N-1-1 Reactive Upgrades

Similar documents
2017 RTEP Assumptions for Western Sub-Region

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC

Feasibility Study on Load Flow and Short Circuit Project

Transmission Expansion Advisory Committee JCPL Supplemental Projects

Sub Regional RTEP Committee Mid-Atlantic

ISO New England Data Modeling Requirements

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

2009 SPP TransCanada Pipeline Study Report

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Public Service Company of New Mexico

Generation Interconnection Feasibility Study Report

Transient Stability Improvement of Long Transmission Line System by Using SVC

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines

MISO Transmission Planning BPM 020 Updates February 16, 2016

A guide on PowerWorld Simulator ver. 12.0

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Simulation and Analysis of Static Var Compensator with Matlab

Hybrid STATCOM / SVC Workgroup 15 th May 2014

Generation, Transmission, and End User Facilities

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Local Area Studies Update - PACW Kevin Putnam

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

System Studies for American Transmission Co. s Benson Lake SVC Project

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

FACTS and HVDC for Grid Connection of Large Wind Farms

Generation Interconnection (GI) as an Input to Multi-Driver Approach

Final Report. Mini Project TET Group nr 7 - Project nr 4. Students: Hans Lavoll Halvorson, NTNU

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM

edart Quick Reference Guide

Perry. Lakeshore. Avon. Eastlake

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC

Optimal Placement and Sizing of SVC for Improving Voltage Profile of Power System

HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM

ATC Zone 2 Projects Update U.P. Energy Summit

Voltage Control in Southwest Utah With the St. George Static Var System

Standard Development Timeline

National Load Despatch Centre Power System Operation Corporation

MISO PJM Joint and Common Market Cross Border Transmission Planning

ipcgrid 2015 March 26, 2015 David Roop Director Electric Transmission Operations Dominion Virginia Power

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

1 Description of Methodology for Volt / Var Optimization

Generation Interconnection (GI) as an Input to Multi-Driver Approach

XXXXX XXXX Wind Generation Project

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

POWER SYSTEM SECURITY CONCEPTS

ABB static var compensator stabilizes Namibian grid voltage

Voltage Profile Improvement of Transmission Lines Using Static VAR Compensator

Transient Stability Analysis with PowerWorld Simulator

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Tutorials. Tutorial: Creating a New Case Page 1 of 13

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50

Modeling and Simulation in XENDEE

Warrenton Wheeler Gainesville 230kV Reliability Project

Standard Development Timeline

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

This webinar brought to you by the Relion product family

Geomagnetic Disturbances

MISO PJM Joint and Common Market Cross Border Transmission Planning

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Smart Distribution Technology

10 th Annual University of Pittsburgh Electric Power Industry Conference

University of California, Santa Cruz Baskin Engineering School Electrical Engineering Department

Effect of Topology Control on System Reliability: TVA Test Case

Performance analysis of FACTS devices in steady state power flow

Analysis of Power System Stability by Using Optimally Located SVC and STATCOM

PowerWorld s Experience Using Real-Time Power System Models

PRC Coordination of Protection Systems for Performance During Faults

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Alternative Improving the Quality of Sub-Voltage Transmission System using Static Var Compensator

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Year Assessment Preliminary Solutions

2012 Grid Assessment Results CAISO Stakeholder Meeting September 26-27, 2012

G. Larry Clark Principal Engineer Power Delivery Alabama Power Company, A Southern Company

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

Introduction to new ABB STATCOM portfolio Power Grid Integration FACTS

Re-Dispatching Generation to Increase Power System Security Margin and Support Low Voltage Bus

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

The Efficient Way. SVC PLUS Innovation meets experience. Answers for energy.

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO

Application of overvoltage protection to the Peruvian Power System

ENTSO-E connection network codes Implementation guidance documents. Joint DSO response paper

Capacitor Only SVC Voltage Control Algorithm

USE CASE 14 CONTROLLED ISLANDING

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL

Sub Regional RTEP Committee Western Region ATSI

Real-time Power System Operation. Energy Management Systems. Introduction

Generation Interconnection Feasibility Study Report

Current Trends in UPS Technology. Voltages

Transient stability of 11-bus system using SVC and improvement of voltage profile in transmission line using series compensator

Transcription:

N-1-1 Reactive Upgrades

Previous Analysis Discussed at November 2011 TEAC Voltage collapse for multiple 500 kv N-1-1 contingency pairs A number of reactive upgrade locations evaluated to determine a optimal locations of a recommended solution Analysis included a review of several previously approved reactive upgrades 2

Status of N-1-1 Reactive Upgrades Location Altoona 230 kv Reinforcement Recommended to PJM Board December 2011 250 MVAR SVC PJM Board Status December 2011 Doubs 500 kv Loudoun 500 kv 300 MVAR switched shunt and an increase (~50 MVAR) in size of existing switched shunt 450 MVAR SVC and 300 MVAR switched shunt Pleasant View 500 kv 150 MVAR switched shunt Mansfield 345 kv Hunterstown 500 kv 100 MVAR FSS and two 100 MVAR switched shunt 500 MVAR SVC Meadow Brook 500 kv 600 MVAR SVC Petersburg 500 kv (a.k.a. Mt. Storm Valley) 250 MVAR SVC Approved for inclusion in the RTEP Decision Deferred Until Next PJM Board Meeting in February 2012 3

Mt. Storm & Mt. Storm Valley (a.k.a. Petersburg) 4

Mt. Storm - Valley Reactive Upgrade Status Previous Recommendation to PJM Board for a 250 MVAR SVC at a new station called Petersburg in the Mt. Storm - Valley Stakeholder suggestion to locate the SVC at Mt. Storm Board decision deferred pending additional review of alternatives 5

Previous Analysis November 2011 Previous analysis and subsequent recommendation for Petersburg SVC location was based on the assumption of a 1.04 p.u. scheduled voltage at Mt. Storm generation Updated analysis with Mt. Storm generation regulating to 1.05 p.u. improves performance of the Mt. Storm SVC location 6

Existing Mt. Storm bus regulation (520 kv / 1.04 p.u.): Nominal Voltage Magnitude Limit 520 kv Emergency Voltage Magnitude Limit 525 kv Mt. Storm Bus Regulation Units currently often operate in the lead (absorb MVAR) to maintain voltage Operated in the lead 75% of the hours in 2011 Not ideal for stability Proposed regulation (525 kv / 1.05 p.u.): Nominal Voltage Magnitude Limit - 525 kv Emergency Voltage Magnitude Limit - 538 kv (1.075 p.u.) Units will operate in the lag (produce MVAR) more often More stable 7

Mt Storm Petersburg Valley a.k.a. Mt. Storm - Valley 8

Mt. Storm - Valley Existing Configuration Proposed Configuration 9

Comparison of N-1-1 Transfer Capability 10

Configuration Mt. Storm Location SVC remains integrated with the remaining transmission system following any single contingency (other than the SVC) Petersburg Location SVC becomes radial following the loss of either Mt Storm to Petersburg 500 kv or following the loss of Petersburg to Valley 500 kv 11

Mt. Storm & Petersburg Considerations Criteria Violation Performance Petersburg 500 kv Mt. Storm 500 kv Equivalent both locations resolve N-1-1 criteria violations N-1 Performance Equivalent Both locations resolve N-1 reactive limits N-1-1 Performance Petersburg average transfer capability slightly higher Configuration Operations 2 Outlets SVC becomes radial post contingency Coordinate across multiple sites 8 Outlets - SVC remains integrated with the system post contingency Coordinate single site Land & ROW New Existing CPCN Required Not Required Construction Schedule Mt. Storm construction schedule is shorter Cost $45 12 $36

Recommendation Change the voltage regulation set point at Mt Storm to 1.05 pu Install 250 MVAR SVC at Mt Storm 500 kv Assign construction responsibility to Dominion 13

Hunterstown and Rio 14

Technology Previous recommendation to PJM Board to install an SVC at Hunterstown and a new station Rio located west of Meadow Brook Stakeholder suggestion a combination of Fast Switched Shunts and static capacitors would be more appropriate 15

Mt Storm Rio Meadow Brook 16

Mt. Storm Rio Meadow Brook Existing Configuration Proposed Configuration to tap existing Mt. Storm Meadowbrook 500 kv and Greenland Gap Meadowbrook 500 kv 17

SVC Reactive Reinforcement Technology Fast Switched Shunt Voltage Support Dynamic Static Control Linear Discrete (On/Off) Reactive Envelope Absorb and Produce MVAR Produce MVAR Static Capacitor Reaction Time Cycles 3 Seconds Operator Control Operations Ancillary Benefits Linear support of pre and post contingency voltage system dynamic stability, coordination, control, operations Discrete voltage support, automatically switched post contingency Can be automatically switched Discrete voltage support, manually switched 18

SVC Utilization - Performance of Solution Alternatives Output (MVAR) of reactive devices under N-1-1 conditions 19

Voltage Recovery Analysis PJM Voltage Recovery Criteria Voltage must recover to 0.7 p.u. within 20 cycles (1/3 of a second) after the fault is cleared Voltage must recover to 0.9 p.u. within 60 cycles (1 second) after the fault is cleared 20

Voltage Recovery Analysis Approximately 46 scenarios Varied outage condition, fault, and load modeling Subsequent slides demonstrate the performance difference between an SVC and Fast Switched Shunt 21

Voltage Recovery Analysis Conservative Load Modeling 250MVAr FSS is turned off and HT 500kV bus voltage is above 1.0 pu. in pre-contingency condition. Conservative load model (PL: 65%,45%,0%; QL: 65%,0%,45%) Outage condition: Conemaugh Juniata 500kV line. Contingency: three phase fault at Keystone 500kV in the line of Keystone-Juniata 500kV. 22

Voltage Recovery Analysis Voltage Recovery Analysis 2015 MAAC peak load stability case Conservative load model Hunterstown 500 kv Voltage* FSS Switches at 3 seconds Performance Fast Switched Shunt SVC * Post contingency voltage for an N-1 initial condition with an additional N-1 fault (combination CEII) 23

Voltage Recovery Analysis Stressed Import Hunterstown 500 kv Voltage* Voltage Recovery Analysis under a stressed import 2015 MAAC peak load stability case with stressed import Conservative load model Performance Fast Switched Shunt SVC * Post contingency voltage for an N-1 initial condition with an additional N-1 fault (combination CEII) 24

Voltage Recovery Analysis Hunterstown 500kV* Voltage Recovery Analysis 1.1 2015 MAAC peak load stability case Performance SVC Fast Switched Shunt Bus Voltage Magnitude (pu) 1 0.9 0.8 0.7 SVC FSS 0.6 0.5 0.0 0.5 1.0 1.5 2.0 2.5 3.0 Time (sec) *Post contingency voltage for an N-1 initial condition with an additional N-1 fault (combination CEII) 25

Voltage Recovery Analysis Hunterstown 500kV* Voltage Recovery Analysis 1.03 2015 MAAC peak load stability case Performance SVC Fast Switched Shunt Bus Voltage Magnitude (pu) 0.98 0.93 0.88 SVC FSS 0.83 0.78 0.0 0.3 0.6 0.9 1.2 1.5 1.8 2.2 2.5 2.8 3.1 3.4 3.7 4.0 4.3 4.7 5.0 Time (sec) *Post contingency voltage for an N-1 initial condition with an additional N-1 fault (combination CEII) 26

SVC Drivers Previous slides show the superior performance of the SVC compared to either Fast Switched Shunts or Static Capacitors Steady state analysis shows how the reactive output of the SVC would automatically change post contingency Dynamic analysis shows the benefits of SVC to recover voltages post contingency Ability of SVC to absorb reactive power will help to improve system voltage profile during light load periods SVC will help to improve dynamic stability SVC will help to replace dynamic reactive capability lost due to generation deactivations 27

Recommendation Install a 500 MVAR SVC at Hunterstown 500 kv Assign construction responsibility to First Energy Install a 600 MVAR SVC at Rio 500 kv Assign construction responsibility to Primary Power 28

Next Steps Review results with PJM Board on February 7 th Schedule a PJM Board conference call after March 1 st to consider recommendations Comments can be sent to RTEP@pjm.com 29