INTERCONNECTION FACILITIES STUDY REPORT

Similar documents
TSR A & B - FACILITIES STUDY REPORT

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Q44 Generation Interconnection

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Generation Interconnection Feasibility Study Report

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

Small Generator Interconnection System Impact Study Report. Completed For Q0047

PG&E Transmission Interconnection Handbook

Interconnection and Transmission

PacifiCorp Transmission Technical Workshop

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Feasibility Study on Load Flow and Short Circuit Project

Generation Interconnection Feasibility Study Report

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

OC IEEE IAS/PES Meeting February 21, 2013

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

INTERCONNECTION FACILITIES STUDY REPORT

Intelligent Grid and Lessons Learned. April 26, 2011 SWEDE Conference

RFP Attachment 13. January 2010

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

Power System Network Simulator (PSNsim)

Facilities Study for XXXXXXXXXXXX 50 MW PV

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

Supplemental Information

Southern Company Smart Grid

Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

DECK All-In-One Enclosure. Quick Installation Guide for Field Installers

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

Checklist for Submission to Utility

Chapter 2 State Estimation and Visualization

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

Advanced Protection and Control Technologies for T&D Grid Modernization

Presented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011

Design of Coal Mine Power Supply Monitoring System

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM

1. Project Description

Grid Interconnection of Renewable Generation

Public Service Company of New Mexico

Network Configuration Document Selection for New Substations Framework

Bulletin Installation of solar photovoltaic systems Rules , , , , and

USE CASE 14 CONTROLLED ISLANDING

November 29, ECE 421 Session 28. Utility SCADA and Automation. Presented by: Chris Dyer

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

Designing a new IEC substation architecture

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)

October 05, ECE 421 Session 12. Utility SCADA and Automation. Presented by: Chris Dyer

Real-time Power System Operation. Energy Management Systems. Introduction

Interconnection Application

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY

Blackstart Hardware-in-the-loop Relay Testing Platform

XXXXX XXXX Wind Generation Project

March 4, Mona Substation Line position & assoc relaying, communications & metering

Flexible High-Speed Load Shedding Using a Crosspoint Switch

Electric Utility Facility Connection Requirements

MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES

Studies Overview and Data Requirements. Robert Pan

How To Help Electronic Equipment Survive The Storm

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WN U-60 Original Sheet No. 152

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

ELECTRICAL, INSTRUMENTATION & CONTROL SYSTEMS

REAL-TIME MONITORING DATA SPECIFICATION

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

ICX-CMOS-E-2006 Electrical / I&C Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field

Title Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP)

SWITCHYARD SYSTEM BC1-SS-11-SD TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1

JEA. Facility Connection Requirements

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

Document C0. Use for:

Substation SCADA Monitoring

Distributed Generation Requirements Update

LCRA Transmission Services Corporation. Facility Connection Requirements

Line reactors SINAMICS. SINAMICS G120P Line reactors. Safety information 1. General. Mechanical installation 3. Electrical installation 4

This webinar brought to you by the Relion product family

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

Smart Distribution Technology

Local Area Studies Update - PACW Kevin Putnam

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

System Studies for American Transmission Co. s Benson Lake SVC Project

DRAFT. Application Note: Modbus/RS485 Wiring for Conext Core XC Series Inverters. 1.0 Introduction DANGER. 1.1 Related Documents

Stem Beach Solar 1041 Application

Transcription:

Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7

DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES THIS DOCUMENT WAS PREPARED FOR TRI-STATE GENERATION AND TRANSMISSION ASSOCIATION, INC. (TSGT) IN RESPONSE TO A TRANSMISSION SYSTEM INTERCONNECTION REQUEST. NEITHER TSGT, NOR ANY PERSON ACTING ON BEHALF OF TSGT: (A) MAKES ANY REPRESENTATION OR WARRANTY EXPRESS OR IMPLIED, WITH RESPECT TO THE USE OF ANY INFORMATION, METHOD, PROCESS, CONCLUSION, OR RESULT DISCLOSED IN THIS DOCUMENT, INCLUDING FITNESS FOR A PARTICULAR PURPOSE; OR (B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER, INCLUDING ANY CONSEQUENTIAL DAMAGES, RESULTING FROM USE OF THIS DOCUMENT OR ANY INFORMATION CONTAINED THEREIN. 2 of 7

CONTENTS 1. INTRODUCTION 1.1. Objective 1.2. Background 1.3. Scope 2. INTERCONNECTION OF BISON SUBSTATION 2.1. General Discussion 2.2. Bison Substation Description 2.3. Springer Substation Work Description 3. GENERATING FACILITY PERFORMANCE VERIFICATION 4. SCHEDULE 5. REFERENCES 6. LIST OF ATTACHMENTS 3 of 7

1. INTRODUCTION 1.1 Objective This report presents the Interconnection Facilities Study results for interconnection of a proposed 30 MW solar generating facility (the Project) to Tri-State Generation and Transmission Association s (Tri-State) 115kV transmission system in north central New Mexico. 1.2 Background The Project has selected a Point of Interconnection (POI) approximately five miles from Springer Substation on the Springer-York Canyon 115kV Transmission Line, where a new Tri- State interconnection substation called Bison Substation will be constructed. Bison Substation will be a simple 115kV tap substation with a single 115kV breaker installed for line protection. Additional equipment will be installed to accommodate a future ring-bus expansion without the need to take line or bus outages. The Bison Substation property is expected to be directly adjacent to Tri-State s existing transmission line. The Interconnection Customer s substation is expected to lie directly east of Bison Substation with connection to the solar farm substation by a tubular bus extension between the two substations. A Final System Impact Study (SIS) report for this project dated November 19, 2009 has been issued and posted on Tri-State s OASIS web site. The study was conducted in accordance with Tri-State s Large Generator Interconnection Procedures (LGIP) and entails steady state power flow, dynamic stability, short circuit analysis and preliminary cost and schedule estimates for interconnection of the Project as a Network Resource. A conclusion of the SIS report is that the project may be added without Network Upgrades other than the construction of Bison Substation and associated telecommunication additions and modifications. 1.3 Scope This Interconnection Facilities Study Report includes details of the configuration for the construction of the new Tri-State Bison 115kV Substation and associated Network Upgrades. Documents to summarize the construction work required include: electrical one-line diagram, general arrangement drawing, major material lists with cost estimates (± 20% accuracy), and project schedule. Because the Project will be connected to a radial line with multiple loads on the end of the line no outages of the line will be permitted for the proposed construction. Therefore the proposed design will facilitate tapping the line while hot. 2. INTERCONNECTION OF BISON SUBSTATION 2.1 General Discussion Full line sectionalizing will not be required for connection to the radial transmission system. The simple tap breaker configuration will allow isolation of the Bison facility by using the motoroperated switches but not without an interruption to the Bison interconnection. The proposed installation includes high-side bi-directional metering, high-side protection, SCADA system and telecommunications. Communications to Bison Substation will be by digital microwave with one hop to Springer Substation where new terminal equipment will be installed. A component of 4 of 7

the protection design includes a transfer-trip scheme to disconnect the generating facility upon any opening of the Springer Substation 115kV line breaker on the Springer-York Canyon 115kV line. This scheme has been added to address an unacceptable islanding condition that occurs when the Springer 115kV breakers trips. Primary protection (relaying and the interrupting device) for the IC s step-up transformer will be provided by the IC in their substation yard. Equipment in the Bison Substation can be available to provide backup protection for the transformer protection in the event of equipment failure or malfunction in the IC s facility. To facilitate protective relaying, backup power and data acquisition, conduit will be installed between Bison and the IC Substations to contain as a minimum: CT circuits; fiber optic cables for data communication (and breaker failure relaying if requested); circuits for differential tripping; and backup station power. 2.2 Bison Substation Description The layout of the proposed substation is depicted on the attached One-Line Diagram and General Arrangement. The physical layout will provide for a future expansion of the bus arrangement into a possible four-breaker ring bus. 2.2.1 Work to be completed and paid for by the Interconnection Customer Engineer, purchase, construct and own equipment associated with the generating plant and all Interconnection Facilities up to the Point of Ownership Change (POC), as indicated on the attached one-line diagram. Install an interrupting device, associated switch and relaying for transformer protection. Land costs, access roads and any costs associated with obtaining state or local permits for the Project. Backup 120/240V, 25kVA single phase station service for the Transmission Provider s facilities. Provide access to analog, indicating, control and data circuits, as required to integrate into the design and operation of the Tri-State control system. Coordinate with Tri-State to intertie substation ground grids (if applicable), substation fencing, duct bank/conduit between the substations, substation grading plans and the 115kV intertie. 2.2.2 Network Upgrade work at Bison Substation and communication/relay work at Springer Substation to be completed by the Transmission Provider and initially paid for by Interconnection Customer (with cost being refundable per the LGIP) Engineer, purchase, construct, own and operate all Interconnection Facilities and Network Upgrades starting from the Point of Ownership Change (POC). Install two 115kV in-line motor operated disconnect switches (one with load-break capabilities). Install one 115kV circuit breaker Install two 115kV breaker isolation switches. Install one 115kV power potential transformer for primary station service and sync check. 5 of 7

Perform hot line work necessary to connect Bison substation to Tri-State s 115kV transmission line. Install power control assembly with space for switch controls, line and bus differential relaying, battery and DC system, AC system, telecommunications gear, and SCADA equipment. The control system designed for this station will also include the transfer-trip requirement indentified in the SIS for a trip by the Springer breakers serving the Springer-York Canyon line. The estimated cost of this construction is $2,265,000; a copy of the estimate is attached. 2.2.3 Interconnection Facilities work at Bison Substation to be completed by the Transmission Provider and paid for by the Interconnection Customer (with cost being non-refundable per the LGIP) Install three 115kV voltage transformers and three 115kV current transformers for bidirectional metering. Install one 115kV metering disconnect switch. Install one meter panel Install other necessary substation equipment including but not limited to grounding conductor, cable trench, conduit, foundations, support steel, fence, yard surface, static protection and tubular and cable bus. The estimated cost of the Interconnection Facilities construction is $304,000; a copy of the estimate is attached. 2.2.3 Work to be completed and paid for by the Transmission Provider Install four 115kV disconnect switches for the future installation of a ring-bus. 2.3 Springer Substation Work Description 2.3.1 Work to be completed and paid for by the Interconnection Customer None 2.3.2 Work to be completed by the Transmission Provider and initially paid for by Interconnection Customer (with cost being refundable per the LGIP) To accommodate the required transfer-trip to Bison Substation in the event the Springer- York Canyon transmission line breaker trip, some minor protection and telecommunications work will need to be performed. The cost for this work is included in the Network Upgrades estimate. 3. GENERATING FACILITY PERFORMANCE VERIFICATION Results of the SIS indicate that the IC will need to install additional equipment to provide the voltage regulation and reactive support capabilities required. Verification of these capabilities as 6 of 7

measured at the Point of Interconnection (POI) bus will be required when the facility is ready for commercial operation. Detailed discussion on this topic is contained in the SIS Final Report. 4. SCHEDULE A Gantt chart schedule is attached for the engineering and construction of the Bison Substation interconnection facilities. The schedule starts with the receipt of funds and execution of an E&P agreement on September 14, 2009. After the Project start, engineering and construction activities continue assuming timely execution of the LGIA and receipt of final project funding. The estimated duration from the receipt of funds is 10 months. The current estimated in-service date is June 1, 2010, but Tri-State will make all reasonable attempts to improve on this date. 5. REFERENCES [1] Jeremy Sneath and Andrew Issacs P.E., Updated Interconnection System Impact Study Report Final Report November 19, 2009. Queue Interconnection Request No. TI-08-0312, 30MW Photovoltaic Facility near Springer, New Mexico prepared for Tri-State Generation and Transmission Association, Inc., Final Review by: Ray LaPanse 6. LIST OF ATTACHMENTS Drawings Bison Substation: One-Line Diagram Preliminary General Arrangement Cost Estimates Bison Substation (Network Upgrades) Estimate, dated 10/19/09 Bison Substation (Interconnection Facilities) Estimate, dated 10/19/09 Schedule Bison Substation MS Project Gantt Chart, dated 11/30/09 7 of 7