Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Similar documents
North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

ENMAX Power Corporation

Community Update. May 31, 2011

Community Update. June 8, 2011

Community Update. June 21, 2011

Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

STUDY REPORT #1 ADDENDUM

Community Update. June 30, Presented at: York Civic Centre

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

Downtown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary

Stakeholder Engagement Summary Report Vancouver Airport Fuel Delivery Project Fuel Receiving Facility October 13, 2015

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

Downtown Boise Multimodal Center

Subject YRRTC Accomplishments and Highlights

Baseline Bridge Crossing. Priorities Committee Meeting

PROJECT TIMELINE. Next steps. Plan. Start of Service

BC OnLine. Site Registry User s Guide. Last Updated June 11, 2014

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE

Discussion Guide. Benvoulin Substation Project.

Planning for Resiliency. June 20, 2017 Richard Tetreault, PE WSP USA Office Lead VT, NH, and ME

Dallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office

DESIGN CRITERIA MEMORANDUM

CITY OF VANCOUVER ADMINISTRATIVE REPORT

Environmental Impact Questionnaire

The Corporation of Delta COUNCIL REPORT Regular Meeting. Delta Fibre Optic Backbone Completion

Ells River Substation Telecommunication Tower

Infrastructure PA Stephen Lecce

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008

ENMAX Generation Portfolio Inc.

PARTICIPANT INVOLVEMENT PROGRAM

SWLRT Community Advisory Committee Meeting. June 27, 2013

System Expansion Implementation Plan. Board Meeting, April 2017

2018/ /21 SERVICE PLAN

Commercial Broadway Station Phase 2 Upgrades

Provo-Orem Bus Rapid Transit

AOA Model Project: Year 1 Progress Summary. Funded by FIA. Prepared for:

City Hall,18 th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2 NOTICE OF INTENDED PROCUREMENT

Cedar Rapids ITS Deployment Project

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM

ALBERTA TRANSPORTATION TENDER SCHEDULE

Vancouver Terminal Grain Storage Project. Feedback Form Inside. Community Engagement. October 1 19, 2012 PROJECT OV ERVIE W

Corridor Management Committee. January 12, 2017

Approval of Medical Center New Entrance Agreement

S T A F F R E P O R T

Subdivision Application Form

ROSS REGIONAL OPEN SPACE STRATEGY. Ecosystem Services Meeting June 12 th, Introduction to ROSS & Ecosystem Services Valuation Needs

Provincial Land Tax Reform

Cornerstone of downtown; Gateway to the state

Memorandum CITY OF DALLAS

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Land Information Ontario

2018 Priorities. Staff Lead Legend: 2 P age DCAO GMDS CAO GMEPW. Mayor and Council

Kansas Division. January 31, 2018

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

PUBLIC WORKS ORGANIZATIONAL CHART

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

Vegreville Office Telecommunication Tower Replacement

Project Information Form - Project Solicitation for the Round 1 Implementation Application

BALTIMORE UTILITY ASSET MANAGEMENT DIVISION

CONTINUUM PLANNING AND DEVELOPMENT TRUST. Urban Regional Environmental. constant reforms

Study Area and Location District PSA Ward ANC Phase Description A Proposed I-395 Southwest after Exit 4, Eastbound

RECORD OF PRE-APPLICATION MEETING FOR THE PROPOSED SANRAL PROJECT TO WIDEN THE N3 (AND PORTION OF N2) BETWEEN DURBAN AND PIETERMARITZBURG

What is Integrated Land Management?

Earthquake Preparedness

Northwest Needs Improvements Survey

CITY OF KIRKLAND TRAFFIC IMPACT ANALYSIS GUIDELINES

Overview September 7, 2017

Minutes of Meeting City of Mississauga Flooding Task Force Meeting No. 1

Benbow 397S Substation Upgrade Needs Identification Document

Lease of City-Owned Property at 455 Industrial Ave to United We Can

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

The Maryland Transit Administration. A Plan to Connect Baltimore

RCMP Support / Bylaw Services Department

Bill Jackson Asst. Statewide Utility Engineer, Office of Construction MDOT SHA

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton

Contractor Alliancing Sean Mooney Programme Manager

Development of Standardized Bridge Systems

Reston Town Center North Development. Community Update

Appendix C.6. Best Management Practices for Construction Activities

Metrolinx / Toronto Transit Plan April 28, Jack Collins Vice President, Rapid Transit Implementation

City of Airdrie Capital Budget & Plan

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

Annual Public Meeting Windsor, Ontario February 11, 2016

Why is Indiana using P3s?

Emergency Management Update. June 2018

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ]

First Coast Outer Beltway

Public Works 2017 Budget Presentation. Public Works What We Do

Applicant Type (Conditional Use Permit, Variance, Tract Map, etc.): Applicant: Address: Phone(s): Fax:

Applying Mitigation. to Build Resilient Communities

November 28, 2012 ALTERNATIVES ANALYSIS PUBLIC MEETING

Transcription:

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Welcome Thank you for attending this community engagement on the Trans- Canada Highway 1 West Project, part of the Highway 1 to Four-Laning Program. You can provide us with your feedback by: completing the hard-copy feedback form and leaving it with a member of our team filling out the feedback form online at: gov.bc.ca/bchwy1-projects mailing your feedback form to: nfrastructure ATTN: West Project 447 Columbia Street, BC V2C 2T3

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM The West project is a $162.7-million partnership between the Province of B.C. and the Government of Canada to upgrade six kilometres of the Trans-Canada Highway through the west side of the City of and the Neskonlith and Adams Lake ndian Reserves. The project will improve the safety and reliability of one of our most important commercial trade and tourist routes. Work will involve: four laning the highway with a better alignment building a new four-lane bridge over the Salmon River improving access with an interchange, intersection upgrades and new frontage roads improving safety with a pedestrian/cyclist trail network and wider shoulders installing median barrier along the highway

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM 50 Street NW SWTSEMALPH R#3 Segment 1 R#3 to 1 st Ave SW S h u s w a p L a k e The project segment boundaries have been adjusted to provide efficiencies with the phasing of construction contracts and to allow time for the acquisition of ndian Reserve land. Second Nations Road The project will be delivered in three phases: Segment 1: R#3 to 1st Avenue SW Four laning 2.8 km of highway First Nations Road SWTSEMALPH R#3 Segment 2: 1st Avenue SW to 10th Avenue SW Four laning 2.2 km of highway 10 th Avenue 1 th Avenue SW New nterchange Palmer Creek 1 st Avenue SW CTY OF SALMON ARM Salmon New Salmon River Bridge River SWTSEMALPH R#7 Leonard Creek CTY OF SALMON ARM 5 th Avenue SW Segment 3 10 th Ave SW to 10 th St SW Segment 3: 10th Avenue SW to 10th Street SW Four laning 1.1 km of highway Existing Salmon River Bridge Segment 2 1 st Ave SW to 10 th Ave SW 10 th Avenue SW

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Project Development Stages R#3 to 1st Avenue SW 1st Avenue SW to 10th Avenue SW 10th Avenue SW to 10th Street SW Conceptual Planning Preliminary Design Functional Design Detailed Design Tender & Construction Data Collection Develop Options Evaluate Options Design Shortlisted Options Value Analysis Re ne Designs Archeological Assessment Tender Drawings Construction Documents Early Works Construction Activities Risk Assessment Business Case First Nations Consultation Community Engagement Public Open House Road Safety Seek Partnerships Cultural Assessment First Nations Consultation Stakeholder Meetings Environmental Assessments Geotechnical Assessments First Nations Consultation Stakeholder Meetings Value Engineering First Nations Accommodation Property Acquisition Environmental Permitting Public Open House Major Works Construction Activities Archaeological, Cultural, and Spiritual Monitoring Community Engagement Community Engagement Public Open House Public Open House

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM n June 2015, the ministry held an open house to introduce the West project. Since then, the ministry has moved forward with design work based on public feedback and continuing consultation with the City of, First Nations, local businesses and property owners. The ministry began discussions with potentially affected property owners early in the project and has acquired most of the approximately 50 properties that are impacted. Acquisition of ndian Reserve #3 and ndian Reserve #7 lands is also required. n September 2016, the federal government announced its contribution of up to $48.5 million toward the project. Site clearing and building demolitions have taken place in preparation for construction. The first tender will involve placing preload materials to compress soft soils and relocating utilities from 1st Avenue SW to 30th Street SW. The ministry anticipates tendering this preload work this winter for construction in spring 2018.

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Segment 1: 1 Ave SW Glendale Road R#3 to 1st Avenue SW Features will include: First Nations Road mproved Access to R #3 and Residences Second Nations Road Extension Second Nations Road 2.8 km of four laning to increase safety and capacity for highway travellers mproved access to Switsemalph R#3 land mproved Access to R #3 and Residences Trans-Canada Highway 4 Lanes The ministry is working with the Neskonlith ndian Band to determine access road solutions and acquire the land needed for construction. SWTSEMALPH R #3 TCH Four Lane and Access Design Subject to Land Aquisition Negotiations with Neskonlith ndian Band R#3 to 1st Avenue SW, looking southwest

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM mproved Fully Signalized 10 Ave SW ntersection New Sidewalks mproved 30 St SW ntersection Wetland and Turtle Spawning Habitat Continuous Frontage Road New nterchange Multi-Use Path New Four Lane Bridge 30 St SW Multi-Use Path Continuous Frontage Road Service and Attraction Signs to be nstalled Trans-Canada Highway 4 Lanes Multi-Use Path Existing Salmon River Bridge Salmon River Road Segment 2: 1st Avenue SW to 10th Avenue SW Features will include: A new four-lane bridge Continuous frontage roads and improved 30th Street intersection between the new interchange at Salmon River Road and 10th Avenue SW to provide local mobility and safe customer access to businesses New sidewalks and a three-metre wide multi-use pathway to improve safety for pedestrians and cyclists 1st Ave SW to 10th Ave SW, looking south Service and Attraction Signs to direct motorists to businesses and attractions Work completed to date: Building demolitions Tree and brush clearing Construction of a new wetland and turtle-spawning habitat to mitigate for impacts to the environment

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Segment 3: 10 St SW mproved 10 St SW ntersection CTY OF SALMON ARM 10th Avenue SW to 10th Street Features will include: New 15 St SW ntersection Trans-Canada Highway 4 Lanes 10 Ave SW mproved intersections with dedicated left and right turn lanes at 10th Avenue SW and 10th Street SW A new intersection at 15th Street SW mproved Fully Signalized 10 Ave SW ntersection 17 St SW The ministry is working with the Adams Lake ndian Band to determine access road solutions and acquire the land needed for construction. 20 St SW SWTSEMALPH R #7 TCH Four Lane and Access Design Subject to Land Acquisition Negotiations with Adams Lake ndian Band Continuous Frontage Road 10 Ave SW Continuous Frontage Road 10th Ave SW to 10th St., looking northeast

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Rehabilitating the Salmon River Bridge Subject to an agreement with the City of, the old section of the Trans-Canada Highway including the existing Salmon River Bridge will become a municipal frontage road. The Salmon River Bridge was built in 1946 and widened in 1964. A 2015 independent engineering assessment determined that the bridge is in good condition and with some rehabilitation will provide another 20 to 25 years of service before further rehabilitation or replacement is needed. The ministry will carry out and pay for the bridge rehabilitation before the municipality takes over responsibility. The work is valued at up to $500,000 and would include: Repairing the abutment deck joints Repairing the concrete deck and curb Cleaning and re-coating steel stringers Repairing the stream bank and installing rip rap to protect against erosion

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Mitigating Flood Risk ncreased Culvert, Storm Drain, and Ditch Capacity New Four Lane Bridge Frontage Road Lowered to Reduce Flood Risk Existing Salmon River Bridge ncreased Culvert and Ditch Capacity Salmon River Road 10 Ave SW The new highway and frontage roads are designed to help protect the environment, infrastructure and neighbouring properties from floods and erosion. During a 200-year flood event: the new bridge will clear span the Salmon River and provide two metres of clearance, allowing debris to pass Shuswap Lake backs up the Salmon River to the existing TCH bridge girder, but the water velocity is low and not a significant risk to the bridge or roadway passage of flood water in the existing bridge area will be improved by lowering the frontage road elevation east of the bridge increased culvert, storm drain and ditch capacity will improve drainage on nearby roads and reduce flooding risk

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Mitigating Flood Risk Abandoned bridge piles will be removed from the Salmon River bed to improve flow and reduce debris jams during high water.

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Next Steps R #3 to 1st Avenue SW 1st Avenue SW to 10th Avenue SW 10th Avenue SW to 10th Street SW continue working with Neskonlith ndian Band to determine access solutions and acquire land needed for the project complete functional design start design work following completion of Land Use Plan advertise preload construction tender this winter begin preload construction in spring 2018 advertise grading and structures tender in spring 2018 continue working with Adams Lake ndian Band to determine access solutions and acquire land needed for the project begin construction in summer 2019

nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Thank you for attending. Please provide your feedback by: Completing the feedback form and leaving it with our team Filling out the feedback form online at gov.bc.ca/bchwy1-projects by December 17, 2017. Mailing your form to: nfrastructure ATTN: West Project 447 Columbia Street, BC V2C 2T3 Project information is available at: gov.bc.ca/bchwy1-projects