SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

Similar documents
Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Joint Transmission Planning Base Case Preparation Process

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models

Proposed Improvements for NERC MOD Standards July 10, 2012

PRC Coordination of Protection Systems for Performance During Faults

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

ISO New England Data Modeling Requirements

Standard Development Timeline

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

Reliability Coordinator Procedure

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

Reliability Standard Audit Worksheet 1

National Load Despatch Centre Power System Operation Corporation

Procedure For NPCC Bulk Electric System Asset Database

BESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2

Interconnection Application

New Brunswick 2018 Annual Implementation Plan Version 1

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

REAL-TIME MONITORING DATA SPECIFICATION

STCP22-1 Issue 003 Production of Models for GB System Planning

Reliability Standard Audit Worksheet 1

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Standard CIP Cyber Security Critical Cyber As s et Identification

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

Standard CIP Cyber Security Critical Cyber As s et Identification

Transmission Register PTO Admin User Manual. Version 1.0

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Feasibility Study on Load Flow and Short Circuit Project

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

Generation, Transmission, and End User Facilities

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019

Power System Studies. The Power of Trust. The Future of Energy.

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

Studies Overview and Data Requirements. Robert Pan

Standard Development Timeline

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Standard CIP Cyber Security Security Management Controls

Dynamic Load Models in PowerWorld Simulator

Standard Development Timeline

Project Data Update Package Instruction Manual (PDUP-IM)

Supplemental Information

Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool. Eleanor Ewry

Project Consideration of Commission Directives in Order No. 693

Table of Contents. TOP TOP BA Data Request and Specification Guidelines. Operating Procedure

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

DRAFT Reliability Standard Audit Worksheet 1

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015

Section 10 of BPM for TPP- Generator modeling webinar

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1

Unofficial Comment Form Project Disturbance Monitoring

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

NERC Overview and Compliance Update

Standards. Howard Gugel, Director of Standards Board of Trustees Meeting May 5, 2016

Bulk Electric System Definition Changes and Reporting

Instructions. Interconnection Customer declares its intention to interconnect with the AEP Distribution System.

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

WECC and Base Case Development Process D E C E M B E R 1 2, J O N AT H A N Y O U N G

Standards Authorization Request Form

Open Access Transmission Tariff of Southern Companies

BPA and NERC, WECC, ERO

Transmission Distribution Microgrid - DER

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

Standards Authorization Request Form

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

TransWest Express Transmission Project Interregional Transmission Project Submittal

Interconnection and Transmission

2014 Annual Compliance Assessment

INTERCONNECTION FACILITIES STUDY REPORT

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

Standard INT Interchange Authority Distributes Arranged Interchange

Draft CIP Standards Version 5

CIP V5 Implementation Study SMUD s Experience

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

RELIABILITY OF THE BULK POWER SYSTEM

STCP 04-3 Issue 005 Real Time Data Provision

Transcription:

SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1

TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1: Generic MOD-032 Modeling Process Overview... 3 1.4 Responsible Entities... 4 1.5 Data Submittal Delegation Options... 4 DATA SUBMISSION REQUIREMENT... 5 2.1 Load Serving Entity...5 Table 2-1: Typical data to be submitted by the LSE... 5 2.2 Generator Owner...5 Table 2-2: Typical data to be submitted by the GO... 5 2.3 Transmission Owner...6 Table 2-3: Typical data to be submitted by the TO... 6 POWERFLOW MODEL DEVELOPMENT... 7 3.1 Data Format...7 3.2 Level of Detail...7 3.3 Case Types / Scenarios...7 3.4 Schedules for Data Submission...8 3.5 Distribution or Data Posting Requirements...8 3.6 MOD-032-1 Requirements and Effective Dates...8 3.7 Demand Forecast and Load Allocation...9 3.8 Steady-State, Dynamic, and Short Circuit Model Development...9 MOD-032-1 ATTACHMENT 1... 10 REVISION HISTORY... 13 1

INTRODUCTION 1.1 Purpose North American Electric Reliability Corporation s (NERC) Reliability Standard MOD-032-1 pertains to system-level modeling and validation to establish consistent modeling data requirements and reporting procedures for development of planning horizon cases necessary to support analysis of the reliability of the interconnected transmission system. Reliability Standard MOD-032-1 is a consolidation and replacement of existing MOD- 010-0, MOD-011-0, MOD-012-0, MOD-013-1, MOD-014-0, and MOD-015-0.1, and it requires data submission by applicable data owners to their respective Transmission Planners and Planning Coordinators to support the Interconnection-wide case building process in their Interconnection. This procedure provides guidance for SMUD, as a registered Planning Coordinator, with respect to data for power system modeling and analysis. The Western Electricity Coordinating Council (WECC) is SMUD s designated Electric Reliability Organization (ERO) and develops a series of power flow and dynamics simulation models which are then used by SMUD and other WECC members for performing reliability/powerflow and economic planning studies. These studies are needed to fulfill various NERC standards and WECC compliance requirements. The purpose of this document is to outline these data reporting procedures needed to support the development of steady state powerflow and dynamics simulation base case models. These models are required to realistically simulate steady state and dynamic behavior of the transmission system while being compliant with MOD-032-1. Currently, Pacific Gas and Electric (PG&E) is the Area Coordinator, and is the entity currently responsible for collecting and submitting SMUD s data to WECC. The Area Coordinator function will soon be replaced by the Planning Coordinator (PC) function per MOD 032-1. WECC had been developing a new system with Siemens called Model on Demand (MOD) software as part of WECC s Base Case Coordination System (BCCS). The BCCS website and MOD software did not work right and were full of software bugs. The Technical Studies Subcommittee and Planning Coordination Committee recommended terminating the software development. As such, SMUD will continue to submit base case modeling data to the Area Coordinator (PG&E) as part of the base case development process. SMUD is the NERC registered Planning Coordinator for SMUD s transmission footprint. Currently, SMUD submits modeling data to PG&E per requirements of the WECC Data Preparation Manual (DPM). The DPM was developed and is maintained by the System Review Working Group (SRWG) and provides guidance and procedures for submitting data for building powerflow basecases. Similarly, SMUD has established a set of common procedures for submitting data needed for developing planning models as described in this document. The procedures have been established pursuant to requirement R1 of MOD-032-1 and also intend to parallel and compliment requirements in the WECC DPM. 2

The Modeling Data Requirements & Reporting Procedures (MDRRP) manual is posted on the SMUD Oasis website at the following location (http://www.oasis.oati.com/smd1) per requirement R 1.3 of MOD-032-1. 1.2 Audience The procedure is written by Transmission Planners (TP) for existing and future TPs, Planning Coordinators (PC), Generator Owners (GO), Load Serving Entities (LSE), Transmission Owners (TO), Resource Planners (RP), Transmission Service Providers (TSP), and Balancing Authorities (BA), for whom SMUD is the Planning Coordinator. 1.3 Process Overview Figure 1-1 provides a high-level overview of the data modeling process. SMUD Data Owners (Internal SMUD Departments) SMUD WECC Coordinate data collection process (R1) Send data requests to data owners annually or as necessary for special projects Review data requests Provide new and updated data (R2) Respond to technical concerns from PC or TP (R3) Incorporate data into models and update GE-PSLF base cases Send models to WECC via Data Representitive (R4). This refers to the existing process with SMUD's Area Coordinator (PG&E). Create Western Interconnection models. SMUD reviews the models as part of the SRWG process and provides updates as necessary Figure 1-1: Generic MOD-032 Modeling Process Overview 3

1.4 Responsible Entities As per requirements in MOD-032-1 R2, data owners are responsible for providing the data necessary to model their assets to its TPs and PCs as described in this document. TPs may notify data owners that they do not want the data and that it should only be sent to the planning coordinators. Data owners and their respective data submission responsibilities are listed below. o TOs are responsible for providing data for modeling existing and approved future transmission facilities o LSEs are responsible for providing load related data such as load allocation for load models in power flow scenarios o GOs are responsible for submitting modeling data for existing and future generation facilities with a signed interconnection agreement o RPs are responsible for providing loads and resources data such demand forecasts o TPSs and BAs currently do not own any facilities and thus do not have any data submittal requirements 1.5 Data Submittal Delegation Options Load Serving Entities, Generator Owners LSEs and GOs will coordinate with their interconnected TO and provide data and ensure their data is consistent with TO submitted topology. The LSE or GO may request assistance or delegate load modeling responsibilities to the TO or PC. Unregistered Entities TOs should submit best known data for unregistered entities in their footprint. This will allow for higher quality modeling and could improve the accuracy of powerflow studies. 4

DATA SUBMISSION REQUIREMENT MOD-032-1 Attachment 1 lists the modeling data to be submitted and is summarized below. The attachment is also provided at the end of this document. 2.1 Load Serving Entity The LSE shall provide the load forecast for varying scenarios being modeled. The LSE must use the bus numbers assigned to them by the Planning Coordinator. SMUD s Distribution Planning department provides annual updates for load distribution to the Transmission Planning department (known as Grid Planning department at SMUD). The load allocation factors are then used by the transmission planning department to model load in the SMUD distribution system. Table 2-1 provides a summary of data required. Table 2-1: Typical data to be submitted by the LSE Steady-State Dynamics Short Circuit Real and reactive power demands on the load buses Load composition N/A In-service status Protection relays N/A Location of new expected loads N/A N/A 2.2 Generator Owner The GO shall provide the data necessary to model their generator facilities. The GO shall use bus numbers assigned to them by the Planning Coordinator. Data for existing and planned generators with interconnection agreements should be submitted. Generator test data shall be provided to the Planning Coordinator (SMUD) so that base case models can be updated accordingly. SMUD s Power Generation department should provide updates to generation data as necessary, and provide generator testing data when available. Table 2-2 provides a summary of data to be submitted by the GO. Table 2-2: Typical data to be submitted by the GO Steady-State Dynamics Short Circuit Generator Generator For applicable steady-state items: Generator step-up (GSU) transformer data Excitation system Positive sequence data Station service load Turbine / Governor Zero sequence data Seasonal output capabilities Power system stabilizer Negative sequence data Reactive shunt devices Protection relays N/A 5

In-service status N/A N/A PV/Wind system N/A N/A 2.3 Transmission Owner The TO shall provide the data necessary to model their transmission facilities. The TO shall use transmission line IDs and bus numbers assigned to them by the Planning Coordinator. Data for existing and planned transmission lines should be submitted. Line rating changes shall be provided to the Planning Coordinators so that base case models can be updated accordingly. Table 2-3 provides a summary of data to be submitted by the TO. Table 2-3: Typical data to be submitted by the TO Steady-State Dynamics Short Circuit System topology Protection relays For applicable steady-state items: Buses N/A Positive sequence data AC transmission lines N/A Zero sequence data HVDC transmission lines N/A Negative sequence data Transformers N/A Mutual line impedance data Reactive shunt devices N/A N/A 6

POWERFLOW MODEL DEVELOPMENT 3.1 Data Format The powerflow modeling data is to be submitted to SMUD via email with data. Models are developed using General Electric s Positive Sequence Load Flow (GE-PSLF) software application and need to adhere to WECC s DPM in order to be implemented in GE-PSLF powerflow base cases. Data submitted should be compatible with GE-PSLF versions currently specified by WECC. Modeling data requests and notifications from WECC are sent to the Planning Coordinator and the PC will determine if updates or more data is required from the data submitters. 3.2 Level of Detail SMUD maintains models with the following level of detail for base cases: o Generators are modeled down to the low-side of the generator step up transformer with the exception of aggregated PV power plants such as SMUD s Feed-In-Tariff solar power plants. These plants are currently modeled at the load bus. o Loads are modeled as lump sum on the transmission buses at the 69 kv level or are modeled down to lower voltage levels as necessary. One example of this is the downtown Sacramento network where load is modeled down to 12kV level. Station service load is aggregated and modeled at the generator buses. o All other equipment at 69kV level and above is modeled. This includes transmission lines, transformers, shunt capacitors, shunt reactors, as well as other equipment surpassing the 69 kv threshold. o SMUD s models are to be modeled in WECC DPM defined Area 30 and in Zone 322. DPM Defined SMUD owner number is 363. 3.3 Case Types / Scenarios SMUD builds models to represent the powerflow conditions specified by WECC. WECC uses a document prepared by the SRWG called the Base Case Compilation Schedule. Typically, WECC builds several near term (year 0 to 5) and long term cases (year 5-10). These cases represent typical scenarios such as heavy or light load conditions during summer, winter, and spring. WECC also builds special cases as necessary and these cases can have their own specific set of requirements. o Summer Peak Load (HS) is defined as heavy summer peak load expected to be served per the WECC Base Case Compilation Schedule o Summer Light Load (LS) is defined as light summer load expected to be served per the WECC Base Case Compilation Schedule o Winter Peak Load (HW) is defined as heavy winter peak load expected to be served per the WECC Base Case Compilation Schedule o Winter Light Load (LW) is defined as light winter load expected to be served per the WECC Base Case Compilation Schedule o Spring Peak Load (HSP) is defined as heavy spring peak load expected to be served per the WECC Base Case Compilation Schedule 7

o Spring Light Load (LSP) is defined as light spring peak load expected to be served per the WECC Base Case Compilation Schedule 3.4 Schedules for Data Submission SMUD s data submittal schedules and timelines are determined on a yearly basis by WECC as part of the Base Case Compilation Schedule. This document can sometimes be modified during SRWG meetings to accommodate pressing needs and is subject to change. WECC posts the Base Case Compilation on their website. A link to the 2016 Base Case Compilation Schedule is pasted below: https://www.wecc.biz/reliability/2016-base-case-compilation-schedule- PCC%20Approved.pdf A link to the 2015 schedule is pasted below: https://www.wecc.biz/reliability/2015_base_case_compilation_schedule-v4.doc 3.5 Distribution or Data Posting Requirements The Modeling Data Requirements & Reporting Procedures (MDRRP) manual is posted on the SMUD Oasis website at the following location (http://www.oasis.oati.com/smd1 ). This document will also be emailed to contacts (SMUD Internal Departments) at BAs, TOs, GOs, LSEs, and TSPs within the SMUD footprint. 3.6 MOD-032-1 Requirements and Effective Dates There are 4 requirements for MOD-032-1. The first requirement (R1) is effective on 07/01/2015. R2, R3, and R4 become effective on 07/01/2016. o R1 requires each PC and TP to jointly develop steady-state, dynamics, and short circuit modeling data requirements and reporting procedures for the PC s planning area. This is the basis for developing the MDRRP. o R2 requires each BA, GO, LSE, RP, TO, and TSP to provide steady-state, dynamics, and short circuit modeling data to their TP(s) and/or PC(s) according to the modeling data requirements and reporting procedures developed by their TP(s) and/or PC(s). o R3 deals with data quality and requires each BA, GO, LSE, RP, TO, and TSP to either provide updated data or a technical explanation for maintain current data within 90 days of receipt of written notification from its PC and/or TP. o R4 requires each PC to provide models for its planning area reflecting data provided to it under R4 to the ERO to support creation of Interconnection-wide case(s) that includes the PC s planning area. 8

3.7 Demand Forecast and Load Allocation SMUD s Resource Planning department provides a yearly demand forecast. Demand data from this report is used to build current year and future year cases. The demand data is then broken down into lump sum load components. Information for this is provided in the load allocation spreadsheet created by SMUD s Distribution Planning department. The load allocation data is also provided annually. 3.8 Steady-State, Dynamic, and Short Circuit Model Development SMUD develops these models as per the WECC DPM. The steady state models represent the normal operation of the power system and are time independent. The dynamic models are time dependent and are used for transient stability studies. Typical transient stability simulations are in the timeframe of 0 to 20 seconds. Short circuit data is required for generators, transformers, and transmission line. Short circuit data is provided by SMUD s SPAC department. 9

MOD-032-1 ATTACHMENT 1 Data Reporting Requirements The table, below, indicates the information that is required to effectively model the interconnected transmission system for the Near-Term Transmission Planning Horizon and Long-Term Transmission Planning Horizon. Data must be shareable on an interconnectionwide basis to support use in the Interconnection-wide cases. A Planning Coordinator may specify additional information that includes specific information required for each item in the table below. Each functional entity1 responsible for reporting the respective data in the table is identified by brackets [functional entity] adjacent to and following each data item. The data reported shall be as identified by the bus number, name, and/or identifier that is assigned in conjunction with the PC, TO, or TP. steady-state (Items marked with an asterisk indicate data that vary with system operating state or conditions. Those items may have different data provided for different modeling scenarios) 1. Each bus [TO] a. nominal voltage b. area, zone and owner 2. Aggregate Demand 1 [LSE] a. real and reactive power* b. in-service status* 3. Generating Units 2 [GO, RP (for future planned resources only)] a. real power capabilities - gross maximum and minimum values b. reactive power capabilities - maximum and minimum values at real power capabilities in 3a above c. station service auxiliary load dynamics (If a user-written model(s) is submitted in place of a generic or library model, it must include the characteristics of the model, including block diagrams, values and names for all model parameters, and a list of all state variables) 1. Generator [GO, RP (for future planned resources only)] 2. Excitation System [GO, RP(for future planned resources only)] 3. Governor [GO, RP(for future planned resources only)] 4. Power System Stabilizer [GO, RP(for future planned resources only)] 5. Demand [LSE] 6. Wind Turbine Data [GO] 7. Photovoltaic systems [GO] 8. Static Var Systems and FACTS [GO, TO, LSE] 9. DC system models [TO] 10. Other information requested by short circuit 1. Provide for all applicable elements in column steadystate [GO, RP, TO] a. Positive Sequence Data b. Negative Sequence Data c. Zero Sequence Data 2. Mutual Line Impedance Data [TO] 3. Other information requested by the Planning Coordinator or Transmission Planner necessary for modeling purposes. [BA, GO, LSE, TO, TSP] 1 For purposes of this attachment, the functional entity references are represented by abbreviations as follows: Balancing Authority (BA), Generator Owner (GO), Load Serving Entity (LSE), Planning Coordinator (PC), Resource Planner (RP), Transmission Owner (TO), Transmission Planner (TP), and Transmission Service Provider (TSP). 2 For purposes of this item, aggregate Demand is the Demand aggregated at each bus under item 1 that is identified by a Transmission Owner as a load serving bus. An LSE is responsible for providing this information, generally through coordination with the Transmission Owner. 3 Including synchronous condensers and pumped storage. 10

for normal plant configuration (provide data in the same manner as that required for aggregate Demand under item 2, above). d. regulated bus* and voltage set point* (as typically provided by the TOP) e. machine MVA base f. generator step up transformer data (provide same data as that required for transformer under item 6, below) g. generator type (hydro, wind, fossil, solar, nuclear, etc.) h. in-service status* 4. AC Transmission Line or Circuit [TO] a. impedance parameters (positive sequence) b. susceptance (line charging) c. ratings (normal and emergency)* d. in-service status* 5. DC Transmission systems [TO] 6. Transformer (voltage and phase-shifting) [TO] a. nominal voltages of windings b. impedance(s) c. tap ratios (voltage or phase angle)* d. minimum and maximum tap position limits e. number of tap positions (for both the ULTC and NLTC) f. regulated bus (for voltage regulating transformers)* g. ratings (normal and emergency)* h. in-service status* 7. Reactive compensation (shunt capacitors and reactors) [TO] a. admittances (MVars) of each capacitor and reactor b. regulated voltage band limits* (if mode of operation not fixed) c. mode of operation (fixed, discrete, continuous, etc.) d. regulated bus* (if mode of operation not fixed) e. in-service status* 8. Static Var Systems [TO] a. reactive limits b. voltage set point* c. fixed/switched shunt, if applicable d. in-service status* 9. Other information requested by the Planning Coordinator or Transmission Planner necessary for modeling purposes. [BA, GO, LSE, TO, TSP] 11

the Planning Coordinator or Transmission Planner necessary for modeling purposes. [BA, GO, LSE, TO, TSP] 12

REVISION HISTORY Version Date By Summary of Changes 1.2 11/10/2015 Prabal Singh Modified document to reflect the cessation of using MOD software for the BCCS process. SRWG confirmed this recommendation from the TSS and PCC during the SRWG meeting from 11/4/15 11/5/15. 1.1 07/10/2015 Prabal Singh Revisions and Clarifications 1.0 06/30/2015 Prabal Singh Initial Development 13