Project Overview/Update: Advanced Signal System CBOSS PTC

Similar documents
Caltrain Local Policy Maker Group (LPMG) Meeting. Agenda

FINAL REPORT AUGUST 2013

Electrification - Infrastructure Construction activities in Segment 2:

OVERVIEW: POSITIVE TRAIN CONTROL (PTC) June 2018

Opening the New Woodrow Wilson Memorial Bridge: Planning & Implementing a Major Traffic Switch

OVERVIEW: POSITIVE TRAIN CONTROL (PTC) December 2017

Positive Train Control (PTC) Implementation on A-train Commuter Rail. Updated July 31, 2018

Update on Positive Train Control (PTC)

Girard Siding Environmental Assessment (EA) Public Meeting. May 23, 2013

VTA s BART Silicon Valley Phase II Extension

ACEC State Markets Conference April 2018

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Girard Siding Environmental Assessment (EA) Public Meeting. May 23, 2013

Positive Train Control (PTC) Update. February 24, 2014 APTA Meeting

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

Crystal Springs Upland School Transportation Demand Management Plan. March 2016

Addison, Irving Park, Montrose, and Damen Stations Community Meeting

CONNECTING AND TRANSFORMING CALIFORNIA. Frank Vacca, Chief of Rail Operations UNLV Symposium October 17, 2018 Las Vegas, Nevada

STAFF REPORT. Meeting Date: To: From: La Cienega Station. Subject: Attachments:

Corridor Management Committee. January 14, 2016

Construction Phase Public Outreach Plan

SPECIAL MEETING AGENDA PENINSULA CORRIDOR JOINT POWERS BOARD Bacciocco Auditorium, 2 nd Floor 1250 San Carlos Avenue, San Carlos CA 94070

Managed Lane owner decision needed San Mateo County s options Understanding revenues & costs Pros & cons of County s options Proposed next steps

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Corridor Management Committee. January 12, 2017

Transportation & Mobility

VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group

Study Session Project Update & Google Fiber's FTT Project Master Plan for the City of Santa Clara. o Google Fiber studying 34 cities (Feb 2014)

Dulles Area Transportation Association

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

10.1 BIBLIOGRAPHY Noise and Vibration Study Yard and

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

Maximizing Asset ROI for Self & Clients in a Public Sector Setting. July 16 th San Diego

Purple Line Extension Section 1 Construction Community Meeting November 16, 2017

Points of Discussion. Big Dig Project Schedule Next 6 Months of Construction Site Logistics Truck Traffic

VTA s BART Silicon Valley Phase II Extension

SAN JOSE COMMUNITY WORKING GROUP. San Jose City Hall August 16, 2018 San Jose, CA

Department Total Worker Count by Location/Budget Unit Count of Worker Row Labels Total 1100D Board of Supervisors

Managing DC Work Zones: DDOT s Citywide Transportation Management Plan

Rail Division Update. Presented to Joint Appropriations Subcommittee on Transportation. Paul C. Worley, CPM Rail Division Director February 28, 2013

TOUR OF RAIL OPERATIONS CONTROL CENTER Washington Metropolitan Area Transport Authority Monday, September 23, 2013

Board of Directors April 25, BART The Next 40 Years BART Metro Vision Update Enhancing Service, Capacity and Coverage

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

VTA s BART Silicon Valley Phase II Extension

White paper June ARINC RailwayNet HOSTED POSITIVE TRAIN CONTROL (PTC) COMMUNICATION SOLUTION

FIBER OPTIC RESOURCE SHARING IN VIRGINIA

Customer Service You Can APP reciate! Blending Mobile Apps, Web Requests and Technology

# I-2. Date of Meeting: May 2, 2017 BOARD OF SUPERVISORS BUSINESS MEETING INFORMATION ITEM. Quarterly Metrorail Construction Status Report

North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009

210,000 rsf Typical floorplate 67,549 rsf

2014 ITS 3C Summit GDOT TMC Reconfiguration


Implementation Plan FY

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS

The Maryland Transit Administration. A Plan to Connect Baltimore

Provo-Orem Bus Rapid Transit

VTA Board of Directors: FOR YOUR INFORMATION ONLY

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Muni Service Equity Strategy. Presentation to SFCTA Plans and Programs Committee April 19, 2016

Silicon Valley Power:

ROARING BROOK COMMUNITY INFORMATIONAL MEETING TACONIC STATE PARKWAY (TSP) AT PUDDING STREET INTERCHANGE

Calendar PPF Production Cycles Non-Production Activities and Events

C Line Rapid Bus 90% Design

VTA s BART Silicon Valley Phase II Extension Project

Delivering Communications Solutions in a. Syl Santo, RCDD. Stantec Consulting

Mountain Corridor Incident Management Program

REQUEST FOR PROPOSALS FOR WEBSITE REDESIGN

I-20 EAST TEXAS CORRIDOR STUDY. TxDOT Planning Conference, Corpus Christi June 4 th, 2014

A TRANSFORMATIVE INVESTMENT IN CALIFORNIA S FUTURE

Mid-Atlantic Traffic Incident Management Training Facility Feasibility Study

City of San José PRT Project. Austin Smith

FRONTCOUNTER USER GUIDE

Virginia Department of Transportation Hampton Roads Bridge-Tunnel Action Plan Implementing the Independent Review Panel Recommendations

Corridor Management Committee Meeting. June 4, 2014

Downtown Boise Multimodal Center

Dupont Circle Escalator Replacement

System Expansion Implementation Plan. Board Meeting, April 2017

Product Guide Verizon Pennsylvania Inc. Verizon Pennsylvania Inc. Original Sheet 1 TABLE OF CONTENTS. Business Exchange Service...

The Blue Line Extension

Northern Redmond-Kirkland Area Electric System

MVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014

I-95 Express Toll Lanes

Los Angeles Metro Upcoming Tunneling Opportunities

SAFETY ON THE IH 35 EXPANSION PROJECTS. Andy Petter, P.E. - Waco District

Expansion Options and Fiber Line Extension Policy

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT

Doug Couto Texas A&M Transportation Technology Conference 2017 College Station, Texas May 4, 2017

Community Advisory Committee. June 5, 2017

City of Ketchum Broadband Strategic Plan Executive Summary Report September 12, 2013

Neutral Host Reimbursable Capital Project

DISASTER PREPAREDNESS IN THE COUNTY: IMPROVEMENTS NEEDED

FY International City/County Management Association (ICMA) Benchmarking Results

Fairfax County Comprehensive Transit Plan and Transit Development Plan

Transportation Demand Management (TDM) Plan

VTA s BART Silicon Valley Phase II Extension

8505 Baycenter Road Jacksonville, FL

Johnson City ITS Project Pre-Bid Meeting Minutes State Pin #

VTA s BART Silicon Valley Phase II Extension

M50 Demand Management Study

Northern Virginia Transportation Authority

Transcription:

Project Overview/Update: Advanced Signal System CBOSS PTC Board of Directors September 5, 2013 CBOSS PTC - What is it? Communications Based Overlay Signal System Positive Train Control Fiber Optic Network Project Requirements Includes federal mandate (PTC) Improves Caltrain performance Project Partners Federal Railroad Administration, Union Pacific, California High-Speed Rail Authority Needed for Blended System 2 1

CBOSS PTC Requirements PTC Prevent train-to-train collisions Prevent over speed derailments Prevent incursions into established work zones Prevent movement through a misaligned switch Interoperability Caltrain Enhanced crossing safety / performance Improved headways and operational flexibility Enforcement of scheduled station stops Schedule management Employee In Charge 3 Project Total Cost and Milestones Description Project Planning and Procurement Cost (in millions) Milestones $5 2010-2011 Phase 1 - Critical Design $25 2012 2013 Phase 2 - Final Design, Data Communications Subsystem & Fiber Backbone Installation $51 2013 2014 Phase 3/4 - Installation, Testing, Commissioning $150 2014 2016 (Revenue service Oct. 2015) Total $231 4 2

Segments South to North Segment 1 (SSF SF) 8 Miles Segment 3 SJ Santa Clara (S of Lafayette St) Segment 2 Santa Clara (N of Lafayette St) Sunnyvale Mountain View Palo Alto Menlo Park Atherton Redwood City San Mateo County San Carlos Belmont San Mateo San Bruno SSF (S of Oyster Point) Segment 1 SSF (N of Oyster Point ) Brisbane SF Segment 2 (Santa Clara - SSF) 36 Miles Segment 3 (San Jose - Santa Clara) 8 Miles 5 Installation Milestones (Entire Corridor) Data Communications Subsystem Installation* Wayside Interface Units Installation* Data Communications Subsystem Testing Work Windows: 8pm 4 am weekday 8pm 6am weekend Day work when possible Backup Central Control Facility (BCCF) Office Installation Central Control Facility (CCF) Office Installation Onboard Installation Segment 3 CBOSS PTC Static, Dynamic, Pre FRA & FRA Testing * Segments 2 & 1 CBOSS PTC Static & Dynamic Testing * 6 Month Demonstration Testing Revenue Service (Oct 15) 2013 2014 2015 2016 6 3

Milestones (Example San Jose) Fall 13 Winter 13/14 Spring 14 Summer 14 Fall 14 Winter 14/15 Data Communications Subsystem Installation Bore /Trench Three weeks Inner-Duct Two weeks Cable One week Radio Frequency Base Stations Two weeks Wayside Interface Units Wayside Installation Eight weeks Testing Static Testing One week Data Communications Subsystem Test One week Dynamic Testing One week FRA Related Testing TBD 7 Fiber Installation Trench (with mini excavator or by hand, within the Caltrain right of way) Conduit placed in trench (~42 deep x 9.5 wide, within the Caltrain right of way) Potholing (Vacuum-excavation preparing the job site, within the Caltrain right of way) 8 4

Fiber Installation continued Boring (required at many crossings, within the Caltrain right of way) Conduit on tunnel or bridge (clamps/hangers, may require lane closure during off-peak hours) 9 Base Station Installation Pour foundation Example 80 pole already on right of way Base station footprint 10 5

Base Station Map Segment 1 (BS 01, TBS 4, 3, 2 and 1) Segment 2 (BS 09 through BS03) Segment 3 (BS 11, BS10) 11 Base Station Installation 14 Base Stations within the Caltrain right of way Many near Caltrain stations Located within the ROW in the following cities: San Francisco (5) Unincorporated San Mateo County Brisbane Palo Alto Burlingame Sunnyvale San Mateo (2) Santa Clara San Jose 8 x 8 ft. shelter and 40-80 ft. poles Average two weeks installation per base station 12 6

Outreach Pro-active Approach Activities (March August 2013) City/County Staff Coordination Group (3 meetings) Local Policy Maker Group (2 meetings) Next meeting follow-up on night work activities One-on-one (each of the17 cities/3 counties) Provided fact sheets, and tentative jurisdiction schedule Discussed tailored outreach and review process for communication material Federal and State Staff Quarterly Call Follow-up e-mail with project update 13 On-going Outreach Project Information Distribution Website (fact sheets, presentations, FAQ) Dedicated project hotline line and project e-mail Weekly updates on website, social media and through construction e-notice Direct mailers along both sides of the tracks Next Steps Permits / Installation coordination Continue outreach coordination (each jurisdiction) Continue briefing interested groups, as requested 14 7

Questions 15 8