Corridor Management Committee. January 12, 2017

Similar documents
Corridor Management Committee. December 17, 2014

Community Advisory Committee. June 5, 2017

Corridor Management Committee. January 14, 2016

Corridor Management Committee Meeting. June 4, 2014

SWLRT Corridor Management Committee. November 26, 2018

Joint Business and Community Advisory Committee Meeting. April 15, 2015

SWLRT Community Advisory Committee Meeting. June 27, 2013

C Line Rapid Bus 90% Design

Electrification - Infrastructure Construction activities in Segment 2:

APPENDIX C SOURCES & REFERENCES CITED

Los Angeles Metro Upcoming Tunneling Opportunities

Business Advisory Committee. October 1, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Section 4: Citizen s Guide to SDEIS

The Blue Line Extension

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT

Dallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension

Reston Town Center North Development. Community Update

Metropolitan Council. Transportation Division Proposed Transit Capital Program

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

System Expansion Implementation Plan. Board Meeting, April 2017

10.1 BIBLIOGRAPHY Noise and Vibration Study Yard and

Joint Committee Report

Dulles Area Transportation Association

Record of Public Comment on Central Corridor SDEIS

Northern Virginia Transportation Authority

Moving Forward with Transit Oriented Communities

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008

Construction Phase Public Outreach Plan

Community Update. May 31, 2011

ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n

STATE STREET CORRIDOR

Metropolitan Council meeting: February 22, 2012

Provo-Orem Bus Rapid Transit

GDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010

STUDY REPORT #1 ADDENDUM

# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

Stem Beach Solar 1041 Application

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft

Physical Security Reliability Standard Implementation

Community Update. June 21, 2011

Downtown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

WRI BUILDING EFFICIENCY INITIATIVE BUILDING EFFICIENCY INITIATIVE, WRI ROSS CENTER FOR SUSTAINABLE CITIES

Recommendation to Board. Final Action

Corridor Management Committee. February 6, 2013

Click to edit Master title style Click to edit Master title style

GATEWAY PROGRAM OVERVIEW AND UPDATE

A RESOLUTION. WHEREAS, On January 20, 2017, the inauguration of the 47th President of the United States of

Downtown Boise Multimodal Center

Hennepin Avenue Downtown

Central Corridor. - Central Corridor. Management Committee, Light Rail Transit. Rail-Volution - Weaving Transit into Existing Communities

Minutes - Standing Policy Committee on Finance - April 9, 2015 REPORTS

Metro Mot opo'"'" T""''"""~" '"'"""''

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

Veirs Mill Road Metrobus Improvements Request to Conduct Public Hearing

The Commonwealth of Massachusetts

Maximizing Asset ROI for Self & Clients in a Public Sector Setting. July 16 th San Diego

Alliant Energy Center Comprehensive Master Plan O v e r s i g h t C o m m i t t e e

CLAYTON COUNTY TRANSIT INITIATIVE. Technical Advisory Committee/ Stakeholder Advisory Committee Webinar August 29, 2017

Schematic Design Overview Project Review Stakeholder Engagement Project Delivery Method Upcoming Milestones

Metrolinx / Toronto Transit Plan April 28, Jack Collins Vice President, Rapid Transit Implementation

Canadian Infrastructure Report Card

Executive Director s Report May 23, 2017

STATEWIDE CENTERLINE INITIATIVE EDITED: MAY 17, 2013

BCI Principles & Criteria: Revision

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

Community Update. June 8, 2011

Fairfax County Comprehensive Transit Plan and Transit Development Plan

Developing a Cross Part Client Level Data System

Dallas Streetcar Central Link Locally Preferred Alternative Selection

ARLINGTON COUNTY, VIRGINIA

I-495 & I-270 Managed Lanes Study. Edit presentation title MM/DD/YYYY 1

Malibu Civic Center Stakeholders Meeting. October 25, 2012

CITY OF VANCOUVER ADMINISTRATIVE REPORT

Municipal Broadband Project. City Council Meeting February 4, 2016

TO: Regional Transportation Council DATE: May 2, 2014

2014 BOND PROGRAM UPDATE

An Introduction to the SEforALL Building Efficiency Accelerator Belgrade BEA Kick-off Meeting 31 October 2016 Eric Mackres,

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014

Georgia: Power Transmission Enhancement Project financed by Asian Development Bank (ADB)

Phase Two: Plan Recommendations Public Comment Summary Report June 23, 2016

Internal Audit Follow-Up Report. Multiple Use Agreements TxDOT Office of Internal Audit

NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance

S-03-SegB: South Federal Way to Fife LRT

Boardman to Hemingway Project Advisory Team

Contractor Alliancing Sean Mooney Programme Manager

Rail Division Update. Presented to Joint Appropriations Subcommittee on Transportation. Paul C. Worley, CPM Rail Division Director February 28, 2013

Transcription:

Corridor Management Committee January 12, 2017 1

Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2

3 Chair s Update

2016 Major Project Milestones Achieved March: Received Municipal Consent from the five corridor cities & Hennepin County July: FTA & Met Council published the Final Environmental Impact Statement August: Received local funding commitments o Counties Transit Improvement Board o Hennepin County Regional Railroad Authority o City of Brooklyn Park o Minnesota Department of Transportation o Hennepin County 4

2016 Major Project Milestones Achieved August: Completed 30% design Submitted FTA New Starts with materials demonstrating completion of Project Development September: FTA issued Record of Decision & Met Council determined Final EIS is adequate Met Council adopted revised project scope and budget Met Council applied for Entry into Engineering Staff participated in 140 community events/meetings/advisory committee meetings 5

6 2017 Project Activity Overview

Overall Project Schedule Project Development 2014 2015 2016 2017 2018 2019 2020 2021 ROD Engineering Construction FFGA LRV Production & Testing Fare Collection Production, Testing Systems Testing Revenue Operations 7

Major 2017 Milestones FTA Grants Entry to Engineering January 2017 Complete 60% Civil & OMF Design March 2017 Complete 60% Systems Design May 2017 FTA Risk Assessment June 2017 FTA Financial Capacity Assessment June 2017 LONP Submittal for Advanced Construction June 2017 Complete 90% Civil Design August 2017 Application for Full Funding Grant Agreement September 2017 Complete 90% OMF Design September 2017 Complete 90% Systems Design October 2017 Complete 100% Civil Design December 2017 8

FTA New Starts 2017 Key Activities FTA authorizes Entry to Engineering FTA conducts Risk Assessment FTA conducts Financial Capacity Assessment Met Council prepares and submits Full Funding Grant Application 9

Environmental Section 106 (Historic/Cultural Resources): Complete interpretive plan design Complete Construction Protection Plan Consult to meet SOI standards: milestones at 60/90/100% design Wetlands Permitting: Submit permit request to USACE / local jurisdictions Receive permit prior to advanced construction Complete Phase II Investigation: Receive RAP approvals from MPCA Incorporate actions into contract specifications 10

Agreements Railroads: Canadian Pacific BNSF Utilities (requiring substantial relocation): Xcel MCES Construction Cost Participation Agreements: MnDOT Hennepin County Local municipalities 11

12 Design Advancement

2017 Design Advancement Activities 60% design plans Plan production underway March: Distribute 60% plans for stakeholder review Design details to resolve prior to 90% plan production Robbinsdale Park and Ride Oak Grove Park and Ride West Broadway streetscape Olson Memorial Highway streetscape Drainage North of TH 610 13

2017 Design Advancement Activities 90% design plans April: Begin production August: Distribute 90% plans for stakeholder review 100% design plans September: Begin production December: Deliver Bid packages ready early 2018 14

Potential Advanced Construction Activities 15

Potential Advanced Construction Activities MCES sewer relocation Floodplain mitigation Theodore Wirth Parkway bridge reconstruction Bassett Creek tunnel reconstruction Procurement of Xcel transmission poles 16

Theodore Wirth Parkway Bridge MCES Forcemain / Floodplain Mitigation Bassett Creek Tunnel 17

Proposed Construction Packages Civil 1 & 2: Civil 1: Target Field Station thru CSAH 81 flyover bridge Civil 2: Jolly Lane to Operations & Maintenance Facility o Roadway o Utilities o LRT guideway o Stations o Park and Rides Systems: Traction power Overhead catenary system Communications Rail signaling 18

Proposed Construction Packages Operations Maintenance Facility: Brooklyn Park o OMF building o Yard track o Vehicle storage o Light maintenance o Paint and body bay Franklin O&M Building o Overhaul bay expansion o Rail control center expansion 19

BLRT / SWLRT Joint Contracting Efforts Supervisory Control and Data Acquisition (SCADA) contractor: Rockwell Collins (ARINC) Traction Power Substations Target Field Station Light Rail Vehicles BLRT options to the SWLRT procurement Fare Collection 20

Right of Way Appraisals and acquisition prioritized based on: Minneapolis Park and Recreation Board property Railroad parcels Advanced construction parcels Parcels that include relocation 21

22 Public Involvement

Public Involvement Activities Support Design/Engineering activities Large format meetings at 60% design Neighborhood meetings Staff project Advisory Committees Share project information through website, newsletters Coordinate project information sharing efforts with project partners 23

Updated Corridor Flyover Video: Preview 24

2017 CMC Meeting Schedule

2017 Meeting Schedule Second Thursday of the month: 1:30 to 3:00 PM Held at Hennepin County Rockford Library (Crystal): February 9 March 9: Brooklyn Park Library April 13 May 11 June 8 July 13 August 10 September 14 October 12 November 9 December 14 26

More Information Website: BlueLineExt.org Email: BlueLineExt@metrotransit.org Twitter: @BlueLineExt 27