UK EPR GDA PROJECT. Name/Initials Date 30/06/2011 Name/Initials Date 30/06/2011. Resolution Plan Revision History

Similar documents
Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Criticality control in SFP. Radwaste and Decommissioning

UK EPR GDA PROJECT. Name/Initials Date 30/06/2011 Name/Initials Date 30/06/2011. Resolution Plan Revision History

Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0028 Safety System Logic & Control (SSLC) Class 1 HMI

Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0027 Hardwired Back Up System

AIMMS Function Reference - Date Time Related Identifiers

Pennington County Government Justice Center. Schematic Design - October 27, 2015

European Developments

CIMA Certificate BA Interactive Timetable

GDA Step 2 Assessment of Security for Generic Design Assessment of Hitachi GE s UK Advanced Boiling Water Reactor (UK ABWR) OFFICIAL

Undergraduate Admission File

GUIDANCE ON THE SECURITY ASSESSMENT OF GENERIC NEW NUCLEAR REACTOR DESIGNS

76 days Wed 8/24/16 Wed 12/7/16 Daniel Wang,Shreyas Makde,Madhavi Potluri,Roua 2 Requirements analysis 11 days Wed 8/24/16 Wed 9/7/16

MISO PJM Joint and Common Market Cross Border Transmission Planning

Capacity building in the IAEA Action Plan on Nuclear Safety

Grid Code Planner EU Code Modifications GC0100/101/102/104

Asks for clarification of whether a GOP must communicate to a TOP that a generator is in manual mode (no AVR) during start up or shut down.

REGULATORY, FINANCIAL AND POLITICAL CHALLENGES TO NEW BUILD: THE EDF EXPERIENCE

New Concept for Article 36 Networking and Management of the List

CIMA Asia. Interactive Timetable Live Online

RPS Work Item: Beta Testing of Message Standard

CIMA Asia. Interactive Timetable Live Online

SCHEDULED PROGRAMMES/COURSES APRIL 2017 MARCH 2018 (MIND KINGSTON / MANDEVILLE CAMPUSES & MONTEGO BAY)

Stakeholder consultation process and online consultation platform

Work to establish standard ENTSOE STAKEHOLDER COMMITTEE 1

March 22, 2016 Design Presentation. March 18, 2016 Budget. March 22, 2016 Schedule

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

10/16/2016 CPET 490 SENIOR DESIGN PROJECT PHASE I ANDROID GOLF STATISTICS TRACKER. Brad Sorensen Kory Martin PROJECT SUMMARY

DIRECTORS OF METHODOLOGY/IT DIRECTORS JOINT STEERING GROUP 18 NOVEMBER 2015

MISO PJM Joint and Common Market Cross Border Transmission Planning

IT Updates. Maryland Health Benefit Exchange Board Meeting April 15, Presented by: Isabel FitzGerald Secretary, DoIT

BANGLADESH UNIVERSITY OF PROFESSIONALS ACADEMIC CALENDAR FOR MPhil AND PHD PROGRAM 2014 (4 TH BATCH) PART I (COURSE WORK)

UK Link Committee Meeting. Xoserve Report Pack. Meeting Date: 12 th January 2017 Reporting Month: December 2016

4. ENCOUNTER DATA PROCESSING PROCEDURES A. General Information

nuclearsafety.gc.ca Implications of the Fukushima Daiichi Accidents for the New Builds Design Requirements in Canada

SCHEDULED PROGRAMMES/COURSES APRIL 2018 MARCH 2019 (MIND KINGSTON / MANDEVILLE CAMPUSES & MONTEGO BAY)

Japan s Measures against Spam

WORKPACKAGES Month

Compliance Enforcement Initiative

COURSE LISTING. Courses Listed. with SAP Hybris Marketing Cloud. 24 January 2018 (23:53 GMT) HY760 - SAP Hybris Marketing Cloud

Final Project Report

Freedom of Information Act 2000 reference number RFI

ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS

SME License Order Working Group Update - Webinar #3 Call in number:

Commonwealth of the Northern Mariana Islands

BEST PRACTICE GUIDE ON THE USE OF THE ELECTRONIC COMMON TECHNICAL DOCUMENT

Withdrawal of Text Processing (Business Professional)

Transition Implementation Status Reporting. 31 March 2016

ICT PROFESSIONAL MICROSOFT OFFICE SCHEDULE MIDRAND

UPCOMING PROGRAMMES/COURSES APRIL 2016 MARCH 2017 (MIND KINGSTON & MANDEVILLE CAMPUSES)

OFFICIAL COMMISSIONING OF SECURITY SYSTEMS AND INFRASTRUCTURE

1. News coverage: Phyllis Ruzicka, Senior Editor Standards. Contact information: phone 708/ , fax 708/

11 days Mon 12/7/15 Mon 12/21/15. 4 days Tue 12/8/15 Fri 12/11/ days Mon 1/4/16 Mon 2/29/16. External Milestone. Manual Summary Rollup Split

Coursework and Controlled Assessment Timetable

INFORMATION TECHNOLOGY SPREADSHEETS. Part 1

Website Redevelopment Content Information Session. Presentation by

SCHEDULED PROGRAMMES/COURSES APRIL 2018 MARCH 2019 (MIND KINGSTON / MANDEVILLE CAMPUSES & MONTEGO BAY)

Countermeasures against Mobile spam

DEPARTMENT OF THE ARMY *ER U.S. Army Corps of Engineers CECW-EC Washington, DC Administration PROJECT SCHEDULES

Demand Estimation Sub Committee Ad-hoc Work Plan

DATE OF BIRTH SORTING (DBSORT)

Package RcppBDT. August 29, 2016

AWS-SCWI. American Welding Society Senior Certified Welding Inspector. Certification Programs for the Year 2018

Transition Implementation Status Reporting. 12 August 2016

REPORT ON TELECOMMUNICATIONS SERVICE QUALITY WINDSTREAM FLORIDA, INC.

Section 1.2: What is a Function? y = 4x

Next Steps for WHOIS Accuracy Global Domains Division. ICANN June 2015

MA SREC-II Extension Application Instructions

software.sci.utah.edu (Select Visitors)

Privacy and Proxy Service Provider Accreditation. ICANN58 Working Meeting 11 March 2017

IATF Transition Strategy Presenter: Mrs. Michelle Maxwell, IAOB

IATF Transition Strategy Presenter: Cherie Reiche, IAOB

COURSE LISTING. Courses Listed. Training for Database & Technology with Modeling in SAP HANA. 20 November 2017 (12:10 GMT) Beginner.

T2S PROGRAMME STATUS AS OF MID-SEPTEMBER

CPD Summary Guide Version:3.1

Internal Audit Follow-Up Report. Multiple Use Agreements TxDOT Office of Internal Audit

151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued April 23, 2015)

Training of BRs/NCs reviewers and experts for Biennial Update Reports technical analysis. 5 th BRs and NCs lead reviewers meeting

ENTSO-e Operational Security Network Code. OS Code Objectives. Update for JESG meeting 20 th Feb 2013

0522: Governance of the use of as a valid UNC communication

Grade 4 Mathematics Pacing Guide

The Proposer recommends that this modification should be assessed by a Workgroup

Energy Storage and Distributed Energy Resources Phase 2 Implementation

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

NORTHWEST. Course Schedule: Through June 2018 MICROSOFT ACCESS. Access 2016 / Access 2010 / Last Revised: 11/13/2017

North American Portability Management, LLC LNPA Transition Contingency Rollback. Industry Working Session January 16 th, 2018

Much more than Rules need to be in place by 2014

Monthly SEO Report. Example Client 16 November 2012 Scott Lawson. Date. Prepared by

Pushing the Limits. ADSM Symposium Sheelagh Treweek September 1999 Oxford University Computing Services 1

Council, 8 February 2017 Information Technology Report Executive summary and recommendations

SD3-60 AIRCRAFT MAINTENANCE MANUAL REF. No 360/MM

This report is based on sampled data. Jun 1 Jul 6 Aug 10 Sep 14 Oct 19 Nov 23 Dec 28 Feb 1 Mar 8 Apr 12 May 17 Ju

Strategic Reserve in Belgium Design and functioning

What future changes are planned to improve the performance and reliability of the Wairarapa Connection?

* - Note: complete submissions are to be submitted at least two weeks before any deadline to ensure timely closure.

Workgroup Terms of Reference and Membership

0522: Governance of the use of as a valid UNC communication

IGO/INGO Identifiers Protection Policy Implementation. Meeting with the IRT 9 March 2016

The State of the Raven. Jon Warbrick University of Cambridge Computing Service

TCA metric #3. TCA and fair execution. The metrics that the FX industry must use.

FedRAMP: Understanding Agency and Cloud Provider Responsibilities

Transcription:

RP unique number: Page GI-UKEPR-RP-01-RP 0 30/06/2011 1 of 5 Approved for EDF by: A. PETIT Approved for AREVA by: C. WOOLDRIDGE Name/Initials Date 30/06/2011 Name/Initials Date 30/06/2011 Resolution Plan History Rev. Description of update Date issued 0 First revision 30/06/2011 1.0 GDA ISSUE GDA Issue Title Main Assessment Area Related Assessment Area Radiological Zoning and Bulk Shielding Radiological Protection Civil Engineering GDA Issue Radiological zoning for restriction of exposure to ionising radiation of workers is fundamental to the design of the nuclear island, and bulk shielding is inextricably linked with civil engineering aspects of that design. The radiological zoning classification scheme underpinned by design shielding calculations is not referenced in the GDA submission for the UK EPR design. 2.0 OVERVIEW OF SCOPE OF WORK ONR considers that the arguments presented in the current GDA EPR PCSR to justify the adequacy of the shielding included in the generic design are not sufficient. EDF and AREVA have submitted methodologies of radiation protection studies and radiation protection guidelines, and have provided samples of calculations in the Reactor Building and Fuel Building. However, ONR requests that the arguments presented in the PCSR Chapter 12.3 should be supplemented by additional information in a supporting overview document as a direct reference from the PCSR. The overview document in turn will reference to supporting calculations and design detail to substantiate the claims and arguments made in the PCSR. The FA3 EPR bulk shielding is the GDA reference for the UK EPR bulk shielding, although some amendments to radiological zoning in other areas is expected during Phase 2 licensing to take account of future operators requirements. During the meeting between ONR and the RP on 14 December 2010, ONR was shown the radiological zoning classification scheme for the FA3 EPR and high-level summary shielding substantiation documentation for parts of the nuclear island. GI erp Form Version 001

Page GI-UKEPR-RP-01-RP 0 30/06/2011 2 of 5 ONR s view is that radiological zoning for restriction of exposure to ionising radiations of workers is fundamental to the basic design of the UK EPR. The evidence that is required for GDA is as follows. 1. A radiological zoning classification scheme for the nuclear island (Reactor, Fuel, Safeguard and Auxiliary Buildings) for the UK EPR GDA reference design should be submitted. 2. The shielding calculations for the UK EPR GDA reference design to ensure adequate bulk shielding provided by nuclear island construction concrete should be completed. 3.0 GDA ISSUE ACTIONS AND RESOLUTION PLAN DELIVERABLES 3.1 Action GI-UKEPR-RP-01.A1 Action I/D GI-UKEPR-RP1.A1 Action Description Provide an overview document that supplements the claims and arguments presented in the PCSR Chapter 12.3 with additional information on the radiological zoning classification scheme for the nuclear island, including dose rate criteria and predictions for all modes of plant operation, for occupied areas as a direct reference from the PCSR. A radiological zoning classification scheme should be provided to demonstrate that there is adequate shielding provision for all areas of the facility. This should be presented as an overview document that provides information / documentation which summarises the dose rates and radiological classifications within all rooms and for all modes of plant operation (for example, power operation, outages, refuelling). The document should include information / documentation on the Reactor Building, Fuel Building, Safeguard Building, and Auxiliary Building. The overview document should summarise the results of shielding calculations to show that the predicted dose rates within each area of the plant meet the radiological classification. The response should, as a minimum, summarise the following information for each room of the facility: Room descriptor and number / designation. Radiological classification (namely dose rate criteria). Dose rate prediction(s) for each room giving the maximum dose rate present during all modes of operation (for example, power operation, outages, refuelling). Reference to shielding assessments / calculations containing data regarding the assumed radiation sources, shielding provisions and calculated dose rates. With agreement from the Regulator this action may be completed by alternative means.

Page GI-UKEPR-RP-01-RP 0 30/06/2011 3 of 5 3.1.1 Planned submissions in response to GI-UKEPR-RP-01.A1 3.1.1.1 Description of Scope of Work EDF and AREVA will issue by July 2011 a first version of an overview document presenting the radiation protection zoning of the EPR nuclear island (Reactor, Fuel, Safeguard and Auxiliary Buildings) with the following information: Room descriptor and number / designation. Radiological classification (namely dose rate criteria). Dose rate prediction(s) for each room giving the maximum dose rate present during all modes of operation (for example, power operation, outages, refuelling). Reference to shielding assessments / calculations from Flamanville 3 containing data regarding the assumed radiation sources, shielding provisions and calculated dose rates. A progress meeting about ONR feedback will be held at the beginning of October 2011: - Identification of rooms for a sampling assessment, - Questions on the overview document and on the calculation notes. The answers to all ONR questions will be provided by EDF and AREVA by mid January 2012 (letters, supporting references or parts of supporting references requested by ONR). A draft update of impacted PCSR Sub-chapter 12.3 will be sent by end November 2011. An update of the overview document and the final version of the updated PCSR Sub-chapter 12.3 will be sent by end March 2012. Out of scope of work: specific UK EPR calculation documents will be performed during Nuclear Site Licensing. 3.1.1.2 Description of Methodology to be employed The overview document will be a completion of existing information from the radiation calculations performed on the EPR Flamanville 3. This document will be classed as level 2 information as a direct reference from PCSR Sub-chapter 12.3 and will be included in the UK EPR GDA Submission Master List. It will include drawings of the different levels of the nuclear island, with colours attributed to each room and corresponding to the radiation classification of the room. The drawings will be completed by tables giving the name and the maximum dose rate of each room. If calculations were performed for different states of the plant (power, outage ), the maximum dose rate for each state will be given. The information given in the overview document will be supported by references to calculation notes and study notes for the EPR Flamanville 3 (level 4 information in French language).

Page GI-UKEPR-RP-01-RP 0 30/06/2011 4 of 5 3.1.1.3 Deliverable description Submission date to ONR First version of an overview document of the radiation protection zoning of the EPR Flamanville 3 nuclear island (Definitive title and reference to be defined, see contents in section 3.1.1.1). Responses to ONR s questions: - Letters, - transmission of an extract of a supporting reference if necessary, - transmission of a supporting reference if necessary. 15/07/2011 Final responses / submissions by 13/01/2012 Update of the overview document (following final versions of supporting calculation notes) Update of PCSR Sub-Chapter 12.3 Radiation Protection Measures ( 04 of UKEPR-0002-123) 23/03/2012 Draft on 30/11/2011, Final on 30/03/2012

Page GI-UKEPR-RP-01-RP 0 30/06/2011 5 of 5 4.0 SUMMARY OF IMPACT ON GDA SUBMISSION DOCUMENTATION 4.1 GDA submission documents impacted by GDA Issue and scheduled to be created (C) or updated (U) within GDA GDA Submission Documents C/U Related GDA Issue Action(s) SSER sub-chapters Update of PCSR Sub-Chapter 12.3 Radiation Protection Measures GDA reference design documents (SDM in UKEPR-I-002) None U GI-UKEPR- RP-01.A1 Submission Date to ONR Draft on 30/11/2011, Final on 30/03/2012 Other GDA submission supporting documents Overview document of the radiation protection zoning of the EPR Flamanville 3 nuclear island (Definitive title and reference to be defined) C U GI-UKEPR- RP-01.A1 First version 15/07/2011, update by 23/03/2012

Page GI-UKEPR-RP-01-RP 0 30/06/2011 6 of 5 5.0 JUSTIFICATION OF ADEQUACY EDF and AREVA agreed to provide in the overview document all details requested by the GDA Issue (see paragraph 3.1.2). This document will collect information from existing calculation notes and study notes for the EPR Flamanville 3 which is the GDA reference design for the UK EPR. The values of dose rate in each nuclear island room will show the adequacy of EPR shielding in nuclear island construction concrete. In addition, the sampling assessment of rooms will validate the methodology of calculation notes. 6.0 TIMETABLE AND MILESTONE PROGRAMME LEADING TO THE DELIVERABLES Consult the following page for the associated timetable and milestone programme.

ID Task Name Duration Start Finish 1 Progress Meetings HSE/EA - EDF/AREVA 135 days Fri Oct 7, '11 Thu Apr 12, '12 GI-UKEPR-RP01 Schedule.mpp Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12 Apr ' 2 2 4 1 1 2 2 9 1 2 3 6 1 2 2 4 1 1 2 1 8 1 2 2 5 1 1 2 3 1 1 2 3 7 1 2 2 5 1 1 2 2 9 1 2 3 6 1 2 2 5 1 1 2 2 9 2 Progress Meeting 1 - Feedback on overview document 1 day Fri Oct 7, '11 Fri Oct 7, '11 3 Progress meeting 2 - Feedback on supporting notes 1 day Fri Feb 24, '12 Fri Feb 24, '12 4 Meeting - Closure 1 day Thu Apr 12, '12 Thu Apr 12, '12 5 Action 1 - Overview document 249 days Mon Apr 11, '11 Fri Mar 23, '12 6 Creation of first version 60 days Mon Apr 11, '11 Fri Jul 1, '11 7 Transmission to ONR 0 days Fri Jul 15, '11 Fri Jul 15, '11 7/15 8 ONR review 60 days Fri Jul 15, '11 Thu Oct 6, '11 9 EDF AREVA Answers, translation of supporting notes 67 days Mon Oct 10, '11 Tue Jan 10, '12 10 Transmission to ONR 0 days Fri Jan 13, '12 Fri Jan 13, '12 1/13 11 ONR review 30 days Fri Jan 13, '12 Thu Feb 23, '12 12 Update of the overview document 50 days Wed Jan 11, '12 Tue Mar 20, '12 13 Submission 0 days Fri Mar 23, '12 Fri Mar 23, '12 3/23 14 Action 2 - Impact on PCSR Sub-Chapter 12.3 124 days Mon Oct 10, '11 Fri Mar 30, '12 15 Update 38 days Mon Oct 10, '11 Wed Nov 30, '11 16 Submission of draft update 0 days Wed Nov 30, '11 Wed Nov 30, '11 11/30 17 ONR review 30 days Thu Dec 1, '11 Wed Jan 11, '12 18 Finalisation of PCSR Sub-chapter 12.3 (issue impact) 21 days Fri Feb 24, '12 Fri Mar 23, '12 19 Submission of updated PCSR Sub-chapter 12.3 (including other impacts) 0 days Fri Mar 30, '12 Fri Mar 30, '12 3/3 Project: GI-UKEPR-RP1 Schedule - An Date: Fri Jul 1, '11 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline Page 1