ENMAX Power Corporation

Similar documents
Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ENMAX Generation Portfolio Inc.

MFC Power General Partner Ltd.,

Benbow 397S Substation Upgrade Needs Identification Document

PARTICIPANT INVOLVEMENT PROGRAM

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP)

Ells River Substation Telecommunication Tower

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

Jenner Wind Energy Connection Needs Identification Document

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

Vegreville Office Telecommunication Tower Replacement

ARLINGTON COUNTY, VIRGINIA

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Downtown Boise Multimodal Center

Vancouver Terminal Grain Storage Project. Feedback Form Inside. Community Engagement. October 1 19, 2012 PROJECT OV ERVIE W

Content Copy Of Original

EBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston

NOTICE OF APPLICATION AND WRITTEN HEARING

User Guide. March 2017

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Self-Certification Tutorial. Version 1.0 April 2013

HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION. Presentation to ANC 3E April 13, 2017

Community Update. May 31, 2011

Ministry of Energy, Mines and Petroleum Resources. Guide to Acquiring Crown Petroleum and Natural Gas Tenures

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

Downtown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary

EU DONOR FUNDED SMART GRID PROGRAMME

REVISION HISTORY DATE AMENDMENT DESCRIPTION OF AMENDMENT

ATC Zone 2 Projects Update U.P. Energy Summit

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY

CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA

Stakeholder Engagement Summary Report Vancouver Airport Fuel Delivery Project Fuel Receiving Facility October 13, 2015

Physical Security Reliability Standard Implementation

Community Update. June 8, 2011

Baseline Bridge Crossing. Priorities Committee Meeting

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

Stem Beach Solar 1041 Application

Energy Step Code Implementation Strategy. March 26, 2018

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project

Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018

Commission de l énergie de l Ontario NOTICE OF APPLICATION

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region

ELECTRONIC ASSIGNMENTS PROCEDURES GUIDE. June 2006

Memorandum. This memorandum requires Committee action.

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES

Discussion Guide. Benvoulin Substation Project.

STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION

Critical Cyber Asset Identification Security Management Controls

The Co-operatives Act, 1996 Continuance (Jurisdictional)

CAW Clean Wind Energy Project

Revisions to the Right-of-Way Management Ordinance for Wireless Providers Implementing SB1004

Cereal Hudson. Tariffs. Anthony S. Campagiorni, Esq. Vice President, Regulatory & Governmental Affairs. Requested Revenue Increases

Smart Metering Implementation Programme. Consultation on transitional arrangements in the Smart Energy Code

GC0102 Mod Title: EU Connection Codes GB Implementation Mod 3

Field Testing. *NEW Benefits of Field Testing

Liquidnet Canada Targeted Invitation Functionality Notice of Proposed Changes and Request for Comment LIQUIDNET CANADA

Quest Carbon Capture and Storage Project. Appendix J Public Consultation Activities

TWIN BUTTE ENERGY LTD. Stock Dividend Program FREQUENTLY ASKED QUESTIONS

advantage net working

Malibu Civic Center Stakeholders Meeting. October 25, 2012

ALABAMA FIRE COLLEGE AND PERSONNEL STANDARDS COMMISSION ADMINISTRATIVE CODE CHAPTER 360-X-2 REQUIREMENTS FOR CERTIFIED FIRE FIGHTER TABLE OF CONTENTS

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

City Hall Space Selection 15 Market Square. November 27, 2017

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Application for Variance in a Regional Plan

INVESTING IN SKELTON, SALTBURN & MARSKE

Community Update. June 21, 2011

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor August 13, :30 a.m.

Guidance of NOP Certification system Page 1/8

WebPortal Ticket Entry

ICP. Simplifying. Competition in Connections FOR UNMETERED, METERED AND DISTRIBUTED GENERATION CONNECTIONS

Environmental Monitoring Report. Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project. Semiannual Report January June 2016

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

BC OnLine. Site Registry User s Guide. Last Updated June 11, 2014

File No. SR-NASD-00-70

North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009

SITE DESCRIPTION. Vicinity

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

Project Presentation April, 2017

Stakeholder Engagement Summary Report

bcuc British Columbia Utilities Commission

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

The North American Electric Reliability Corporation ( NERC ) hereby submits

Client Services Procedure Manual

Alberta One-Call Online Request Process

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

Standard CIP Cyber Security Critical Cyber Asset Identification

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS

Overview. Network Fault Restoration v

The Address Point Data Standard for Minnesota Overview and Frequently Asked Questions

Transcription:

Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017

Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application 22769-A001 September 15, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: 403-592-8845 Fax: 403-592-4406 Website: www.auc.ab.ca

Alberta Utilities Commission Calgary, Alberta Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application 22769-A001 1 Decision summary 1. In this decision, the Alberta Utilities Commission must decide whether to approve an application from to replace the underground transmission cables and associated components on the portions of transmission lines 138-1.80L and 138-1.81L that are located underground, and align the new transmission line 138-1.80L cable with the transmission line 138-1.81L cable in a double-circuit duct bank in downtown Calgary (the proposed project). After consideration of the record of the proceeding, and for the reasons outlined in this decision, the Commission finds that approval of the proposed project is in the public interest, having regard to the social, economic and other effects of the proposed project, including its effects on the environment. 2 Introduction and background 2. (ENMAX), pursuant to Permit and Licence 20072-D02-2015, 1 is the operator of the 138-kilovolt (kv) transmission line 138-1.80L from the ENMAX No. 28 Substation to the ENMAX No. 1 Substation in the city of Calgary. ENMAX, pursuant to Permit and Licence EN98-34, 2 is the operator of the 138-kV transmission line 138-1.81L from the ENMAX No. 1 Substation to the ENMAX No. 20 Substation in the city of Calgary. 3. ENMAX filed an application with the AUC for approval for the proposed project, pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act. The application was registered as Application 22769-A001 on June 28, 2017. 4. The Commission issued information requests on July 13, 2017, and ENMAX responded to those requests on July 17, 2017. 5. On July 13, 2017, the Commission issued a notice of application, with a deadline of August 3, 2017, for persons to file a submission regarding their objections, concerns, or support in relation to the application. The notice was sent directly to all landowners, occupants and residents within the first row of buildings adjacent to the proposed project site. The notice was also published on the AUC website and notification was automatically emailed to efiling System users who had chosen to be notified of notices of application issued by the Commission. The Commission issued two additional notices in response to updated stakeholder and address lists 1 2 Transmission Line Permit and Licence 20072-D02-2015, Proceeding 20072, Application 20072-A001, October 27, 2015. Transmission Line Permit and Licence EN98-34, Application 970516, January 5, 1998. Decision 22769-D01-2017 (September 15, 2017) 1

Transmission Lines 138-1.80L and 138-1.81L provided by ENMAX, on July 17, 2017 and then on August 11, 2017. The deadline for submissions was amended to August 25, 2017. 6. On August 1, 2017, the Commission received a statement of intent to participate from Metro Ford Sales Ltd. (Metro Ford). Metro Ford indicated that entrances to its business were situated in the middle of the proposed project. Metro Ford indicated that any disruptions to the entrances would have a serious effect on its business, customers, and employees, and asked to be included in the construction planning. ENMAX filed a response to Metro Ford s submission and indicated that ENMAX was fully committed to communicating the construction plan and collaborating directly with Metro Ford. Metro Ford subsequently filed a letter stating that it was satisfied with ENMAX s response to its concerns. 3 Discussion 7. The underground cables for transmission lines 138-1.80L and 138-1.81L are located between ENMAX No. 1 Substation at 738 9th Avenue S.W. and the overhead structure west of 14th Street on 9th Avenue S.W., south of the Greyhound bus terminal. ENMAX stated that the underground cables for transmission lines 138-1.80L and 138-1.81L are 41 and 40 years old, respectively, and that each cable had reached its life expectancy. ENMAX conducted maintenance tests on the transmission cables for transmission lines 138-1.80L and 138-1.81L and found that both cables have deteriorated. Specifically, the cable sheath jackets are in poor condition, leaving the aluminum sheath susceptible to corrosion. As such, ENMAX proposed to salvage nine kilometres of the old transmission cables, which were oil-filled, and install nine kilometres of new cross-linked polyethylene cables. 8. ENMAX stated that the transmission line 138-1.80L cable was installed within a City of Calgary bridge, the 8th Street Bridge, and that the cable had a sheath fault that would be difficult to repair if it remained within the bridge. As such, ENMAX proposed to align the new transmission line 138-1.80L cable with the new transmission line 138-1.81L cable, along 8th Avenue S.W., and remove the existing transmission line 138-1.80L cable along 9th Avenue S.W. In order to accommodate the transmission line 138-1.80L cable within the existing transmission line 138-1.81L cable alignment, ENMAX proposed to install 1.5 kilometres of double-circuit concrete-encased duct bank. 9. Transmission line 138-1.80L is located between 4941 50th Street, S.W., in the southwest quarter of Section 1, Township 24, Range 2, west of the Fifth Meridian, and 738 9th Avenue, S.W., in the northeast quarter of Section 16, Township 24, Range 1, west of the Fifth Meridian. Transmission line 138-1.81L is located between 738 9th Avenue, S.W., in the northeast quarter of Section 16, Township 24, Range 1, west of the Fifth Meridian, and 2508 Bowness Road, N.W., in the northeast quarter of Section 18, Township 24, Range 1, west of the Fifth Meridian. 10. ENMAX conducted a participant involvement program to inform all potentially affected landowners, occupants, and residents of the proposed project. On May 9, 2017, ENMAX distributed information packages to 245 landowners, occupants and residents located within the first row of buildings adjacent to the proposed project site. ENMAX also engaged in personal one-on-one visits for occupants, residents and landowners adjacent to the proposed project from May 12, 2017 to June 1, 2017. Between May 9, 2017 and May 11, 2017, ENMAX contacted 2 Decision 22769-D01-2017 (September 15, 2017)

Transmission Lines 138-1.80L and 138-1.81L eight stakeholders through email. ENMAX indicated that eight stakeholders raised concerns during the engagement process, all of which regarded construction effects and access. To mitigate the concerns, ENMAX stated it would communicate the construction plan and schedules with stakeholders so that stakeholders would be aware of any disruptions. 11. ENMAX indicated that it did not anticipate any adverse environmental effects as a result of the proposed project. ENMAX stated that both existing underground cables for transmission lines 138-1.80L and 138-1.81L would be removed by open excavation, tested for polychlorinated biphenyl content and disposed of according to applicable federal and provincial regulations. Furthermore, a soil handling plan would be developed to ensure the proper disposal and handling of all soils encountered and would address areas where historic land use near the proposed project area indicated potential for contamination. 12. ENMAX stated that the proposed project would have no effect on existing noise levels and would comply with Rule 012: Noise Control. Any noise from the proposed project would be intermittent and would comply with the City of Calgary noise bylaws. 13. ENMAX indicated that the project cost would be part of its Transmission Capital Maintenance program and estimated it to be approximately $27 million (within +10 to +30 per cent/-10 to -20 per cent accuracy). Construction for the proposed project is expected to take six months to complete and has a proposed in-service date of November 30, 2018. 4 Findings 14. The Commission is satisfied that ENMAX s application complies with the information requirements prescribed in Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments. The Commission accepts ENMAX s submission that the proposed project is necessary to replace aging underground transmission cables, and notes that the proposed project is a part of its Transmission Capital Maintenance program. 15. The Commission is satisfied that the participant involvement program undertaken by ENMAX meets the requirements of Rule 007. The Commission notes that ENMAX has committed to sharing its construction plan and schedules with stakeholders that have expressed concerns with construction impacts. The Commission notes that there are no outstanding public or industry concerns from directly and adversely affected persons on the record of this proceeding, and expects ENMAX to carry forward its commitment to collaborate with stakeholders in order to mitigate any potential concerns or effects to stakeholders during the construction phase of the project. 16. The Commission finds that the proposed project will result in minimal environmental effects through the testing of old underground transmission cables for polychlorinated biphenyl content and the development of a soil handling plan. The Commission also accepts ENMAX s confirmation that the proposed project will have no effect on existing noise levels and will comply with both the Commission s Rule 012: Noise Control and applicable City of Calgary bylaws. Decision 22769-D01-2017 (September 15, 2017) 3

Transmission Lines 138-1.80L and 138-1.81L 17. Based on the foregoing, the Commission considers the application to be in the public interest in accordance with Section 17 of the Alberta Utilities Commission Act. 5 Decision 18. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission approves Application 22769-A001. An amendment to the permit and licence for transmission line 138-1.81L is not required because there is no change to the existing transmission line alignment. The underground cables for transmission line 138-1.80L currently run along 9th Avenue S.W. and will be realigned with transmission line 138-1.81L along 8th Avenue S.W. The existing map in Permit and Licence 20072-D02-2015 for transmission line 138-1.80L incorrectly shows the transmission line along 8th Avenue S.W. Accordingly, an amendment to the permit and licence for transmission line 138-1.80L is also not required as the current map on the permit and licence will show the correct alignment after the completion of the project. Dated on September 15, 2017. Alberta Utilities Commission (original signed by) Henry van Egteren Commission Member 4 Decision 22769-D01-2017 (September 15, 2017)