System Studies for American Transmission Co. s Benson Lake SVC Project

Similar documents
ATC Zone 2 Projects Update U.P. Energy Summit

ABB static var compensator stabilizes Namibian grid voltage

Testing of Real Time Power System Control Software

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

FACTS and HVDC for Grid Connection of Large Wind Farms

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Advanced SIPS using PMU and SCADA data

Introduction to new ABB STATCOM portfolio Power Grid Integration FACTS

HVDC in CSG Challenges and Solutions

Medium Voltage Metal-Enclosed Harmonic Filter Systems

AUAS SVC, PERFORMANCE VERIFICATION BY RTDS AND FIELD TESTS. S. Boshoff C. van Dyk L Becker M Halonen, S Rudin, J Lidholm Dr T Maguire

ABB Surge Arresters Contribution to Power Quality Line Side Protection

Final Report. Mini Project TET Group nr 7 - Project nr 4. Students: Hans Lavoll Halvorson, NTNU

ArresterFacts 029 Distribution System Response to a Lightning Strike. Distribution System Responses to Lightning Strikes

INTERCONNECTION FACILITIES STUDY REPORT

SDG&E s Accomplishments and Future Plans

Mehr Spannungsqualität im Netz mit SVC PLUS. Improvement in Voltage Quality for Power Systems with SVC PLUS

Transient stability of 11-bus system using SVC and improvement of voltage profile in transmission line using series compensator

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Progress Report on the GCC Electricity Grid Interconnection in the Middle East

Transient Stability Improvement of Long Transmission Line System by Using SVC

Karl Iliev, San Diego Gas & Electric Company

Studies Overview and Data Requirements. Robert Pan

NYPA FACTS CSC System

National Load Despatch Centre Power System Operation Corporation

Indian Power Grid Developments

2009 SPP TransCanada Pipeline Study Report

Simulation and Analysis of Static Var Compensator with Matlab

Commission Testing Methods for Protection Systems

Evolution of Control for the Power Grid

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused

American Transmission Company U.P. Energy Summit

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

Feasibility Study on Load Flow and Short Circuit Project

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

Developing a Roadmap for A Smart(er) and Strong Transmission Grid

10 th Annual University of Pittsburgh Electric Power Industry Conference

Grid Operations and Reliability Monitoring/Analysis at American Transmission Company

Application of overvoltage protection to the Peruvian Power System

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS

IEEE PES Swiss Chapter Workshop: Microgrids Evolution and Integration in Modern Power Systems

Year Assessment Preliminary Needs

Small Power Station Surge Protection Analysis and Plan

RFP Attachment 13. January 2010

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,

Iowa State University

N-1-1 Reactive Upgrades

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

Synchrophasor-Based Monitoring, Analysis, and Control

RELIABILITY OF THE BULK POWER SYSTEM

Hybrid STATCOM / SVC Workgroup 15 th May 2014

XXXXX XXXX Wind Generation Project

Multifunctional System Protection for Transmission Lines Based on Phasor Data

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

OVERVIEW: KEY APPLICATIONS

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

SVC Light for rail traction The way to effective grid integration

Products Portfolio. Pole mounted Vacuum Recloser

Generation Interconnection Feasibility Study Report

Main Components of a Static Var Compensator (SVC)

The Efficient Way. SVC PLUS Innovation meets experience. Answers for energy.

Third Generation System of the Future

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Implementing a Dual Triple Modular Redundant Country-Wide Special Protection System

PacifiCorp Transmission Technical Workshop

PLUS Technology for Large Scale Renewable Energy Integration

SIPROTEC 5 New features of V7.5

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection

Memorandum. This memorandum requires Committee action.

Achieving Smarter Grid Operation With On-Line DSA Technology

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC

Maximizing protection coordination with self-healing technology

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

FACTS-Intelligent Solutions for Meeting Challenges in Power Transmission

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

APPENDIX B-2. TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES. and SMALL GENERATION FACILITIES

SIGUARD System for Phasor Data Processing

Quantum Chargers Enhanced AC Line Transient Immunity

SVC FOR MAINTAINING OF POWER QUALITY IN THE FEEDING GRID IN CONJUNCTION WITH AN ELECTRIC ARC FURNACE IN A STEEL PLANT

Revision 6.0. Transmission Interconnection Guide

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

POWER SYSTEM SECURITY CONCEPTS

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB2 INTRODUCTION TO SLIDER BINARY (*.sld) FILES

ASSET RISK MANAGEMENT Criticality Framework

POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER

Medium Voltage Metal-Enclosed Thyristor-Switched Harmonic Filter Banks

Static var compensator (SVC) applications for improving transmission system performance

Power System Protection Training

Standard Development Timeline

Real Time Monitoring of

Modeling and Simulation in XENDEE

POWER FLOW ANALYSIS AND PROTECTION COORDINATION OF REAL TIME SYSTEM

Transcription:

Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC

Outline Introduction to ATC Benson Lake SVC Project Background Project Technical Specifications Design Phase Studies Other thoughts, pictures, questions 2

Introducing ATC Began in 2001 First multi-state, transmission only utility in U.S. 3

Introducing ATC Headquartered in Pewaukee, Wis. 4

Introducing ATC Assets $550 million in 2001 $4.6 billion today 2001 2017 5

Introducing ATC W E O P E R A T E 9,600+ miles of lines & 554 substations in Wisconsin Minnesota Michigan Illinois Historical Peak load of 13,000+ MW 6

Diverse ownership P R I V A T E L Y H E L D B Y 26 Owners utilities municipalities electric companies electric cooperatives 7

Introducing ATC ATC owns and operates several unique devices 8

May 10, 2011 West & Central UP Blackout Upper Peninsula (UP) of Michigan connections circa 2011 East Connections: Two 138-kV submarine cables across the Straits of Mackinac South-Central Connections: One 345-kV and two 138-kV lines from NE WI South-West Connections: One 138-kV and one 69-kV line from North Central WI Load in the central and west UP in the 500 600 MW range East UP was split from the west and served radially from Lower Michigan Split was used to control system overloads due to high flows across the UP Split no longer used due to addition of the Mackinac HVDC project 9

May 10, 2011 West & Central UP Blackout Planned outage of the 345-kV circuit All outage planning and system operating policies and procedures were followed 93 ka Lightning strike caused fault on double circuit 138-kV lines Autoreclose unsuccessful due to large phase angle Remaining 138-kV & 69-kV ties tripped within ~2.5 sec to form an island Outage scenario exceeded operating policies of the time 10

May 10, 2011 West & Central UP Blackout Shield wire received a direct stroke of 93 ka Poor high impedance grounding causes tower to elevate in voltage Due to difficult area geology, not line construction Results in insulation flash-over and faults the middle phase of both circuits Arresters had been installed on the bottom phase of both lines 11

May 10, 2011 West & Central UP Blackout 12

May 10, 2011 West & Central UP Blackout 13

May 10, 2011 West & Central UP Blackout Event Outcomes Update Power Plant protection settings Update T-line reclosing settings Update Operating Procedures Transmission Projects Needed Address series of events leading to May 10, 2011 outages Retirements of old generation Large iron ore mine load changes 14

Bay Lake Projects New North Appleton to Morgan transmission lines New Holmes to Old Mead Road line and Benson Lake SVC 15

Benson Lake SVC Project Highlights Vendor: ABB Rated for 150 Mvar capacitive and 75 Mvar inductive 175 Mvar TCR 50 Mvar TSC 100 Mvar filters: 3 rd, 5 th, 7 th, and 17 th /HP Rated for continuous operation between 0.90 and 1.1 pu voltage on the 138-kV system Size and location of device determined based on dynamic stability studies Commissioning Dates Cold Commissioning: Started March, 2017 Hot Commissioning: Started April, 2017 and concluded with transmission testing mid-may. Commercial as of June 30/July 3 16

Benson Lake SVC Simplified Single-line Diagram Courtesy of ABB 17

Benson Lake SVC VI Diagram, 100 MVA base Courtesy of ABB 18

Benson Lake SVC Many controls to tune and coordinate Control Highlights Planning POV Auto/Manual: Control of voltage/reactive power Power Oscillation Damping Controller (POD): Damp area low frequency oscillations Undervoltage Control Strategy: Optimize behavior during and after system faults Gain Supervision, Optimizer, & Reset: Optimize control gains for weakened system Slow Reactive Power Control: Help ensure voltage control is spread among devices Negative Phase Sequence Controller: Reduce negative sequence area voltages Ground Fault Locator: Detects and locates faults in TSC. Can allow auto restart. TSC Blocking Symmetrical and Unsymmetrical: Prevents overvoltage after fault clearing 19

Benson Lake SVC - POD 60+ faults simulated across intact and prior outage cases (PSS/E Dynamics) Least Squares analysis performed on frequency signal from simulations PSS/E PSSPLT program; suitable given system characteristics Frequency is used as a local proxy for rotor speed of area machines All faults analyzed which results in a range of dominant modes With known system topology and modal analysis results the system can be simplified to a second order system 20

Benson Lake SVC - POD Rotor swing equations can be used as starting point for POD design Application of a signal (K D ) proportional to change in rotor speed can damp the oscillation Rotor Mechanical Equations 21

Benson Lake SVC - POD Frequency deviation as an input An output is a contribution to the SVC voltage reference K is important to test and tune for optimal performance T1, T2, and T3 can be adjusted as needed POD tuning to strike a balance between frequency damping and voltage response Simplified POD Block Diagram 22

Benson Lake SVC - POD Example of frequency/rotor speed damping for a single minor event Blue is no SVC Green is with SVC and no POD Red is with SVC and POD 23

Benson Lake SVC Gain Supervision, Optimizer, & Reset Potential voltage oscillations in weakened grid Voltage regulator gain can be automatically adjusted Simplified Example of Gain Adjustment Courtesy of ABB 24

Benson Lake SVC Slow Reactive Power Control Steady state voltage control should be shared across devices Desirable to maintain dynamic response of the SVC Off is line A in steady state On is line B in steady state Line C represents dynamic resp SRPC Example Courtesy of ABB 25

Benson Lake SVC System Dynamics No SVC Improved System Dynamics SVC with POD 26

Benson Lake SVC Other Thoughts Important to test the device across a wide range of cases and faults Extreme cases, expected real-time cases, load levels, dispatches, etc. Test and compare across multiple platforms Ex. PSS/E Dynamics, PSCAD, & RTDS Detailed modeling of area loads, motors, etc. is important Verifying against real-world data via post-event analysis, PMU data, etc. Ex. Verification of POD performance with PMU measurements 27

Benson Lake SVC October, 2016 November, 2016 28

Benson Lake SVC December, 2016 January, 2017 29

Benson Lake SVC February, 2017 March, 2017 30

Benson Lake SVC April, 2017 May, 2017 31

Benson Lake SVC TCR Valve TSC Valve 32

Thanks to the following Dave Dickmander Consulting Director ABB Inc., Power Consulting Raleigh, NC Mike Marz Principal Transmission Planning Engineer American Transmission Company Waukesha, WI Martin Wastljung System Studies Market Leads Support ABB Inc, FACTS Västerås, Sweden 33

Questions? 34

atc10yearplan.com atcllc.com atc-projects.com 35