USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION

Similar documents
USE CASE 5 PROTECTION ENGINEER CHANGES SETTINGS ACROSS A NETWORK

USE CASE 14 CONTROLLED ISLANDING

USE CASE 8 MAINTENANCE ENGINEER MONITORS HEALTH OF PRIMARY EQUIPMENT

Redundant Bus Protection Using High-Impedance Differential Relays. Josh LaBlanc

System Protection and Control Subcommittee

RelaySimTest. Software for system-based protection testing

Implementing the protection and control of future DC Grids

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field

An Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems

ELG4125: System Protection

C I R E D 22 nd International Conference on Electricity Distribution Stockholm, June 2013

Substation Automation Products. Line differential protection RED670 Relion 670 series

Bus Protection Application Challenges

THE INTEGRATED TESTING SOLUTION

Application Notes on Generator Protection Schemes

SPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS. G. Steynberg

Busbar protection REB 670

F6150. Power System Simulator For Testing Protection Relays and Schemes.

SIPROTEC 5 V7.8 Protection, automation and monitoring for digital substations

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

SEL Time-Domain Link (TiDL ) Technology

1 Description of Methodology for Volt / Var Optimization

Lessons Learned in Static VAR Compensator Protection

Commission Testing Methods for Protection Systems

WHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION. Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District

SCADA Training - T&D Automation

We will discuss two types of loss-of-potential (LOP) logic during this presentation:

Amsterdam 27 September 2017 David MacDonald

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

AUTOMATED FAULT AND DISTURBANCE DATA ANALYSIS. Special Report for PS#2. Special Reporter: Mladen Kezunovic * U.S.A.

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Modular Smart Grid Power Systems Simulators (Utilities)

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series

A Current Based, Communication Assisted High Speed Protection System to Limit Arc Energy. Patrick Robinson Altelec Engineering

DRTS 33. The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters

Chapter 2 State Estimation and Visualization

HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM

Substation Automation Products. Line distance protection REL670/650 Relion 670 and 650 series

DRTS 64. The new generation of advanced test equipment for Relays, Energy meters, Transducers and Power quality meters.

CIM, PI AF and SISCO CIM Adapter Create New Application Opportunities for Utilities

High and Medium Voltage Substation Design, Testing and Maintenance. KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel.

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

MiCOM P521. Fast Feeder Differential Protection

Standard Development Timeline

TWO-WINDING TRANSFORMER DIFFERENTIAL

DISCERN SGAM Visio Template User Guide

COLLABORATE TO WIN. 03/31/2017 Digital Substation Turning IEC61850 features into benefits. Peter Rietmann, Program Manager Digital Substation NA

Catching Falling Conductors in Midair Detecting and Tripping Broken Distribution Circuit Conductors at Protection Speeds

TFS 2100 Traveling Wave Fault Location System

Substation Automation Products. Transformer protection RET670/650 Relion 670 and 650 series

PROTECTION, AUTOMATION & CONTROL

IEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action

PRC Coordination of Protection Systems for Performance During Faults

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements

Use of frame agreement to standardize Protection in Digital Substation Automation Systems, Cooperation between Statnett and ABB

ENTSO-E connection network codes Implementation guidance documents. Joint DSO response paper

Documentation. M-Bus 130-mbx

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation

Application and Research of Integrated Model Between Substation and Dispatch Center

AN ADVANCED APPROACH TO IDENTIFY INRUSH CURRENT AND HARMONICS USING ARTIFICIAL INTELLIGENCE FOR POWER SYSTEM PROTECTION

DGSZV-EP DIGITAL GALVANIC LONGITUDINAL DIFFERENTIAL PROTECTION. Application field

WESTERN PROTECTIVE RELAY CONFERENCE TESTING AND OPERATIONAL EXPERIENCES WITH HIGH SPEED DISTANCE RELAY IN BPA 500 KV SERIES COMPENSATED NETWORK

EMS / DMS. DISTRIBUTION MANAGEMENT SYSTEM- Functional Description

The research and the development of the wide area relaying protection based on fault element identification

Standard Development Timeline

Applications of Automated Protective Relay Testing. Josh LaBlanc

ENTERPRISE-WIDE USES OF DIAGNOSTICS DATA

An expert solution is within your reach. EORSys. We take care of it.

DRTS 33. The new generation of advanced three phase relay test set

DRTS 66. The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters

1. Project Description

Sensitive Earth-fault Relay SPAJ 111 C. Product Guide

BREAKER FAILURE PROTECTION

3- and 4-pole switching in UPS installation

Geomagnetic Induced Current (GIC) Mitigation System Summary for the White Paper

MiCOM P122C Time-Overcurrent Protection

Small Generator Interconnection System Impact Study Report. Completed For Q0047

MiCOM P521. Fast feeder differential protection

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

Smart Grids, Telecontrol and the New Standards. Reliable and secure communication with zenon Process Gateway

Preparing for the Dynamic Grid of Future

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

Evaluation of different solutions of faulted phase earthing technique for an earth fault current limitation

HID. GE Consumer & Industrial Multilin. High Impedance Differential Module Instruction manual GEK Copyright 2005 GE Multilin

PSM 505. Inform IT Power System Monitoring. Stand-alone Fault Analysis and Evaluation Tool. Technical Data. Introduction.

Protection relays.

Testing Instruments Manufactured by

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

UniSec, MV AIS for Secondary Distribution Smart Grid applications

Substation Automation Products. High impedance differential busbar protection REB650 Relion 650 series

Procedures for cross-border transmission capacity assessments PROCEDURES FOR CROSS-BORDER TRANSMISSION CAPACITY ASSESSMENTS.

MiCOM P721 & P723. Numerical High Impedance Differential Relay. Protection Relays. Customer Benefits

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

Automation of Distribution Grid with FLISR using ZigBee Communication

High impedance protection relay

Automated real-time simulator testing of protection relays

Motor Surge Suppressors and Cable Considerations

ABB static var compensator stabilizes Namibian grid voltage

Siemens AG I IA CE CP R&D-VI 4 WERNER-VON-SIEMENS-STRASSE AMBERG, GERMANY

Transcription:

H USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION Use Case Title Adaptive Transmission Line Protection Use Case Summary The requirements for improvement in the performance of protection relays under different system conditions lead to the implementation of adaptive protection that adjusts to changes in the configuration of the electric power system. This is especially important in the cases of double circuit transmission lines or lines that have one or more segments in parallel with one or more transmission lines on the same or on different voltage levels. Changes in the state of any of the parallel lines or the system around them may affect differently the operation of the line protection relays for faults on the protected line or even on some of the parallel lines. The protection system needs to be able to adapt to changes in the system configuration. This requires first of all the availability of a CIM model of the system including detailed information of the mutual coupling between the protected line and any other parallel line in its neighborhood. Information on each substation configuration, as well as the windings and grounding of the transformers is also required. Information on the grounding status of a parallel line out of service is also required. Then, based on the state of the switching devices received through IEC 61850 locally and switching and grounding of transmission lines or other changes in the system configuration received from the system level, the adaptive protection system will change settings or setting groups in one or more relays to adapt to the system or substation changes. This use case follows from the zone of protection definition through the analysis of the different possible modes of operation. The objective is to stress the 61850/CIM interface to discover aspects of the seams which exist between these two standards. The CIM and 61850 must both be used at least at both ends of the process for this use case to be of practical use. H-1

Use Case Detailed Narrative The utility needs to configure the protection of a transmission line that is mutually coupled with one or more other transmission lines on the same or different voltage levels, on the same or different towers as the protected line. It is important to also keep in mind that usually these lines are not transposed and may have unsymmetrical configuration. Parallel transmission lines have been extensively utilized in modern power systems to enhance the reliability and security for the transmission of electrical energy. The different possible configurations of parallel lines combined with the effect of mutual coupling make their protection a challenging problem. Different types of protection and algorithms have been proposed in the past to overcome some of the performance related issues. In addition to the effect of mutual coupling, fault resistance and pre-fault loading consideration, cross-country faults have to be considered as well in order to determine the protection response. In the case of use of distance relays, the determination of the final fault impedance is therefore not that straight forward as a number of system conditions affect it: 1. The dynamic changes of the characteristics of the power system, such as in generation capacity, load and in the network topology 2. Inaccuracies in the measuring instruments, relay measuring inputs, line parameters and protection algorithms 3. The state of the parallel circuit and its grounding. The effect of the dynamic characteristics of the system on protection is normally dealt with by traditionally determining the relay settings according to worst-case scenario studies. Inaccuracies in the electric power system need to be considered in the process. For example, a sequence components based model for a protection coordination study of a transmission line that is not completely transposed, will result in a difference between the results from the simulation and real fault conditions. These are even more complicated in the case of parallel lines because (as described earlier) they may involve mutually coupled circuits with unsymmetrical configurations. Inaccuracies in the image of the primary system conditions seen by the protective relays due to the errors in the measuring circuit can be limited by using properly selected current and voltage transformers and more advanced relay input modules. To compensate for the above described effects, the relay settings require large safety margins. A typical Zone 1 distance setting is 80% of the line impedance, but the effects of unbalance, load current magnitude and direction and system source impedances at the ends of the protected line need also to be considered. These settings have to be appropriate for extremely weak system conditions, as well as in the cases where over or under tripping could further weaken the system and lead to stability problems. H-2

Since distance relay settings may therefore not be appropriate for all system conditions in terms of security and dependability, adaptive protection based on different setting group selection are often considered in practice to improve the protection of double circuit lines. Figure H-1 shows the effect of mutual coupling on a typical double circuit transmission line the simplest case of parallel transmission. Current reversal after initial high-speed trip at an end closer to the fault, followed by current reversal is shown. Figure H-1 Mutual Coupling Effect From the above it is clear that the configuration of the transmission line protection and the knowledge of the current state of all switching devices on any of the parallel circuits are essential for the faster operation of the protection. The topology of the system surrounding both ends of the protected line needs to be known in detail, especially considering the mutual coupling. Since the mutual coupling can be only over a section of the line and the end substations can be far from each other, it is clear that direct communications between the relays protecting the different lines might not be possible. A system level Adaptive Protection (APCU) may be required. H-3

Topology algorithm in APCU determines dynamically the electric scheme of the power system area covering multiple parallel lines. The results from detection of changes in local substation configuration need to be sent to the APCU in order to trigger the adaptive protection change. The local detection is typically based on monitoring the status of auxiliary contact of circuit breaker and isolators or the availability of current flow through the monitored switching devices. Once this data is received in the APCU it is used to determine the global topology of the system. At the end of process, the central unit determines if there is a need for executing adaptive protection functions and sending signals to specific protection IEDs to switch from one to another setting group. It is essential that at each step of the process APCU knows the current state of each protection IED included in the adaptive protection system. The topological model needs to allow the identification of each segment of transmission line running in parallel with a segment from another transmission line, as well as its association with circuit breakers and isolators at each end of these lines. The global system topology is updated every time when a change of state of a switching device is indicated from the available at the system level reports. Once a protection IED receives the command to change its setting group, it needs to send back confirmation indicating that a change has occurred and the active setting group. As described in detail above, the system will require initial configuration process, followed by on-line monitoring of system changes and decisions to activate adaptive protection functions, based on system protection coordination analysis. The configuration process will include the following steps: 1. Building of a system configuration model using a system configuration editor for relay coordination and short circuit analysis and based on data from a CIM system data base 2. Running coordination studies and determining conditions that require switching to adaptive protection mode and its corresponding settings 3. Creating the setting files, including multiple setting groups, for each of the relays included in the system 4. Creating a table with different system topologies and the corresponding setting groups of the IEDs included in the system 5. Downloading the settings in the relays 6. Determining the system topology 7. Activating the required setting groups 8. Reporting the active setting groups to the APCU H-4

Once the system is configured, tested and put in service, it requires changes in configuration based on the continuous monitoring of the state of switching devices through the different IEDs reports. The sequence of actions in this case will be: 1. Detecting the change of state of a switching device 2. Sending the report to the APCU 3. Determining at the APCU the system topology 4. Activating the required new setting groups Each of the above steps imposes specific requirements for the harmonization between IEC 61850 and CIM. 1. Building of a system configuration model using a system configuration editor for relay coordination and short circuit analysis and based on data from a CIM system data base A three phase impedance model (3x3 matrix) for single transmission line is needed. A three phase impedance model for a double circuit line or a section of lines in parallel (6x6 matrix) is needed. Connectivity model for transmission lines is needed to describe a line with multiple segments and multiple mutual couplings. The connectivity model needs to be extended to cover mutual coupling on double circuit or parallel lines. 2. Running coordination studies and determining conditions that require switching to adaptive protection mode and its corresponding settings No changes required. 3. Creating the setting files, including multiple setting groups, for each of the relays included in the system No changes required. 4. Creating a table with different system topologies and the corresponding setting groups of the IEDs included in the system The CIM and IEC 61850 models need to be extended and harmonized to support this function 5. Downloading the settings in the relays No changes required. H-5

6. Determining the system topology No changes required. 7. Activating the required setting groups The CIM model needs to be harmonized to be able to issue a change of setting group command 8. Reporting the active setting groups to the APCU The CIM model needs to be harmonized to be able to perform as a logical node report client The behavior of the adaptive protection system will then be based on the receipt of change of state reports from the IEDs and followed by steps similar to steps 6, 7 and 8 above. Harmonization Tasks Based on the analysis of the above use case, the following harmonization tasks have been identified: A three phase impedance model (3x3 matrix) for single transmission line is needed. A three phase impedance model for a double circuit line or a section of lines in parallel (6x6 matrix) is needed. Connectivity model for transmission lines is needed to describe a line with multiple segments and multiple mutual couplings. The connectivity model needs to be extended to cover mutual coupling on double circuit or parallel lines. The CIM and IEC 61850 models need to be extended and harmonized to support the creation of a table with different system topologies and the corresponding setting groups of the IEDs included in the system The CIM model needs to be harmonized to be able to issue a change of setting group command Business Rules and Assumptions H-6

ACTORS Actor Name Actor Type Actor Description (person, device, system etc.) Protection Engineer Person Designs, tests, verifies, and analyses protection schemes (could be a team) Protection IED Device Monitors system parameters in order to detect fault conditions within its zone of protection and take action Adaptive Protection (APCU) Network Protection Application Protection Coordination Device System System to clear the fault. Determines the change of system topology and the need for adaptive protection action based on active setting group change System uses CIM and IEC 61850 data to read, create and verify protection settings files. for the calculation of short circuit currents and voltages and checking of the coordination of protection relays settings CIM Database System Contains CIM-level system topology and parameters Relay Database System Contains the settings for each setting group for each relay in the adaptive protection system Field Device Communication Interface CIM Model Server System System Generic architectural component that communicates with substation and field devices using IEC 61850. This system can translate IEC 61850 services to GID services. STEP BY STEP ANALYSIS OF EACH SCENARIO Scenario Description Primary Scenario: System configuration Triggering Event Primary Actor Pre-Condition Post-Condition (Identify the name of the event that start the scenario) (Identify the actor whose point-of-view is primarily used to describe the steps) (Identify any pre-conditions or actor states necessary for the scenario to start) (Identify the post-conditions or significant results required to consider the scenario complete) Adaptive protection system is configured and put in service Protection Engineer CIM and IEC 61850 system models are available Adaptive protection system is in service H-7

Steps for this scenario Step # Actor Description of the Step Additional Notes # What actor, either primary or secondary is responsible for the activity in this step? Describe the actions that take place in this step including the information to be exchanged. The step should be described in active, present tense. Elaborate on any additional description or value of the step to help support the descriptions. Short notes on architecture challenges, etc. may also be noted in this column.. 1 Protection Engineer Protection Engineer uses Protection Coordination to build system configuration model 1.1 Protection Coordination 1.2 Protection Coordination 1.3 Protection Coordination Protection Coordination loads existing system model from CIM Model Server Protection Engineer uses Protection Coordination to calculate settings for Protection IEDs Protection Coordination sends protection model changes to CIM Model Server 2 Protection Engineer Protection Engineer runs coordination studies to determine conditions which require adaptive protection mode and the appropriate relay settings. 2.1 Protection Coordination 2.2 Protection Coordination 2.3 Protection Coordination 3 Protection Coordination 4 Adaptive Protection (APCU) 4.1 Adaptive Protection 4.2 Adaptive Protection Protection Coordination creates relay setting files. Protection Coordination creates database of possible system topologies and appropriate settings for groups of relays. Protection Coordination sends database of system topologies to Adaptive Protection Protection Coordination downloads settings into the Protection IEDs. Adaptive Protection determines current system topology Adaptive Protection retrieves current relay settings from Enterprise Communication Gateway Adaptive Protection updates internal system topology model CIM CIM XML IEC 61850 IEC 61850 H-8

Step # 5 Adaptive Protection Scenario Description Actor Description of the Step Additional Notes Primary Scenario: System operation Adaptive Protection transmits relay setting commands based on current topology IEC 61850 Triggering Event Primary Actor Pre-Condition Post-Condition (Identify the name of the event that start the scenario) (Identify the actor whose point-of-view is primarily used to describe the steps) (Identify any pre-conditions or actor states necessary for the scenario to start) (Identify the post-conditions or significant results required to consider the scenario complete) State change of a switching device Adaptive Protection Adaptive protection system is in service Protection settings are updated as system topology changes Steps for this scenario Step # Actor Description of the Step Additional Notes # What actor, either primary or secondary is responsible for the activity in this step? Describe the actions that take place in this step including the information to be exchanged. The step should be described in active, present tense. Elaborate on any additional description or value of the step to help support the descriptions. Short notes on architecture challenges, etc. may also be noted in this column.. 1 Protection IED Protection IED changes state 2 Protection IED Protection IED reports state change to Adaptive Protection 3 Adaptive Protection 4 Adaptive Protection Adaptive Protection Central Unit updates internal system topology model Adaptive Protection Central Unit transmits relay setting commands based on current topology to Protection IEDs 5 Protection IED Protection IED updates internal protection settings based on received data or commands H-9

REQUIREMENTS Functional Requirements Functional Requirements A three phase impedance model (3x3 matrix) for single transmission line is needed A three phase impedance model for a double circuit line or a section of lines in parallel (6x6 matrix) is needed Connectivity model for transmission lines is needed to describe a line with multiple segments and multiple mutual couplings The connectivity model needs to be extended to cover mutual coupling on double circuit or parallel lines The CIM and IEC 61850 models need to be extended and harmonized to support the creation of a table with different system topologies and the corresponding setting groups of the IEDs included in the system The CIM model needs to be harmonized to be able to issue a change of setting group command Associated Scenario # (if applicable) Associated Step # (if applicable) Non-functional Requirements Non-Functional Requirements Associated Scenario # (if applicable) Associated Step # (if applicable) H-10