INCREASING electrical network interconnection is

Similar documents
5 member consortium o University of Strathclyde o Wideblue o National Nuclear Laboratory o Sellafield Ltd o Inspectahire

ACTIVE NETWORK MANAGEMENT FACILITATING THE CONNECTION OF DISTRIBUTED GENERATION AND ENHANCING SECURITY OF SUPPLY IN DENSE URBAN DISTRIBUTION NETWORKS

NIA Progress Report. Programme Summary. 31 July Electricity North West/NIA Programme Summary/31 July 2016 Page 1 of 10

A hybrid slurry CFD model: Euler-Euler to Euler-Lagrange (in development)

Data and Forecasting Summary

Network Configuration Document Selection for New Substations Framework

Toronto Hydro-Electric System Limited EB Exhibit G1 Tab 1 Schedule 1 ORIGINAL Page 1 of 15 SMART GRID PLAN

Project Initiative on GIS-based Tool for Grid Connection Planning. in Thailand Power Network

Third Generation System of the Future

Siemens FuseSaver New half-cycle circuit breaker for rural smart grids to minimize operating costs of feeder and spur lines

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

Minimising the Impact of Disturbances in Future Highly-Distributed Power Systems

University of Strathclyde

Validating Secure and Reliable IP/MPLS Communications for Current Differential Protection

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

Blair, Steven Macpherson (2015) Beckhoff and TwinCAT 3 System Development Guide. [Report], Strathprints

Application of Distributed Intelligence to Automatic Distribution Reconfiguration for Reliability Improvement

Smart Distribution Technology

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

MR. PATRICIO CHRISTIAN VALENZUELA VÁSQUEZ Mobile: SUMMARY

RECONSTRUCTION OF LOW VOLTAGE DISTRIBUTION NETWORKS: FROM GIS DATA TO POWER FLOW MODELS

Building resilience by connecting the dots

Memorandum. This memorandum requires Committee action.

Power Networks Demonstration Centre

Cost and performance implications of infrastructure investment options in the Eskom Distribution network

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region

Academic Leadership and Research in Energy Networks. Stephen McArthur University of Strathclyde

Visual Pose Estimation and Identification for Satellite Rendezvous Operations

Blair, Steven Macpherson and Booth, Campbell (2013) Real-time teleprotection testing using IP/MPLS over xdsl. [Report], Strathprints

Voltage Measurement Accuracy Assessment System for Distribution Equipment of Smart Distribution Network

Grid Interconnection of Renewable Generation

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014

EPRI GIS Interest Group GIS Data Correction

Powering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,

3 General Information Requirements Information requirements can be divided into two categories:

STCP22-1 Issue 003 Production of Models for GB System Planning

Exploiting Multi-agent System Technology within an Autonomous Regional Active Network Management System

OC IEEE IAS/PES Meeting February 21, 2013

IntelliTeam II Automatic Restoration System

HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Executive summary 2. Appendix A - Flexible networks for a low carbon future background 25. Appendix B Selected network group details 27

Auto-Check Circuit Breaker Interrupting Capabilities

The need for a fundamental review of electricity networks reliability standards SMARTGRIDS SECURITY AND RESILIENCE TASK FORCE - WHITE PAPER 2016

Gamma Service Incident Report Final 18/9/14

This webinar brought to you by the Relion product family

Fortum SGEM Program Presentation of ongoing research activities

MODERN-PLANNING TOOLS CONNECTED WITH GEOGRAPHIC INFORMATION SYSTEM IN UTILITY COMPANY

Demonstration Test Bed for Advanced Control Systems

Fair and Effective Management of DNO Connection Queues: Treatment of Requests to Change Connection Applications. Good Practice Guide

SCHEDULE 22 COMMON CONNECTION CHARGING METHODOLOGY

Generation, Transmission, and End User Facilities

Chapter 2 Communication for Control in Heterogeneous Power Supply

SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality,

ASSET RISK MANAGEMENT Criticality Framework

Distribution Long Term Development Statement

MODULAR HUB AND SPOKE 17 NOVEMBER 2017

Smart Grid Development in Ho Chi Minh City

Generation Interconnection Feasibility Study Report

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Modernization of the National Wide Dispatch Centers of CADAFE - Venezuela

UNDERGROUND HV SUBSTATION DESIGN

EPRI Research Plan for Advanced Distribution Automation. Mark McGranaghan Vice President EPRI Solutions, Inc

Challenges in Delivering the Smart Grid

Strathprints Institutional Repository

FCIs reduce fault-locating times and improve reliability metrics, especially the Customer Average Interruption Duration Index (CAIDI).

INTERCONNECTION FACILITIES STUDY REPORT

KEDS DSO Development Plan. George Karagutoff, KEDS CEO Prishtina, Kosovo 20 March, 2018

Exhibit to Agenda Item #1a

Application of MPLS-TP for Transporting Power System Protection Data

Integrating IEC & IEEE 1815 (DNP3)

Volt/VAR Control Options and How to Leverage AMI Data

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Feasibility Study on Load Flow and Short Circuit Project

PRC Coordination of Protection Systems for Performance During Faults

SurvalentONE Distribution Management System

COLLABORATE TO WIN. 03/31/2017 Digital Substation Turning IEC61850 features into benefits. Peter Rietmann, Program Manager Digital Substation NA

February Investor Presentation

CHAPTER 11 HOW TO ENHANCE THE RELIABILITY & POWER QUALITY OF ELECTRICITY SUPPLY

Owner/Operator Forum 12 December

October 2017 INVESTING FOR THE FUTURE. NIE Networks summary business plans

Power systems 5: Protection

Final Determination: Criteria for Assessing Material Inter- Network Impact of Transmission Augmentations

SDG&E s EPIC Demonstration Projects on Emerging Communication Standards. IEC Europe 2017 Conference. Frank Goodman, SDG&E EPIC Program Manager

Generation Interconnection Feasibility Study Report


Cooper Controls Group. The power to drive industry

POWER SYSTEM DATA COMMUNICATION STANDARD

Bus Protection Application Challenges

Quantum Chargers Enhanced AC Line Transient Immunity

Tutorial: Active Network Management

Regional Group Nordic GRID DISTURBANCE AND FAULT STATISTICS

PG&E Transmission Interconnection Handbook

1. Project Description

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

Developing a Roadmap for A Smart(er) and Strong Transmission Grid

What You Should Know About Communication Systems: Business Strategies and Options

Transcription:

Blair, Steven Macpherson and Booth, Campbell and Turner, Paul and Turnham, Victoria (2013) Analysis and quantification of the benefits of interconnected distribution system operation. In: 5th International Conference on Advanced Power System Automation and Protection, 2013-10-28-2013-10-31, Hyatt Regency Jeju Hotel., This version is available at https://strathprints.strath.ac.uk/46658/ Strathprints is designed to allow users to access the research output of the University of Strathclyde. Unless otherwise explicitly stated on the manuscript, Copyright and Moral Rights for the papers on this site are retained by the individual authors and/or other copyright owners. Please check the manuscript for details of any other licences that may have been applied. You may not engage in further distribution of the material for any profitmaking activities or any commercial gain. You may freely distribute both the url (https://strathprints.strath.ac.uk/) and the content of this paper for research or private study, educational, or not-for-profit purposes without prior permission or charge. Any correspondence concerning this service should be sent to the Strathprints administrator: strathprints@strath.ac.uk The Strathprints institutional repository (https://strathprints.strath.ac.uk) is a digital archive of University of Strathclyde research outputs. It has been developed to disseminate open access research outputs, expose data about those outputs, and enable the management and persistent access to Strathclyde's intellectual output.

Analysis and Quantification of the Benefits of Interconnected Distribution System Operation Steven M. Blair, Campbell D. Booth, Paul Turner, and Victoria Turnham Abstract In the UK, the Capacity to Customers (C 2 C) project is underway to determine the potential benefits of increased interconnection in distribution systems, combined with demand side response technology. Managed contracts with customers, i.e., the agreement that certain loads are interruptible following system faults, allows distribution circuits to be loaded beyond the limits presently required for security of supply. This potentially permits load growth but avoids the cost and environmental impact of conventional network reinforcement. This paper provides the results of electrical system modelling to quantify the benefits of the C 2 C operation, using actual circuit data and typical load distributions. Based upon simulations of these circuits, it is shown that increased interconnection generally leads to minor improvements in electrical losses and system voltage. By connecting managed (i.e., interruptible) loads, circuits typically can be loaded significantly further than the present practice in the UK an average increase of 66% for radial operation and 74% for interconnected systems. Index Terms Automation and control, demand side response, distribution, interconnection, load flow. I. INTRODUCTION INCREASING electrical network interconnection is presently of interest for both transmission and distribution systems [1]. For distribution systems, interconnection offers several potential benefits, including: increased capacity for connecting load and generation, and therefore deferral or avoidance of network reinforcement costs; greater flexibility in the use of the available capacity; improved voltage profiles and voltage support; and reduced losses and voltage harmonic distortion due to lower system impedance. This is particularly relevant in the UK where 6.6 kv and 11 kv ring circuits, operating as two radial feeders, are common [2]. This paper quantifies the benefits of increased network interconnection, within the context of the Capacity to Customers (C 2 C) project [3] presently being led by Electricity North West Limited in the UK. The project involves a consortium of ten industrial and academic partners. The aim of the C 2 C Project is to test new technology, network operational practices (i.e., increased network interconnection), and commercial demand response contracts. These changes will allow the network operator to increase the loadings on a selection of trial circuits representing approximately 10% of its 6.6/11 kv network without resorting to conventional network reinforcement. The project will thereby release inherent spare capacity in the S. M. Blair and C. D. Booth are with the Institute for Energy and Environment, Department of Electronic and Electrical Engineering, University of Strathclyde, Glasgow, G1 1XW, UK (e-mail: steven.m.blair@strath.ac.uk). P. Turner and V. Turnham are with Electricity North West Limited, Salford, Greater Manchester, M6 6QH, UK. 6.6/11 kv system in order to accommodate the future forecast increases in demand, whilst avoiding (or deferring) the cost and environmental impacts that are associated with traditional network reinforcement. This paper focuses on the analysis of the effects of C 2 C operation on electrical losses, the circuit voltage profile, and the available network capacity. This has been achieved using real system data for a representative proportion of the trial circuits. II. PROJECT BACKGROUND Fig. 1 provides a simplified overview of the aims of C 2 C. Spare capacity normally reserved for use during circuit outages when the system is operating in a reconfigured state, typically through a shift in the location of the normallyopen point (NOP) will be offered to new customers. This is possible due to a derogation from the normal requirements for security of supply in distribution networks in the UK, governed by Engineering Recommendation (ER) P2/6 [4]. By closing NOPs during normal system operation, additional loads with managed contracts for post-fault conditions can be connected: effectively sharing the capacity available from both radial feeders and avoiding or deferring the need for network reinforcement. The managed contracts permit the C 2 C loads to be interrupted following fault conditions for a defined period of time. As depicted in Fig. 1b, by closing the NOP, it is also possible to connect a single large load using the spare capacity from both radial feeders (where each feeder has a maximum thermal capacity for 6 MVA of load). Network automation is important for ensuring correct and timely restoration of customers after faults, and for managing the available capacity. A field trial of C 2 C operation is presently underway, involving 180 ring circuits throughout the Electricity North West network, as shown in Fig. 2. These circuits have been selected due to their relatively low historical rates of fault occurrence, and to ensure that excessive fault levels are not introduced by closing NOPs; these practical conditions would also be applicable if the C 2 C method is offered beyond the trial period. From the 180 trial circuits, 36 circuits have been selected for detailed monitoring and analysis. A. Circuit Data III. ELECTRICAL SYSTEM MODELLING Data have been combined from a variety of sources, including: detailed distribution network data (including the full electrical topology) in a legacy format; cable and overhead line capacity ratings and impedance values; and historical loading

(a) Conventional radial operation, with no usable spare capacity (emergency capacity not presently offered to customers) Fig. 2. Map of C 2 C trial locations highlighted in yellow, from [5] (Map data 2013 GeoBasis-DE/BKG ( 2009), Google) (b) C 2 C operation, with additional capacity for interruptible loads (large, single load) Fig. 3. Example half-hourly feeder current, 1 st January 2012 (c) C 2 C operation, with additional capacity for interruptible loads (distributed load growth) Fig. 1. Capacity increase due to C 2 C network operation data for all of the year 2012. Fig. 3 and Fig. 4 illustrate typical load current values for two radial feeders which form a ring circuit. IPSA [6] has been used as a platform for integrating the data sources, as well as providing load flow functionality for analysing the performance of the selected ring circuits. Fig. 5 summarises the process of integrating the data sources and generating results. This process is fully automated for all 36 ring circuits. The circuit loading data (as shown in Fig. 4) are processed to interpolate missing data values, although less than 0.5% of load current values are missing due to issues with the SCADA system or otherwise. The mean and peak annual loadings for each feeder are calculated and extracted. The electrical network data is imported into IPSA. Although IPSA has legacy data import functionality, this process has been significantly extended to cater for the requirements of

Fig. 5. IPSA import process Primary 6.6 kv busbar Fig. 4. Example daily mean feeder current, for 2012 this investigation. A geographically-accurate IPSA model of each ring circuit is generated, as illustrated in Fig. 6. Each substation, represented by blue dots in Fig. 6, has a load connected. For simplicity, it is assumed that no distributed generation is connected to the system. A script is executed within the IPSA scripting environment to: 1) Validate the electrical connectivity of the models. 2) Remove necessary elements from each model. 3) Connect a generator to the primary busbar to represent the grid infeed. 4) Determine the load scaling factor which matches the historical loading data for each feeder (based on either the annual mean or annual peak loading data). 5) Perform load flows, in both radial and interconnected configurations, and generate the results. B. Typical Circuit Results Fig. 7a and Fig. 7b illustrate typical load flow results using IPSA, with the system operating in radial and interconnected configurations, respectively. A. Losses IV. RESULTS Fig. 8 summarises the effect of C 2 C operation on electrical (I 2 R) losses, by extrapolating the reduction in total annual losses resulting from interconnected ring circuit operation (relative to radial operation). The majority of ring circuits exhibit NOP Fig. 6. Example of IPSA model of a ring circuit (blue dots represent substations) Fig. 8. Histogram of reduction in annual losses

(a) Load flow radial configuration, mean loading Fig. 7. Example load flow results (b) Load flow interconnected configuration, mean loading an annual reduction in losses of approximately 5 MWh with the C 2 C configuration, assuming mean loadings. This equates to a modest reduction in the mean distribution losses, for the 6.6/11 kv ring circuits under study; the mean total losses are reduced from 0.57% (radial) to 0.53% (interconnected). B. Voltage Fig. 9 illustrates the effect of interconnected operation on the minimum voltage experienced at any point in the ring circuit, at peak loading. These data include all spurs which branch off from the main circuit, which may experience lower voltages than the voltage at the NOP. In most cases, the minimum voltage shows an improvement due to interconnected operation, even at peak loading. C. Capacity The potential capacity available by adopting C 2 C operation has been determined from the maximum possible additional interruptible load which can be connected, assuming that the load growth is distributed evenly throughout each ring circuit. Initially, each circuit is loaded to the conventional (i.e., according to ER P2/6) maximum capacity for non-interruptible loads. In each case, the load is increased until either: 1) A cable or line thermal headroom (i.e., the remaining thermal capacity) constraint is reached, or 2) A steady-state bus voltage constraint is reached (voltage less than 95% nominal voltage). TABLE I COMPARISON OF CIRCUIT CONSTRAINT TYPES Radial operation Interconnected operation Voltage constraints 22% 17% Thermal constraints 78% 83% The results are provided in Fig. 10. Approximately 80% of circuits are limited by a thermal constraint rather than a voltage constraint, as given in Table I. For interconnected operation, a mean increase in loading of 74% is possible, compared with 66% for radial operation; this can be attributed to the reduced occurrence of voltage constraints as shown in Table I. For circuit 16 in Fig. 10, which is a rural network with a significant presence of relatively long overhead lines, the system presently operates close to the voltage limit and there is no prospect for directly adding any interruptible load (without also implementing other measures to support the network voltage). V. CONCLUSIONS The results arising from the analyses of several circuits show that there generally are benefits to distribution losses and voltage support from increased interconnection, but these gains are often marginal. By allowing the connection of interruptible loads, the available capacity for distributed load is significantly

Fig. 9. Summary of difference in minimum voltage for C 2 C operation Fig. 10. Possible increase in circuit capacity resulting from C 2 C operation increased, by approximately 74%. Interconnected operation yields a further improvement in the available capacity, as well as potentially permitting the use of spare capacity from both radial feeders. Further work will analyse the impact of interconnection when connecting distributed generation and the feasibility of connecting single, large loads without requiring conventional network reinforcement. The effects of C 2 C operation on power quality will be evaluated, using data captured from power quality monitoring equipment during the trial. REFERENCES [1] J.-C. Kim, S.-M. Cho, and H.-S. Shin, Advanced Power Distribution System Configuration for Smart Grid, IEEE Transactions on Smart Grid, vol. 4, no. 1, pp. 353 358, Mar. 2013. [2] I. Chilvers, N. Jenkins, and P. Crossley, Distance relaying of 11 kv circuits to increase the installed capacity of distributed generation, IEE Proceedings - Generation, Transmission and Distribution, vol. 152, no. 1, p. 40, Jan. 2005. [3] Electricity North West Ltd., Electricity North West Capacity to Customers (C2C) project, 2013. [Online]. Available: http://www.enwl.co.uk/c2c [4] ENA, Engineering Recommendation P2/6 - Security of Supply, Tech. Rep., 2006. [5] Electricity North West Ltd, C2C - Postcode search, 2013. [Online]. Available: http://www.enwl.co.uk/c2c/are-you-affected/postcode-search [6] TNEI Services Ltd, IPSA Power, 2013. [Online]. Available: http://www.ipsa-power.com/ Steven M. Blair received the M.Eng. degree (with distinction) in computer and electronic systems in 2008, and the Ph.D. degree in electrical engineering in 2013 from the University of Strathclyde, Glasgow, U.K. He is currently a Research Associate at the University of Strathclyde. His research interests include power system protection, fault current limitation, marine electrical systems, communications, and real-time simulation. Campbell D. Booth received the B.Eng. and Ph.D. degrees in electrical and electronic engineering from the University of Strathclyde, Glasgow, U.K, in 1991 and 1996, respectively. He is currently a Senior Lecturer with the Institute for Energy and Environment, Department of Electronic and Electrical Engineering, University of Strathclyde. His research interests include power system protection; plant condition monitoring and intelligent asset management; applications of intelligent system techniques to power system monitoring, protection, and control; knowledge management; and decision support systems. Paul Turner joined United Utilities (subsequently Electricity North West) as a graduate engineer in 1999. Since then he has carried out a variety of roles in the control environment, such as outage planning manager and automation development manager. Paul is an authorised control engineer and is currently the technical manager for the Tier 2 Low Carbon Network Fund project, CLASS.

Victoria Turnham graduated from the University of Manchester in 2008 with a masters degree in electrical and electronic engineering. Since joining United Utilities (subsequently Electricity North West), Victoria has gained experience in EHV strategic network planning and more recently has worked on the technical and research elements of a Tier 2 Low Carbon Network Fund project, Capacity to Customers (C 2 C).