Memorandum. This memorandum requires Committee action.

Similar documents
From: Laura Manz, Vice President of Market & Infrastructure Development

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

Interconnection and Transmission

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

ITC HOLDINGS, CORP. Edison Electric Institute 9

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

Updates and Modifications to Report

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

Grid Interconnection of Renewable Generation

2015 General Rate Case

Updates and Modifications to Report

Generation Interconnection Feasibility Study Report

Dominion Supplemental Projects

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

Updates and Modifications to Report

Introduction to the NYISO

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Project Presentation April, 2017

Feasibility Study on Load Flow and Short Circuit Project

PacifiCorp Transmission Technical Workshop

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

Interconnection Re-MAT September 11, 2013

February 25, Subject: Southern California Edison 2015 Annual Progress Report

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

Generator Interconnection Process. Wholesale Transmission Overview

July 26, Dear Mr. Millar:

TransWest Express Transmission Project Interregional Transmission Project Submittal

Distributed Generation Interconnection in Illinois

History of NERC August 2013

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006

Warrenton Wheeler Gainesville 230kV Reliability Project

History of NERC December 2012

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements

ATTACHMENT I: Generator Interconnection Procedures (GIP)

Southern California Edison. Leading the Way in Electricity TM

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

TransWest Express and Gateway South

The NYISO shall assign a Queue Position based upon the date and time of receipt of the

Agreements & Queue Management

Joint Transmission Planning Base Case Preparation Process

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

RFP Attachment 13. January 2010

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Generation, Transmission, and End User Facilities

Unofficial Comment Form

ONCOR INFRASTRUCTURE DEVELOPMENT

Agreements and Queue Management

Silicon Valley Power:

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace.

Small Hydro Regulatory and Permitting Requirements California

Transmission Register PTO Admin User Manual. Version 1.0

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Agreements and Queue Management

2012 General Rate Case

Supporting Strategic Customers Needs

NERC Overview and Compliance Update

Mocuba The First Utility Scale PV Project in Mozambique

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

Planning for the Future

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection

SDG&E s Accomplishments and Future Plans

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

RELIABILITY OF THE BULK POWER SYSTEM

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014

SOUTHERN CALIFORNIA EDISON COMPANY

Competitive Solicitation Process Enhancements. Status Update / Issue Paper

Data Center Site Assessment and Tiered Designation Program. Northport Industrial Park North Mankato, MN Executive Site Summary

INTERCONNECTION FACILITIES STUDY REPORT

Smart Distribution Technology

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

Q44 Generation Interconnection

Stakeholder Comments Template

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

State Perspectives on the Midwest ISO regional Stakeholder Process: The Indiana Utility Regulatory Commission

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

Valley-Ivyglen and Alberhill Transmission Line Projects

ENMAX Power Corporation

Transcription:

California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure Development Date: June 7, 2006 Re: Approval of City of Riverside 230kV Transmission Interconnection Project This memorandum requires Committee action. EXECUTIVE SUMMARY This memorandum is a request for the ISO Operations Committee to recommend the Board s approval of the City of Riverside 230 kv Transmission Interconnection Project described as Option 1 in this memorandum. This project, which is needed as soon as possible to reliably serve load growth in the City of Riverside, includes a loop in the Mira Loma-Vista #1 230 kv transmission line and construction of a new 230/66 kv Substation. The estimated cost of the project is $ 52.5 million in 2008 dollars - $ 48.2 million for ISO controlled facilities and $ 4.3 million for non-iso controlled facilities. MOVED, that the Operations Committee recommends that the Board of Governors grant its approval of: the City of Riverside Transmission Project (Option 1 as described in this Memorandum dated June 7, 2006) as a necessary and cost effective addition to the ISO Controlled Grid and Directs Southern California Edison (SCE) to complete the construction of the City of Riverside Transmission Project as soon as possible and preferably no later than Q2, 2008; and support of SCE recovery of reasonably incurred costs associated with the permitting and construction of the City of Riverside Transmission Project (Option 1 as described in this Memorandum dated June 7, 2006) in relevant FERC and CPUC rate cases. ISSUE STATEMENT An interconnection study request was made by the Riverside Public Utilities (RPU) for the City of Riverside after Southern California Edison (SCE) had indicated that the existing 230/66 kv point of interconnection between SCE and Riverside at SCE s Vista Substation will not be adequate to serve Riverside s increased load in the future. The 2005 actual peak load 151 Blue Ravine Road Folsom, California 95630 (916) 351-4400

was 552 MW. The projected 2006 peak load of 583 MW (1-in-10 year forecast) will exceed the combined capacity of the two A transformer banks (557 MVA) used to provide service to the City of Riverside. 1 SCE has determined that there are physical size limitations that restrict the expansion of the existing Vista 230 kv switch-rack. Expansion of the 230 kv bus by installation of another 230 kv bus across from the substation connected by 230 kv underground (UG) cables is also not possible due to an existing UG pipeline. Further expansion of the Vista Substation is not viable and it is not desirable to continue with a single point of service for the City of Riverside. A second point of service is required for the City of Riverside. OPTIONS TO SOLVE PROBLEM OR DEAL WITH THE ISSUE Three options were investigated to provide a second point of service to the City of Riverside. Option 1: Loop the existing Mira Loma-Vista #1 230 kv line by building 8.25 miles of new 230 kv double circuit transmission line from the existing Mira Loma-Vista #1 T/L ROW to into a new 230 kv SCE interconnection facility with RPU s new Jurupa Substation in Riverside. Option 2: Build a 230 kv SCE interconnection facility located at Riverside s new Jurupa Substation with two new 230 kv lines from the Mira Loma and Vista substations to the new Jurupa Substation. Option 3: Build a new SCE 230 kv interconnection facility adjacent to the existing Mira Loma Vista 230 kv rightof-way with new 8.25 miles of double circuit 230 kv transmission to a new Riverside 230/66 kv Jurupa Substation. SCE studies concluded that Options 2 was impractical 2 and Option 3 cost higher than Option 1. Option 1 would have no adverse system impacts and no system upgrades are necessary other than those facilities necessary to loop the Mira Loma-Vista #1 230 kv transmission line and the SCE constructed 230 kv substation. The recommended Option 1 is shown in the attached Figure 1. Also shown are the ISO and non-iso controlled facilities. RPU proposes to serve about half of its retail load radially from Vista Substation and the other half from the new Jurupa 230/66 kv substation 283 MW of the year 2008 load will be transferred from six existing 66/12 kv substations currently being supplied from the 230/66 kv Vista Substation. The new 230/66 kv Jurupa Substation is planned to serve up to 560 MW of existing and future load. RPU may not parallel the facilities served by the Jurupa Substation with any other electrical facilities served by SCE or others without receiving review and authorization. POSITIONS OF THE PARTIES Both RPU and SCE support the project and have formally requested ISO Board approval. SCE plans to finance, construct, own and maintain the new transmission facilities of the project upon Board approval and receipt of other necessary regulatory approvals. SCE intends that the $ 48.2 million cost of the ISO-controlled facilities constructed and 1 The capability of the existing supply from Vista may be exceeded this summer. To overcome this Riverside has two internal generating plants, with a combined nominal rating of 140 MW. This generation will be used to maintain the Vista transformer loading within acceptable limits, until the Jurupa Project can be constructed. 2 Option 2 is not feasible due to physical limitation at the Vista 230 kv bus.! Page 2

owned by SCE will be recovered through the ISO transmission access charge. SCE would recover the $ 4.3 million for non-caiso facilities from the City of Riverside (RPU) through their Wholesale Distribution Access Tariff (WDAT). Both SCE and City of Riverside (RPU) are Participating Transmission Owners pursuant to the ISO Tariff. RPU and SCE have entered into an Interim Agreement in order to expedite certain pre-construction activities while an Interconnection Agreement is developed that contains terms for RPU to interconnect to the SCE electrical system and for SCE to construct, own, operate and maintain the 230 kv lines and 230 kv substation developed pursuant to SCE s TO tariff. RPU will construct, own, operate and maintain the 66 kv switchyard facilities with 2-230/66 kv, 280 MVA transformers. MANAGEMENT RECOMMENDATION Based on the assessments performed, ISO Management recommends approval of the City of Riverside Transmission Interconnection Project. The City of Riverside may not parallel the facilities served by the Jurupa Substation with any other electrical facilities served by SCE or others without receiving review and authorization. MOVED, that the Operations Committee recommends that the Board of Governors grant its approval of: the City of Riverside Transmission Project (Option 1 as described in this Memorandum dated June 7, 2006) as a necessary and cost effective addition to the ISO Controlled Grid and directs Southern California Edison Company (SCE) to complete the construction of the City of Riverside Transmission Project as soon as possible and preferably no later than Q2, 2008; and support of SCE recovery of reasonably incurred costs associated with the permitting and construction of the City of Riverside Transmission Project (Option 1 as described in this Memorandum dated June 7, 2006) in relevant FERC and CPUC rate cases.! Page 3

Figure 1 Recommended Option 1 for City of Riverside 230 kv Transmission Interconnection Project To Mira Loma Substation Existing Mira Loma Vista Line #1 230 kv T/L To Vista Substation New 8.25 miles of 230 kv double-circuit transmission line 230 kv Highlight indicates Non-ISO Controlled Facilities New Jurupa Substation SCE Riverside WW WW 230-66 kv, 280 MVA Transformer To City of Riverside! Page 4

! Page 5 Figure 2 Proposed for City of Riverside 230 kv Transmission Interconnection Project