Transition to off-grid

Similar documents
ENERGY STORAGE. CAN WE LEAVE STORAGE TO THE MARKET? ESNA Energy Storage conference, 29 January Mike Wilks, Director

16 November 2016 r. 1

TELECOM & ENERGY «Collaborating to Power the Smart Grids for Digital Growth«

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

E.ON UK plc Group Consolidated Segmental Report. for the year ended 31 December 2011

Submission to ERA. ERA Discussion Paper on 2016/17 Wholesale Electricity Market Report for the Minister. Public 1 September 2017 EDM#

Southern California Edison. Leading the Way in Electricity TM

Integrated Resource Planning April 20, 2010

PHASE I ENERGY STORAGE: LESSONS LEARNED

Description Activities Description. Co-ordination with GB System Operator. Co-ordination with other DSOs and Distribution Networks (including IDSOs)

Internet Interconnection An Internet Society Public Policy Briefing

Introduction to the NYISO

Description of the Application Process for Small Embedded Generators

Alternative Fuel Vehicles in State Energy Assurance Planning

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

ITU Workshop. NGN Regulation and Migration Strategies (13-15 th October, 2010)

New York Market Opportunities

RELIABILITY AS A SERVICE FOR BUSINESS. by MidEnterprises, LLC

IFC ENERGY STORAGE MARKET REPORT

Contribution of France Telecom to the public consultation of the ERG. IP interconnection. November 2006

LEVERAGE A WIRELESS BROADBAND INFRASTRUCTURE TO Open New Revenue Streams

Seminar on African Electrical Interconnection. Module 1. The feasibility of Regional Electricity Cooperation and Integration

Exhibit to Agenda Item #1a

Network Configuration Document Selection for New Substations Framework

Siemens FuseSaver New half-cycle circuit breaker for rural smart grids to minimize operating costs of feeder and spur lines

Development of a National Broadband Strategy Project. Addendum No. 1 to Phase 2 report

Interoute Acquisition Summary. February 26, 2018

EU policy and the way forward for smart meters and smart grids

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Preface Chapter 1. The Challenges of Building a Network

GO15 Reliable & Sustainable Power Grids

27 November 2009 TDC submission: ERG DRAFT Common Position on Next Generation Networks Future Charging Mechanisms/Long Term Termination Issues Draft

Public consultation on the revision of the Recommendation on relevant markets

The HUMANE roadmaps towards future human-machine networks Oxford, UK 21 March 2017

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources.

ETNO Reflection Document in response to ECC/ CEPT consultation on Fixed-Mobile Convergence with Survey of Numbering Related Issues

SHARED SERVICES - INFORMATION TECHNOLOGY

A Framework to Approach Shared Use of Mining Related Infrastructure: ICT

Determining the Costs of Interconnection

Owner/Operator Forum 12 December

MindSphere meets energy

Available Transfer Capability Definitions and Determination

Extract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017

TARGET2-SECURITIES INFORMATION SECURITY REQUIREMENTS

Entergy Arkansas, Inc. Transition Plan Technical Conference #1

Pan-Arab Interconnection and Development of Arab Power Markets

Mohamed Al-Shaikh, BSc MSc CEng MIET Manager, Maintenance - GCCIA

ACH Clearing Rules. Guidance Note No. 5 NEW CLIENTS ELECTRONIC CLIENT AGREEMENTS KEY TOPICS ACH CLEARING RULES. Guidance Note History.

TARIFF APPLICATION FORM INSTRUCTIONS

IP Interconnection. Calvin S. Monson Vice President. Antigua September 2007

Issue 1. August Page 1 of 6. National Security Inspectorate Sentinel House, 5 Reform Road Maidenhead SL6 8BY Website: nsi.org.

LEGAL AND REGULATORY FRAMEWORK AND OPPORTUNITIES FOR OFF-GRID POWER GENERATION IN NIGERIA

The Strategic Implications of VOIP for Regulating the Electronic Communications Markets

Fair and Effective Management of DNO Connection Queues: Treatment of Requests to Change Connection Applications. Good Practice Guide

Response to Draft Guidelines of Good Practice on Electricity Grid Connection and Access (E08-ENM-09-03)

WALKER WIRELESS LIMITED

Capital Contribution Policy for New Load and Network Extensions Marlborough Lines

Graff Search Limited ( Graff Search ) is a recruitment agency and recruitment business.

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Distribution Long Term Development Statement

Infrastructure Contributions Reform in Queensland

The Board grants site licenses for utilities that do not interfere with the park function.

EU DONOR FUNDED SMART GRID PROGRAMME

Schedule 2a for Capital Leases

China Telecom Corporation Limited 2 June 2008

Reviewed by OR Approved by::

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

APPROACHING ROAMING CHARGES PRAGMATICALLY

Toronto Hydro-Electric System Limited EB Exhibit G1 Tab 1 Schedule 1 ORIGINAL Page 1 of 15 SMART GRID PLAN

OECD Experts Meeting on Telecommunications Services

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY

STUDY ON INTERNET PROTOCOL TELEPHONY. March 2004

Remote Prosumers Preparing for deployment

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Energy Security: A Global Challenge

Smart Metering and Smart Grids: the Enel

SERVICE TERMS AND SLA FOR LEASE OF DARK FIBER

Deploying VSaaS and Hosted Solutions using CompleteView

Smart Grid Development in Ho Chi Minh City

SEPTEMBER 2014 NATIONAL BROADBAND NETWORK AND SCHOOLS CONNECTIVITY

SECTOR ASSESSMENT (SUMMARY): INFORMATION AND COMMUNICATION TECHNOLOGY

Tutorial: Active Network Management

Distributed Generation Interconnection in Illinois

Wholesale Very high bit-rate Digital Subscriber Line (VDSL) Service

VOIP in the TAL group. June 15 th, 2005 Buenos Aires, Argentina

Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection

A MODEL FOR INTERCONNECTION IN IP-BASED NETWORKS

Geo-blocking and its impact on consumers

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

Elia Grid International Your expert in power system solutions

Response to Portfolio Committee on Communications. Measures to Reduce Interconnection Rates and High Costs of Telecommunications in South Africa

Final Determination: Criteria for Assessing Material Inter- Network Impact of Transmission Augmentations

Privacy Policy. Information about us. What personal data do we collect and how do we use it?

GD 2018/0020 COUNCIL OF MINISTERS RESPONSE TO THE POLICY PRIORITIES & ACTIONS CHIEF MINISTERS WORKING GROUP ON TELECOMMUNICATIONS

Cloud Computing Standard 1.1 INTRODUCTION 2.1 PURPOSE. Effective Date: July 28, 2015

MFC Power General Partner Ltd.,

Planning and investing in critical utility infrastructure with public consultation

Grid Interconnection of Renewable Generation

ONCOR INFRASTRUCTURE DEVELOPMENT

Agreements & Queue Management

Transcription:

Transition to off-grid Back to the future in a market context Presentation to CIDER 2015 19 August 2015 G Thorpe, Executive Director

Off-grid options Technological development Together with change of policy focus are prompting consideration of entire townships moving off-grid Single customers can move now Individual customer choice What about entire townships or equivalent number of customers? Unlikely to be unanimous agreement but may still be efficient Regulatory framework developed thinking of off on-grid,not on off grid Many regulatory and competitive complications ESAA commissioned OGW to examine these www.esaa.com.au This presentation starts with that work. 2

A reminder of history for context the basis for the back to the future title Circa 1920 - Circa 1930 - The electric power sector started as a collection of unconnected townships with their own generation and demand effectively local grids and distributed generation Townships interconnected to share reserve Circa 1920 - Large scale remotely located generation emerged around fuel (coal and hydro) increasing economies of scale Circa 1930 60 Circa 1950 90 1980s 2000 + Major transmission developed from remote sites to cities State electrification programs Township generation progressively retired withered away but connected by statewide grids electrification of the state seen as a major positive Central generation dominates 2000 - Technology and policies for distributed generation returning distributed generation to economic prospect 2010 - Beginning of reversal to historical trend and move to off-grid townships based on solar/wind/thermal and storage 3

Contracting the boundary of the grid Historically, boundary of grid continually expanded Future may see contraction of boundary of grid? 4

Focus of presentation Presumption is that the technology options are viable It s the economy stupid Regulatory and policy implications of transition to off-grid Issues around forced transfer Individual customers have a right to disconnect now. Groups of customers can agree to go off-grid. Unlikely to get unanimous agreement beyond say 4 or 5 consumers What to do about Ring fencing &cross ownership Generator competition Retail competition Social licence 5

Confirm there is an economic case for transition to off-grid B r e a k e v e n d i s t a n c e ( k M ) 600 500 400 300 200 100 Breakeven distance v peak demand Constructed for Network savings of $150,000/km (full capex), Opex saving $5,900/km/yr) Customer load factor 68%, Generation redundancy N-1 GENERATION SOLN IS PROFITABLE FOR DISTANCE ABOVE EACH CURVE 0 0.5 1 1.5 2 Peak demand (MW) $400/MWh $300/MWh $200/MWh $100/MWh $50/MWh Simple nomogram showing relationship of generation cost, demand profile/size and network distance/cost Read breakeven distance v peak demand In the absence of special conditions such as bushfire risk or inaccessible terrain (for maintenance) the case for off grid is made and is closely related to distance Special conditions generally enhance the case 6

Confirm there is an economic case for transition to off-grid B r e a k e v e n d i s t a n c e ( k M ) 600 500 400 300 200 100 Breakeven distance v peak demand Constructed for Network savings of $150,000/km (full capex), Opex saving $5,900/km/yr) Customer load factor 68%, Generation redundancy N-1 GENERATION SOLN IS PROFITABLE FOR DISTANCE ABOVE EACH CURVE 0 0.5 1 1.5 2 Peak demand (MW) $400/MWh $300/MWh $200/MWh $100/MWh $50/MWh Breakeven for 1MW (chosen load factor and network cost) and diesel generation is 300km Shorter for lower cost generation In the absence of special conditions such as bushfire risk or inaccessible terrain (for maintenance) the case for off grid is made and is closely related to distance Special conditions generally enhance the case 7

Indicators for transition to off-grid Reliability Reliability is low, for example due to single circuit supply prone to interruption and often requiring expenditure on temporary mobile generation during planned or extended forced outages; High operating and minor capital costs E.g. for both routine maintenance and activities such as pole replacement; Location specific risks E.g such as where bush fire risk is high, possibly leading to switching off supply on high risk days; and Local generation Situations where distributed generation already exists and feeds the grid or where fuel is readily available, for example a run of river hydro scheme, an untapped geothermal resource or other local resource. 8

Examples WA Previous widespread electrification policy Assets now ageing and in bushfire area History of switching between isolated and connected status in some locations Tasmania inhospitable terrain, island communities, remote small hydro connections SWER systems significant variation across states Best data from Queensland with 25,000 customers and 65,000km of line But recent expenditure has lifted reliability to these areas hence no immediate need 9

Market and regulatory implications of transition to off-grid Numerous locations operate perfectly satisfactorily without ever having been on-grid But generally: No retail contestability No generation competition Vertically integrated generation, network and retail Regulated price What to do about competitive arrangements in principle? E.g. do consumers lose these rights What if multiple retailers are currently supplying affected customers Do regulatory and statutory arrangements even permit transition to off-grid once on-grid In some cases yes with approval, in some cases no 10

Current regulatory provisions likely to be affected Legal and accounting separation Cost allocation Access to information Physical and functional separation Non discrimination principles 11

Cost and pricing issues DX DX TX DX Generation Generation Generation Current price Current price less TX Breakeven cost = price Off-grid is economic with higher generation but lower network costs 12

Cost and pricing issues X subsidy DX DX DX TX TX Generation Generation Generation Current price Current cost X subsidy no longer needed But who benefits? Allocation of benefit of off grid may be complicated Social Licence at risk if benefit not seen by off grid customers 13

Options (not proposals) Fully integrated generator retailer network business No generator competition, no retail competition Inevitably fully regulated Business owns & constructs generation & networks and dispatch generation (no independent AEMO role) Reduces opportunity for customer choice social licence??? 14

Options (not proposals) Single buyer Regularly used elsewhere as a starting point for reform Centred around a combined network owner/operator, market/system operator obliged to offer access and purchase from independent generation and retail to customers No retail competition, inevitably fully regulated Has some attraction as a middle path for competition but overhead costs may be prohibitive? Social licence also an issue here 15

Options (not proposals) Gen tailer plus independent network No generator competition, no retail competition Separate network business adjacent/existing network business seems likely Inevitably fully regulated energy charges Combined network system operator model (TSO) Social licence Which of these (or other options) is most suited to transactional market model and efficient use of storage, smart grid, distributed (grid and customer premise) generation and demand side? 16

Conclusion Case is made to address probable barriers to a shift back to off-grid Technology is available now and is likely to continue improve Regulatory barriers are real but will involve a number of challenging policy questions that were at the heart of competitive reform 17