NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 2 SUPPLEMENTARY EXAMINATION 2010

Similar documents
NATIONAL CERTIFICATE (VOCATIONAL) ELECTRONIC CONTROL AND DIGITAL ELECTRONICS NQF LEVEL 2 SUPPLEMENTARY EXAMINATION 2010

BS 181 SINGLE CHANNEL POWER SUPPLY USER MANUAL

Instruction Manual. M Pump Motor Controller. For file reference, please record the following data:

LED Slimline PAR RGBW 7x8W

Treadmill Embedded Touch Screen Won t Power Up

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRONIC CONTROL AND DIGITAL ELECTRONICS NQF LEVEL 3 NOVEMBER 2010

ATS-16 HV USER MANUAL. Automatic Transfer Switch 16A / 230Vac V090318

PS 680 SIX CHANNEL POWER SUPPLY WITH AUX MATRIX USER MANUAL

BS 181 SINGLE CHANNEL POWER SUPPLY USER MANUAL

MS-7000: SuperStar Reader

BS 287 DUAL CHANNEL POWER SUPPLY. User Manual. January 2017 V1.0

Connecting a Cisco Input Module

Bulletin Installation of solar photovoltaic systems Rules , , , , and

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

Topic: TB No.: Date: Aug/2017. Model UC4, UC10 & UC45 twin pump variants Regulated 24V Pump Power supply upgrade OVERVIEW

How-To #7: Assemble an H-bridge Circuit Board

Panduit Basic Rack PDU

PS 289 DUAL CHANNEL POWER SUPPLY USER MANUAL

ELECTRICAL SUPPLY TROUBLESHOOTING QUICK GUIDE SAFETY PRECAUTIONS

Operating manual. Series 450. Compact thermometer. BA01235O/09/en/

Model 2460-KIT. Screw Terminal Connector Kit. Description / September 2014 *P * 1

Room unit with PPS2 interface

M E M O R A N D U M I.S.

Avanti HP Series Centrifuges Preinstallation

CONTROL PANEL WIRING SPECIFICATIONS

MS-5000: MiniStar Reader

VBAR 270. User Manual. Version 1.2

SAVE THESE INSTRUCTIONS

Lantech. IPES /100TX with 4 PoE Injectors 24~48VDC Industrial Switch. User Manual

Panduit Basic Rack PDU with Local Meter

OPERATING MANUAL FOR THE 30KV A.C. TEST SET P123. Bicotest High Voltage Products Ltd

Connecting a Cisco Reader Module

dynamic white par manual

CMSA-100 Manual. Cinema Media Server Automation

STATE OF NEW JERSEY BUREAUS OF ITS ENGINEERING AND SAFETY & DATA DEVELOPMENT DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625

APS4 Inductive Proximity Sensors

INSTALLATION INSTRUCTIONS FOR THE MINI-KEY SYSTEM. Doc Rev B

BreezeMAX Wi² and BreezeACCESS Wi² Quick Installation Guide

BS 217 DUAL CHANNEL MASTER STATION USER MANUAL

one cool inverter. GT Series Solar Inverter Quick Install Guide v1.4

Chore-Tronics IDM Board Instruction

MS-5000 MiniStar Reader. Quick Start Guide MS The MS-5000 MiniStar Reader. 1.0 Specifications

Electrical Integration of PV Systems. Ridha Hamidi, Ph.D.

Three Phase Residential Solution for Australia, System Design and Installation Guidelines

OPERATING INSTRUCTIONS 7 SERIES STATIC GENERATORS

VRp Three-Phase Precision AC Voltage Regulator

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRONIC CONTROL AND DIGITAL ELECTRONICS NQF LEVEL 2 NOVEMBER 2009

MULTI 9 System Catalog UL Recognized C60N Supplementary Protectors

Lift Truck Parts Professionals

UNDERGROUND CONSTRUCTION MANUAL SERVICES

National Certificate in Electrical Engineering (Electrician for Registration) (Level 4)

SKIVING MACHINE MAINTENANCE & INSTRUCTIONS MANUAL ASSK2. Allswage UK. Roebuck Street, West Bromwich, B70 6RB

Installing Cisco RP-Series PDUs

Signal Connections CHAPTER

sonnen Installation Practical

Series Amp Quick Connect Input and Output Power Panels

INSTITUTE OF TESTING AND CERTIFICATION (INDIA) PVT. LTD.

Common Departures Interconnecting Facilities Requirements

ArmorConnect Power and Control Media

Connecting a Cisco Output Module

SECTION DISCONNECT SWITCHES

Solar Combiner Enclosure

TRC-190 User s Manual

Model 7705 Control Module

Page 1 of 5. Increased Safety, Encapsulation and Dust

MS-3000 MicroStar Reader

Blue Weapon Laser. User manual UK. Version 1.0

Weathersafe Vision. Installation & Operating Instructions

BLUE 3 INSTALLATION GUIDE

January Bob Wright. 1 P age Bob Wright

DMX Switch Pack. User Manual. EU version shown P/N

RCD Fused Connection Unit Model: RCD10WPV. RCD Double Sockets Models: RCD05WAV, RCD06WPV, RCD07MAV, RCD08MPV. Installation & Operating Instructions

Applying branch circuit breakers and supplementary protectors in North America

DELUXE STEREO AMPLIFIER KIT

KTX REMOTE INSTALLATION INSTRUCTIONS

LC SmartGlass SPD SmartGlass

Series Amp Pad Mount Quick Connect Input and Output Power Panels

ELECTRICIANS REGULATIONS EXAMINATION 21 November 2015 QUESTION AND ANSWER BOOKLET

Electrical Components and Equipment for General Use Self Inspection Checklist

AI-102. IR Illuminator. Installation Guide. Rev IP Surveillance

Installation Instructions for Eaton Surge Protective Device XXCFXXX10-DIN and XXCFXXX10-DIN2

National Certificate in Electrical Engineering (Electrical Appliance and Electronic Servicing) (Level 3)

DIGITAL INPUT/OUTPUT RELAY INTERFACE BMS-IFDD01E

AC Power Meter GPM-8212 USER MANUAL

Electrical Demand Specification (Reference SOP: )

HI-POT TESTER User Manual

Emery County Senior Center Green River 06/07

MULTI 9 System Catalog UL Recognized NC100H Supplementary Protectors

MS-4000: ShootingStar Reader

PM Series Power Meter

DRH Hardware Maintenance Guide

QUICK SETUP GUIDE PMC-1000, PMC-1001, PMM-1000, PMB PM Series Power Meter. Safety Information. Equipment Maintenance and Service.

IT power distribution Power distribution units (PDU) Basic. Versions available:

TRC-190 User s Manual

Control. Part B, Section 2. This section covers the following unit configurations. 3400V 3500V Voltage 1, 2, 3 Pump Piston (D, E, F, G)

This qualification has been revised. The last date to meet the requirements is 31 December 2021.

Installing the Cisco MDS 9020 Fabric Switch

Replacement and Calibration of Electronic Spare (PCB) Cassettes - Rosemount 2120 Vibrating Fork Liquid Level Switch

Applying branch circuit breakers and supplementary protectors in North America

RCC45 ➁ Overview / /

Transcription:

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 2 SUPPLEMENTARY EXAMINATION 2010 (12041032) 4 March (X-Paper) 09:00 12:00 This question paper consists of 6 pages.

(12041032) -2- NC710(E)(M4)V TIME: 3 HOURS MARKS: 100 INSTRUCTIONS AND INFORMATION 1. 2. 3. 4. Answer ALL the questions. Read ALL the questions carefully. Number the answers according to the numbering system used in this question paper. Write neatly and legibly.

(12041032) -3- NC710(E)(M4)V QUESTION 1: BASIC ELECTRICAL CIRCUITS AND SYSTEMS 1.1 You are required to wire a domestic installation comprising of the following: 1.1.1 1.1.2 1x plug circuit 1x light circuit Draw a neatly labelled circuit diagram, to show the wiring of a distribution board for the above circuits indicating ALL necessary components and protective devices. Indicate the size of the circuit breakers and the size of the wires you are going to use for the circuits. (10) 1.2 Compare a geyser and stove sub- circuit. How do they differ with respect to: 1.2.1 1.2.2 1.2.3 The size of the circuit breakers used The size of the conductors used Their application (2) (2) (2) 1.3 Explain how you would secure the following: 1.3.1 1.3.2 Surface mounted PVC conduit Surface mounted twin flex cable (2) 1.4 Sketch the IEC symbols of the following components. 1.4.1 1.4.2 1.4.3 1.4.4 1.4.5 A double-wound transformer A coil A fuse A single-pole switch A two-way switch (5) 1.5 After the wiring of an installation is completed, certain tests have to be completed to ensure it corresponds with the requirements laid down by SANS 10142. A certificate of compliance will then be issued. List FIVE compliance test that are compulsory. (5) 1.6 What is the purpose of the thermostat as used in a geyser? (2) [30]

(12041032) -4- NC710(E)(M4)V QUESTION 2: WIRE WAYS AND LOW VOLTAGE CABLES 2.1 The cable from the supplier's meter box must be connected to the distribution board in your home. 2.1.1 2.1.2 How would you secure the PVC wire armoured cable to the metal distribution board? What tools would you use to secure the cable to the distribution board? 2.2 A newly built house needs to be wired. What types of wire ways would you use to wire this house? (2) 2.3 Choose a statement from COLUMN B that matches a statement in COLUMN A. Write only the letter (A E) next to the question number (2.3.1 2.3.5) in the ANSWER BOOK. COLUMN A COLUMN B 2.3.1 2.3.2 2.3.3 2.3.4 2.3.5 Line taps Soldered joint Mechanical connector Scotch cast joint Wire way A B C D E joining kit for armoured and unarmoured cables flexible conduit join overhead lines Britannia joint ferrule (5 1) (5) 2.4 A three-core cord was fitted to a three-pin plug. It was done in the following way: the blue conductor was connected to the load/live pin; the brown conductor was connected to the neutral pin and the green and yellow conductor was connected to the earth pin. Was the three-core cord correctly connected to the three-pin plug? If not how would you change the wiring on the three-pin plug. 2.5 When a PVC conduit is used in wire ways, wires need to be pulled into the conduit. 2.5.1 2.5.2 What tool would you use to pull the wires into the conduit? Explain how you would use this tool to get the wires into the conduit. (1) [20]

(12041032) -5- NC710(E)(M4)V QUESTION 3: ELECTRIC MACHINES 3.1 List THREE types of direct current machines in general use. 3.2 Compare the operation of a DC Motor with that of a DC Generator. (Focus should be on energy conversion.) (4) 3.3 What key information is found on the nameplate of a motor? List THREE points? 3.4 Indicate whether the following statements are TRUE or FALSE. Write only 'true' or 'false' next to the question number (3.4.1 3.4.7) in the ANSWER BOOK. Checklist for mechanical inspection: 3.4.1 3.4.2 3.4.3 3.4.4 3.4.5 3.4.6 3.4.7 Make sure all covers and guards are in place. Check the bearings for wear. Inspect the brushes regularly for wear. Check if all mounting brackets are secure. Check the nameplate to see if all given data is clearly legible. Check the stator frame and shields. Make sure that the brush holders are accurately set. (7 1) (7) 3.5 A DC motor fails to start. What checks will you perform to establish the fault? [20] QUESTION 4: FAULT-FINDING AND TESTING 4.1 List TWO testing instruments you would use to test or to do fault-finding on components. (2) 4.2 Compare the operation of a fuse and a circuit-breaker. (4) 4.3 A fuse needs to be tested to see whether it is functional or not, after it has been removed from the circuit. 4.3.1 4.3.2 What testing instrument can be used to perform this test? How is the test done? (1) [10]

(12041032) -6- NC710(E)(M4)V QUESTION 5: PROTECTION AND MEASURING INSTRUMENTS 5.1 5.2 5.3 5.4 5.5 List FIVE meters that require replacement on a regular basis. List THREE types of displays that are used in measuring instruments. Compare a pre-paid meter with a kilowatt-hour meter. A meter could be mounted in different ways. List THREE ways meters could be mounted on walls or panels. A faulty metering unit needs to be replaced. Explain how you would replace the metering unit. (5) (4) (6) [20] TOTAL: 100