The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft

Similar documents
Policy Document. PomSec-AllSitesBinder\Policy Docs, CompanyWide\Policy

REPORT 2015/149 INTERNAL AUDIT DIVISION

Governing Body 313th Session, Geneva, March 2012

Information Technology Disaster Recovery Planning Audit Redacted Public Report

Reviewed by ADM(RS) in accordance with the Access to Information Act. Information UNCLASSIFIED.

Corporate Security & Emergency Management Summary of Submitted 2015 Budget From Rates

VMware vcloud Air Accelerator Service

Introduction to Business continuity Planning

CASE STUDY: RELOCATE THE DATA CENTER OF THE NATIONAL SCIENCE FOUNDATION. Alan Stuart, Managing Director System Infrastructure Innovators, LLC

Birmingham Community Healthcare NHS Foundation Trust. 2017/17 Data Security and Protection Requirements March 2018

Symantec Data Center Migration Service

ITSM20F_Umang. Number: ITSM20F Passing Score: 800 Time Limit: 120 min File Version: 4.0. Exin ITSM20F

Request for Proposal for Technical Consulting Services

<PROJECT NAME> IMPLEMENTATION PLAN

Management s Response to the Auditor General s Review of Management and Oversight of the Integrated Business Management System (IBMS)

Chapter 8: SDLC Reviews and Audit Learning objectives Introduction Role of IS Auditor in SDLC

Manchester Metropolitan University Information Security Strategy

Service Description: Advanced Services Fixed Price Cisco WebEx Advise and Implement Service (0-5,000 Users) (ASF- WBXS-UC-PDIBSE)

Mathematical and Statistical Sciences

WELCOME TO ITIL FOUNDATIONS PREP CLASS AUBREY KAIGLER

Office of the City Auditor 2014 Third Quarter Activity Report November 25, 2014

Service Description: Advanced Services- Fixed Price: Cisco UCCE Branch Advise and Implement Services (ASF-CX-G-REBPB-CE)

Service Description: Identity Services Engine Implementation-Subscription Service

Transition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

PK0-004 comptia. Number: PK0-004 Passing Score: 800 Time Limit: 120 min.

Request for Proposal. I. Introduction. II. Scope of Work. IT Managed Services Support. IT Environment. Main Facility

TDWI Data Governance Fundamentals: Managing Data as an Asset

(Office 365) Service Level Expectation

Certification Standing Committee (CSC) Charter. Appendix A Certification Standing Committee (CSC) Charter

Policy. Business Resilience MB2010.P.119

Mitigation Framework Leadership Group (MitFLG) Charter DRAFT

Business Continuity Management Standards A Side-by-Side Comparison

THE PATH TO LOWEST TOTAL COST OF OWNERSHIP WITH INDUSTRIAL AUTOMATION OPERATIONAL SYSTEMS. Avoiding Downtime with a Positive ROI

IT Audit Process Prof. Liang Yao Week Six IT Audit Planning

Position Description IT Auditor

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

FedRAMP: Understanding Agency and Cloud Provider Responsibilities

Data Centre. Design and Build. Everything you need to know about designing, installing and maintaining a. Data Centre

Physical Security Reliability Standard Implementation

Service Description: Advanced Services Fixed Price

REPORT 2015/186 INTERNAL AUDIT DIVISION

01.0 Policy Responsibilities and Oversight

OG0-091 Q&As TOGAF 9 Part 1

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Unofficial Comment Form Project Modifications to CIP Standards Requirements for Transient Cyber Assets CIP-003-7(i)

State of Nevada Legislative Counsel Bureau 401 S. Carson Street Carson City, NV voice facsimile

Cisco Director Class SAN Planning and Design Service

Certified Information Systems Auditor (CISA)

VMware BCDR Accelerator Service

The Common Controls Framework BY ADOBE

Report to the Business Administration Committee Recommendation to Award a Contract for Datacenter Colocation and Associated Support Services

Corridor Management Committee. January 12, 2017

Government Resolution No of February 15, Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security

INFORMATION TECHNOLOGY NETWORK ADMINISTRATOR ANALYST Series Specification Information Technology Network Administrator Analyst II

Standard CIP Cyber Security Critical Cyber Asset Identification

September 2010 Version 0.9

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities

13.f Toronto Catholic District School Board's IT Strategic Review - Draft Executive Summary (Refer 8b)

Architecture and Standards Development Lifecycle

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.

Services Summary. Deliverables. Location of Services. Services Assumptions & Exclusions. General Project Management

Critical Cyber Asset Identification Security Management Controls

Any observations not included in this report were discussed with your staff at the informal exit conference and may be subject to follow-up.

Information Technology Branch Organization of Cyber Security Technical Standard

"Charting the Course... Certified Information Systems Auditor (CISA) Course Summary

Effective: 12/31/17 Last Revised: 8/28/17. Responsible University Administrator: Vice Chancellor for Information Services & CIO

ANZSCO Descriptions The following list contains example descriptions of ICT units and employment duties for each nominated occupation ANZSCO code. And

White Paper. How to Write an MSSP RFP


Data center relocation needs physical infrastructure availability evaluation and standardization. Martin Puš, SYSTEMING Prague, 4th October 2016

I. PURPOSE III. PROCEDURE

Government of Ontario IT Standard (GO ITS)

FedRAMP Plan of Action and Milestones (POA&M) Template Completion Guide. Version 1.2

Appendix 3 Disaster Recovery Plan

Federal Data Center Consolidation Initiative (FDCCI) Workshop III: Final Data Center Consolidation Plan

Response to Wood Buffalo Wildfire KPMG Report. Alberta Municipal Affairs

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

The Internet Society. on behalf of. The IETF Administrative Oversight Committee REQUEST FOR PROPOSALS. for

Annexure 08 (Profile of the Project Team)

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

UNIVERSITY OF MASSACHUSETTS AMHERST INFORMATION SECURITY POLICY September 20, 2017

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

Appendix 6 Operational Support Systems Change Management Plan

Scope Cyber Attack Task Force (CATF)

Standard Development Timeline

A Practical Guide to Avoiding Disasters in Mission-Critical Facilities. What is a Disaster? Associated Business Issues.

Using ITIL to Measure Your BCP

Process Definition: Security Services

OE-PM Project Charter Document

EX0-101_ITIL V3. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0. Exin EX0-101

Government of Ontario IT Standard (GO ITS) GO-ITS Number 56.3 Information Modeling Standard

Information Technology Services. Informational Report for the Board of Trustees October 11, 2017 Prepared effective August 31, 2017

6/5/ Michael Hojnicki Chief of Technology and Administrative Services

Groton Data Center Migration Project

Request for Proposal

0522: Governance of the use of as a valid UNC communication

DISASTER RECOVERY PRIMER

SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality,

RFP Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service

Transcription:

The Project Charter Project Title: VDI Data Center Design and Build Project Sponsor: South Alberta Data Centers Inc. (SADC Inc.) Project Customer: The City of Calgary Project Manager: Moe Yousof Document History: Revision Number Date of Issue Author Description Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft Version 1.0 November 3 rd, 2014 Moe Yousof Executive Committee Review 1. Background The move towards cloud computing has become prevalent in the Canadian workplace for all the benefits it provides over conventional computing. Cloud computing reduces total cost of ownership, facilitates easier access to applications and data, provides better control for administration of the IT infrastructure, and helps the environment through offering greener and more economic desktop structure. Virtual Desktop Infrastructure (VDI) is the implementation that the City is adopting to move into the cloud, and this move calls for a data center to work as the beating heart of this infrastructure. The City of Calgary is sponsoring a project to designing and build the VDI Data Center. This data center will host more than 10'000 virtual machines and 15'000 user accounts, and will provide access to all the applications that is used by the different business units of the City. The new VDI-DC will also allow the storage of all VM images and user data to be consolidated and re-organized from several storage islands into one physical and logical unit. This gives the IT infrastructure of the City the scalability, performance, fault tolerance, and manageability required to meet current and future needs. The storage cluster will also eliminate the need to disrupt services when hardware upgrades are required.

The directive for this initiative was provided by the IT Planning group and the City Advisory Committee and was approved by the Steering Committee and the City Council on the 15th of September, 2015. 2. Purpose and Description The purpose of this project is to build a data center facility. It will start with the planning and design phase that is then followed by the build and construction phase. The site of the data center will be provided by the City of Calgary. The site will fulfill all the site selection criteria that is provided in document to the City. The design and build of the VDI Data Center will be implemented by South Alberta Data Centers Inc. After the new data center gets to be commissioned, all current virtual machines (VMs) and related data stores will be migrated to the new centralized data center. South Alberta Data Center Inc is contractually obligated to provide continuous service to it is customers. As the interruption is unavoidable, the goal of this project will be to control and to minimize the interruptions to the current services when migrated to the new data center. 3. Scope 3.1 In scope The following items are included within the scope of the project: Gather and compile all the business and technical requirements that will be used to design, build, and operate the VDI-DC. Inspect and prepare the site that will host the VDI-DC and make sure it complies with the site selection criteria that is provided to the City. Prepare all the plans and designs of the VDI-DC that adheres to the business and technical requirements, provide a balance between performance, availability, stability, data protection, and costs, and that is based on a scalable hardware infrastructure to supports any expansion of the facility to meet with the future needs of all business unites of the City.

Provide and implement the structural, electrical, mechanical, and networking components that form the physical foundations of the VDI-DC. Develop a disaster recovery plan for the VDI-DC. Note: Implementing the disaster recovery plan will be a separate project. Test and commission the VDI-DC. Migrate systems, applications and other services (physical and virtual) running on equipment on other data centers to the VDI-DC. 3.2 Out of scope: The following items are specifically excluded from the scope of the project: Relocating or moving any equipment or furniture provided by the City to the site of the VDI- DC. Planning, designing, and building a data center that will be used for any other purpose besides the Virtual Desktop Infrastructure needs of the business unites of the City. Training for staff that will be operating the facility. Developing operational processes that will be used by the facility. 4. Deliverables and Milestones The following is a list of the project deliverables and milestones: - Planning and Communication Prepare and Prioritize Facility Requirements (Business and Technical) Prepare Workload Assessment Document Develop Project Management Plan Develop Communications Plan Develop Change Management Plan Develop Quality Control and Assurance Plan Develop Risk Mitigation Plan Develop Migration Strategy Plan

Develop Disaster Recovery Plan Prepare Project Budget Outline and Details - Quality Control and Assurance Assign Members of Quality Control and Assurance Team - Contractor and Vendor Selection Prepare Selection Criteria Initiate Request for Proposals Review and Evaluate Request for Proposals Select Contractors and Vendors - Site Preparation Complete Site Inspection Plan and Design Floor and Layout Build and Install Floor and Layout - Facility Requirements Estimate and Design Electrical Wiring and Cabling Requirements Build and Install Electrical Wiring and Cabling Estimate and Design Power Requirements Build and Install Power Equipment Estimate and Design Standby Power Requirements Build and Install Standby Power Equipment Estimate and Design Cooling Requirements Build and Install Cooling Equipment Estimate and Design Fire Protection and Suppression Requirements Build and Install Fire Protection and Suppression Equipment

Estimate and Design Networking Requirements Build and Install Networking Cables and Equipment - Servers Requirements Determine Data Center Capacity, Tire Level, and Servers Requirements Plan and Design Scalable Structure of the Facility Procure Servers and Racks Install Racks and Servers - Facility Commissioning Commission a Fully Operational Data Center that Meets and Exceeds the VDI Needs of the City of Calgary Benchmark Report to Validate Successful Operation - VMs and Data Store Migration Execute Migration Plan Benchmark Report to Validate Successful Migration - Closing Project Prepare Project Closing Report 5. Funding and Budget The project is totally funded by the City of Calgary. Total budget approved for the project is $4 Million. Budget outline and details will be prepared and approved in a separate document. 6. Timeframe and Schedule

The project official start date is November 1st, 2015. The project is estimated to be completed in 5 months and the end date of the project is designated on March 31st, 2015. Detailed schedule will be develop separately. 7. Approach The approach used for this project includes the following: South Alberta Data Center Inc. (SADC Inc.) will be in charge of the management and coordination of all activities, tasks, and sub-project across the process of designing and implementing the VDI-DC. SADC Inc. will be responsible for: o Developing and maintaining the overall project plan and schedule. o Documenting and managing issues and risks across all teams. o Establishing project management templates and repeatable processes to manage the VDI- DC project. o Establishing standard migration strategies, templates, and repeatable processes o Make the migration process as efficient and low risk as possible. SADC Inc. will be in charge of designing the VDI-DC and overseeing its implementation through selected contractors and vendors. SADC Inc. will be in charge of developing the the VDI-CD disaster recovery plan. SADC Inc. alongside with contractors and contractors will be responsible for planning the VDI-DC sub-projects. SADC Inc. will be coordinating with the IT Services from the City of Calgary to monitor schedules and budgets, assist with resolving issues and risks, and plan and execution migration of existing VMs and data stores. Migration to the VDI-DC must use low risk and thoughtful approaches to avoid unplanned outages.

8. Assumptions Assumptions for this project include: Project site will be provided by the City of Calgary and will meet the site criteria specified in the site selection document Current network infrastructure will be sufficient to meet the needs of the centralized VDI data center The City of Calgary IT Services resources and staff will be available when and as they are needed Planning, design, server procurement and installation, and management consultancy of the project will be provided directly by SADC Inc. Vendors will be contracted to implement structural, electrical, mechanical, and networking requirements of the project Budget will be available on time and as scheduled and approved The Scope of the project is limited to that described in this charter 9. Dependencies Dependencies for this project include: The City of Calgary IT Services The City of Calgary Corporate Security The City of Calgary Corporate Assets 10. Constraints Constraints for this project include: Project site provided by the city needs to be handed over to the project team before December 1st, 2014

11. Risks The project will have a Management Consultant team that will provide quality control and be in charge of quality assurance. This team will continually evaluate and assess project risks and make sure all project requirements are met as defined in the project plan. Initial risks to this project include: Risk Probability Impact Mitigation Strategy Project cost exceeds assigned budget Design faults due to capacity or reliability of power, cooling, or fire suppression systems 4. Very Low 4. Very Low 1. Severe Management Reserve will be used to avoid major impact. Initial capacity of servers will be reduced if Management Reserve did not cover extra cost, provided that structural and technical design will be kept fully scalable. 1. Severe Power, cooling, and fire suppression designs and implementation will be contracted to vendors with solid business record. A management consultant team will be closely monitoring quality of external vendors and assure they all meeting or exceed project minimum requirements. CoC Corporate Security delay in tasks require their approval or interference CoC ITServices resources and staff not available according to schedule 1. High 2. Significant Work closely with CoC Corporate Security to keep them updated about tasks that require their interference. Get their approval about these tasks beforehand to prevent any delay of project implementation. 2. Medium 2. Significant Work closely with CoC ITServices to keep updated about their recourses and staff availability. Add external recourses when CoC ITServices are not available for tasks on critical path.

Migration of critical business units interrupt their critical operations Project site is not handed over on scheduled time 2. Medium 2. Significant Implement the Migration Strategy plan and closely monitor the migration process until completed and tested successfully both by the technical team and the business unit personnel. 3. Low 2. Significant Inform CoC that delay in handing over project site will impact overall schedule. Fast Track project schedule when possible to reduce impact and Crash project schedule if resources are available to meet deadline. Delay in RFP process 3. Low 2. Significant Closely monitor RFP process to prevent any major delay in reviewing and selecting vendors and contractors. Present network infrastructure does not meet minimum requirement for operation of the VDI-DC 3. Low 2. Significant Fully inspect CoC network infrastructure connect to the VDI-DC site and assess its capacity. Immediately report any shortage of capacity and request crash upgrade of short segments. Flood 4. Very Low 2. Significant Implementation will be significantly impacted by flood and there is very little that can be done about that. However, structural and technical implementation of the VDI-DC is going to based on flood resistant designs as the operation of the data center is require to continue in case of flood hits the city for critical business unit to efficiently work and operate at such times. The management consultant team will monitor implementation of designs to assure they meet requirements for flood resistance.

CoC delay in moving equipment provided by them to be used at the VDI-DC CoC delay in moving furniture provided by them to be used at the VDI-DC 3. Low 3. Moderate Inform CoC Corporate Assets about equipment move tasks that are required to be completed by them. Follow up with them to make sure tasks are completed according to schedule agreed upon. 3. Low 4. Minor Inform CoC Corporate Assets about furniture move tasks that are required to be completed by them. Follow up with them to make sure tasks are completed according to schedule agreed upon. 12. Acceptance Criteria There are 7 criteria that are required for the project to be accepted at handover: 1. Design and implementation of the VDI-DC adheres to the business and technical requirements collected from all business units of the City of Calgary. 2. Structural implementation of power, cooling, and fire suppression of the VDI-DC adheres to Tire 3 of data center designs. 3. Structural implementation of the VDI-DC adheres to ASCE/SEI 24-05 standards of flood resistant designs. 4. Structural and Technical implementation of the VDI-DC is scalable to supports expansion of the facility to double of the initial required workload. 5. All VMs and data stores currently in operation are migrated to the VDI-DC. 6. The functionality of services offered by the current VMs and data stores after being moved to the VDI-DC are retained as they were before the move. 7. Outages of services caused by the migration are kept to a minimum. 13. Stakeholders A registry of all internal and external stakeholders will be prepared as a separate document and will include contractors and vendors selected through the RFP process.

14. Communication Plan A meeting will be held on the first business day of every week throughout the project lifecycle to discuss project progress and any issues related to it that require a stakeholder attention. These meetings will be attended by the members of the executive committee and a representative from each contractor or vendor. Any other stakeholder will be invited to attend the meetings as needed or required. An email will be sent out biweekly to all stakeholders to inform about the progress of the project. Details communication plan will be prepared as a separate document. 15. Governance and Decision Rights Project leadership expects project level decisions to be made and project activities to be completed at the lowest possible level within the project structure. Issues, regardless of where they come from or how they surface, will be reported to the appropriate team lead to be logged and managed. Risks affecting the project can be suggested and reported by anyone but require the project manager approval to officially open a project level risk. Issue, risk, and change management will follow a standard process that will be described in separate project documents. However these items will be escalated to the executive committee or the the executive sponsor for action by the project manager depending on their severity and time sensitivity. Any email or voice message sent to the executive committee chairman or the project executive sponsor that requires a decision to be made will specify a decision date or time within reasonable limits. If the project manager received no answer from the executive committee chairman or the project executive sponsor by the specified date or time this will imply approval on decision and the project may continue. If the executive committee chairman or the project executive sponsor does not approve the decision or requires further clarification they must contact the project manager within the specified timeline to avoid any delay in schedule.

17. Approval The project charter has been reviewed and accepted as written. Approval is given to move forward with the project as outlined in this document. Celine Dion Project Executive Sponsor South Alberta Data Centers Inc. Date Moe Yousof Project Manager South Alberta Data Centers Inc. Date