CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012

Similar documents
Expanding Metering and Telemetry Options Technical Stakeholder Initiative

Table of Contents. Purpose. Meter Data Acquisition and Processing Procedure. Procedure No Version No. 1.3 Effective Date 2/14/2018

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

EIM Entity Readiness Criteria May 6, 2015

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Small Hydro Regulatory and Permitting Requirements California

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

New Resource Implementation & Market Modeling

GO15 Reliable & Sustainable Power Grids

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

CAISO RIG Acceptance Test Procedure

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.


Interconnection and Transmission

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Table of Contents. Purpose. Certification of Metering Facilities. Procedure No Version No. 1.4 Effective Date 2/14/2018. Operating Procedure

Agreements and Queue Management

Agreements and Queue Management

BPM Proposed Revision Requests (PRR): Summary Report Attachment 2

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

Demand Response User Guide DRRS Enhancement Market Simulation. Version 1.0 August 18, 2016

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

Stakeholder Comments Template. Energy Storage and Distributed Energy Resources (ESDER) Phase 4. Submitted by Organization Date Submitted

Agreements & Queue Management

Overview of DSASP; Telemetry/Communication Alternatives

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

Generator Interconnection Process. Wholesale Transmission Overview

State Perspectives on the Midwest ISO regional Stakeholder Process: The Indiana Utility Regulatory Commission

From: Laura Manz, Vice President of Market & Infrastructure Development

Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative. Revised Scope and Schedule

_ Dear Secretary Bose: The attached. Folsom, CA

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

FERC Order 841: Leveling the Playing Field for Energy Storage Resource Market Participation April 4, 2018

Standard TOP Transmission Operations

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Specific topics covered in this brief include:

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Microgrid Automation on an IOT Backbone

Coordinate Interchange

Coordinate Interchange

TOP for Transmission Operators

Meter Configuration and RIG Details Checklist

Modifications to TOP and IRO Standards

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements

Introduction to the NYISO

ENERGY MANAGEMENT SYSTEM. ABB Ability Network Manager EMS Operational confidence.

Electric Program Investment Charge Joint IOU Stakeholder Webinar

Business Practice Manual Change Management Meeting

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Storage Integration

Distributed Generation Requirements Update

Chapter 8: Smart Grid Communication and Networking

primary Control Center, for the exchange of Real-time data with its Balancing

Smart Grid Vision DRAFT FOR DISCUSSION PURPOSES ONLY

Stakeholder Comments Template

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Electric Access System Enhancement (EASE)

Business Practice Manual Change Management Meeting

Reliability Coordinator Procedure

Entergy Arkansas, Inc. Transition Plan Technical Conference #1

Market Participant User Guide ISO Reliability Requirements Application (IRR UI)

Grid Interconnection of Renewable Generation

Modifications to TOP and IRO Standards

FNM Expansion Training Webinar

Data Release & Accessibility

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

Business Practice Manual Change Management Meeting

Standard INT Dynamic Transfers

Powerex EIM Implementation Informational Call. Mark Holman, Powerex Don Tretheway, California ISO October 3, 2017

Bright Ideas: Member Feedback Process

Glencoe Light and Power

Standard Development Timeline

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

Uninstructed Deviation Penalty Charge Types 4470, and 4480

Energy Imbalance Market Technical Workshop. BAA Real-Time Congestion Balancing Account August 12, 2013

Standard CIP Cyber Security Critical Cyber As s et Identification

TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

CPS Energy Metering Strategies. Anthony Hawkins Senior Project Manager Energy Delivery & Solutions

Decorah City Council - January 16, Decorah Power Municipal Electric Utility (MEU) Feasibility Study

The current state of the electrical grid And the technologies that will enable its transformation

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

Standards. Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013

Integrated Resource Planning April 20, 2010

Standard INT Dynamic Transfers

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

1. Responsibilities. Settlement Quality Meter Data (SQMD) Plan Submission & Approval Process (External) Operating Procedure

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

SOUTHERN CALIFORNIA EDISON COMPANY

Jim Brenton Regional Security Coordinator ERCOT Electric Reliability Council of Texas

Standard CIP Cyber Security Critical Cyber As s et Identification

Transcription:

CAISO Metering & Telemetry Requirements Jeremy Laundergan - Director, EnerNex November 8, 2012

Background and Overview Both federal and state regulatory authorities are advocating the participation of Distributed Energy Resources (DER) in wholesale electricity markets Intermittent renewable resources like Solar and Wind Demand Response (DR) resources. Market rules and requirements for metering and telemetry were developed over many years with large capacity generation resources in mind. A review of the existing metering and telemetry requirements has the potential to identify alternative requirements and technical solutions that meet the California ISO needs for resiliency and reliability. 2

Project Description The CAISO has multiple documents that describe metering and telemetry processes, guidelines & requirements These document provide a mix of "true" requirements (technology independent functional and non-functional business and technical requirements - the what) And specific technology or implementation requirements or specifications (the how) This project analyzed the documentation and captured the requirements in a matrix that maps the business and operational requirements to the required implementation technology attributes. 3

Project Goal This project is part of the first phase in a multi-phase project to Review the metering and telemetry documents Link them in a traceable fashion to the underlying rationale Evaluate technology alternatives that might support those base requirements. The goal is to provide the CAISO, external entities and interested stakeholders a more diverse set of options clearly linked to market and resource types and their specific operational and business requirements with associated costs. 4

Phased Approach The is a four phase project. This first phase completed Research to identify metering and telemetry requirements from existing CAISO documentation A summary of metering and telemetry requirements and a categorization of their attributes including Requirement Type (functional, non-functional, business rule) Applicable Metered Entity (ISO, Schedule Coordinator), Markets (day-ahead, real-time), Market Product (Energy, Ancillary Services), Resource Type (Generator, Intermittent, Demand Response), CAISO System and/or Generator System, Resource Size Applicable Standard. 5

Documents Reviewed CAISO Fifth Replacement FERC Electric Tariff Business Practice Manual for Metering G001-New Meter Installations G002-Unscheduled Meter Outages G003-Change of Metered Entity Ownership Business Practice Manual for Direct Telemetry RIG Engineering and Deployment Guide RIG/DPG Validation Procedure Scheduling Coordinator Agreement Meter Service Agreement for ISO Metered Entities Meter Service Agreement for Scheduling Coordinators California ISO Station Power Program Overview "Station Power Portfolio Application Form" Procedure: Station Power Portfolio Application Engineering Specification for Polyphase Meters (MTR 10-99 ISO Meter Maintenance Form G004-Scheduled Communication Outages G005-Routine Testing/Maintenance of CAISO Meters G006-Validation, Estimation and Editing G007-CAISO Metering Guideline Netting G008-CAISO Metering Guideline Manual Meter/Recorder Reading G009-ISO Meter Inspection G010-Exemption from Compliance G012-ISO Meter Audit 6

Resource Types with Specific Requirements Aggregator Automatic Generation Control (AGC) Demand Response Eligible Intermittent Resources (EIR) Generator Intermittent Intermittent - Solar Intermittent - Wind Intermittent, Proxy Demand Resource (PDR) Proxy Demand Resource (PDR) Qualifying Facility (QF) 7

Systems with Specific Requirements Automated Dispatch System (ADS) Energy Communications Network (ECN) Energy Management System (EMS) Remote Intelligent Gateway (RIG) Revenue Meter Data Acquisition and Processing System (RMDAPS) Scheduling and Logging for ISO of California (SLIC) Settlement Quality Meter Data System (SQMDS) Supervisory Control and Data Acquisition (SCADA) 8

Business Needs satisfied by Requirements Accuracy Contingency Facility Modifications Meter Service Agreement Security Additional Metering Cyber Security Forecast Netting Settlement Aggregation Data Access Inspection Notification Settlement Quality Meter Data (SQMD) Approval Data Collection Installation Outage System Compatibility Audit Data Format Line Loss Correction Performance Telecommunications Authority Data Interval Load Profiles Physical Security Testing Availability Data Retention Load Schedule CAISO Payments Calendar Data Storage Locatonal Marginal Pricing (LMP) Point of Delivery (POD) Redundancy Third Party Access CAISO Time Standard Deadband Low Voltage Side Reliability Validation Capacity Limit Direct Meter Connection Maintenance Certification Documentation Meteorological Command & Control Exception & Error Meter Communications Responsibility Revenue Quality Meter Data (RQMD) Revoke Configuration Exemption Meter Data Access SCADA Transmission Charges Voice Communications 9

Conclusions & Recommendations This phase of the project successfully captured and associated 932 requirements from 25 documents This is a first step in developing more flexible and economically feasible metering and telemetry options The project team recommends pursuing subsequent phases: Phase 2: Review, Compare and Summarize other ISO and Regional Transmission Organization (RTO) Documentation Phase 3: Technology Assessment, Implementation Options, Cost and Recommendations Phase 4: Update CAISO Documentation Phase 5: Pilot Deployment of Selected Options 10