS PERSPECTIVE ON INTERNATIONAL CLIMATE CHANGE POLICY

Private Sector Engagement in DRR in Jordan

Terms of Reference (ToR) for ICAT support to MRV in the Energy Sector in Kenya

SIDS Symposium UNOPS as a partner in projects in island states Session III: What does it take for Governments to successfully mobilize partnerships

WHO/AFRO SLIPTA UPDATE

Background Document for Agenda Item 3: Briefing from the Secretariat on launch of the Green Coalition on the Belt and Road Initiative

INFORMATION TECHNOLOGY ONE-YEAR PLAN

Southeast Florida Regional Climate Change Compact Update. Broward Climate Change Task Force February 16, 2017

Seminar on African Electrical Interconnection. Module 1. The feasibility of Regional Electricity Cooperation and Integration

An Introduction to Network Codes & The Links Between Codes

ADB s Energy Program in Myanmar

EU for Climate Action in the ENI Southern Neighbourhood

Online meeting Steering Committee of the Global Alliance for alternatives to DDT

JOINT STATEMENT BY THE MINISTRY OF ENERGY OF THE RUSSIAN FEDERATION AND THE INTERNATIONAL ENERGY AGENCY

MABITSI LEGODI SENIOR MANAGER:BUSINESS DEVELOPMENT

COMPLIANCE MONITORING REPORT

Regional Center for Renewable Energy and Energy Efficiency. Who we are

The UNDP Low Emission Capacity Building (LECB) Programme: A global initiative to support mitigation action LEDS, NAMAs & MRV

ASSEMBLY 37TH SESSION

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft

Closing the Infrastructure Gap: The World Bank s contribution. Infrastructure Consortium for Africa

JOINT AFRICA-EU STRATEGY - ANNUAL REFERENCE GROUP ON INFRASTRUCTURE MEETING- VENUE:

HEALTH INFORMATION INFRASTRUCTURE PROJECT: PROGRESS REPORT

Server Virtualisation Assessment. Service Overview

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009

NEPAD s Impact on the Growth of ICT: Broadband Infrastructure Network ready for roll-out

Resolution adopted by the General Assembly. [on the report of the Second Committee (A/60/488/Add.3)]

An Introduction to the SEforALL Building Efficiency Accelerator Belgrade BEA Kick-off Meeting 31 October 2016 Eric Mackres,

NORTHPINE COMMUNITY IMPROVEMENT DISTRICT IMPLEMENTATION PLAN 01 st July th June 2022

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

REPORT 2015/149 INTERNAL AUDIT DIVISION

EU-UNDP Capacity Building Programme on Climate Change

ITU REGIONAL ECONOMIC & FINANCIAL FORUM OF TELECOMMUNICATIONS/ICT FOR AFRICA INTERNATIONAL ROAMING SADC PERSPECTIVE

Africa s Time for ACTION. The Role of JAPAN in PIDA. Interconnecting, integrating and transforming a continent

Post Disaster Needs Assessment Guide and

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

National Disaster Risk Management Plan Disaster Management Centre Ministry of Disaster Management

Pilot Study on Big Data: Philippines. World Telecommunications/ICT Indicators Symposium (WTIS) November 2017 Hammamet, Tunisia

AFRICA S S DEMAND FOR INFRASTRUCTURE. ICA Senior Level Meeting January 17, 2007 Berlin, Germany

NAMA Fair COP 21, Paris December 2, 2015

Minneapolis Clean Energy Partnership Energy Vision Advisory Committee (EVAC) 4/16/2015

Contents USER S MANUAL 1

ENTSO-E working to fulfill the 3 rd Package

The Road to Paris. Towards the 2015 Climate Agreement

Mohinder Gulati Chief Operating Officer Sustainable Energy for All (SE4All)

Resolution adopted by the General Assembly. [on the report of the Second Committee (A/64/417)]

Implementation Status & Results Bangladesh BD Identification System for Enhancing Access to Services (IDEA) Project (P121528)

Status of REDD+ Readiness in Process in Ethiopia. Eyob Tenkir National REDD+ Secretariat, Ministry of Environment and Forest

DISCUSSION PAPER. Recommendations for a common UN System wide agenda on NCDs

The 10YFP Programme on Sustainable lifestyles and education

Physical Security Reliability Standard Implementation

International cooperation on power interconnection: Mongolian Regulatory perspective

Pan-Arab Interconnection and Development of Arab Power Markets

ESFRI Strategic Roadmap & RI Long-term sustainability an EC overview

Transcription:

Southern n Power Pool Energising the region for economic development 1 MONTHLY REPORT Issue No. R12-17 December 2017 CONTENTS Meetings, Workshops and Conferences.. 1 Welcome and Induction for SAPP Coordination Centre Manager... 1 SAPP Meeting with EOH... 2 SAPP Finance Working Group Meeting 2 System Operations... 2 System Disturbances... 2 Equipment Outage... 2 Technical... 2 SAPP Master Plan... 2 SAPP EAPP Transmission Integration Study... 3 SAPP Wheeling Charges and Transfer Limits... 3 Electricity Trading... 3 Energy Traded... 3 Market Clearing Prices... 3 Market Revenues... 4 Update on SAPP Projects... 4 Botswana - South (BOSA) Interconnector... 4 Angola Namibia Interconnector... 4 Zimbabwe Zambia- Botswana - Namibia (ZIZABONA) Interconnector... 4 Mozambique Zambia Transmission Project... 4 Kolwezi Solwezi Transmission Project... 5 Tanzania - Zambia... 5 Luapula Hydro Electric Scheme... 5 Environmental Corner... 5 Clean Energy Financial Mechanism Conference... 5 Upcoming Events... 6 Project Advisory Unit. SAPP Staff Members and Management Committee representatives Meetings, Workshops and Conferences SAPP Management and Management Committee representatives Welcome and Induction for SAPP Coordination Centre Manager The SAPP Coordination Centre Manager, Eng. Stephen Dihwa started work on 1 December 2017. An induction program was undertaken at the SAPP Coordination Centre and at the SAPP

2 were affected in that hour. Refer to Figure 1 below for the general outlook of reported SAPP system disturbances from December 2016. Eng. Stephen Dihwa, SAPP Coordination Centre Manager SAPP Meeting with EOH SAPP and EOH met on the 12 th of December 2017 for a kick-off meeting on the implementation of the migration of the SAPP Market Trading Platform into the cloud. Amongst other things, they discussed the environmental plan and setup of the system. The first phase of the system migration is expected to be completed in the 1 st week of February. SAPP Finance Working Group Meeting The SAPP Finance Working Group met on 14 December 2017 in Johannesburg, South. The Working Group reviewed the year /19 budget for the SAPP Coordination Centre including that for the SAPP Project Advisory Unit. The Working Group also reviewed the external audit compliance register. System Operations System Disturbances In the month of December 2017, one SAPP system disturbance was reported. A faulty current transformer (CT) in Zambia caused a 66 kv bus bar fault and subsequent loss of big customer load. Energy interchange on interconnectors Figure 1 - Reported SAPP System Disturbances Equipment Outage The 220 kv Victoria Falls Sesheke line in Zambia, which is in the path of the Zambia - Namibia interconnection, was taken out of service on 9 December 2017, to allow for commissioning works of new equipment at Victoria Falls Substation. The 330 kv Leopards Hill Kabwe line no. 3 in Zambia was taken out of service on 16 and on 17 December 2017 for maintenance. This reduced the power wheeling capacity to Copperbelt Energy Company in Zambia and Katanga region in DR Congo. The 330 kv Zimbabwe Zambia tie line no. 1 was taken out of service on 21 December 2017 to facilitate commissioning works of the new 300 MW Kariba South Extension power plant. Technical SAPP Master Plan The final report for the SAPP generation and transmission master plan was delivered in December 2017.

3 SAPP EAPP Transmission Integration Study The draft studies report covering the landscape, Market Analysis and Modelling, Preliminary Power System Studies, Trading Environment, and Operations and Planning was delivered by the Consultant. The EAPP and SAPP are reviewing the report and the details will be discussed at a workshop scheduled in February. Traded Volumes in MWh in DAM, IDM, FPM-W and FPM-M for the month of December 2017 SAPP Wheeling Charges and Transfer Limits Following the commissioning of new generation and transmission projects in 2017, the SAPP updated the wheeling charges, transmission losses factors, operating reserve requirements and transfer limits applicable for. Electricity Trading Energy Traded Trading in the market was marginally lower during the month of December 2017 when compared to November 2017. Total traded volumes on the Day Ahead market (DAM), intra-day market (IDM), Forward Physical Market Monthly (FPM-M) and Forward Physical Market Weekly (FPM-W) increased by 4.3% to 233,863.60 MWh in the month of December 2017, from the November 2017 volume of 224,142.40 MWh. Below is the overview of volumes traded in DAM, IDM, FPM-M and FPM-W for the month of December 2017. Market Clearing Prices Non off-peak prices increased by 1% from 5.772USc/KWh in November 2017 to 5.828USc /KWh in December 2017. Off Peak prices decreased by 1.9% from 2.726USc/KWh in November 2017 to 2.674USc/KWh in December 2017. The average price for the Peak period was higher by 3.9% at 8.87USc/KWh in December 2017 from the November average peak price of 8.54USc/KWh. Standard period average prices increased from the November 2017 average prices of 5.775USc/KWh to 6.049USc/KWh in December 2017. The average Off Peak price also increased by 5% from 2.65USc/KWh in November 2017 to 2.78USc/KWh in December 2017. The monthly average Day Ahead market clearing price (MCP) was slightly lower during the month of December 2017 at 4.69USc/KWh when compared to the 4.85USc/KWh recorded in November 2017.

4 Angola Namibia (ANNA) Interconnector The Angola Namibia Interconnector prefeasibility report was approved by the stakeholders covering the options and line route selection, market analysis, preliminary design, pre-feasibility financial analysis and cost estimates and potential commercial structures. The next stage is to carry out a detailed feasibility study. Daily Average MCP prices April 2017 to December 2017. The average peak spot price for the IDM for the month of December 2017 was 7.695 USc/KWh from the November 2017 average of 7.28 USc/KWh. The average standard price increased from 5.616 USc/KWh in November to 5.638 USc/KWh in December 2017. The average off peak price also increased from 2.675 USc/KWh in November to 2.909 USc/KWh in December 2017. Market Revenues A total of USD11,595,410.56 was exchanged on the DAM, IDM, FPM-W and FPM-M market during the month of December 2017 when compared to a total of USD11,030,820.93 exchanged in November 2017. The change is mainly attributed to changes in traded volumes. Zimbabwe Zambia- Botswana -Namibia (ZIZABONA) Interconnector The business case development, basic design and project cost estimates have now been produced. The funding for the construction will need to be secured and discussions are at an advanced stage for securing funding for the Zimbabwe- Zambia portion. As for the Zambia Namibia portion, SAPP PAU is working with the sponsors to develop a funding solution. An implementation agreement has been drafted and it is being reviewed by the sponsors. Mozambique Zambia Transmission Project This project consists of a 400 kv Interconnector between Mozambique and Zambia. Update on SAPP Projects Botswana - South (BOSA) Interconnector The commercial structure and options were presented by the consultant for discussions. The BOSA ESIA still needs to be approved. SAPP PAU hosted an environmental workshop for the environmental stakeholders from

5 Mozambique and Zambia. The PAU environmental specialist facilitated the meeting which resulted in a comprehensive understanding of the environmental procedures in the two countries. Technical assessments for the Feasibility Studies and the ESIA process were completed during the month. The No objection from the AfDB to appoint the consultants was obtained paving the way for contract signing. The implementation agreement, i.e. the Joint Development Agreement (JDA) was drafted and is currently being reviewed by the sponsors. The project is on track and within budget. The timelines for the ESIA and technical feasibility studies are indicated below: February : Kick Off meeting March : Inception Report September : Preliminary Feasibility Report May 2019: Final Feasibility Report September 2019: Final Design report SAPP PAU and the sponsors started business case development discussions and the project structures from a legal and financial perspective are being developed. Kolwezi Solwezi Transmission Project This is a transmission Interconnector between Democratic Republic of Congo and Zambia. The technical and environmental bids were evaluated. The No objection from the AfDB to appoint the consultants for the technical studies was obtained paving the way for contract signing. Tanzania Zambia Interconnector SAPP attended the presentation of the draft feasibility report by AECOM the consultants appointed by NELSAP. The final report has been issued after incorporating comments raised by the sponsors on the draft report. Luapula Hydro Electric Scheme This is a cascading Hydroelectric Scheme between DRC and Zambia on the Luapula River. The evaluation of the submissions for the technical feasibility study is complete. The kickoff meeting occurred in November 2017. The inception report was submitted in December 2017. The Feasibility Studies are currently on track and no delays are envisaged. Discussion with the sponsors on the financial and legal structuring has started. This will be followed up with a joint financial and legal meeting between the sponsors in February. On the ESIA, a consultant is still to be appointed. Environmental Corner Clean Energy Financial Mechanism Conference Meeting the long-term objective of the Conference of Parties 21 on Climate Change (COP 21, Paris Agreement) and the commitments made in Nationally Determined Contributions (NDCs) requires climate-resilient, low-carbon investments at an unprecedented speed and scale. The demand to finance these investments from countries such as the SAPP member states is large and growing and, if well planned, can support sustainable growth, improve livelihoods, create jobs while delivering climate benefits. There is abundant financial capital available but much of it is currently earning low or even negative returns. Public and private institutional investors have both the capacity and appetite to deploy massive amounts of capital to finance the green transition in emerging countries, but are hindered by a lack

6 of scalable investments, delivery vehicles, appropriate policy environments and risk mitigation mechanisms. In partnership with the Infrastructure Development Bank of Zimbabwe (IDBZ), the Reserve Bank of Zimbabwe (RBZ), the Ministry of Environment, Water and Climate, the SAPP and United Nations Climate Change (UNFCCC), convened the GREEN INVESTMENT CATALYST ROUND-TABLE at the Victoria Falls from 7 to 8 December, 2017. The main objective was to explore the possibility of using capital markets to channel more resources for low carbon, climate resilient development. DATE 13-14 Jan Upcoming Events EVENT IRENA Assembly, Abu Dhabi, United Arab Emirates 16 Jan Joint MSC OSC Meeting, Johannesburg, South 17 18 Jan MSC Meeting, Johannesburg, South The meeting was concluded with the agreement to develop the Clean Energy Fund for SAPP (CEF4SAPP) that would take the following approaches: 17-18 Jan Power Supply Emergency & Blackstart Working Group Meeting, Johannesburg, South Establish an advisory Ad-hoc Working Group to advice on CEF4SAPP; Develop the CEF4SAPP to aid the mainstreaming of Nationally Determined Contributions (NDCs) plans and policies within SAPP country economies, driving mitigation and adaptation/resilience ambition upwards Design the CEF4SAPP to provide funding for Renewable Energy generation, transmission and distribution including energy efficient initiative/measures to: include a demonstration pilot project; seek the endorsement of SAPP members (Management and Executive Committees) and relevant SADC member states (energy, water and environment); include a financial intermediary, accredited by the Green Climate Fund (GCF) and Green Energy Fund (GEF) 19 Jan Special Management Committee Meeting, Johannesburg, South 23 Jan Meeting on Clean Energy Financing between the SAPP and the UN Climate Change Secretariat, Harare, Zimbabwe 23 24 Jan 1-2 Feb 15 16 Feb, 6 8 Feb AFSEC/IEC Conformity Assessment Capacity Building Workshop, Johannesburg South Crime Prevention Working Group Meeting, Swaziland Integrated Demand Management Meeting, Namibia SAPP EAPP Transmission Integration Study Workshop, Dar es Salaam, Tanzania 20 21 Feb Energy Indaba, Johannesburg, South

7 26 Feb - 2 Mar 21 22 Mar 27 28 Mar April April 15-17 May 26-29 June Sept Oct SAPP Sub Committee & Management Committee Meetings, Lusaka, Zambia SAPP Executive Committee Meeting, Swaziland Power Electricity World, Johannesburg, South Quality of Supply Working Group Meeting, Johannesburg, South SAPP Human Resources Working Group Meeting, Gaborone, Botswana Utility Week, Cape Town, South IEEE PES- IAS Power Conference, Cape Town, South SAPP Sub Committee and Management Committee Meetings, Tanzania SAPP Executive Meetings, Zimbabwe