Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation

Similar documents
Busbar protection REB 670

Bus Protection Application Challenges

Substation Automation Products. High impedance differential busbar protection REB650 Relion 650 series

SPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS. G. Steynberg

Effective commissioning of bus bar protection systems using a dynamic simulation in the field

An Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems

1. Project Description

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series

SEL-487B. A Powerful Solution for Busbar Differential Protection. Bus Differential and Breaker Failure Relay

Redundant Bus Protection Using High-Impedance Differential Relays. Josh LaBlanc

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

We will discuss two types of loss-of-potential (LOP) logic during this presentation:

Substation Automation Products. Line differential protection RED670 Relion 670 series

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field

This application note describes configuring automatic bus transfer (ABT) logic with two V57 relays.

Sensitive definite time or inverse time earth-fault stage for back-up residual earthfault

Substation Automation Products. Bay control REC670/650 Relion 670 and 650 series

ELG4125: System Protection

PROTECTION, AUTOMATION & CONTROL

Network Configuration Document Selection for New Substations Framework

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements

Sensitive Earth-fault Relay SPAJ 111 C. Product Guide

Distributed bus protection application in a platform for process bus deployment in the SMART SUBSTATION

EE 868: Digital Techniques for Power System Protection. Laboratory Assignment #2 (Feb. 8 (12pm)) Overcurrent Relay Coordination

ABB Data Center Forum 2017

Power System Protection Laboratory Electric Power and Energy Engineering

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

Earth-fault Relay SPAJ 110 C. Product Guide

Substation Automation Products. Line distance protection REL670/650 Relion 670 and 650 series

CSC-150 Busbar Protection IED Technical Application Manual

System Protection and Control Subcommittee

Substation Automation Products. Transformer protection RET670/650 Relion 670 and 650 series

Application Techniques CENTERLINE 2100 Motor Control Centers

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION

Landsnet-Icegrid. Requirements for protection and control systems. Principles for the Icelandic power transmission network.

Use of frame agreement to standardize Protection in Digital Substation Automation Systems, Cooperation between Statnett and ABB

High impedance protection relay

Modern techniques for Protecting Busbars in HV networks

High Impedance Protection Relay SPAE010, SPAE011. Product Guide

Combined Overcurrent and Earth-fault Relay SPAJ 141 C. Product Guide

THE INTEGRATED TESTING SOLUTION

Christian Pinzon, ABB Power Grids The power of one solution for distributed busbar protection What s new in Relion REB500 version 8?

Combined Overcurrent and Earth-fault Relay SPAJ 140 C. Product Guide

Feeder protection relay SPAA 121 C. Product Guide

- Optional separate COMBITEST test switch for reliable and safe testing 1MRK BEN

Auxiliary Units for 7SR23 High Impedance Protection Energy Management

AUTOMATED TESTING OF BUSBAR DIFFERENTIAL PROTECTION USING A SYSTEM-BASED APPROACH. Christopher Pritchard, Florian Fink

CSC-150 Busbar Protection IED Product Guide

User s Guide REXA 103. General. 1MRK UEN Replaces UG E Version 1 August ABB Network Partner AB

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

User Manual. AQ-F215 Simulator

DGSZV-EP DIGITAL GALVANIC LONGITUDINAL DIFFERENTIAL PROTECTION. Application field

Numerical Protective and Management Relays

MiCOM Agile P746. Grid Solutions. Key Benefits. Numerical Busbar Protection. A Combination of Speed, Security and Selectivity. About MiCOM P40 Agile

Jehanpour Ranjkesh, Integrator Partner Seminar 2012 Station level product news Automation Controller COM600

Bus Bar Protection Applications Seminar

3a. IEM Indoor Metal Clad Medium Voltage Switchgear 25KV a. Section INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

WHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION. Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District

DGBV-EP DIGITAL GENERATOR AND GENERATOR-TRANSFORMER UNIT PROTECTION. Field of application

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

ABB static var compensator stabilizes Namibian grid voltage

About Georgia Transmission Corporation (GTC)

MMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A

Innovation on Medium Voltage Switchgear

Power systems 5: Protection

1S20. Arc Fault Monitor Relay. Features. Introduction. ARC Fault Protection

Commission Testing Methods for Protection Systems

Using the Bitronics 70 Series to Improve Local Monitoring and Control

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

Hierarchical protection control system of smart substations

Evaluation of different solutions of faulted phase earthing technique for an earth fault current limitation

Bus Differential and Breaker Failure Relay. Advanced bus protection with built-in breaker failure detection

Bus Differential and Breaker Failure Relay. Advanced bus protection with built-in breaker failure detection

Relion 605 series. Self-powered feeder protection REJ603 Product Guide

A Current Based, Communication Assisted High Speed Protection System to Limit Arc Energy. Patrick Robinson Altelec Engineering

Grid Automation Controller COM600 How it fits into the Smart Grid?

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.

Applications of Automated Protective Relay Testing. Josh LaBlanc

Transformer Protection and Control RET630 Numerical transformer protection in medium voltage networks

DIGITAL RELAY OF PROTECTION AND AUTOMATION SERIES PC83 AND PC830

Bus Differential and Breaker Failure Relay. Advanced bus protection with built-in breaker failure detection

Power Transmission Division Link between power generation and distribution

Bus Bar Protection Relay B-PRO 4000

Protection relays.

OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER

TFS 2100 Traveling Wave Fault Location System

Implementing the protection and control of future DC Grids

Residual overvoltage relay

This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB

SYMPATHETIC INRUSH PHENOMENA IN PARALLEL AND SERIES CONNECTED TRANSFORMERS USING PSCAD

SIA-C. Overcurrent and Earth Fault Protection Relay for Secondary Distribution. Dual & Self Powered. Main characteristics

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

SIPROTEC 5 Application Note

Arc protection relay. Features Three-phase overcurrent function. Application

Date of Publication: THREE PHASE LINE FAULT DETECTION ON DISTRIBUTION LINES USING GSM TECHNIQUE

Standard Development Timeline

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

Synchro-check relay. Application

USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION

Transcription:

111 Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation Z. Gajić (ABB, Sweden) JP Wang / PW Gong / YS Xu (ABB China) ZX Zhou (CERPI, China) Summary Power utilities are aware of the specific characteristics and requirements for their network. For this reason, they may require additional functionalities from the protective devices and secondary systems included in their power network. Therefore State Grid Cooperation of China (SG) requires a number of specific tests to be conducted on the protection system proposed for a particular application to prove the suitability of the proposed protection system for the specific application. Only when all of these tests are successfully passed, the protection system is certified for use in State Grid s network which has 70% of total installed capacity of China. China Electric Power Research Institute (CEPRI) is given the tasks for carrying on this type of dynamic tests to check if the protection system can fulfil SG s requirement by using the power system dynamic simulator in CEPRI s test centre. Keywords Relay Protection, Busbar Protection, Differential Protection 1 Introduction The 500kV busbars are extremely important nodes in State Grid s transmission network. Thus, busbar protections for these stations have to fulfil very strict requirements, which are set down by the China national testing standards. Two typical station layouts are used in the busbar protection tests, mainly one-and-a-half breaker station and double-bus single-breaker station with a bus coupler bay [1]. The numerical busbar protection has been tested on an analogue power system simulator in order to verify that it can handle both station configurations. Different operating conditions for the busbar protections have been tested as listed below: Internal and external metallic faults (i.e. without fault resistance) Internal faults with fault resistance Evolving faults Circuit Breaker Failure Faults during a power swing in a network Internal and external faults during active load-transfer for double-bus single-breaker station layout CT saturation for external faults Open CT secondary circuits Line and power transformer energization Internal and external faults during off-nominal power system frequency condition 111-1

Special test for one-and-a-half breaker station (internal faults with out-feed currents) DC power switching (off/on) while relay is in service and busbar is loaded Altogether 1528 test cases on an analogue power system simulator were performed [1]. The behaviour of the numerical busbar differential protection IED [2] during these operating conditions will be presented. Some of the results will be presented by using the captured disturbance files. 2 Relay Operating Principles The basic concept for any bus differential relay is practically a direct use of Kirchoff s first law that the sum of all currents connected to one differential protection zone shall be zero. If that is not the case, an internal fault has occurred. In other words, as seen by the busbar differential protection the sum of all currents which flow into the protection zone (i.e. currents with positive value) must be equal to the sum of all currents that flow out of the protection zone (i.e. currents with negative value), at any instant of time. Such interpretation enables quite efficient implementation of a numerical bus differential relay algorithm, because any differential zone can be represented by just three quantities, as shown in Figure 1, regardless the number of actually connected feeders. Here: Figure 1: Representation of the bus differential protection zone i in is total instantaneous incoming current flowing into the bus i out is total instantaneous outgoing current flowing from the bus i d is instantaneous differential current By looking into the property of only three quantities it is possible to make a numerical busbar differential protection relay which can: Operate quickly for internal faults due to the fact that i in becomes much larger than i out during an internal fault (i.e. current flows into the faulty bus but it doesn t flow out from the faulty bus) Remain stable for external faults followed by CT saturation due to a fact that for short period of time, immediately after the fault current zero crossing, i in will be equal to i out (i.e. before any CT goes into saturation) Detect an open CT secondary circuit in any one of the connected feeder CTs when one of i in or i out remain unchanged while the other experiences a sudden drop in magnitude 111-2

These are actually the very similar methods used by analogue, moderate impedance bus differential relay which has been successfully used in practice for many years [3]. For more information regarding numerical implementation please refer to [2]. 3 Relay Test Setup 3.1 Double-bus single-breaker station layout For the double-bus single-breaker station layout four feeder bays and one bus-coupler bay were used during the testing. Only the disconectors auxiliary contacts and CT input (three of them with ratio 2500/1 and one with ratio 1250/1) were available from each feeder bay. From the bus-coupler bay only one CT set (with ratio 2500/1) and auxiliary contacts of the CB were available to the busbar protection during the testing. The five fault positions were used: Internal fault on Busbar I Internal fault on Busbar II Internal fault in Dead-zone between bus-coupler CB and between bus-coupler CT External fault on Feeder 1 External fault on Feeder 3 3.2 One-and-a-half breaker station layout For the one-and-a-half breaker station layout two full diameters (e.g. altogether four feeders) were used during the testing. Only four CT inputs, all with ratio 2500/1 A, were connected to the busbar protection. The four fault positions were available as follows: Internal fault on Busbar I Internal fault on Busbar II External fault on Feeder 1 (locates as upper feeder in the first diameter) External fault on Feeder 3 (locates as upper feeder in the second diameter) Additional fifth feeder, with CT ratio 2500/1 was connected to the lower busbars in order to test internal faults with out-feed conditions. During all tests busbar differential protection operated as required. Table 1 provides overview about all test results. 3.3 Busbar Protection Settings Only the most important setting parameters will be presented here. During all tests the differential protection minimum pickup level was set to 800A primary. The differential protection slope is fixed to 0.53 and can not be changed by the end user. The built-in open CT detection feature was set to 200A primary. Same settings were used for both differential zones. Pickup for built in breaker failure protection was set to 250A primary with time delay t2=0,15s. 4 Testing Results During all tests busbar differential protection operated as required. Table 1 provides short overview about all tests: 111-3

TABLE I: Summary of test results Test Point Test Description Relay Performance Internal and external metallic faults Internal resistive faults Evolving faults External faults with CT saturation Faults during active loadtransfer Power swing and faults during power swing Open secondary CT circuits Energising of a bussection, line and transformer Faults during off-nominal frequency conditions Special test for one-anda-half breaker station layout Circuit breaker failure DC supply power off/on test All types of internal and external faults without fault resistance were simulated. Internal single-phase-to-ground fault with fault resistance of 100Ω and phase-to-phase fault with fault resistance of 25Ω. External fault evolves into internal fault with different evolving time (i.e. 10-200ms). Internal fault in one section evolves into internal fault on the other section with different evolving time (i.e. 10-200ms). Simultaneous double internal faults in both busbar sections. Simulate all types of external faults followed by a CT saturation in the faulty feeder. Internal and external faults were applied while one feeder bay was simultaneously connected to both busbar sections Cause dynamic power system instability in the tested system with the centre of a power swing close to the protected busbar. Apply internal and external faults during the swing. Open one phase of a loaded CT on its secondary side. Apply internal and external faults after that. Energise a healthy bus-section via bus-section CB. Energise a line. Energise a transformer. Energise a fault bus-section via bus-section CB. Apply internal and external faults during off-nominal frequency conditions (e.g. 48Hz & 52Hz) Internal fault situation in which current flow out from the faulty busbar. Bus-coupler CB failed to trip for internal busbar fault. Feeder CB failed to trip for external fault. During normal through-load condition DC power supply to the relay was switched off and on. * Operating time measured by external recorder (include relay trip output contact time) faults. Protection operated selectively for all internal faults. Operating time was from 11.2ms to 19.0ms* Protection operated correctly for all fault types. For single-phase-to-ground faults operating time was from 15ms to 27.5ms and for phase-to-phase fault operating time was from 12ms to 20ms* faults. Protection operated selectively when fault evolves into internal. Protection remained stable for all test cases. Fastest time to saturation achieved during testing was 2.8ms Protection correctly tripped both busbar sections for all internal faults. Protection remained stable for all external faults. faults. Protection operated selectively for all internal faults. Protection could detect the open CT circuit in all test cases. Behaviour for consecutive internal/external faults was in accordance with the relay setting. Protection behaved as expected during these tests (e.g. remained stable and only tripped when energising a faulty bussection) faults. Protection operated selectively for all internal faults. Protection operated selectively for such special internal faults. Protection correctly tripped all adjacent breakers for all CB failure test cases. Protection behaved as expected during these tests (e.g. remained stable) 111-4

Three selected test cases are presented. Disturbance files captured by busbar protection relay are used in the following figures. In Figure 2 external fault followed by faulty feeder CT saturation is presented. The relay remained fully stable for this external fault. In Figure 3 internal fault is presented. The relay operated quickly in less then half-a-cycle. In Figure 4 evolving fault is presented. The relay operated quickly once the fault becomes internal. Feeder #3 Current Waveforms Current [ka] 40 IL1 IL2 20 IL3 0 20 40 4 4.5 5 5.5 6 Time [Cycles] Figure 2: Faulty feeder CT saturation for external fault Feeder #4 Current Waveforms Current [ka] 40 IL1 IL2 20 IL3 BBP_TRIP 0 20 40 0 2 4 6 8 10 Time [Cycles] Figure 3: Internal L3-to-ground fault Feeder #4 Current Waveforms Current [ka] 50 IL1 IL2 IL3 BBP_TRIP 0 50 0 2 4 6 8 10 Time [Cycles] Figure 4: External L3-to-ground fault evolves into internal L2-to-ground fault 111-5

5 Conclusion After all these tests, the protection relay [2] was officially approved by CEPRI to be used for busbar protection applications in China for all voltage levels up to and including 500kV. References [1] CEPRI Inspection and Test Report, Document No: 2006008 [2] ABB Document 1MRK 505 178-UEN, "Technical reference manual, Busbar Protection IED REB 670", Product version: 1.1, ABB Power Technologies AB, Västerås, Sweden, Issued: March 2007 [3] T. Forford and J.R. Linders, A Half Cycle Bus Differential Relay and its Application, IEEE Transaction on Power Apparatus and Systems, Vol.PAS-93, July/Aug. 1974. 111-6