Regulating and pricing network access

Similar documents
On the Road to a Common Market: The European Electricity Market and the Role of Regional Cooperation. Mark Copley 27/05/14

Response to Draft Guidelines of Good Practice on Electricity Grid Connection and Access (E08-ENM-09-03)

Smart Metering and Smart Grids: the Enel

Cross-Border participation in the GB Capacity Market. Elaine O Connell 15 th January 2015

COMMISSION STAFF WORKING DOCUMENT EXECUTIVE SUMMARY OF THE IMPACT ASSESSMENT. Accompanying the document

MODULAR HUB AND SPOKE 17 NOVEMBER 2017

The future role of DSOs in the context of the Clean Energy for All Europeans package

SMART METERING IN THE CZECH REPUBLIC, VIEWED BY EZ DISTRIBUCE

An Integrated Platform for Increased FLEXIbility in smart TRANSmission grids with STORage Entities and large penetration of Renewable Energy Sources

An Introduction to Network Codes & The Links Between Codes

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

An Energy Community for the Future Key Findings of the Report of the High Level Reflection Group. Barbora Jaksova, Energy Community Secretariat

BEMIP implementation WG. Interconnectors Market development

Discussion on measuring electricity security of supply and potential indicators of Smart Grids

Revised Pilot Framework Guideline on Capacity Allocation Mechanisms E10-GWG December 2010

Public consultation on the revision of the Recommendation on relevant markets

20 December All TSOs of the Capacity Calculation Region Hansa, taking into account the following: Page 1 of 7

DS3 Ambitious approach to future network requirements. Mo Cloonan Commission for Energy Regulation, Ireland

OPUC Transmission Workshop 2 FERC Pro Forma Transmission

Power System Interconnection and Energy Security

Description Activities Description. Co-ordination with GB System Operator. Co-ordination with other DSOs and Distribution Networks (including IDSOs)

INTERACTION BETWEEN RPS AND SBC POLICIES

TSO-DSO RELATIONS IN THE FUTURE EUROPEAN POWER SYSTEM

THE GAS INTERCONNECTION POLAND LITHUANIA (GIPL)

Anna Butenko User-centered innovation and regulatory framework

The road to Toll Interoperability the impact on the road concessionaires of the EU directive changes.

Development of a National Broadband Strategy Project. Addendum No. 1 to Phase 2 report

Residual Auction Revenue Rights

Residual Auction Revenue Rights

DSTI/ICCP/TISP(2000)6 COMMUNICATIONS OUTLOOK 2001

GDF SUEZ Infrastructures Business Line. Yves Colliou

European Distribution System Operators for Smart Grids

Bill and Keep as the Efficient Interconnection Regime?: A Reply. Abstract

COMMUNICATIONS OUTLOOK 1999

ENTSO-E working to fulfill the 3 rd Package

CGM and Energy Data Architecture a TSO Perspective

Residual Auction Revenue Rights Enhancement

The new Electricity Market Design a smart regulation for smart distribution networks?

ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE

From: Laura Manz, Vice President of Market & Infrastructure Development

All Baltic CCR TSOs amended proposal for the fallback procedures in accordance with Article 44 of the Commission Regulation (EU) 2015/1222 of 24 July

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Supplementary Information Sheet on State aid to broadband

Telecom Decision CRTC

ENTSOG update and view on Germany

Perspectives and actions for the implementation of Smart Grids into the internal energy market

Policy and regulatory framework: what are the next challenges to tackle?

(Ordinance of the Ministry of Posts and Telecommunications No. 64-November 16,

HAKOM NEXT GENERATION NETWORK AND REGULATORY CHALLENGES. Prof. Ignac Lovrek, Ph.D. Dražen Lučić, Ph.D. Gašper Gaćina

Readiness of Individual European Recycling Companies. Hosted by StorageTek

Forum Energia Regulation of energy markets Klaus Gerdes Lisbon, October 19th 2006

Cost Saving Measures for Broadband Roll-out

ICB Industry Consultation Body

Drivers and regulatory framework to roll out the Smart Grid deployment in Europe

International Mobile Roaming -

Demand response in blocks of buildings: the DR BOB project

Introduction to the NYISO

INOGATE Technical Secretariat Key Expert 2: Nikos Tsakalidis Electricity & Gas Activities Tashkent, January 2014

Energy Community Distribution System Operator Initiative

Joint Office of Gas Transporters xxxx: <Introduction of a Discretionary Release Mechanism for Non-Obligated Annual NTS Exit (Flat) Capacity>

European regime for interconnection

The Regional Electricity Market Platform

Network Codes, Governance and Regulatory issues for the Transition towards up to 100% RES

Electricity Market Integration 2.0 in Central and South East Europe Potential benefits: markets and institutions

Gas Sector Development in Ukraine. Focus on selection of GTS partner and unbundling. Milan Sedláček, eustream, a.s.

TELECOM & ENERGY «Collaborating to Power the Smart Grids for Digital Growth«

Electricity Security Assessment Framework

GAS INTERCONNECTION POLAND LITHUANIA (GIPL) STATUS AND POTENTIAL IMPACT ON THE BALTIC STATES MARKET

A Framework to Approach Shared Use of Mining Related Infrastructure: ICT

A European Perspective on Smart Grids

Day Ahead Fallback proposal Explanatory note

GO15 Reliable & Sustainable Power Grids

Elia Grid International Your expert in power system solutions

Digitalisation of the energy system. Marc VAN STIPHOUT, UNIT C2 European Commission DG ENERGY

EU energy policy and the role of smart grids Mark van Stiphout DG Energy

IFC ENERGY STORAGE MARKET REPORT

Next Generation Scada Architectures

Policy drivers and regulatory framework to roll out the Smart Grid deployment. Dr. Manuel Sánchez European Commission, DG ENERGY

Policy goals and contribution of the Task Force for the implementation of Smart Grids

SAMENA Regulatory Summit 2013 Kuwait:

EDISON S COMMENTS ON ERGEG PUBLIC CONSULTATION ON PILOT FRAMEWORK GUIDELINES ON ELECTRICITY GRID CONNECTION

Grid Interconnection of Renewable Generation

Lex Mundi Telecommunications Regulation Multi-Jurisdictional Survey

Optimizing wind farms

INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010

User Guide. March 2017

Regional Power Grid Connectivity in North-East Asia

International cooperation on power interconnection: Mongolian Regulatory perspective

Questions and answers on the revised directive on waste electrical and electronic equipment (WEEE)

ENTSO-E connection network codes Implementation guidance documents. Joint DSO response paper

Seminar on African Electrical Interconnection. Module 1. The feasibility of Regional Electricity Cooperation and Integration

KEY INFRASTRUCTURE CONCEPTS. Dr. Allen Eisendrath Office of Infrastructure & Engineering, USAID/Washington

mr. sci. Suada Hadžović, dipl.ing.el. Communications Regulatory Agency Bosnia and Herzegovina Ohrid, Republic of Macedonia, May 24 26, 2017.

TABLE OF CONTENTS. General Information. I. Territory to Which the Rate Schedule Applies... 9

The below represents a summary of Section 1 of Chapter 9 of the National Integrated ICT Policy White Paper.

APMS CONFERENCE 2017 EECC: GET PRO-INVESTMENT MEASURES BACK ON TRACK. Manuel Braga Monteiro Deutsche Telekom Group Prague, 31st October 2017

Contacts. CEDEC Marc Malbrancke, Coordinator CEDEC WG Network Code

EXPERIENCE OF LIBERIA IN SETTING UP THE RURAL ENERGY STRATEGY AND MASTER PLAN

Modelling approach and tool

A New Right for Industrial Data Producers Searching for an Appropriate Framework for a European Data Economy

Transcription:

Regulating and pricing network access László Szabó ERRA Training 5-8 March, 2013, Budapest

Lecture outline Network: an essential infrastructure Getting connected Pricing the use of existing electricity networks Regulatory models of network upgrade and expansion RES-E challenge to network regulation and pricing 2

The significance of networks network externalities 3 A new network user increases consumer benefit for those already using it The more people use the network, the more valuable the network service is (mobile phones, Facebook) Positive social externalities of electrification (economic development, education )

The significance of networks essential facility Essential facility: without access to such a facility, it is impossible to serve a given market (the only port on an island; the single airport of a country; the electricity network of a region ) Major characteristics: Access to it is critical to serve end customers Traditionally it is owned by a vertically integrated company Access can only be granted by the vertically integrated company or can be enforced by regulation Natural monopoly; it does not worth to duplicate it 4

Special characteristics of networks High fixed costs, almost negligible marginal costs ( network losses) MC-pricing certainly not enough to cover all costs of the firm Hungary (2005): AC = 5 MC (electricity distribution) AC-pricing likely to result in significant efficiency loss Essential facility all market actors need access to the network vertically integrated network operators have an incentive to distort competition Capacity constraints certain network elements are prone to congestion, especially crossborder interconnectors Physical laws additional rules that define the flow of gas or electricity on the network (e.g. Kirchoff laws) especially important if congestion is present Investment incentives short term efficient pricing may not induce efficient network investment

Regulatory consequences from network characteristics The benefit from new connection is not only enjoyed by the new user but by the formers as well Public purpose line Part of connection cost is legitimate to socialize If competition is introduced on an energy market, essential facilities have to be identified E.g. electricity network including distribution and transmission parts In the case of non-natural monopolies, market analysis might be needed (e.g. natural gas storage) Third party access should be granted to essential facilities Main rule: regulated access Negotiated access: when can it be useful? 6

Lecture outline Network: an essential infrastructure Getting connected Pricing the use of existing electricity networks Regulatory models of network upgrade and expansion RES-E challenge to network regulation and pricing 7

Getting connected - questions Who can initiate a new connection? Benefits? Costs? Who should pay for the costs? Should the cost of connection depend on the location of the connection point? Is there any reason to socialize (include into transmission tariff) 100% of connection cost for some new market participants? What to do with excess demand for connection at a connection point (substation)? How to establish priorities for new connection? How to plan for the expansion of the grid? Regulator might be in charge to get involved in giving answers! 8

Connection cost allocation regimes Total cost of connection: direct cost of connection to a network substation and the potential additional costs of network upgrade and/or expansion that the new connection might make necessary Super shallow connection charge: developer/customer only pays for the direct cost of connection to a substation Shallow connection charge: developer/customer has to pay for the direct cost of connection and also for the necessary upgrade of the existing grid Deep connection charge: developer/customer has to pay for the total cost of connection Advantages, disadvantages? Who should establish the cost of connection? Should the allocation of connection cost be regulated or left to the parties? 9

EU regulators about renewable electricity (RES-E) grid integration Charges for connecting to and using the [electricity] system should, in principle, be transparent, cost-reflective and not dependent on the source of the electricity. (Regulatory aspects of the integration of wind generation in European electricity markets. A CEER Conclusions Paper, Ref: C10-SDE-16-03. 7 July 2010, pp. 20-22.) Issues with RES-E integration: Should the connection cost of high quality but distant RES resources into the grid be socialized? To handle excess demand for connection queue management 10

Hungarian regime Small customers pay a regulated charge depending on the capacity of connection Shallow connection charge regime: High voltage customers and generators pay 70% and 100% of the investment cost, respectively Network upgrade cost is socialized Network company becomes the owner of network assets, even if the new user paid for it Asset value financed by network user deducted from regulatory asset base (RAB) for tariff calculation 11

Lecture outline Network: an essential infrastructure Getting connected Pricing the use of existing electricity networks Regulatory models of network upgrade and expansion RES-E challenge to network regulation and pricing 12

Network access and usage - questions Once connected can network operator deny access to the grid? Only according to pre-defined rules, mostly due to system security causes Network company has to explain; financial liability Network access in case of congestion? Can priority access to the grid be justified? In Europe, a usual mode of RES-E support 13

Congestion management methods Non-market oriented first-come first-served proportional reduction of demand non-transparent methods (favoritism) Market oriented auctions one-sided, two-sided, common, coordinated nodal pricing zonal pricing market splitting, market coupling Real-time redispatching, counter-trading 14

Nodal pricing Network access charges are calculated for each node of injection and/or load separately These charges reflect the marginal cost of using a specific network node (Locational Marginal Pricing) Differences in nodal charges are related to network losses and congestion at the nodes Advantages: Price signal for future network users where to connect to the grid Helps to manage network congestion by affecting future choices for new connections/developments Not simple, but implementable: applied in New Zealand, PJM, New York 15

Market oriented methods Coordinated auction: First, the transmission market clears After the closure of the transmission market, the energy market opens and clears Efficient working of the transmission market requires perfect foresight from traders regarding the energy market In zonal pricing: Market coupling: Joint allocation methods of two markets Two markets are joined in a zone, if no congestion is present between them Market splitting: First, compute a single system electricity price as if no congestion existed If line capacities are exceeded, then split the market into submarkets until a solution can be found

Financing the network in case of a regulated access system 17 Cost assessment, establishment of annual revenue requirement Design of network tariffs Customer groups Single- or multi part tariffs Recovery of network loss / non-payment Rules to change network tariffs (price regulation)

Tariff design questions - incentives Access charge is location-dependent (entry exit) or post stamp kind? The role of capacity and electricity based tariff components in network tariffs Country-wise uniform or regionally differentiated network tariffs? Who should pay the network tariffs: load (L), generation (G) or both? Network tariff as a mean to collect revenue for special purposes (e.g. subsidy for the poor) Network CAPEX to become part of RAB ex ante or ex post? Major considerations: location of load / generation; stability and predictability of network service remuneration; fairness in cost allocation 18

Post stamp pricing Does not recognize that users cause different costs to the network operator AC-pricing in general it means uniform pricing, but can be differentiated by time use. inefficient in itself, but can be combined with non-linear schemes to increase efficiency Cost of congestion management (redispatch) distributed evenly among system users Creates incentives to free-ride on the system Not necessarily bad, if congestion is a rare problem in the network cost differences in service provision are small Cross-subsidization is present

20 The share of capacity and energy related tariff components in European transmission tariffs electricity gas

21

Comparison of the structure of EU electricity transmission tariffs, Euro/MWh 22

Lecture outline Network: an essential infrastructure Getting connected Pricing the use of existing electricity networks Regulatory models of network upgrade and expansion RES-E challenge to network regulation and pricing 23

Financing new major lines Model 1 Merchant or private line Exclusive use of capacity by developers No (or negotiated) third party access - no regulated access tariff Line pays back from the price difference between the markets it connects Estlink 24

25 Financing new major lines Model 2 USA: market based development - Rockies Express Gas Pipeline Completed in 3 years Regulated rate of return: 10.2% (before crisis; new projects: 12%)

Financing new major lines Model 3 Government financed investment: Kazakhstan China gas pipeline Sufficient government funding needed 26

Financing new major lines Model 4 European Union Main rule: regulated third party access (rtpa) Line pays back from regulated tariff set by national regulator(s) In case of new major infrastructure development: Commission / ACER might provide exemption from rtpa 27

Lecture outline Network: an essential infrastructure Getting connected Pricing the use of existing electricity networks Regulatory models of network upgrade and expansion RES-E challenge to network regulation and pricing 28

RES-E challenge to network regulation and pricing Ambitious targets for all EU Member States Not only a financing problem, but also reaches the limits of the network capacities in many countries New challenges: distributed production New tools: smart grids helping to detect price signals

30 Challenges for the EU integrating massive renewable electricity generation and completing internal electricity and gas markets

Various country approaches of RES-E connection Italy: Semi-shallow cost charging, according to a well defined formula Mapping the network elements for connection capacities TSO/DSO have grid connection and grid reinforcement obligations as well TSO/DSOs are incentivised to connect RES-E, they have binding deadline for connection (with penalty) Intensive smart grid developments helps to detect price signals

Various country approaches of RES-E connection Denmark: Shallow cost charging cheapest in Europe cost are born by consumers TSO/DSO have grid connection and grid reinforcement obligations as well Network is developed till the last sub-station (even in the case of offshore wind parks) TSO has no deadline on decision Intensive smart grid developments, one of the most advanced in Europe

Various country approaches of RES-E connection The Czech Republic: Hybrid cost charging, according to a pre-set level (Euro/MW connected) Significant speculative demand for connection appeared in the system later solved by deposit obligations TSO/DSOs are dis-incentivised to connect RES-E Lagging smart grid developments

THANK YOU FOR YOUR ATTENTION! lszabo@uni-corvinus.hu www.rekk.eu 34