Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Similar documents
Studies Overview and Data Requirements. Robert Pan

bcuc British Columbia Utilities Commission

Grid Interconnection of Renewable Generation

Agreements and Queue Management

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

Interconnection Re-MAT September 11, 2013

Agreements and Queue Management

PHASE I ENERGY STORAGE: LESSONS LEARNED

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Colstrip Transmission System. Transmission Service and Interconnection Processes and Procedures

WN U-60 Original Sheet No. 152

Stakeholder Comments Template

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

The NYISO shall assign a Queue Position based upon the date and time of receipt of the

Generator Interconnection Process. Wholesale Transmission Overview

ATTACHMENT I: Generator Interconnection Procedures (GIP)

MEMORANDUM. Robert Kreszswick, Director, Membership Services Department. Web CRD Electronic Procedures for Forms U4 and U5

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

Agreements & Queue Management

Generation, Transmission, and End User Facilities

Specific topics covered in this brief include:

REDIRECT OF A TRANSMISSION RESERVATION

From: Laura Manz, Vice President of Market & Infrastructure Development

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Feasibility Study on Load Flow and Short Circuit Project

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

10. Unbundled Dark Fiber 10.1 General

Ministry of Energy, Mines and Petroleum Resources. Guide to Acquiring Crown Petroleum and Natural Gas Tenures

OPUC Transmission Workshop 2 FERC Pro Forma Transmission

Checklist for Submission to Utility

Kendrick School. Admission into Year 7 in September Application Process & Key Dates

Prepared Testimony of. Bohdan R. Pankiw. Chief Counsel Pennsylvania Public Utility Commission. before the

March 11, Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3

GST/HST Info Sheet GST/HST Info Sheet

E-rate Program Applicant Training Fiber Options

Small Hydro Regulatory and Permitting Requirements California

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

SSC Transformation Initiative Fairness Monitoring Services

WEBSITE DESIGN, DEVELOPMENT AND HOSTING SERVICES

APPENDIX LETTER CODE DESCRIPTION Appendix D2 Scheduled ENROL/ 3PENR

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Reference Guide DBidS

Welcome to the new BC Bid!

Open Access Transmission Tariff Business Practices Manual Chapter K: Designation of Resource as a Network Resource

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Southwest Power Pool BUSINESS PRACTICES WORKING GROUP Conference Call/Web Cast February 7, 2012

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Open Access Transmission Tariff of Southern Companies

REQUEST FOR PROPOSALS KOOTENAY SPORT FISHING PROJECT

ELECTIVE INTERCONNECTION FACILITIES

Request for Quotation RFQ SUBJECT: FT-IR SYSTEM

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018)

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Cross-Border participation in the GB Capacity Market. Elaine O Connell 15 th January 2015

REGIONAL GAS MARKET COORDINATION GROUP. Progress report No. 2 December 2015 February 2017

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

EB CDM Exemption Hydro One Networks' Undertaking Responses ONLY HYDRO ONE UNDERTAKINGS Undertaking Description Filed Date Note

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources.

Published: December 15, 2016 Revised: December 15, 2016

Grid Code Planner EU Code Modifications GC0100/101/102/104

FY 2019 E-rate Form 470 Filing Guide

Published: December 15, 2017 Revised: December 15, 2017

Robin Hood Energy Feed-In Tariff Application Form

MARTINSVILLE CITY PUBLIC SCHOOLS RFP FOR INTERNET SERVICES NOVEMBER 1, 2014

Session 2: CORSIA MRV System: Monitoring of CO 2 Emissions. ICAO Secretariat

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

Kingdom of Saudi Arabia. Licensing of Data Telecommunications Services

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

Interchange Distribution Calculator Billing

GUIDELINES FOR RWANDA INTERNET EXCHANGE POINT (RINEX) MANAGEMENT

ORDER NO * * * * * * * * On April 21, 2017, Baltimore Gas and Electric ( BGE ) requested that the

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016)

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

COMPANY (MU1) FORM FILING - EXTENDED

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

NorthWestern Energy (NWMT)

Town of Gilmanton, New Hampshire SELECTMENS OFFICE

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Financial Planning Institute of Southern Africa SETTING THE STANDARD. Continuous Professional Development (Cpd) Policy

Robin Hood Energy Feed-in Tariff Application Form

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

A Regulatory Perspective on Distributed Generation

Physical Security Reliability Standard Implementation

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Association of Psychology Postdoctoral and Internship Centers INTERNSHIP MATCHING PROGRAM

SOUTHERN CALIFORNIA EDISON COMPANY

MISO-PJM Cross-Border Planning. February 19, 2014 MISO-PJM JCM

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

Transcription:

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick 2:10pm Transmission Interconnection Process II Calin Surdu 2:40pm Distribution Interconnection Process Laila Bassim 3:10pm BREAK 3:25pm Studies Overview and Data Requirements Robert Pan 3:55pm Wind Interconnection Requirements Steven Pai 4:20pm Key Dates and Reminders Bryan Corns 4:30pm Wrap-up & Thank-You Bryan Corns 2

Introduction BCTC: Market Operations and Development Rohan Soulsby Director, Market Operations and Development Bryan Corns Manager Interconnections Ryan Hefflick Client Services Manager Calin Surdu Client Services Manager Lorrie MacGregor Client Services Manager Jason Rennie Client Services Manager Jim Ko Market Operations Project Manager Brenda Ambrosi Customer Services Manager System Planning and Performance Assessment Robert Pan Interconnections Planning Manager Steven Pai Chief Planning Engineer BC Hydro: Generator Interconnection and Transmission Services Laila Bassim Specialist Engineer 3

BC Transmission Corporation (BCTC) Provincial Crown Corporation that was incorporated May 2, 2003 Responsibilities: - plan, operate, maintain, and manage BC Hydro s high-voltage electric transmission system - provide wholesale transmission services - provide interconnection services - provide open, non-discriminatory access to eligible customers for transfer capability by administering the Open Access Transmission Tariff (OATT) Operates under the Transmission Corporation Act Regulated by the British Columbia Utilities Commission (BCUC) 4

Purpose Further to BC Hydro s morning session, which provided an overview of the Clean Power Call RFP, the registration process and timeline, BCTC s afternoon session will provide general technical information required by applicants in order to participate in the Clean Power Call 5

Important Dates to Remember: October 17, 2008 - Initial Interconnection Request Submission November 17, 2008 - Complete Interconnection Application Submission 6

Second Workshop: September 15, 2008 - Time and location to be announced, all participants in this July workshop will be notified - Limited to Proponents registered in Clean Power Call and their Consultants - More detailed discussion on Interconnection Request submissions BCTC will accept Interconnection Requests for the Clean Power Call following the September workshop 7

Transmission Interconnection Process I Ryan Hefflick

9

CPC Interconnection Process: IR Submission 10

The Key to a Valid Transmission IR Submission: What Must You Do to be Successful? For Transmission Interconnections, you must provide the following to BCTC by October 17, 2008: Interconnection Request Form Provide 1 hardcopy of the Interconnection Request form, signed and stamped by a Professional Engineer, along with an electronic copy Cheque for $15,000 BCTC will start accepting Transmission Interconnection Requests (IR) for the CPC following BCTC s September 15, 2008 Interconnection Workshop 11

CPC Interconnection Process: Deficiency Review & Final Submission 12

The Key to a Valid Transmission IR Submission: What Must You Do to be Successful? For Transmission Interconnections, you must provide the following to BCTC by November 17, 2008: Completed Interconnection Request Signed Feasibility Study Agreement Second Cheque for $15,000 Proof of Site Control (Optional) 13

The Key to a Valid Transmission IR Submission: Keys to Success - Begin working on completing the IR data form Today - Seek the assistance of a qualified Engineering Services provider The Interconnection Request must be signed and sealed by a Professional Engineer licensed in BC (Requirement of the Engineering Act of BC Better chance of getting it right the first time 14

The Key to a Valid Transmission IR Submission: Keys to Success - Point of Interconnection (POI) The POI is key to the Interconnection Process The POI must be a clear and specific point on the existing BC Transmission System Control of POI» The owner of the POI must submit the IR 15

The Key to a Valid Transmission IR Submission: Keys to Success - Plant Capacity Ultimate size of the project in Megawatts Consistent with future bid to BCH Remember to account for any options for a one time increase in capacity - Plant Configuration Configuration of the project One-line diagrams 16

The Key to a Valid Transmission IR Submission: Keys to Success - Demonstration of Site Control Ownership / Lease / Right to Develop the property Option to Purchase or Lease Business arrangement with entity that has Site Control Optional at Feasibility Study stage Required prior to System Impact Study 17

The Keys to a Valid Transmission IR Submission: Keys to Success Material Change - Under the SGIP Tariff, a material change between or within a study will result in loss of queue position. To avoid this you must: Ensure that your Plant Capacity is sufficiently large to cover your one time capacity increase under the terms of the RFP Ensure that your Point of Interconnection is finalized 18

Final Reminders What you need to do Checklist You must provide to BCTC by: Interconnection Request Form Cheque for $15,000 October 17, 2008 November 17, 2008 Valid Interconnection Request Form Signed Feasibility Study Agreement Cheque for $15,000 Demonstration of Site Control (Optional) 19

Final Reminders If by 4:00 PM on November 17, 2008 the Interconnection Request is incomplete or any of the other required documents or deposit is absent, your application will be withdrawn and you will not be permitted to proceed in the Clean Power Call 20

Questions 21

Transmission Interconnection Process II Calin Surdu

Interconnection Process - Feasibility Study 23 October 17 2008 Interconnection Request to BCTC November 17 2008 4 PM PPT Final Submission Date February 23 2009 Study Report Published Mid-April through Mid-June 2009 BC Hydro Announces Successful Projects

Interconnection Process - Feasibility Study At 4:01 PM on November 17, 2008 - All Transmission and Distribution Interconnection projects that have complete applications will be assigned an Interconnection Queue position with a common date / time stamp, which ensures all projects are treated the same during the studies and evaluation. - The generation interconnection queue is located on the BCTC website http://www.bctc.com/interconnectionqueue.aspx - The Feasibility Study begins with the development of study base cases that all projects within the RFP will use. 24

25

Interconnection Process - Feasibility Study Feasibility Studies will be performed for both Transmission and Distribution Interconnections - Transmission Interconnection projects will be studied solely by BCTC - Distribution Interconnection projects will be studied by: BC Hydro for the interconnection and distribution related issues; and BCTC for Transmission and Transmission / Distribution interface issues 26

Interconnection Process - Feasibility Study The Feasibility Study will include the following studies: - Power Flow Analysis Determines if there are any overloads or voltage problems caused by the project - Short Circuit Analysis Determines if any equipment requires replacement due to increased fault levels 27

Interconnection Process - Feasibility Study The Feasibility Study will deliver: - A list of Facilities required to interconnect the Independent Power Producer to the Transmission System - A non-binding good faith cost estimate for the Interconnection Facilities - A non-binding good faith time estimate to construct the Facilities 28

Interconnection Process - Feasibility Study The Feasibility Study will be: - Delivered to the Independent Power Producer and BC Hydro on February 23, 2009 - Posted on the BCTC website on March 9, 2009 Corporate information will be removed from posted report 29

Interconnection Process Evaluation & Selection 30

Interconnection Process - BC Hydro Evaluation BC Hydro may request special studies to assist it in its evaluation 31

Interconnection Process - BC Hydro Selection Projects that are not selected will be withdrawn from the Interconnection Queue Projects that are selected will: - Move from CEAP to the SGIP process - Be tendered a Combined Study Agreement BCTC may hold a workshop for selected projects to discuss the next phase of the interconnection process 32

Interconnection Process Cost Responsibility The Independent Power Producer will pay all study costs related to the Interconnection Studies. - Interconnection Feasibility Study ($30,000 deposit) - Interconnection Impact Study ($75,000 deposit) - Interconnection Facilities Study ($150,000 deposit) BCTC only charges actual costs 33

Interconnection Process Cost Responsibility Generator ICIF POCO TPIF POI Transmission System Network Upgrades for both the sole use of the Generator and general benefit to the system NU Key Terms: Interconnection Customer Interconnection Facilities (ICIF) Point of Change of Ownership (POCO) Transmission Provider Interconnection Facilities (TPIF) Point of Interconnection (POI) Network Upgrades (NU) 34

Interconnection Process Cost Responsibility Interconnection Customer Interconnection Facilities (ICIF) - Built, owned and funded by the Customer Transmission Provider Interconnection Facilities (TPIF) - Built by BCTC - Owned by BC Hydro - Funded by the Customer Network Upgrades (NU) - Built and Funded by BCTC - Owned by BC Hydro - Covered by a Security posted by the Customer pursuant to BC Hydro s RFP 35

SGIP - Overview High level overview of SGIP is necessary to provide background for the CEAP process CEAP is in effect up to the selection of successful projects Successful projects will move into the SGIP process 36

CEAP Process (located on BCTC website www.bctc.com) 37

What BCTC Will Do For You Review IR for completeness and work with Independent Power Producer to resolve deficiencies - Up until November 17, 2008 Study individual Interconnection Requests via the Feasibility Study - November 18, 2008 to February 22, 2009 Release Feasibility Study - February 23, 2009 38

What BCTC Does to Assist BC Hydro Perform special studies for BC Hydro during its evaluation and selection process - February 24, 2009 up to June, 2009 39

Questions 40