Minnesota Hosting Capacity Analysis

Similar documents
Hosting Capacity Webinar. Summary of April 28, 2017 Stakeholder Engagement Group Meeting

Feeder Hosting Capacity and Impacts of Distribution Connected Generation. NGN Tutorial. Prepared for GOTF October 22, 2017

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Minnesota DER Interconnection Process Kristi Robinson, P.E.

Hosting Capacity for Distributed Energy Resources on Distribution Feeders A Case Study

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014

JU Stakeholder Engagement Webinar

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

ENTSO-e Operational Security Network Code. OS Code Objectives. Update for JESG meeting 20 th Feb 2013

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Feasibility Study on Load Flow and Short Circuit Project

Standard Development Timeline

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

RFP Attachment 13. January 2010

Geomagnetic Disturbances

G. Larry Clark Principal Engineer Power Delivery Alabama Power Company, A Southern Company

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Integration of DER: Advanced Modeling and Simulation

Data and Forecasting Summary

Standard Development Timeline

PacifiCorp Transmission Technical Workshop

Specific topics covered in this brief include:

Electric Program Investment Charge Joint IOU Stakeholder Webinar

Microgrids and Distribution Utilities

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

Minnesota Public Utilities Commission

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

An Illinois Perspective

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019

Studies Overview and Data Requirements. Robert Pan

Smart Distribution Technology

Open Access Transmission Tariff of Southern Companies

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

PSS SINCAL Hosting Capacity Analysis. IEEE PES General Meeting 2017 Chicago - July 16-21, 2017

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A

GRID MODERNIZATION REPORT INTRODUCTION

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

From: Laura Manz, Vice President of Market & Infrastructure Development

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Grid Interconnection of Renewable Generation

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

Final Determination: Criteria for Assessing Material Inter- Network Impact of Transmission Augmentations

Smart Grid Demonstration Project

Generator Interconnection Process. Wholesale Transmission Overview

Generation Interconnection Feasibility Study Report

Integrated Grid. Barbara Tyran Executive Director, Government & External Relations. Midwest Energy Policy Conference October 2016

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

STCP22-1 Issue 003 Production of Models for GB System Planning

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

EPRI Research Plan for Advanced Distribution Automation. Mark McGranaghan Vice President EPRI Solutions, Inc

Powering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director

ENMAX Power Corporation

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

Colorado PUC E-Filings System

Distributed Generation Interconnection in Illinois

Year Assessment Preliminary Needs

Physical Security Reliability Standard Implementation

DOE Initiatives in the U.S. Transmission Sector

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

MISO-PJM Cross-Border Planning. February 19, 2014 MISO-PJM JCM

Smart Grid Task Force

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

February 22, Via Electronic Filing

October 30, Via Electronic Filing

Stakeholder Comments Template

Published: December 15, 2016 Revised: December 15, 2016

Board of Directors Meeting. April 27, 2017

Flexible Distributed Generation. FDG-A March Area (EPN) December 2016

Standard Data Exchanges for Distribution System Management

Example. Section: PS 709 Examples of Calculations of Reduced Hours of Work Last Revised: February 2017 Last Reviewed: February 2017 Next Review:

Published: December 15, 2017 Revised: December 15, 2017

Public Service Company of New Mexico

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support

Southern Company Smart Grid

2017 RTEP Assumptions for Western Sub-Region

Auction Calendar 2017/2018 for Capacity Allocation Mechanism Network Code

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.


MISO PJM Joint and Common Market Cross Border Transmission Planning

Transforming the Electric Grid

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

Electric Transmission and Distribution Future R&D Needs

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

GRID MODERNIZATION INITIATIVE PEER REVIEW

Memorandum. This memorandum requires Committee action.

NOT PROTECTIVELY MARKED. Public SPA Board Meeting Date 15 December 2016 Assembly Room, Tulliallan, Alloa

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

1 Description of Methodology for Volt / Var Optimization

Standard Development Timeline

Generation, Transmission, and End User Facilities

Grid Modernization in New York: The Role of New Technologies and Early Lessons Learned

IEEE Std 382-Draft. Status Report: April 2006

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

Transcription:

Minnesota Hosting Capacity Analysis MIPSYCON November 8, 2017 Chris Punt, P.E.

Outline What is Hosting Capacity? Background DRIVE Results Visualization Accuracy Timeline Next Steps 2

What is Hosting Capacity? The Electric Power Research Institute (EPRI) has defined hosting capacity as the amount of DER that can be accommodated on the existing system without adversely impacting power quality or reliability. 3

What is Hosting Capacity? Fundamental Requirements 4

What is Hosting Capacity? Differing Methodologies Iterative vs. Streamlined Iterative More data intensive More accurate for interconnection studies Streamlined Faster processing 5

What is Hosting Capacity? Usage 6

Background Minn. Stat. 216B.2425, subd. 8. requires that a utility operating under an approved multiyear rate plan: shall conduct a distribution study to identify interconnection points on its distribution system for small-scale distributed generation resources and shall identify necessary distribution upgrades to support the continued development of distributed generation resources, and shall include the study in its report required under subdivision 2. 7

Background 12/1/15 Filed first Grid Modernization Report 6/28/16 MPUC Order to complete Hosting Capacity Analysis 12/1/16 Filed first Hosting Capacity Report 3/20/17 Filed Supplemental Comments due to MPUC Information Request 5/05/17 Filed Reply Comments addressing all stakeholders concerns 6/15/17 MPUC Hearing 8/01/17 MPUC Order for next analysis 11/1/17 Filed second Hosting Capacity Report 8

Background August 1, 2017 Commission Order Detailed enough to provide developers with a starting point Detailed enough to inform future Distribution System Planning Efforts Downloadable results Provide methodology, assumptions, details, etc. in Report Report on accuracy of the analysis File Hosting Capacity report on annual basis (November 1 st ) Color coded map 9

DRIVE Distribution Resource Integration and Value Estimation Developed by EPRI Utilizes Synergi models Produces tabular and visual results User Group Widely Utilized NY Joint Utilities Southern Co Salt River Project TVA 10

DRIVE Methodologies Analysis: Adds DER to the feeder Small Distributed Large Centralized Large Distributed 11

DRIVE 2017 Key Analysis Assumptions 0.98 leading power factor of new DG installations Daytime Minimum loading at 20% of Peak Substation and Transmission Capacity exists Year ahead capacity projects added Solar Gardens Anticipated additions through signed interconnection agreements 12

DRIVE Power Factor Impact Unity => 2.5 MVA 0.98 => 5.0 MVA 0.95 => 8.75 MVA 13

DRIVE Thresholds 14

DRIVE Minimum Hosting Capacity The Maximum Amount of DER that can be accommodated anywhere on the feeder Maximum Hosting Capacity The Maximum Amount of DER that can be accommodated at one point on the feeder 15

Results 2017 1047 feeders Average min hosting capacity = 1.5 MW Approximately 75% limited by Over-Voltage and 25% limited by Thermal Overloads Small percentage limited by reduction of reach, additional fault current, and voltage deviation 177 feeders with zero hosting capacity 619 feeders with 1 MW or greater of hosting capacity Average max hosting capacity = 6.1 MW Feeders with more hosting capacity had: Higher concentration of load Shorter feeder lengths Higher voltages 16

Results 17

Visualization Mapping Results Security vs. Usability https://www.xcelenergy.com/working_with_us/how_to_interconnect/hosting_capacity_map_disclaimer 18

Accuracy Hosting Capacity is difficult to compare to Interconnection Studies Different models and modeling techniques Changing Criteria Differing Assumptions Interconnection studies didn t originally contain baseline hosting capacity Many of the hosting capacity results already contained projects that had been studied Processes are evolving and will better align and stabilize with each iteration 19

Accuracy Compared 15 Locations Mostly favorable results Hosting Capacity was conservative where unfavorable 20

Timeline 2017 Process 21 Pre Work (January - May) GIS improvements and map testing Upgrade and Test software DRIVE and Synergi Threshold setting and buy-in Synergi Training/Documentation Source Impedance creation Build Models (June - August) => Integrate with planning cycle in future Model existing generation Utilize forecasted 2018 peak data and interconnection queue process Run DRIVE to perform the analysis (August - September) Format results and map (September - October) Write Report (October)

Next Steps Distribution Planning Part of Process Utilize Results Continued Improvements Tool Modeling Process improvements Mapping Detail Features Industry Collaboration Methods for Increasing Hosting Capacity * Source: ICF Integrated Distribution Planning Report 22