Want to make your inspectors happy?

Similar documents
Microinverters And The Solar Industry

Rapid Shutdown Requirements for NEC 2017

Electrical Integration of PV Systems. Ridha Hamidi, Ph.D.

More Questions from Inspectors Numerous PV Systems Pose Issues

M250 (M LL) Safety

M215 (M215-60) Safety

Enphase S-Series Microinverter and Engage Cable Safety

M215 Microinverter Installation Planning

Model Number Electrical Compatibility Module Connector Type M LL-S22 M LL-S22-NA M LL-S23 M LL-S23-NA

Stalking the Elusive and Somewhat Strange PV System

M215-Z Safety Information (M LL-IG-ZC)

Introduction to the Inspection Checklist for Rooftop Solar Photovoltaic (PV) Systems in Goshen, IN

M215 Safety (M LL-S22-IG / S23-IG / S24-IG)

Installing Enphase M250 and M215 Microinverters

Installing Enphase IQ 6 and IQ 6+ Microinverters

PV Rapid Shutdown device

Installing Enphase IQ 7, IQ 7+ and IQ 7X Microinverters

Bulletin Installation of solar photovoltaic systems Rules , , , , and

DOWNLOAD PDF ENPHASE M250 INSTALLATION GUIDE

1. Section Lightning Protection for lightning protection system. D. The installation shall be in conformance with NEC Article 285.

Entry Level Assessment Blueprint Electrical Occupations

CALIFORNIA ERIC GARCETTI MAYOR

FORM FOR PROPOSAL FOR 2014 NATIONAL ELECTRICAL CODE

Enphase Engage Cable and Accessories

TECHNICAL BRIEF. Planning for an IQ Microinverter System. IQ 6 and IQ 6+ Micros

Installation/User Manual

Installation / User Manual

SECTION TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

Bulletin Installation of Solar Photovoltaic Systems Section 50; Rules: , , ; Tables 11 and 19 Issued July 2010

Enphase IQ 7, IQ 7+, and IQ 7X Micros

Installation Guide for America Solar Wholesale Photovoltaic Modules

Enphase M215 (original)

Enphase IQ 6 and IQ 6+ Micros

Enphase IQ 7, IQ 7+, and IQ 7X Micros

Installation and Operations Manual. Enphase Microinverter Models M190 and M210

SolarEdge SolarEdge, Enphase Value Comparison July 8, 2011

Enphase IQ 6 and IQ 6+ Micros

Spring Test 9 due 05/11/2013

Enphase M215 Microinverter , Rev 06

Installation and Operations Manual. Enphase Microinverter Model M215

Enphase Microinverter Model M215

Enphase M215 Microinverter , Rev 06

Spacing Requirements for Power Distribution and Terminal Blocks

Installation and Operations Manual. Enphase Microinverter Models M190 and M210

Increasing Data Center Efficiency by Using Improved High Density Power Distribution

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

Switch-disconnectors OTDC and OTDCP Switches for photovoltaic applications

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

AC Solar Warehouse Installation and Commissioning Checklist

ADDENDUM FOR 20, 27, & 28 OPTIONS

RESIDENTIAL PV OPTIMIZATION WITH SMA POWER+ SOLUTION

Installation and Operations Manual Micro-Inverter M S

An Urgent Bulletin from CSA Group

SIEMENS HEALTHCARE INTEGRATED ELECTRICAL CABINET

Enphase M250 Microinverter

Enphase M250 Microinverter

G320 I C R O I N V E R T E R U S E R M A N U A L

Installer Summit August, 2015 Mark Farrelly Global Business Director

DIVISION 16 SECTION Surge Protective Device Submittal (SPD)

Product Details. Contents. Features and Mounting Options for SUNNY STRING-MONITOR SSM24-11

File E Project 91SC COMPONENT POWER SUPPLIES INFORMATION TECHNOLOGY EQUIPMENT INCLUDING ELECTRICAL BUSINESS EQUIPMENT

Posi-Lok Plugs and Panels

PLT. Breaker-based transfer switch open, closed or soft transition amps. Specification sheet

System Design Guide. APsystems YC Photovoltaic 3-Phase Grid-connected Microinverter. APsystems. Version 1.1 3/15

Quick Start Guide TS A

Installing Enphase IQ 7, IQ 7+ and IQ 7X Microinverters

Eaton s Innovative Technology Surge Suppression Guideform Specification High Exposure DIVISION 16 SECTION 16289


Eaton s Innovative Technology Surge Suppression Guideform Specification Low Exposure DIVISION 16 SECTION 16289

Spring Test 5 due 4/26/2013

Explosion-Protected Arc-Fault Protection ExAFCI Arc-Fault Circuit Interrupter

1. Coordination of series-rated devices is permitted where indicated on Drawings.

Omnitron Systems Technology, Inc. 1. iconverter. 19-Module Managed Power Chassis User s Manual

SECTION (16410) - ENCLOSED SWITCHES AND CIRCUIT BREAKERS

2G Engine Installation

Document C0. Use for:

CenterPoint Energy P O Box 1700 Houston, TX

Residential Storage Solution for North America. Accessory: Rapid Shut-down System (RSS) Features:

Installation/User Manual

PDI Modular Compact Remote Power Panel

INSTALLATION AND COMMISSIONING CHECKLIST

ASCO 920 Remote Control (RC) Switches

ProHarvest PRO208 5k75 (HiQ TS208 5k75) Inverter System Installation & Safety Manual

Instruction Manual. Electrical Management System (EMS) EMS-HW30C & EMS-HW50C

SolarEdge. Distributed Solar Power Harvesting Systems. Installation of the SolarEdge System SolarEdge

Dual-Feed 80A Auto Low Voltage Disconnect Panel - 80LVD02

Spring Test 17 due 06/14/2013

iconverter 2-Module Power Chassis

UL TEST REPORT AND PROCEDURE

920 Remote Control (RC) Switches

Please carefully read the following installation and safety instructions. Non-compliance with these instructions may void the module warranty.

UL TEST REPORT AND PROCEDURE

Issued February DATA SHEET 5SX2 MCB. Based on Siemens Industrial Control Catalog

Instructions. Interconnection Customer declares its intention to interconnect with the AEP Distribution System.

HIGH POWER CONTACT ELECTRICAL SPECIFICATIONS

Installation and Operations Manual. Enphase Micro-Inverter Models M and M

Interconnection Application

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

Installation / User Manual

Transcription:

Want to make your inspectors happy? Mark Baldassari Director, Codes and Standards

Agenda Inspectors How to make your inspector happy Common Misconceptions Installing Microinverters Disconnect Means Grounding Particularly UL 2703 Rapid Shutdown 2

How to make your inspector happy? Find out what they want Get all the data they need Site plans Single line drawings Data sheets Check your calculations Conductor sizing, insulation type, temperature rating OCPD sizing, branch and main Busbar Ampacity Make your submittal package consistent Make every package look like the last If changes are made on site then update the permit 3

Disconnecting Means

Disconnecting Means Readily and Non-Readily Accessible Locations Section 690.15 - Inverters have disconnects from all sources of power Required for maintenance Shall be grouped at or within sight of the inverter Section 690.6 - Alternating-Current Modules (ACM) are exempt from dc circuit requirements, including; disconnects GFI, etc But, section 690.6(C) does require an ac disconnect Microinverters and ACMs located not readily accessible locations Section 690.15(A) requires inverters mounted in not readily accessible locations to have ac and dc disconnects at the inverter Section 690.13(A) requires an additional ac disconnect located in a readily accessible area, normally at ground level This disconnect could be a utility-required ac disconnect or backfeed breaker in a load center 5

Disconnecting Means - Connectors Section 690.17(E) Exception permits connectors to be used as ac and/or dc disconnecting means Must be listed and identified for use and meet the requirements of 690.33 Section 690.33(B) Guarding Touch safe Section 690.33(E)(1) Requires a tool to disconnect load-break rated connectors All Enphase Microinverters connectors have been certified by an NRTL for load-break operation, they are guarded, and are located within sight of the inverter 6

Grounding and Bonding

System Grounding Neutral Bar is bonded to Ground Bar through Main Bonding Jumper Ground Bar is bonded to Grounding Electrode through Grounding Electrode Conductor (GEC) Equipment Grounding Conductor (EGC) bonded to Ground Bar GEC is required because a current-carrying conductor (neutral) is intentionally bonded to ground 8

Lay-In Lug Bonding Bond to ground PV Modules, Racking, Microinverters Lay-in lugs on each module, bonded together through Array EGC Microinverter EGC bonded to Array EGC then homerun to Main Panel 9

UL 2703 Certified System Modules bonded to racking through UL 2703 device Microinverters bonded to racking through UL 2703 device Enphase Microinverters and Engage Cable system is UL certifies under a Component Recognition as a bonding component for UL 2703 racking systems Microinverter EGC provides grounding for the array 10

690.12 Rapid Shutdown

690.12 Rapid Shutdown of PV Systems on Buildings Required for buildings Residential and Commercial Not required for ground mount, carports, or detached garages Requirement for controlled conductors 1.5 m (5 ft) inside a building 3 m (10 ft) from a PV array Controlled conductors limited to not more than 30 V and 240 volt-amperes within 10 seconds 12

Rapid Shutdown Initiator Enphase Microinverters meet these requirements. They always have and always will RSS is initiated by ac circuit breaker Utility-interactive microinverters will shut down within 2 seconds as verified under UL 1741 certification All conductors in controlled zone are forced to 0 V at 0 amps in less than 2 seconds 13

Summary

Key Points Inspectors Find out what they want Make your submissions consistent Common Misconceptions Installing Microinverters Disconnect Devices Enphase Microinverter connectors meet the requirements Grounding Particularly UL 2703 Save money, save time, improved grounding Rapid Shutdown System Enphase Microinverters meet NEC requirements. They always have and always will 15

Resources Permitting Solar American Board of Codes and Standards Expedited Permit Process http://solarabcs.org/about/publications/reports/expedited-permit/index.html CA Governor s Office of Planning and Research Solar Permitting Guidebook http://www.opr.ca.gov/s_renewableenergy.php Disconnecting Means Enphase Energy Support, search for disconnect https://enphase.com/en-us/support/technical-brief-connectors-ac-disconnects-pvapplications-interpreting-nec-requirements-60 Grounding and Bonding Enphase/ Unirac UL 2703 Bonding video https://www.youtube.com/watch?t=23&v=9gm_vvebatk Rapid shutdown Enphase Energy Support, search for disconnect https://enphase.com/en-us/support/enphase-topic-brief-rapid-shutdown 16

Questions 17