Interconnection and Transmission

Similar documents
Generator Interconnection Process. Wholesale Transmission Overview

Interconnection Re-MAT September 11, 2013

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Small Hydro Regulatory and Permitting Requirements California

INTERCONNECTION FACILITIES STUDY REPORT

Agreements and Queue Management

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Grid Interconnection of Renewable Generation

Agreements and Queue Management

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

Southern California Edison. Leading the Way in Electricity TM

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014

Agreements & Queue Management

PG&E Transmission Interconnection Handbook

July 26, Dear Mr. Millar:

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012

Generation, Transmission, and End User Facilities

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Feasibility Study on Load Flow and Short Circuit Project

Overview of DSASP; Telemetry/Communication Alternatives

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report

November 29, ECE 421 Session 28. Utility SCADA and Automation. Presented by: Chris Dyer

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Southern Company Smart Grid

From: Laura Manz, Vice President of Market & Infrastructure Development

TransWest Express Transmission Project Interregional Transmission Project Submittal

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Updates and Modifications to Report

Introduction to the NYISO

Copyright 2013 OSIsoft, LLC. 1

SDG&E s Accomplishments and Future Plans

October 05, ECE 421 Session 12. Utility SCADA and Automation. Presented by: Chris Dyer

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017

Chapter 2 State Estimation and Visualization

Smart Grid Development in Ho Chi Minh City

Preparing for the unexpected: Transmission Planning in ERCOT

DUKE ENERGY OHIO SMART GRID / GRID MODERNIZATION. Don Schneider GM, Smart Grid Field Deployment May 24, 2012

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012

A.I Task Order 1 - Technical and Analytical Services 1. SCOPE OF WORK. Deliverablc(s): CPUC Implementation Plan Filed. EXHIBIT A: Scope of Services

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Electric Utility Facility Connection Requirements

The current state of the electrical grid And the technologies that will enable its transformation

_ Dear Secretary Bose: The attached. Folsom, CA

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

Electric Program Investment Charge Joint IOU Stakeholder Webinar

T&D Challenges and Opportunities

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM)

Smart Grid Vision DRAFT FOR DISCUSSION PURPOSES ONLY

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.

ATTACHMENT I: Generator Interconnection Procedures (GIP)

Reliability Coordinator Procedure

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,

Specific topics covered in this brief include:

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

PacifiCorp Transmission Technical Workshop

Peak Reliability Coordination Services in the West March 30, 2018

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013

Electric Access System Enhancement (EASE)

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

REAL-TIME MONITORING DATA SPECIFICATION

Smart Distribution Technology

Evolution of Control for the Power Grid

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

Q44 Generation Interconnection

Entergy Arkansas, Inc. Transition Plan Technical Conference #1

Western States Power Crisis EPRI White Paper - An Overview -

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

THE INTERCONNECTION HANDBOOK

Advanced Monitoring Technologies for Grid Reliability, Market Efficiency, and Grid Security

WN U-60 Original Sheet No. 152

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Glencoe Light and Power

Standards. Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

Advanced Protection and Control Technologies for T&D Grid Modernization

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

LADWP POWER INFRASTRUCTURE PLAN

RFP Attachment 13. January 2010

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Appendix I: LOAD OPERATING AGREEMENT

Transcription:

Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015

Interconnection and Transmission Topics Covered Interconnection Studies Voltage Considerations Transmission vs. Distribution System Connection Power or Load Flow Interconnection Standards Application Processes Costs and Timing Network vs. Direct Assignment Upgrades & Costs Financial Security Interconnection Agreement Curtailment Issues Economic / congestion / Over-Generation Emergency / dispatch down

Interconnection Studies Purpose: Determine impacts on the transmission and/or distribution Determine cost to interconnect utility facilities Determine system upgrade costs trans. & dist. Study Types: Fatal Flaw or Initial Site Assessment Feasibility System Impact Facility Operational

Voltage Considerations Transmission Level: Dependent on specific utility 69kV to 500kV Dependent on generator resource size Directly affects the cost to interconnect Distribution Level: 12kV to 69kV, possibly as low as 4160v Generally there are capacity limits on lower voltage lines; i.e. ~ 10 MW on a 12kV Line More sensitive to voltage fluctuations

Transmission Access Considerations Proximity of transmission lines and substations Available Transmission Capacity Interconnection Facilities and Cost Tap, loop-in, available breaker position; project size Planned transmission upgrades Transmission Service / Wheeling Charges going across BA boundaries

Transmission vs. Distribution System Connection Effects on Interconnection Costs ( Tap to an existing line) 500 kv Tap Unavailable 230 kv Tap Unavailable 115 kv - $1M to $3M 69 kv - $0.5M to $2M This would include: Possible pole-line reconfiguration SCADA controlled switches Direct Transfer Trip (DTT) Telecom

Transmission vs. Distribution System Connection Effects on Interconnection Costs ( Loop-in station to an existing line) 500 kv - $25M to $40M (generally the utility won t segment a 500 kv line) 230 kv - $20M to $30M 69 kv or 115 kv - $7M to $15M This would include: Transmission line reconfiguration New or expanded switching station RTU / Telecom CTs/PTs Breakers, disconnects Protection relays

Interconnection Standards Need Grid Reliability and Stability to Overcome and Compensate for Intermittency Low Voltage Ride-Through (LVRT) Frequency Disturbance Ride-Through Capability Power Factor (Reactive Power) Set-point Capability Supervisory Control and Data Acquisition (SCADA) Capability Coming Soon Ramp Rate Limits & Control Up and Down Remote set-point control (voltage / power factor) Controlled Dispatch or Power Management

Application Processes Costs and Timing Transmission FERC Jurisdictional Large Generator Interconnection Procedures (LGIP) Large Generator Interconnection Agreement (LGIA) RTO/ISO/Utility Variations Exist Cluster Process Independent Study Fast Track (up to 5 MW) Serial Process o Feasibility Study o System Impact Study o Facilities Study

Application Processes Costs and Timing Distribution Wholesale Distribution Access Tariff (WDAT) FERC jurisdictional wholesale energy sales generally follow the LGIP process Rule 21 (CA CPUC Jurisdictional) - Similar to IEEE-1547 Serial Process o Initial Review (Fast Track Screening up to 3 MW) o Supplemental Review o System Impact Study o Facilities Study Included in CAISO Cluster Process for Deliverability Assessment

Application Processes Costs and Timing The Interconnection Request (IR) Example Application Deposits CAISO - $50,000 plus $1000/MW ($250K max.) PG&E/SCE/SDG&E WDAT - $50,000 plus $1000/MW LADWP - $250,000 IID $250K for >20 MW; $150K for =< 20 MW APS - $250K for >75 MW; $160K for =<75 MW NVE - $10,000 (referred to as Pre-Application Deposit) WAPA/WALC - $10,000

Study Timelines Serial Process Feasibility 45 to 60 days; $25k to $35K System Impact 90 to 120 days; $50k to $75K Facilities 120 days; $75K to $100K Cluster Process Aggregate impact of multiple interconnections One or two study windows per year (CAISO has 1 window per year) Phase 1 and Phase 2 Study process ~ 2 years Example CAISO Sub Groupings within a Cluster Fresno-Kern region for PG&E North of Lugo (SCE) part of East of Lugo Bulk System

Network vs. Direct Assignment Upgrades & Costs Network Transmission System Upgrades supporting Reliability and Deliverability or Network Service o Line Reconductoring or New Transmission Lines o Circuit Breaker upgrades due to exceeding SCD o Transformer replacement o Special Protection Schemes (SPS) Direct Assignment Distribution System upgrades and Utility Interconnection Facilities o Point of Interconnection (POI) facilities o Dist. Line Reconductoring o Dist. Facility upgrades (breakers, fuses, reclosers, etc.)

Network vs. Direct Assignment Upgrades & Costs Network Upgrades Reimbursable o Reimbursed via transmission service credits o Reliability Network Upgrades (RNU) reimbursed up to $60,000 per MW (CAISO) following Commercial Operation o Deliverability Network Upgrades (DNU) reimbursed 100% (under CAISO Phase 2 Option A approach) following Commercial Operation Direct Assignment Non-Reimbursable cost to project

Financial Security Relative to the CAISO and PTO WDAT Cluster Study Process o Security Posting due following Phase 1, Phase 2, and at the start of Construction o Phase 1 Financial Security (FS) due 90 Calendar Days following issuance of Phase 1 Study Report (60 CDs following issuance of System Impact Study report for Independent Study Process) o Phase 1 FS (two FS postings required) Network Upgrades: Lesser of $20,000/MW; or 15% of allocated Network upgrade estimated costs; or $7.5M (for Large Generators); and no less than $500K For Small Generators: Lesser of $20,000/MW; or 15% of allocated Network upgrade estimated costs and no less than $50K

Financial Security cont... Relative to the CAISO and PTO WDAT Cluster Study Process o Phase 1 FS (two FS postings required) cont. PTO Interconnection Facilities FS: Lesser of $20,000/MW; or 15% of allocated Interconnection Facilities estimated costs; or $7.5M (for Large Generators); and no less than $500K For Small Generators: Lesser of $20,000/MW; or 15% of allocated Network upgrade estimated costs and no less than $50K o Phase 2 Financial Security (FS) due 180 Calendar Days following issuance of Phase 2 Study Report (120 CDs following issuance of Facilities Study report for Independent Study Process)

Financial Security cont... Relative to the CAISO and PTO WDAT Cluster Study Process o Phase 2 FS (two FS postings required) cont. Network Upgrades: Lesser of $15M; or 30% of allocated Network upgrade estimated costs and no less than $500K for Large Generators); For Small Generators: Lesser of $1M; or 30% of allocated Network upgrade estimated costs and no less than $100K PTO Interconnection Facilities FS: Lesser of $15M; or 30% of allocated Interconnection Facilities estimated costs; and no less than $500K for Large Generators For Small Generators: Lesser of $1M; or 30% of estimated Interconnection Facilities costs and no less than $50K o 3 rd Financial Security Posting is 100% due at the start of Construction

Interconnection Agreement Contract or Agreement between the Interconnecting Utility and the Generator. For CAISO Controlled Grid Interconnections this is a three party agreement. Agreement incorporates the engineering, procurement, construction and operation of the Generator s facilities interconnecting to the Transmission Owner s electric system. Incorporates the results of the Facilities Study or Phase 2 Study results LGIA or SGIA (Large and Small Generator Interconnection Agreements) are generally pro forma contracts (no touch)

Interconnection Agreement cont... Negotiations are limited to the Attachments to the IA. o o o o o o Interconnection & Transmission Description and Costs of the Generating Facilities Upgrades and Interconnection Facilities, Single-Line diagram and Metering Equipment Milestones: Contract performance, Utility In-Service Dates, Synchronization Date, Trial Operation Date, Commercial Operation Date (COD) Special or Additional Operating Requirements Affected Systems interaction Utilities Upgrades and estimated upgrade costs (transmission, distribution, SPS, communications) Interconnection Requirements (LVRT, FRT, PF, SCADA)

Curtailment Issues A key issue from a due diligence perspective Probability Duration and quantity Timing of occurrence Economic / congestion / Over-Generation Generally, self-scheduled renewable resources are the last to be curtailed. Curtailment would be prioritized economically with price-sensitive generator offers first in line Curtailments applied where most effective mitigation is possible Potential in Spring cases when Loads are light and sun is bright

Curtailment Issues cont.. Dispatch Down is essentially describing events that could effectively cause a generating facility to be either ordered to reduce energy production; or be removed, separated or otherwise caused to cease energy flow to the system. System Owners and Operators are bound to protect the system Effected by Scheduled and Unscheduled maintenance Ongoing scheduled outages to accommodate system upgrades Emergency or Forced outages due to storms and fire Terms and Conditions generally addressed in PPA

Interconnection and Transmission

ZGlobal Inc. MANAGEMENT TEAM WITH HANDS-ON EXPERIENCE AND IN-DEPTH KNOWLEDGE OF CALIFORNIA AND WESTERN ELECTRICAL GRIDS ZGlobal leadership team members: Played a significant role in operations and planning for Pacific Gas & Electric s and Imperial Irrigation District s electric grid operation, transmission and procurements from 1971 2000. Led the initial start-up team that designed, implemented and operated the CAISO Electricity Market and the Electric Grid from 1998 2004. Led the implementation of the CAISO Nodal Market. Directed CAISO Grid Operations from 2000 2011 including: The design and implementation of CAISO s new state-of-the-art control center located in Folsom, Ca. and it s backup center in Southern California. Implemented the Synchrophasor System, which increases the grid operators visibility of bulk power system conditions in near real-time, and enables earlier detection of problems that threaten grid stability or cause outages.

Services Provided T&D Planning and Engineering Energy Markets and Reliability Analysis Infrastructure Development (DG) Market Analytics Our Clients Generation Owners and Developers State and Federal Agencies Local Public Power and Irrigation Districts Regulated and Non-regulated Utilities Water Agencies and Districts Private Equity, Banks and Hedge Funds Regulators Large Industrial and Manufacturing Entities Electric Operations (24x7) Infrastructure Development (T & D & G) T&D Planning & Engineering

T&D Planning & Engineering Interconnection and Transmission Transmission & Distribution Engineering & Planning Services Generation Interconnection T&D Planning T&D Planning & Design System Impact & Facility Studies Power Flow & Stability Analysis Detailed Engineering Design T&D Engineering Owner s Engineering Staff Emerging Technologies