Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Similar documents
SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Joint Transmission Planning Base Case Preparation Process

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models

Standard CIP Cyber Security Critical Cyber As s et Identification

New Brunswick 2018 Annual Implementation Plan Version 1

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

Proposed Improvements for NERC MOD Standards July 10, 2012

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

PRC Coordination of Protection Systems for Performance During Faults

Standard CIP Cyber Security Critical Cyber As s et Identification

ISO New England Data Modeling Requirements

Reliability Standard Audit Worksheet 1

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Standard Development Timeline

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

Standard INT Interchange Authority Distributes Arranged Interchange

REAL-TIME MONITORING DATA SPECIFICATION

Reliability Coordinator Procedure

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL

Bulk Electric System Definition Changes and Reporting

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

Introduction to Generation Availability Data System (GADS) Wind Reporting

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

BESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2

Studies Overview and Data Requirements. Robert Pan

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

DRAFT Reliability Standard Audit Worksheet 1

Transmission Register PTO Admin User Manual. Version 1.0

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

XXXXX XXXX Wind Generation Project

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015

Reliability Standard Audit Worksheet 1

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

Supplemental Information

Glencoe Light and Power

Standard Development Timeline

2014 Annual Compliance Assessment

North Gila-Imperial Valley #2 Transmission Project

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

STCP22-1 Issue 003 Production of Models for GB System Planning

Generation, Transmission, and End User Facilities

Draft CIP Standards Version 5

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB2 INTRODUCTION TO SLIDER BINARY (*.sld) FILES

MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS

A guide on PowerWorld Simulator ver. 12.0

Procedure For NPCC Bulk Electric System Asset Database

Section 10 of BPM for TPP- Generator modeling webinar

Project Consideration of Commission Directives in Order No. 693

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Disturbance Monitoring and

National Load Despatch Centre Power System Operation Corporation

STCP 04-3 Issue 005 Real Time Data Provision

DER Data Collection Guideline. Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017

Standard CIP Cyber Security Security Management Controls

Power System Network Simulator (PSNsim)

Simulation and Analysis of Static Var Compensator with Matlab

Power System Studies. The Power of Trust. The Future of Energy.

Interconnection Application

Geomagnetic Disturbances

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Feasibility Study on Load Flow and Short Circuit Project

Tutorials. Tutorial: Creating a New Case Page 1 of 13

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC

NERC and Regional Coordination Update

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM. July 2011 UPDATED STANDARDS

requirements in a NERC or Regional Reliability Standard.

Small Generator Interconnection System Impact Study Report. Completed For Q0047

NERC Notice of Penalty regarding Upper Peninsula Power Company, FERC Docket No. NP09-_-000

WECC Criterion INT-001-WECC-CRT-3

Standards Authorization Request Form

Transmission Distribution Microgrid - DER

N-1-1 Reactive Upgrades

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

A. Introduction. B. Requirements and Measures

Dynamic Load Models in PowerWorld Simulator

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

Chapter 3 MODELING OF SHUNT FACTS DEVICES. The Shunt FACTS Devices are used for voltage control and

Data Preparation Tools and Dynamic Models for System Studies with Distributed Series Impedances and Distributed Static Series Compensators

FACTS and HVDC for Grid Connection of Large Wind Farms

Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays

Electric Transmission Reliability

INTERCONNECTION FACILITIES STUDY REPORT

Standard INT Dynamic Transfers

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

Transcription:

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016

APS Requirements for Data for Power System Modeling and Analysis Table of Contents Table of Contents... 2 1 Purpose... 3 2 Applicable Performance Requirements... 3 2.1 R1.... 3 2.1.1 R1.1.... 3 2.1.2 R1.2.... 3 2.1.3 R1.3.... 4 3 Version History... 4 Appendix A... 5 2 P age

APS Requirements for Data for Power System Modeling and Analysis 1 Purpose The purpose of these requirements is to ensure that Arizona Public Service Company (APS) is compliant with North American Electric Reliability Corporation (NERC) Reliability Standard MOD-032-1. Specifically, these requirements are intended to establish consistent modeling data rules and reporting procedures for development of planning horizon cases necessary to support analysis of the reliability of the interconnected transmission system. 2 Applicable Performance Requirements In determining compliance with MOD-032-1, the compilation of data to construct planning horizon cases must be consistent with the following requirements: 2.1 R1. Each Planning Coordinator and each of its Transmission Planners shall jointly develop steady-state, dynamics, and short circuit modeling data requirements and reporting procedures for the Planning Coordinator s planning area that include: 2.1.1 R1.1. The data listed in Attachment 1 of MOD-032-1: Attachment 1 of MOD-032-1 is included as Appendix A. In addition, the data specified in the WECC Data Preparation Manual for Interconnection-wide Cases 1 is also to be included. 2.1.2 R1.2. Specifications of the following items consistent with procedures for building the Interconnection-wide case(s): 2.1.2.1 R1.2.1. Data format: The format that is acceptable for those items listed in Attachment 1 of MOD-032-1 is provided in the WECC Data Preparation Manual for Interconnection-wide Cases. Also, the data should be in the GE PSLF format for inclusion into WECC bulk cases and the WECC Master Dynamics File. 2.1.2.2 R1.2.2. Level of detail to which equipment shall be modelled: As is the case for R1.2.1, the WECC Data Preparation Manual for Interconnection-wide Cases describes the detail needed for accurate and complete modeling in WECC bulk cases. 1 References to the WECC Data Preparation Manual for Interconnection-wide Cases refer to the most current available version WECC is utilizing at the time of the data submittal. 3 Page

APS Requirements for Data for Power System Modeling and Analysis 2.1.2.3 R1.2.3. Case types or scenarios to be modeled: The case scenarios including generation and load patterns are provided in the WECC Base Case Compilation Schedule 2. 2.1.2.4 R1.2.4. A schedule for submission of data at least once every 13 calendar months: APS uses the WECC Base Case Compilation Schedule. Provided in the WECC Base Case Compilation Schedule is a detailed schedule of submitting data and compiling WECC bulk cases. 2.1.3 R1.3. Specifications for distribution or posting of the data requirements and reporting procedures so that they are available to those entities responsible for providing the data: As the Planning Coordinator and Transmission Planner APS will review its MOD-032-1 Requirements for Data for Power System Modeling and Analysis annually. If changes are made, the current version of its MOD-032-1 Requirements for Data for Power System Modeling and Analysis will be distributed under the email address TRANSMPLNCOMP@APS.COM. APS requires those submitting data as fulfillment of these requirements to use this email address as well. In addition, APS maintains a posting of its MOD-032-1 Requirements for Data for Power System Modeling and Analysis on APS s OASIS page in the MOD-032 folder, which is in the NERC Documentation folder under the Transmission Planning folder; Transmission Planning NERC Documentation MOD-032. 3 Version History Version Change Date Change Tracking Author Approval Approval Date 1.1 6.29.2015 Original Barrie Kokanos Jason Spitzkoff 6.29.2015 1.2 12.29.2016 Minor edits Lisa Billy Jason Spitzkoff 12.29.2016 2 References to the WECC Base Case Compilation Schedule refer to the most current available version WECC is utilizing at the time of the data submittal. 4 Page

Appendix A MOD-032-01 Attachment 1

MOD-032-01 ATTACHMENT 1: Data Reporting Requirements The table, below, indicates the information that is required to effectively model the interconnected transmission system for the Near- Term Transmission Planning Horizon and Long-Term Transmission Planning Horizon. Data must be shareable on an interconnectionwide basis to support use in the Interconnection-wide cases. A Planning Coordinator may specify additional information that includes specific information required for each item in the table below. Each functional entity 1 responsible for reporting the respective data in the table is identified by brackets [functional entity] adjacent to and following each data item. The data reported shall be as identified by the bus number, name, and/or identifier that is assigned in conjunction with the PC, TO, or TP. steady-state (Items marked with an asterisk indicate data that vary with system operating state or conditions. Those items may have different data provided for different modeling scenarios) 1. Each bus [TO] a. nominal voltage b. area, zone and owner 2. Aggregate Demand 2 [LSE] a. real and reactive power* b. in-service status* 3. Generating Units 3 [GO, RP (for future planned resources only)] a. real power capabilities - gross maximum and minimum values b. reactive power capabilities - maximum and minimum values at dynamics (If a user-written model(s) is submitted in place of a generic or library model, it must include the characteristics of the model, including block diagrams, values and names for all model parameters, and a list of all state variables) 1. Generator [GO, RP (for future planned resources only)] 2. Excitation System [GO, RP(for future planned resources only)] 3. Governor [GO, RP(for future planned resources only)] 4. Power System Stabilizer [GO, RP(for future planned resources only)] 5. Demand [LSE] short circuit 1. Provide for all applicable elements in column steady-state [GO, RP, TO] a. Positive Sequence Data b. Negative Sequence Data c. Zero Sequence Data 2. Mutual Line Impedance Data [TO] 3. Other information requested by the Planning Coordinator or Transmission Planner necessary for modeling 1 For purposes of this attachment, the functional entity references are represented by abbreviations as follows: Balancing Authority (BA), Generator Owner (GO), Load Serving Entity (LSE), Planning Coordinator (PC), Resource Planner (RP), Transmission Owner (TO), Transmission Planner (TP), and Transmission Service Provider (TSP). 2 For purposes of this item, aggregate Demand is the Demand aggregated at each bus under item 1 that is identified by a Transmission Owner as a load serving bus. A Load Serving Entity is responsible for providing this information, generally through coordination with the Transmission Owner. 3 Including synchronous condensers and pumped storage. Page 12 of 19

steady-state (Items marked with an asterisk indicate data that vary with system operating state or conditions. Those items may have different data provided for different modeling scenarios) real power capabilities in 3a above c. station service auxiliary load for normal plant configuration (provide data in the same manner as that required for aggregate Demand under item 2, above). d. regulated bus* and voltage set point* (as typically provided by the TOP) e. machine MVA base f. generator step up transformer data (provide same data as that required for transformer under item 6, below) g. generator type (hydro, wind, fossil, solar, nuclear, etc) h. in-service status* 4. AC Transmission Line or Circuit [TO] a. impedance parameters (positive sequence) b. susceptance (line charging) c. ratings (normal and emergency)* d. in-service status* 5. DC Transmission systems [TO] 6. Transformer (voltage and phase-shifting) [TO] a. nominal voltages of windings b. impedance(s) c. tap ratios (voltage or phase angle)* d. minimum and maximum tap position limits e. number of tap positions (for both the ULTC and NLTC) f. regulated bus (for voltage regulating transformers)* g. ratings (normal and emergency)* h. in-service status* 7. Reactive compensation (shunt capacitors and reactors) [TO] a. admittances (MVars) of each capacitor and reactor b. regulated voltage band limits* (if mode of operation not fixed) c. mode of operation (fixed, discrete, continuous, etc.) d. regulated bus* (if mode of operation not fixed) e. in-service status* 8. Static Var Systems [TO] dynamics (If a user-written model(s) is submitted in place of a generic or library model, it must include the characteristics of the model, including block diagrams, values and names for all model parameters, and a list of all state variables) 6. Wind Turbine Data [GO] 7. Photovoltaic systems [GO] 8. Static Var Systems and FACTS [GO, TO, LSE] 9. DC system models [TO] 10. Other information requested by the Planning Coordinator or Transmission Planner necessary for modeling purposes. [BA, GO, LSE, TO, TSP] short circuit purposes. [BA, GO, LSE, TO, TSP] Page 13 of 19

steady-state (Items marked with an asterisk indicate data that vary with system operating state or conditions. Those items may have different data provided for different modeling scenarios) a. reactive limits b. voltage set point* c. fixed/switched shunt, if applicable d. in-service status* 9. Other information requested by the Planning Coordinator or Transmission Planner necessary for modeling purposes. [BA, GO, LSE, TO, TSP] dynamics (If a user-written model(s) is submitted in place of a generic or library model, it must include the characteristics of the model, including block diagrams, values and names for all model parameters, and a list of all state variables) short circuit Page 14 of 19