Metrolinx / Toronto Transit Plan April 28, Jack Collins Vice President, Rapid Transit Implementation

Similar documents
Community Update. May 31, 2011

WHY UNDERGROUND TRANSIT?

Community Update. June 8, 2011

Community Update. June 21, 2011

Community Update. June 30, Presented at: York Civic Centre

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Subject YRRTC Accomplishments and Highlights

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

Greater Toronto Area

Infrastructure Ontario Approach to large infrastructure and real estate projects. Partnering to modernize Ontario s infrastructure

Collaborative Intelligent Transportation Systems (ITS) Initiatives with Neighbouring Jurisdictions

GDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010

Operations. Business Plan Overview

MARTA BOARD OF DIRECTORS OCTOBER 4, 2018

SECTION 106 ACTIVITIES ANNUAL REPORT

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

SECTION 106 ACTIVITIES ANNUAL REPORT

Dallas Streetcar Central Link Locally Preferred Alternative Selection

2018 OPERATING BUDGET BRIEFING NOTE 2018 Preliminary Position Changes

Airports Infrastructure and Financing. ACI-LAC Annual Conference and Exhibition Brasilia, November 8 10, 2016

City of Toronto Accessibility Design Guidelines 2015

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 29, 2016

Corridor Management Committee. January 12, 2017

Transportation and Road Improvement GO Bond. September 2016 Report

STATE STREET CORRIDOR

CITY OF VANCOUVER ADMINISTRATIVE REPORT

Procuring New Infrastructure for Canada s Municipalities

Elite Construction Inc.

High Speed Rail Update

S-03-SegB: South Federal Way to Fife LRT

The Evolution of Public-Private Partnerships in Canada

vision42

System Expansion Implementation Plan. Board Meeting, April 2017

DISTRICT OF MUSKOKA COUNCIL PRESENTATION RE: CONNECT TO INNOVATE HIGH SPEED FIBRE OPTIC APPLICATION

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS

Kuwait Railroad & Rapid Transit Systems. Eng. Khaled A. Al-Awadhi General Manager Kuwait Metro Rapid Transport Co.

CLIMATE BONDS STANDARD VERIFICATION LETTER

Region of Waterloo Corporate Services Facilities & Fleet Management

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

CAPACITY BUILDING WORKSHOP FOR TRAFFIC MANAGEMENT INFORMATION CONTROL CENTRES (TMICC) AND NATIONAL URBAN TRANSPORT HELPLINE (NUTH)

Professional Engineers Ontario. canada s anti-spam. Guidelines for Chapters

THE BILLY BISHOP TORONTO CITY AIRPORT PEDESTRIAN TUNNEL CONNECTING INVESTORS, TRAVELLERS AND CITIZENS

Metropolitan Council. Transportation Division Proposed Transit Capital Program

GTA West Corridor Review

MOTION NO. M Task Order 2 with the City of Des Moines for the Federal Way Link Extension

Provo-Orem Bus Rapid Transit

GST/HST Info Sheet GST/HST Info Sheet

Planning & Growth Management Committee

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

OF ELECTRICAL AND ELECTRONICS ENGINEERS POWER & ENERGY SOCIETY

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Transportation Demand Management: The Mississauga Experience Lorenzo Mele TDM Coordinator

The Blue Line Extension

Provincial Land Tax Reform

Emergency Management BC Update

Section 4: Citizen s Guide to SDEIS

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension

MVTA-Prior Lake-Shakopee Merger. SCALE Presentation, October 10, 2014

1 WATER AND WASTEWATER CAPACITY ASSIGNMENT TO SUPPORT APPROVED GROWTH

Memorandum of Understanding between the Central LHIN and the Toronto Central LHIN to establish a Joint ehealth Program

Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008

DART s Program of Inter-Related Projects. Joint DART and Transportation and Trinity River Project Committee 10 November 2014

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012

Gateway Transportation Collaboration Forum. 21/01/2015 Gateway Transportation Collaboration Forum 1

Supplemental Details - Capital Funding Source Summary Cap Fund Cap Fund Cap Fund - 21

CPM Certification Examination

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

R ental of C ollege F acilities Policy

NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance

Approval of Medical Center New Entrance Agreement

Corridor Management Committee. January 14, 2016

Port Governance: A Canadian Perspective

EST PLENARY SESSION 5

2018 Priorities. Staff Lead Legend: 2 P age DCAO GMDS CAO GMEPW. Mayor and Council

U.S. System Summary: OHIO HUB

1.0 PURPOSE AND NEED

Interoute Acquisition Summary. February 26, 2018

Due Diligence Checklist #20

Drinking Water Emergency Management Ministry of the Environment 2012 Drinking Water Leadership Summit October 25, 2012

Infrastructure PA Stephen Lecce

Cyber Security Strategy

Core Capacity Transit Study. San Francisco County Transportation Authority October 17, 2017

NOW IS THE TIME. to secure our future

New York Building Congress May 24, Uday Durg, P.E. Senior Vice President & Chief Engineer MTA Capital

Open house April 26 & 27, 2017

GROSS REVENUE CHARGE AND OTHER WATER AGREEMENT COSTS REGULATED HYDROELECTRIC

Corporate Security & Emergency Management Summary of Submitted 2015 Budget From Rates

Attachment A. TransformTO Short-term Strategies Business Cases

Building Strategies & Sustainability

PROJECT TIMELINE. Next steps. Plan. Start of Service

We reserve the right to cancel your participation in this program at any time.

Municipal Broadband Project. City Council Meeting February 4, 2016

RCMP Support / Bylaw Services Department

The second life of Yerevan Metro

Annual Report for the Utility Savings Initiative

Transcription:

Metrolinx / Toronto Transit Plan April 28, 2011 Jack Collins Vice President, Rapid Transit Implementation 1

Overview 1. Principles in Developing the Plan 2. Metrolinx / Toronto Transit Plan 3. The Plan and Projects 4. Memorandum of Understanding 5. Next Steps 2

Principles in Developing the Plan To formulate the revised plans, Metrolinx set out five guiding principles: We need to achieve both regional and local transportation objectives. The regional objectives are set out in Metrolinx s The Big Move There can be no cost increases to the Province We need to avoid loss of existing investments and any penalties We have to deliver results to citizens as quickly as possible We need to minimize impacts on traffic 3

Metrolinx / Toronto Transit Plan 2010 Estimated Cost = $12.91B Provincial share = $8.4B City / Other share = $4.18B Federal Share: $333M 4

Metrolinx / Toronto Transit Plan Summary Statistics Project Total km Tunnel km Total Stations Schedule 2010 Cost SHEPPARD EAST SUBWAY Don Mills to Scarborough Centre SHEPPARD WEST SUBWAY Yonge to Downsview NEW SUBWAY YARD EGLINTON- SCARBOROGUH CROSSTOWN LRT Jane / Black Creek to Scarborough Centre 8 8 7 2011-2019 $2.75 B 5.45 5.45 2 2011-2019 $1.48 B n/a n/a n/a 2016-2020 $0.5 B 25.2 19.5 26 2011-2020 $ 8.18 B Totals 38.65 32.95 35 2011-2020 $12.91 B 5

The Plan and Projects Eglinton-Scarborough Crosstown Light Rail Transit (LRT) 25.2 km east-west LRT corridor between Scarborough Centre and Jane Street / Black Creek 19 km of tunnelled LRT along Eglinton connected with continuous through-running service along upgraded SRT alignment (5.7 km, elevated and at-grade, 0.5 km tunnelled) to Scarborough Centre Opportunity for Metrolinx / GO express bus service from Jane / Black Creek to Pearson Airport via Renforth Gateway Up to 26 stations Cost estimate for the combined project is $8.18B (2010$) Sheppard East Subway An extension of the existing Sheppard Subway, easterly from current terminus at Don Mills Station to a new terminus at Scarborough Centre Approximately 8 km in length / up to 7 new stations Cost estimate (excluding a new yard): $2.75B (2010$) Sheppard West Subway An extension of the existing Sheppard subway westerly from the current terminus at the Yonge-Sheppard Station to a new terminus at Downsview on the University-Spadina line Approximately 5.5 km in length / 2 new stations Cost estimate: $1.4B Finch West Enhanced Bus Service: TTC will operate enhanced bus services between the new Finch West subway station to Humber College Note: all rail estimates include vehicles, stations, maintenance and storage facilities, rail and signal systems 6

Memorandum of Understanding (MOU) General Non-binding agreement between the Ontario, Metrolinx and the City of Toronto to establish the guiding principles for continuing to move forward on these projects Provides framework for negotiation of agreements to be approved by each party s governing body Key Responsibilities: Metrolinx is responsible for securing funding, environmental approvals, designing, coordinating, planning, constructing and implementing the Eglinton- Scarborough Crosstown LRT project. Metrolinx will own and control this project. Toronto is responsible for securing funding, environmental approvals, designing, coordinating, planning, constructing and implementing subway extensions along Sheppard Avenue (east and west). Toronto will own and control these projects. 7

MOU Financial Responsibilities Metrolinx will contribute up to $8.4B (2010$) to the program The City of Toronto is responsible for the funding and financing initiatives related to the Sheppard subway projects. If the cost of the Metrolinx project is $8.4B or less, the balance of the funds could fund the Sheppard East subway up to a maximum provincial contribution of $650M The Province, other relevant Ministries and Metrolinx will work with Toronto to identify legislative amendments and regulations which may be necessary or desirable to facilitate Toronto s ability to finance and build the Toronto Projects Toronto may propose amendments that include, but are limited to, its ability to finance the Toronto Project through the use of development charges and municipal tax increment financing. Once such amendments have been identified and mutually agreed to by the parties, the relevant Ministries will propose the legislative and regulatory amendments to the Government The City of Toronto will not be able to access the education component of the municipal property tax for project financing Losses or penalties incurred due to contract cancellations, suspensions or reductions are the responsibility of Toronto. Amount and terms of repayment to be negotiated 8

MOU Other Both Metrolinx and the City of Toronto, at their own costs, are required to complete amended environmental assessments for these projects The parties will work together to facilitate each other s assessments Metrolinx and the Province will support the City s efforts to: Transfer the $333M commitment from the federal government towards the Sheppard East LRT to the Sheppard subway Obtain financial support from the P3 Canada fund The City of Toronto will be responsible for the transit operations of the completed Sheppard subway projects The operations, revenues and expenditures of the Eglinton-Scarborough Crosstown LRT will be determined in a future negotiated agreement between Metrolinx and the City of Toronto 9

Next Steps Work continuing on Eglinton project: Continue to advance mid-town tunnel section Complete Light Rail Vehicles design Conduct preliminary engineering review for Eglinton east tunnel segment Prepare for amendments / update to Environmental Assessment Additional Eglinton planning work will be required to determine: Station requirements and locations along Eglinton east Kennedy Station configuration McCowan yard configuration Jane / Black Creek terminus alignment Operation concept / scenario 10

www.metrolinx.com Thank you 11