NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance

Similar documents
US 101 HOV PROJECT Status Report SBCAG BOARD MEETING JANUARY 21, 2016

Internal Audit Follow-Up Report. Multiple Use Agreements TxDOT Office of Internal Audit

Management s Response to the Auditor General s Review of Management and Oversight of the Integrated Business Management System (IBMS)

Honorable Mayor and Members of the City Council. Memorandum of Understanding: Interstate 80 Integrated Corridor Mobility (I-80 ICM) Project

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

INSPIRE status report

Facebook West Campus. Planning Commission Meeting February 25, 2013

Dulles Area Transportation Association

SECTION 106 ACTIVITIES ANNUAL REPORT

Corridor Management Committee. January 12, 2017

The Internet Society. on behalf of. The IETF Administrative Oversight Committee REQUEST FOR PROPOSALS. for

Staff Report City of Manhattan Beach

10.1 BIBLIOGRAPHY Noise and Vibration Study Yard and

SECTION 106 ACTIVITIES ANNUAL REPORT

Dallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office

Recommendation to Board. Final Action

Citizen Science and Nontraditional Partner Monitoring: Memorandum of Understanding

REQUEST FOR PROPOSALS ZONING ORDINANCE

ARLINGTON COUNTY, VIRGINIA

Project Presentation April, 2017

13543/17 PhL/at 1 DG G 3 B

Policy on the Standardisation of Documentation

REPORT 2015/149 INTERNAL AUDIT DIVISION

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

Click to edit Master title style Click to edit Master title style

Program Management Office January, 2012

Adoption of the Town of Putnam Valley Comprehensive Plan and the Future Adoption of Zoning and Subdivision Amendments to Implement the Plan

RESOLUTION NO Adopted by the Housing Authority of the City of Sacramento. December 3, 2013

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft

Memorandum of Understanding between the Central LHIN and the Toronto Central LHIN to establish a Joint ehealth Program

Corridor Management Committee. December 17, 2014

Cross Community Working Group (CWG) To Develop An IANA Stewardship Proposal. On Naming Related Functions. Discussion Document for ICANN52 Singapore

Metrolinx / Toronto Transit Plan April 28, Jack Collins Vice President, Rapid Transit Implementation

Mitigation Framework Leadership Group (MitFLG) Charter DRAFT

GDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010

The Final Rule on Work Zone Safety and Mobility

II. PROJECT DESCRIPTION D. HISTORY AND EVOLUTION OF THE PROPOSED PROJECT 1.0 BACKGROUND AND CONTEXT FOR THE PROPOSED PROJECT

MAJOR PROJECTS STRATEGY

Policy. Business Resilience MB2010.P.119

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket

Recommendation to Board. Final Action

Mathematical and Statistical Sciences

AGENDA 5. ALBERT ROBLES CENTER (ARC) DESIGN-BUILD PROJECT PROGRESS REPORT 6. ALBERT ROBLES CENTER (ARC) OUTREACH PROGRAMS UPDATE

Draft Thick RDDS (Whois) Consensus Policy and Implementation Notes

IT Governance ISO/IEC 27001:2013 ISMS Implementation. Service description. Protect Comply Thrive

Systems and software engineering Requirements for managers of information for users of systems, software, and services

Physical Security Reliability Standard Implementation

ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

4E Information/Action

Adopt a resolution (Attachment 16) approving amendments to the North 40 Specific Plan.

CITY OF VANCOUVER ADMINISTRATIVE REPORT

SEAWALL EARTHQUAKE SAFETY & DISASTER PREVENTION PROGRAM

TERMS OF REFERENCE. Scaling-up Renewable Energy Program (SREP) Joint Mission. Lesotho

Saving the Project Brief document under its own name

NATIONAL INFRASTRUCTURE COMMISSION CORPORATE PLAN TO

Westin Good Faith Effort Outreach Letter

CDISC Operating Procedure COP-001 Standards Development

MVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014

No Hard Copies: Creating Web-based Plans. North Texas Elected & Appointed Officials Planning Workshop July 15, 2016

{(. }.) Ordinance Fact Sheet 'P..o... ~~

CGI Deliverables Approval and Maintenance Process

National Pooling Administration Contract #FCC13C nd Revised Change Order Proposal #3B

System Expansion Implementation Plan. Board Meeting, April 2017

The Internet Society. on behalf of. The IETF Administrative Oversight Committee. Request for Proposal. RFC Editor RFC Format CSS Design

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

SACOG Board of Directors

Information Technology Disaster Recovery Planning Audit Redacted Public Report

S542: Combining Form-Based and Conventional Code Elements

5 of overriding considerations, related to full implementation of Habitat Mitigation Actions

ITEM 43. Simpson dba Basecamp Environmental

Standards and Guidelines Notebook September 1, 2017

This document is a preview generated by EVS

Request for Qualifications for Audit Services March 25, 2015

Government Resolution No of February 15, Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security

IS Audit and Assurance Guideline 2001 Audit Charter

Fairfax County Comprehensive Transit Plan and Transit Development Plan

Standards Authorization Request Form

Network Working Group Request for Comments: 3563 Category: Informational July 2003

Schematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones

INTERIM Reclamation Waiver Process per Rule 1001.c Last Updated December 17, 2015

Criminal Case Information System for Public Defenders [Section 18B.10 of S. L , as amended by Section 18A.2 of S.L.

Annual Report for the Utility Savings Initiative

Meeting Date: October 24, 2018

History of NERC December 2012

Implementation of the NATS-only recommendations of the Independent Enquiry

Academic Program Review at Illinois State University PROGRAM REVIEW OVERVIEW

MAASTO TPIMS Systems Engineering Analysis. Documentation

I-95 Corridor Coalition. Multi-State VMT-Based Road-User Fee Initiative. Mark F. Muriello

Reston Town Center North Development. Community Update

King County Ombudsman Whistle-Blowers Office Complaint

Railroad-DOT Mitigation Strategies (R16) An Overview. March 2016

California Pavement Preservation (CP 2 ) Center

Case 1:98-cv CKK Document Filed 06/15/2006 Page 1 of 7 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

Internal Audit Report. Electronic Bidding and Contract Letting TxDOT Office of Internal Audit

port Ager1da March 3, 2014 TO: Honorable Mayor and City Council FROM: Department of Information Technology

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

Transcription:

NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY ITEM: 6B SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance Jacobs Engineering has completed Task 1 with amendment 1. The following Task Order 1 deliverables have been completed: Aerial topographic surveys and a portion of the base mapping Defining the Route Adoption limits (see attached letter) Assist in developing the cooperative agreement with Caltrans Drafted the Project Charter and Risk Plan with Caltrans (These will need minor revisions based on new Route Adoption strategy) Defining the Environmental Strategy with Caltrans Issued Notice of Preparation for the environmental document Drafted Purpose and Need for project (Will need revision based on new Route Adoption strategy) Determining the appropriate traffic model and completed data collection Coordinating with local planning documents Developing Public Outreach Communications Plan, project brochure, and conducted two public scoping meetings Initiating environmental technical studies Refined the Scope, Cost and Schedule for subsequent Task Orders Task Order 2 and Task Order 3 are proposed to run concurrently. Task Order 2 will address CEQA and Route Adoption documentation for the approved Route Adoption strategy from McHenry to SR 120. Task Order 3 will address CEQA EIR/ NEPA Tier 1 EIS for the entire corridor from SR 99 to SR 120 and a project specific scoping document for a buildable Phase 1 project (from Oakdale westerly as funding allows). The cost, scope and schedules for these two tasks are attached. The combination of these two tasks will complete the current Jacobs Engineering contract. Subsequent tasks and contract will be to provide PS&E (Plans, Specifications and Estimates) documents for Phase 1. STAFF RECOMMENDATIONS: Approve Task Order #2 and Task Order #3 to the Jacobs Engineering contract. FISCAL IMPACT: There is no fiscal impact beyond the contract amount approved for Jacobs Engineering.

North County Corridor Task 2/ Task 3 Cost, Scope and Schedule Jacobs Engineering Contract Jacobs Engineering proposed to complete a route adoption document to secure the interregional funding committed by the Caltrans Director, Will Kempton. In addition, the proposed scope consisted of a Program Level (Tier 1) Project Approval and Environmental Document for the entire North County Corridor (NCC) project (from State Route 99 to State Route 120) and a project level EIR/EIS for a buildable phase of the project. Jacobs original proposal was for $6.4M. The NCCTEA authorized a contract in the amount of $5.8M. An initial task order (T.O #1) for an amount of $580,194 was recommended by the staff to enable Jacobs to better formulate strategies and lay the ground work that would lead to the Route Adoption strategy and identify an overall approach to deliver the program level environmental document. The Task Orders presented below are within the originally approved contract amount of $5.8M. The Consultant team had several meetings with Caltrans management, JPA staff, JPA Technical Advisory Committee, NCC Project Manager and the NCCTEA Manager and has finalized a strategy that is acceptable to Caltrans and the JPA Staff. The staff believes that the strategy agreed with Caltrans will expedite the project and position the JPA for the 2010 STIP funding. The Consultant team also had several meetings with the Caltrans Environmental staff and has finalized the optimum delivery strategy to finish the CEQA program level environmental document on time to accompany the California Transportation Commission (CTC) Route Adoption approval. Based on these discussions Task Order #2 and Task Order #3 were developed and consists of the following. Task Order #2 Deliverables & Completion Schedule 1. Route Adoption CEQA Document September 2009 2. Route Adoption Report September 2009 3. PSR-PDS for entire corridor to enable programming October 2009 4. Legislative support July 2009 Task Order #3 Deliverables & Completion Schedule 1. Tier 1 EIR/EIS and a Project Report for the adopted State Route (McHenry Ave to SR 120) July 2012 2. Tier 1 EIR/EIS and a Project Report for the local road portion from SR 99 to McHenry Avenue July 2012 3. Project Specific EIR/EIS and a Project Report for a phase 1 buildable segment July 2012