MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007

Similar documents
1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.

LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL. September 2001

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

Feasibility Study on Load Flow and Short Circuit Project

Terry Williams Tennessee Valley Authority

Getting Effective Transmission Built on the SPP-MISO Seam. MISO-SPP IPSAC Meeting March 2016

MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.

Generation Interconnection Feasibility Study Report

Enhanced Curtailment Calculator Update

Wide Area Measurements & Control Systems

2016 Fall ITO Stakeholder Meeting. Topics in Operations

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

2009 SPP TransCanada Pipeline Study Report

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support

Bulk Electric System Definition Changes and Reporting

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Coordinate Interchange

Coordinate Interchange

WECC Path Concept White Paper

Unused Generation Capacity Study Scope. Informational Analysis

WIND ENERGY, CONGESTION MANAGEMENT, AND TRANSMISSION RIGHTS ISSUE DESCRIPTION/PROBLEM STATEMENT. August Issue Brief

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

Year Assessment Preliminary Needs

Peak Reliability Coordination Services in the West March 30, 2018

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

ATC Zone 2 Projects Update U.P. Energy Summit

MOD Transmission Reliability Margin Implementation Document

Cherrywood Circuit Breaker Incident - December 12, 2005

Available Transfer Capability Definitions and Determination

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Generation Interconnection Feasibility Study Report

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

Seams Management at the RTO level

XXXXX XXXX Wind Generation Project

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

November 9, Revisions to the Violation Risk Factors for Reliability Standards IRO and TOP

Open Access Transmission Tariff of Southern Companies

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Operating Reliability Subcommittee Presentations. February 10-11, 2015

COM Communications and Coordination

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

WECC Criterion INT-001-WECC-CRT-3

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Generation, Transmission, and End User Facilities

December 13, Sw. Power Pool, Inc., 144 FERC 61,224 (2013) ( September 2013 Order ).

primary Control Center, for the exchange of Real-time data with its Balancing

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Building a Topology Estimator for Large Inter-regional Networks

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources.

Standard Development Timeline

CROW Outage Scheduler Web GUI Tutorial

Supplemental Information

Standards Authorization Request Justification

NERC CIP Information Protection

System Studies for American Transmission Co. s Benson Lake SVC Project

Unofficial Comment Form Project Disturbance Monitoring

_ Dear Secretary Bose: The attached. Folsom, CA

NERC Overview and Compliance Update

Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.:

AC-DC ERCOT. Bill Bojorquez Dejan J. Sobajic ERCOT Grid Engineering LLC. June 6, 2005 Les Diablerets, Switzerland

Standard EOP Disturbance Reporting

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

Standard Authorization Request Form

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

PRC Coordination of Protection Systems for Performance During Faults

Transmission Reliability Margin Implementation Document (TRMID)

ISO-NE Demand response season preparation webinar

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Standard CIP Cyber Security Critical Cyber As s et Identification

MTEP16 South SPM #3 MISO Louisiana Project Information

ERO Certification and Review Procedure

Planning for the Future

Designation and Termination of Network Resources

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

Electric Transmission Reliability

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Project Consideration of Commission Directives in Order No. 693

System Data Exchange (SDX) Users Manual. Table of Contents

Sub Regional RTEP Committee Mid-Atlantic

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols

Interchange Distribution Calculator Billing

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

WECC Criterion INT-001-WECC-CRT-2.13

Transmission Service Reference Manual. May 08, 2017

Network Integration Service

City of Grand Island Tuesday, February 28, 2017 Council Session

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1

Transcription:

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007 Report submitted to NERC on: July 12, 2007. This report is submitted in accordance with the NERC Transmission Loading Relief (TLR) Investigation Procedure for the TLR events that occurred on Flowgate 14266 June 11, 2007. The MISO systems detected high post-contingent flows on Wisdom-Triboji 161kV line for loss of (flo) the Sherco #3 unit. This event resulted in curtailment of firm transmission service and a reduction obligation (or requirement) due to Network/Native Load (NNL) impacts. 1. Description of purpose/cause of hold/curtailment: The definition of flowgate 14266 is listed below. Monitored Facility: Wisdom-Triboji 161kV Contingent Facility: Sherco #3 2. Facility/Flow gate limitations and flow at the time the TLR was initiated: Flowgate 14266 measures and captures the flow on the Wisdom-Triboji 161kV line for the loss of the Sherco #3 unit. The Wisdom-Triboji 161kV line is limited by 223 MVA thermal emergency rating. On June 11, 2007, heavy south to north power transfer through Iowa caused an increased flow in Wisdom-Triboji 161kV line for the loss of Sherco #3 unit. At 11:00 EST, the calculated post contingency flow on Wisdom-Triboji 161kV line for the loss of Sherco #3 unit reached 229 MVA. The MISO RC initiated internal MISO market redispatch as well as committed MISO market generation to reduce the post contingency flow in the flowgate. At 15:15 EST, the calculated post contingency flow on Wisdom-Triboji 161kV line for the loss of Sherco #3 unit reached 249 MVA. At this point, NERC IDC showed there was not sufficient non-firm scheduled on FG14266 and TLR 5B was issued at 15:20 EST for FG 14266 to be effective across 15:30 EST. At this time the MISO RC contacted MEC to assist them in finding a generation pairing to fulfill their NNL obligation as prescribed by the NERC IDC. MEC decided to curtail a transaction with WAPA that would result in the proper amount of relief for their NNL obligation. As the NERC IDC showed the insufficiency of non-firm schedule curtailment to relieve flow, TLR 5 was issued for a total of three continuous issuances. The TLR was reduced to level 3A x 18:00 EST and was terminated at 20:00 EST when flows decreased to acceptable levels. Page 1 of 5

3. TLR Level 5 issuance information, timing (EST), firm tag and NNL reduction information obtained for flowgate #14266 June 11, 2007: TLR LEVEL TIME (EST) 5B 15:30 5A 16:00 Firm Transaction / Curtailment Information 3 tags of (7-F) = 3 MW schedules curtailed to provide.2 MW relief MISO Market responsibility = 43.3 MW 4 tags of (7-F) = 19 MW schedules curtailed to provide 1.4 MW relief MISO Market responsibility = 46.4 MW 5A 17:00 MISO Market responsibility =.7 MW None 3A 18:00 All firm schedule and NNL were reloaded 0 20:00 NNL Reduction Requirement MEC 6.6 MEC 8.8 NNL Mitigation: MEC NNL obligation was met by curtailing a schedule with WAPA which increased Oahe and decreased the output of the Wisdom CT. MISO Market responsibility was met by internally committing and dispatching market generation via the AREVA UDS dispatch tool. 4. Transmission and generation outage or changes from prediction that may have contributed: Significant Transmission Outages: Raun-Lakefield 345kV line Planned outage Elk-Brewster 161 kv - Planned outage Pomeroy-NW Fort Dodge 161 kv - Planned outage Significant Generator Outages in the Region: King = 585 MW Boswell 4 = 580 MW Leland Olds 1 = 222 MW Square Butte 2 = 455 MW Coal Creek 1 = 550 MW Mankato 2 = 182 MW Faribault 1 = 160 MW Total Generation off = 2734 MW System Condition Summary: Heavy south-to-north power transfer across northwest Iowa occurred due to the outages as above and high load to the north. The heavy south-to-north power flows increased the post contingent loading in Wisdom-Triboji 161kV line. Page 2 of 5

It should be noted that MISO next day analysis did not show this violation originally, however the subsequent rerun following the Boswell 4 forced outage did show this constraint loaded to 106%. The Coal Creek emergency outage started at 14:05 EST, this was not included in either study. 5. Procedures implemented prior to hold/curtailment: MISO Market redispatch was implemented prior to the TLR event. 6. Compare Complete Transaction Curtailment List with the Whole Transaction List as generated by the IDC, before and after curtailments: Firm transactions impacting the flow gate by 5% or greater were curtailed. 7. Known Transactions not in the IDC and actions taken: There were no known transactions not in the IDC at the time this TLR was in effect that were impacting this flow gate. 8. RCIS or other system messages: Information was provided to NERC Reliability Coordinators via the NERC IDC. The IDC automatically sends TLR Level information to the RCIS. Curtailment information was communicated to the MISO control areas via the MISO MCN and ICCS messaging systems. 9. State estimator snapshots and security analysis including contingency analysis or stability analysis along with any other recorded data indicating the need for TLR: Real-time security analysis was monitored by the System Operator at the ATC control center and by the Reliability Coordinator at the MISO West Reliability Center. TLR relief requirements were calculated by using the real-time security analysis tool, and by monitoring the real-time loading on the monitored element. 10. ATC Limitations before, during, and after the event: There were no ATC limitations for this event. 11. Description of actions taken to avoid future hold/curtailments: The MISO RC followed the direction given in the special operating guide for the Raun- Lakefield 345kV planned outage which identified this constraint. 12. Re-dispatch actions taken: This was a thermal overload. Re-dispatch procedures were used in addition to mitigate NNL responsibility as prescribed by the NERC TLR procedure. 13. If Firm transaction curtailments took place, description of Transactional Contribution Factor calculation and results as well as how necessary relief was obtained through network service and native load contributions: MEC NNL obligation was met by curtailing a transaction from their Wisdom CT to Oahe in WAPA. Page 3 of 5

Non-Market Balancing Authority actions to mitigate the NNL requirements: 1530-1600 EST CA IDC NNL INC (MW) DEC (MW) GSF % Actual NNL Response MEC 6.6 WAPA - Oahe Wisdom 22.3 6.7 MW Non-Market Balancing Authority actions to mitigate the NNL requirements: 1600-1700 EST CA IDC NNL INC (MW) DEC (MW) GSF % Actual NNL Response MEC 8.8 WAPA - Oahe Wisdom 22.3 8.9 MW 14. Other options considered before/during to avoid hold/curtailment: The MISO Reliability Coordinator brought on line all available quick start units in the MISO market and re-dispatched market generation for this constraint. The following units were called on line to relieve loading: Lime Creek CT 1 Lime Creek CT 2 Pleasant Valley CT 1 Pleasant Valley CT 2 Pleasant Valley CT 3 Anson CT 2 Lakefield CT 2 Lakefield CT 3 Lakefield CT 4 Lakefield CT 5 Lakefield CT 6 Cambridge CT Inver Hills CT 1 Inver Hills CT 2 Inver Hills CT 3 Inver Hills CT 4 Inver Hills CT 5 Inver Hills CT 6 Page 4 of 5

15. The following chart identifies the flowgate loading for the TLR level 5 event: Wisdom-Triboji 161kV flo Sherco #3 on June 11, 2007. 300 250 200 MW 150 100 50 0 8:32:23 10:20:06 11:19:46 12:31:05 13:17:07 14:02:23 14:50:20 15:40:15 16:34:04 17:33:20 Time (EST) RTCA Flow Emergency Limit 16. Lessons Learned In summary, the combination of planned outages, the forced outages of Boswell 4 and Coal Creek 1 caused significant stress to the Wisdom-Triboji 161kV line. The MISO RC did have an agreed upon plan with MEC and CBPC to take the Wisdom CT off line in the event of the Sherco #3 trip. This along with the curtailments and re-dispatch would relieve the loading on the Wisdom-Triboji 161kV line in the event of the contingency. This is shown on the graph with the post contingent flows dropping as the Wisdom CT started down between 15:00 EST and 16:00 EST, coming off line at 1800 EST. Page 5 of 5