Enclosure: Pasco County Ridge Road Extension Monthly Status Report

Similar documents
Corridor Management Committee. January 12, 2017

Task Name Duration Start Finish Predecessors. Inactive Summary. Manual Task. Duration-only. Manual Summary Rollup. Manual Summary.

Unified Development Code. Public Workshop No. 3 November 7, 2017

Quanta Resources Corporation Superfund Site, Operable Unit 1 (OU1) Edgewater, New Jersey Progress Report July 2015

Reston Town Center North Development. Community Update

Pennington County Government Justice Center. Schematic Design - October 27, 2015

Case 1:98-cv CKK Document Filed 06/15/2006 Page 1 of 7 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

Dallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office

IATF Transition Strategy Presenter: Mrs. Michelle Maxwell, IAOB

IATF Transition Strategy Presenter: Cherie Reiche, IAOB

U.S. General Services Administration Planned Refresh of TDR Pilot Schedules / SINS

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

Dulles Area Transportation Association

MAJOR PROJECTS STRATEGY

EBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston

Specific topics covered in this brief include:

SECTION 106 ACTIVITIES ANNUAL REPORT

DEPARTMENT OF THE ARMY *ER U.S. Army Corps of Engineers CECW-EC Washington, DC Administration PROJECT SCHEDULES

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

2015 Major Projects Work Program

CADD Manual Revisions

GENERATOR ADDENDUM TO MAGNOLIA GARDENS ASSISTED LIVING COMPREHENSIVE EMERGENCY MANAGEMENT PLAN

SECTION 106 ACTIVITIES ANNUAL REPORT

II. PROJECT DESCRIPTION D. HISTORY AND EVOLUTION OF THE PROPOSED PROJECT 1.0 BACKGROUND AND CONTEXT FOR THE PROPOSED PROJECT

CIMA Certificate BA Interactive Timetable

Implementation of the NATS-only recommendations of the Independent Enquiry

Overview of ABET Kent Hamlin Director Institute of Nuclear Power Operations Commissioner TAC of ABET

Continuously Operating GPS Reference Network. Jim Waters, PE, RLS Assistant Director, Design Division

SEAWALL EARTHQUAKE SAFETY & DISASTER PREVENTION PROGRAM

E-rate Program Applicant Training Fiber Options

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Stem Beach Solar 1041 Application

JOINT APPLICATION FOR INDIVIDUAL ENVIRONMENTAL RESOURCE PERMIT/ AUTHORIZATION TO USE STATE-OWNED SUBMERGED LANDS/ FEDERAL DREDGE AND FILL PERMIT

Internal Audit Follow-Up Report. Multiple Use Agreements TxDOT Office of Internal Audit

DFARS Cyber Rule Considerations For Contractors In 2018

IMPORTANT MEETING ACCESS INFORMATION!

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY DEPARTMENT OF PROCUREMENT

Northern Virginia Transportation Authority

Physical Security Reliability Standard Implementation

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

The Proposer recommends that this modification should be assessed by a Workgroup

UK EPR GDA PROJECT. Name/Initials Date 30/06/2011 Name/Initials Date 30/06/2011. Resolution Plan Revision History

DFARS Safeguarding Covered Defense Information The Interim Rule: Cause for Confusion and Request for Questions

Provider Monitoring Process

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE

MPM210: Introduction to Project Management 1. MPM210: Introduction to Project Management. Project Plan for Learning Modules.

Organizational Structure of the Toronto Environment Office

Conference Call Dates

Request for Qualifications for Audit Services March 25, 2015

ERO Enterprise Strategic Planning Redesign

Southwest Florida Water Management District Application and Response Submittal Guide

Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0027 Hardwired Back Up System

Data for Accountability, Transparency and Impact Monitoring (DATIM) MER Data Import Reference Guide Version 2. December 2018

ICANN Internet Assigned Numbers Authority Monthly Report March 16, For the Reporting Period of January 1, 2011 January 31, 2011

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Table of Contents 6.1 CORRESPONDENCE

Ministry of Government and Consumer Services. ServiceOntario. Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report

T2S PROGRAMME STATUS AS OF MID-SEPTEMBER

Continuing Care Reporting System Data Submission User Manual,

DELTA LTMS ALTERNATIVES DEVELOPMENT WORK GROUP MEETING. U.S. Army Corps of Engineers 1325 J Street Sacramento, CA MEETING NOTES

Program Management Office January, 2012

Hendry, Angela. Dear Professor Mellors. I would like information under the FOI Act on the following:

Street Works Qualifications, Training and Accreditation Update

Scheduling. Scheduling Tasks At Creation Time CHAPTER

Certification Commission of NAMSS Policies and Procedures

11 days Mon 12/7/15 Mon 12/21/15. 4 days Tue 12/8/15 Fri 12/11/ days Mon 1/4/16 Mon 2/29/16. External Milestone. Manual Summary Rollup Split

SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT. Environmental Resource Permit Application and Response Submittal Guide

MAASTO TPIMS Systems Engineering Analysis. Documentation

Published: December 15, 2016 Revised: December 15, 2016

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Seven

Helpdesk. Shopping for Technology. Talkin Tech Highlights... Computing on the Go!

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report.

Case Study: Pepco Holdings Smart Meter Deployment Dale P. Gant, Pepco Holdings, Inc. AMI Project Team, Manager of Meter Services, Delmarva Power

Published: December 15, 2017 Revised: December 15, 2017

Downtown Boise Multimodal Center

ENMAX Generation Portfolio Inc.

Karen O. Zwolak Tampa Electric Company 702 N. Franklin Street Tampa, FL

World Class Tests Application Form (Spring 2018)

National Pooling Administration Contract #FCC13C nd Revised Change Order Proposal #3B

SSC Transformation Initiative Fairness Monitoring Services

Agenda Event Analysis Subcommittee Conference Call

Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0028 Safety System Logic & Control (SSLC) Class 1 HMI

Internal Quality Assurance Report. Inspector General Department

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

SECTION 10 CONTRACTING FOR PROFESSIONAL SERVICES CONSULTANT COMPETITIVE NEGOTIATION ACT (CCNA)

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

Audit and Compliance Committee - Agenda

Request for FTE Design Exceptions & Variations Checklist

Classification: UNCLASSIFIED Caveats: NONE. Ms. Kelly,

DHSMV ITN FRVIS Equipment Refresh Addendum No. 5

Amy Wells Brennan, Esq. Assistant General Counsel (813) x. 4658

Summary Project Summary. External Tasks External Milestone. Page 1

Tri-County Academy 400 Cox Ferry Road Flora, MS 39071

Former DuPont Barksdale Works Project Update

Daily briefing. October 16, Columbia Gas ColumbiaGas.com

COUNTY AUDIT HILLSBOROUGH COUNTY, FLORIDA CONSULTANT COMPETITIVE NEGOTIATION ACT (CCNA) PROCUREMENT PROCESS AUDIT REPORT # 251

Transcription:

PASC COUNTY FLORIDA --,.. A. June 6, 2018 - -- ------- Mr. Shayne Hayes, Section Chief Pensacola Permits Section US Army Corps Engineers, Jacksonville District 41 North Jefferson Street, Suite 301 Pensacola, FL 32502 Re: SAJ-2011-00551 (SP-TSH) Subject: 2018 Summary and Project Status Report Dear Mr. Hayes: The purpose of this letter is to provide the Corps of Engineers with a status report for the May 11, 2017 Request for Additional Information (RAI) in regards to the ongoing permitting activities for the proposed Ridge Road Extension project, reference number SAJ-2011-00551 (SP-TSH). The attached report has been prepared as a collaborative effort with our co-applicant, the Florida Turnpike Enterprise. The co-applicants will continue to prepare documentation required by the RAI. Sincerely, 'JtJtM c:v4--/ Jh,-,/z-c :af Margar t W. Smith, P.E. Engineering Services Director/County Engineer Enclosure: Pasco County Ridge Road Extension Monthly Status Report ENGINEERING ADMINISTRATION West Pasco Government Center 8731 Citizens Drive, Suite 321 New Port Richey, FL 34654 mwsmith@pascocountyfl.net 727.847.2411

January 9, 2019 Pasco County/Florida s Turnpike Enterprise Ridge Road Extension Monthly Status Report December 2018 PURPOSE Provide a report on the status of the Ridge Road Extension (RRE) Clean Water Act (CWA) Section 404 permit application being processed by the U.S. Army Corps of Engineers (USACE). BACKGROUND Pasco County and the Florida s Turnpike Enterprise (FTE) are co-applicants for a Section 404 permit from USACE. The purpose of the RRE project is to construct a four-lane divided highway that improves traffic mobility and provides an additional hurricane evacuation route for the County s coastal residents. In April 2015, the co-applicants filed a comprehensive alternatives analysis comparing parameters for 17 alternatives. In April 2017 USACE made a preliminary determination that the Least Environmentally Damaging Practicable Alternative (LEDPA) is modified Alternative 7, the co-applicants revised preferred alternative. Given this preliminary determination, the co-applicants have developed a detailed project management plan for completing the remaining requirements for USACE to conclude its review and reach a final permit decision. This report provides an up to date status of the activities conducted by the co-applicants, USACE, and others to complete those requirements. COORDINATION Representatives of Pasco County, FTE, NV5 (RRE engineer of record) and Dawson and Associates (D&A--Pasco County s USACE Section 404 Permitting Consultant) conduct regular conference calls and electronic communications with USACE to coordinate activities to fulfill USACE s CWA 404 permit review requirements. USACE tracks the overall CWA 404 process for the co-application using a summary flow chart. The current version of the USACE Flow Chart dated September 5, 2018 is enclosed. The co-applicants follow a detailed RRE Design and Permitting Schedule. This schedule, which is based on the project management Critical Path Method (CPM), breaks down the major tasks in the USACE flow chart by relating the interdependencies of each activity to another. The January 4, 2019 update to the CPM schedule is enclosed. 1

January 9, 2017 DECEMBER 2018 STATUS In anticipation of a request from USACE related to the modified permit application, the County has completed preliminary work to address any changes in the Phase II cumulative and indirect impact assessment. This draft is currently being reviewed internally. The draft revised Biological Assessment (BA) has also been completed and is undergoing an internal team review. The updated cumulative and indirect impact assessment and revised BA will be submitted to USACE for its review in early 2019. Once these documents are completed the co-applicants will be able to submit a formal reply to the May 11, 2017 USACE RAI. USACE acknowledges that the standard 45-day deadline contained in the RAI is not relevant in this case, and that the co-applicants are demonstrating suitable progress toward completing the information requested in the RAI through these periodic reports, conference call discussions, and the incremental submittal of information that is outlined in the RAI. Feedback from USACE is pending regarding comments received from the recent Public Notice, UMAM and FTE Mitigation Plan. The CPM has been updated based on assumptions for the upcoming activities. Progress on January 4, 2019 RRE Design and Permitting Schedule activities are noted below. - Activity 24 USACE Review FTE Mitigation Plan Ongoing, initial USACE comments expected soon - Activity 26 USACE Review Prelim UMAM Completed - Activity 27 Prepare Final UMAM Completed - Activity 29 USACE Review and Approve Final UMAM Underway - Activity 33 USACE Reviews and Compiles Comments Ongoing - Activity 35 Draft Update Cumulative and Indirect Impacts Additional internal team review and updates ongoing - Activity 36 - Draft Update BA Additional internal team review updates ongoing - Activity 52 SWFWMD CRI Responses Underway - Activity 70 90% Roadway and LA Plans Ongoing - Activity 71-90% Bridge Plans - Ongoing The revised RRE Design and Permitting Schedule currently indicates a permit decision by USACE mid-september 2019 (unchanged from the November 2018 report). 2

January 9, 2019 2018 RECAP Several important activities took place in 2018 which affected the RRE/Suncoast Parkway interchange Section 404 permit application. Most importantly, Pasco County conducted an indepth re-evaluation of the design intent of the Phase II portion of the RRE. This re-evaluation was prompted by the change in ownership of a large track of property east of the Suncoast interchange. After conducting a traffic and hurricane evacuation analysis of a few design options, the original single access design for Phase II was found lacking when compared to a more straightforward arterial roadway design. On August 13, 2018, the County formally submitted to USACE a request to modify the Phase II design approach for Modified Alternative 7 of the 2015 alternatives analysis. USACE published a new Public Notice on September 25, 2018 to solicit public comments regarding the permit application modification. The County awaits input from USACE regarding the nature of the public comments. Other important activities conducted in 2018 follow: - On March 5, 2018 County representatives briefed HQUSACE leaders on the status of the RRE permit application. - County and FTE representatives met with USACE Jacksonville District regulatory members on July 15 and November 29 to review matters related to the permit application. - UMAM analysis was conducted for the entire RRE/Interchange project and submitted to USACE for its review. USACE comments have been addressed and expecting concurrence in early 2019. - Proposed compensatory mitigation plans were submitted to USACE by the County and FTE. NEXT STEPS The co-applicants will submit their revised Cumulative and Indirect Impact Reports and updated BA in January 2019. Once USACE has evaluated comments from the new Public Notice, USACE may request further analysis and data from the co-applicants. The USACE review of the FTE compensatory Mitigation proposal is also expected in January 2019. The co-applicants will complete their detailed work to respond to the USACE May 11, 2017 RAI. The co-applicants will forward a letter to USACE providing the status of their activities. Weekly conference calls with USACE will continue. 3

January 9, 2019 Submitted by: Dwight Beranek, P.E Senior Advisor Dawson & Associates Attachments: - USACE Flow Chart dated September 5, 2018 - Project CPM dated January 4, 2019 CF: Margaret Smith Sam Beneck Annemarie Hammond Dave Barrows Rick Capka Tom Montgomery Steve Lewis Colleen Kruk 4

* For reference only. Subject to updates and/or revisions. Updated 5 September 2018.

ID Task Task Name DurationStart Late Finish Half Predecessor 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Mode N J M M J S N J M M J S N J M M J S N 0 RRE_Schedule_Modified Phase II 749 dayfri 11/11/16 Wed 9/25... 1 County Administrative Activities 507 dayfri 3/24/17 Wed 9/25/19 2 County Decision Mitigation Bank 27 days Fri 3/24/17 Mon 5/1/17 3 CO 17 Scope of Work Development 16 days Mon 4/17/17 Mon 5/8/17 2 4 CO 17 Scope/Hours/ Fee Negotiation 15 days Mon 5/15/17 Fri 6/2/17 3FS+4 days 5 County Processing Agenda Items for CO 1725 days Mon 6/5/17 Fri 7/7/17 4 6 County BOCC Approval of CO 17 10 days Mon 7/10/17 Fri 7/21/17 5 7 County BOCC Approval of CO 19 10 days Tue 9/4/18 Mon 9/17/18 8 County Reserve Mitigation Credits 86 days Fri 12/22/17 Fri 4/20/18 38 9 County Purchase Mitigation Credits 5 days Wed 10/17/18Tue 9/17/19 8,28 10 County Coordination with Turnpike (FTE) 30 days Mon 5/1/17 Fri 6/9/17 18 11 County R/W Transfer with SWFWMD 60 days Wed 2/21/18 Wed 9/25/19 53FF+5 day 12 County R/W Acquisition from Len-Angelin180 daywed 6/21/17 Wed 9/25/19 13 USACE Permit Coordination 748 dayfri 11/11/16 Tue 9/24/19 14 USACE Alternative Analysis Review 120 dayfri 11/11/16 Thu 4/27/17 17FF 15 USACE RAI 67 days Thu 12/8/16 Fri 3/10/17 16 County RAI Response 22 days Mon 3/13/17 Tue 4/11/17 15 17 USACE Review RAI Response 11 days Wed 4/12/17 Wed 4/26/17 16 18 USACE Preliminary LEDPA Determination 1 day Fri 4/28/17 Fri 4/28/17 14 19 USACE Issues Second RAI 1 day Mon 5/8/17 Mon 5/8/17 20 USACE PJD Approval 58 days Wed 3/29/17 Fri 6/16/17 21 USACE Wetland Impacts Min. Coord. 52 days Wed 6/21/17 Thu 8/31/17 56 22 Prepare USACE Permit Plans 18.5 daywed 7/26/17 Fri 9/15/17 21 23 Prepare Draft USACE Mitigation Plan (FTE)11 days Tue 2/27/18 Tue 3/13/18 24 USACE Review FTE Mitigation Plan 145 daywed 3/14/18 Tue 12/25/18 23 25 Prepare Prelim. UMAM (PC & FTE) 143 daymon 9/18/17 Wed 4/4/18 22 26 USACE Review Prelim UMAM 182 daythu 4/5/18 Fri 12/14/18 25 27 Prepare Final UMAM (PC & FTE) 3 days Mon 12/17/18Wed 12/19/... 26 28 Submit Final Mitigation Plan (PC & FTE) 10 days Wed 10/3/18 Tue 1/8/19 24 29 USACE Review and Approve Final UMAM &10 days Thu 12/20/18 Tue 1/22/19 28,27 30 County Notifies USACE Ph II Modification 12 days Mon 7/30/18 Tue 8/14/18 31 USACE Issues new Public Notice 30 days Wed 8/15/18 Tue 9/25/18 30 32 Public Notice Comment Period 43 days Wed 9/26/18 Sat 11/24/18 31 33 USACE Reviews and Compiles Comments 20 days Mon 11/26/18Fri 12/21/18 32 34 USACE Provide Guidance on Add'l App Req12 days Mon 12/24/18Tue 1/8/19 33 35 Draft Update Cumulative & Ind. Impacts A25 days Thu 9/20/18 Tue 1/29/19 7FS+2 days 36 Draft Update BA 20 days Thu 12/13/18 Tue 1/29/19 7,29FF+5 da 37 Draft Update Alt Analysis for Mod 7 - Phas15 days Wed 1/9/19 Tue 1/29/19 7FS+2 days 38 USACE Review Draft Cumul & Sec. Analysi 25 days Wed 1/30/19 Tue 3/5/19 35,36,37 39 Final Updates to C & I Analysis, BA 20 days Wed 3/6/19 Tue 6/25/19 34,38 40 USACE S-7 ESA Consultation 98 days Fri 2/8/19 Tue 6/25/19 28,38SS+7 d 41 USACE Completes EA & SOF 45 days Wed 6/26/19 Tue 8/27/19 40,39 Task External Tasks Manual Task Finish-only Manual Progress Project: RRE_Schedule_Modified Date: Fri 1/4/19 Split Milestone Summary External Milestone Inactive Task Inactive Milestone Duration-only Manual Summary Rollup Manual Summary Deadline Critical Critical Split Project Summary Inactive Summary Start-only Progress

ID Task Task Name DurationStart Late Finish Half Predecessor 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Mode N J M M J S N J M M J S N J M M J S N 42 USACE Sends 3(c) Letter to EPA 15 days Wed 8/28/19 Tue 9/17/19 41 43 USACE Issues Permit 5 days Wed 9/18/19 Tue 9/24/19 53,40,9,42 44 SWFWMD Permit Coord 471 daymon 5/8/17 Tue 9/17/19 45 Pre-App Meeting 1 day Mon 5/8/17 Mon 5/8/17 46 ERP Modification Application Preparation 153 daywed 12/20/17Fri 7/20/18 66 47 SWFWMD Review 12 days Mon 7/23/18 Tue 8/7/18 46 48 SWFWMD Issues RAI 1 day Wed 8/8/18 Wed 8/8/18 47 49 Prepare SWFWMD Mitigation Plan 75 days Tue 6/19/18 Mon 11/5/18 48 50 RAI Responses 63 days Mon 8/13/18 Wed 11/7/18 49 51 SWFWMD Review and CRI Issuance 16 days Mon 11/5/18 Mon 11/26/... 50 52 CRI Responses 45 days Tue 11/27/18 Tue 8/20/19 51 53 SWFWMD Permit Issuance (401 Certificati20 days Tue 1/29/19 Tue 9/17/19 52 54 Design & Bidding Activities 621 daywed 5/10/17 Wed 9/25/19 55 Design Activities 490 daywed 5/10/17 Tue 4/2/19 56 Preliminary Line and Grade 30 days Wed 5/10/17 Tue 6/20/17 20,18 57 Bridge Type & Size Report 20 days Wed 5/17/17 Tue 6/13/17 56SS+5 day 58 County Review 10 days Wed 6/21/17 Tue 7/4/17 56 59 Preliminary Geotech for Bridges 95 days Mon 7/24/17 Fri 12/1/17 56SS+10 da 60 Supplemental Survey 180 daymon 7/24/17 Sun 4/1/18 56,6 61 30% Roadway Plans 30 days Mon 7/24/17 Fri 9/1/17 58,6 62 30% Bridge Plans 30 days Mon 7/24/17 Fri 9/1/17 58,6 63 County Review 25 days Mon 9/4/17 Fri 10/6/17 61,62 64 LA Concept Plans 57 days Thu 8/10/17 Fri 10/27/17 58 65 County LA Review 11 days Mon 10/30/17Mon 11/13/... 64 66 60% Roadway Plans 52 days Mon 10/9/17 Tue 12/19/17 61,63 67 LA 60% Plans 78 days Mon 11/13/17Wed 2/28/18 65 68 County Roadway Plan Review 92 days Thu 12/21/17 Fri 4/27/18 66FS+1 day 69 County LA Review 42 days Thu 3/1/18 Fri 4/27/18 67 70 Final Geotech for Bridges 62 days Mon 12/4/17 Tue 2/27/18 62,59 71 90% Roadway & LA Plans 110 daymon 4/30/18 Tue 1/22/19 68 72 90% Bridge Plans 120 daymon 10/16/17Tue 1/22/19 62,63,59,70 73 County Review 10 days Wed 1/16/19 Tue 2/5/19 71,72 74 100% Roadway Plans 20 days Wed 1/30/19 Tue 3/5/19 73 75 100% Bridge Plans 20 days Wed 1/30/19 Tue 3/5/19 73 76 Specification Package 10 days Wed 2/27/19 Tue 3/19/19 74,75 77 County Review 10 days Wed 3/13/19 Tue 4/2/19 76 78 Project Bidding 131 daywed 3/27/19 Wed 9/25/19 79 Final Bid Documents 15 days Wed 3/27/19 Tue 4/23/19 77 80 County Bid Process 60 days Wed 4/17/19 Tue 7/16/19 79 81 County Contractor Selection 50 days Wed 7/10/19 Tue 9/24/19 80 82 Begin Construction 1 day Wed 9/25/19 Wed 9/25/19 81,10,43FF Task External Tasks Manual Task Finish-only Manual Progress Project: RRE_Schedule_Modified Date: Fri 1/4/19 Split Milestone Summary External Milestone Inactive Task Inactive Milestone Duration-only Manual Summary Rollup Manual Summary Deadline Critical Critical Split Project Summary Inactive Summary Start-only Progress