PG&E Transmission Interconnection Handbook

Similar documents
PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

Generation, Transmission, and End User Facilities

Transmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel

Glencoe Light and Power

MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

REAL-TIME MONITORING DATA SPECIFICATION

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

THE INTERCONNECTION HANDBOOK

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

INTERCONNECTION FACILITIES STUDY REPORT

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Revision 6.0. Transmission Interconnection Guide

JEA. Facility Connection Requirements

INTERCONNECTION FACILITIES STUDY REPORT

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)

Appendix I: LOAD OPERATING AGREEMENT

Electric Utility Facility Connection Requirements

Interconnection and Transmission

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

Document C0. Use for:

SCADA Training - T&D Automation

INTERCONNECTION STANDARDS FOR GENERATING FACILITIES (GF) CONNECTED TO THE FORT COLLINS DISTRIBUTION SYSTEM. July 2011 UPDATED STANDARDS

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

High and Medium Voltage Substation Design, Testing and Maintenance. KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel.

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM

Substation SCADA Monitoring

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

Substation Automation Products. Line differential protection RED670 Relion 670 series

ELG4125: System Protection

Facility Connection Requirements

Small Generator Interconnection System Impact Study Report. Completed For Q0047

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

Instructions. Interconnection Customer declares its intention to interconnect with the AEP Distribution System.

Power System Network Simulator (PSNsim)

COGENERATION INTERCONNECTION REQUIREMENTS. Parallel Operation of Connecting Parties Generation

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

GREAT RIVER ENERGY. May 2014 GREAT RIVER ENERGY

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

Disturbance Monitoring and

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6

Midwest Energy, Inc. Distributed Generation Interconnection Expedited & Standard Process Application

Small Hydro Regulatory and Permitting Requirements California

APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS. for GENERATION & INTERCONNECTION FACILITIES

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

LCRA Transmission Services Corporation. Facility Connection Requirements

LCRA Transmission Services Corporation. Facility Connection Requirements

PRC Coordination of Protection Systems for Performance During Faults

WN U-60 Original Sheet No. 152

Redundant Bus Protection Using High-Impedance Differential Relays. Josh LaBlanc

Substation Automation Products. Line distance protection REL670/650 Relion 670 and 650 series

BREAKER FAILURE PROTECTION

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

CenterPoint Energy P O Box 1700 Houston, TX

Standard Development Timeline

PRC System Protection Coordination Supplementary Reference

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY

Branch Procedure. Document No. Issue No. : : 29/06/ /06/2021 (Supersedes CEOP8012, Generation Connection: Protection Guidelines, Issue 4.

APPENDIX B-2. TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES. and SMALL GENERATION FACILITIES

Interconnection Application

TRANSMISSION FACILITIES INTERCONNECTION REQUIREMENTS

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

1. Coordination of series-rated devices is permitted where indicated on Drawings.

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Design of Coal Mine Power Supply Monitoring System

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

ISO New England Data Modeling Requirements

Technical Requirements for High-voltage DC Power Feeding Interfaces of ICT equipment

Supplemental Information

Exelon Energy Delivery Interconnection Guidelines for Generators Greater than 2 MVA and Less than or equal to 20 MVA

Advanced Protection and Control Technologies for T&D Grid Modernization

Description of the Application Process for Small Embedded Generators

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards

Network Configuration Document Selection for New Substations Framework

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

JEA Facility Interconnection Requirements

Demonstration Test Bed for Advanced Control Systems

Operations ISO Version: 1.6. Effective Date: 8/02/2018. Fieldwork Guide. Fieldwork Guide

Substation Automation Products. Generator protection REG670/650 Relion 670 and 650 series

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements

CHAPTER 11 HOW TO ENHANCE THE RELIABILITY & POWER QUALITY OF ELECTRICITY SUPPLY

Power Systems Communications Implementation of IEC61850 in a Substation Environment

PG&E 500 kv Protection Standard Design and Development

Transcription:

Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New Transmission and Generation Facilities... IN-2 I-3.2. Existing Load or Transmission Facilities... IN-2 I-3.3. Existing Generation Facilities... IN-3 I-4. ELECTRIC INDUSTRY RESTRUCTURING... IN-3 I-5. PROCEDURES FOR DEVELOPING TRANSMISSION PLANS AND COORDINATED JOINT STUDIES... IN-4 I-5.1. Procedures for Developing Transmission Plans... IN-4 I-5.2. Procedures for Coordinated Joint Studies... IN-5 I-6. ORGANIZATION OF HANDBOOKS... IN-5 I-7. STANDARD AND PROJECT-SPECIFIC INTERCONNECTION REQUIREMENTS... IN-6 I-8. CUSTOMER-OWNED EQUIPMENT REQUIREMENTS... IN-6 I-9. COMPLIANCE WITH NERC INTERCONNECTION STANDARDS... IN-7 I-10. GENERAL RECOMMENDATIONS CONCERNING THE CONTENTS OF LOCAL CEQA DOCUMENTS... IN-10 I-10.1. EIR adopted with significant and unavoidable impacts in any environmental impact categories... IN-10 I-10.2. First section in your document... IN-10 I-10.3. Mitigation Measures v. APMs... IN-11 I-10.4. Not Obligating PG&E... IN-11 I-10.5. Local Ordinances... IN-11 I-10.6. Building Code Exemption... IN-12 I-10.7. General Worst-Case Assumptions... IN-12 I-10.8. Impact analyses sections... IN-13 I-10.9. Aesthetics... IN-13 I-10.10. GHG analysis... IN-13 I-10.11. GHG APMs... IN-14 I-10.12. SF 6 -specific APMs... IN-14 GLOSSARY... GL-1 SECTION L1-D: REVENUE-METERING REQUIREMENTS FOR DISTRIBUTION LOAD-ONLY ENTITIES... L1-D-1 PURPOSE... L1-D-1 L1-D.1. REVENUE METERING REQUIREMENTS FOR LOAD ENTITIES... L1-D-1 L1-D.1.1. Wholesale Service... L1-D-1 L1-D.1.2. End Users (Retail Service)... L1-D-1 L1-D.1.2.1. PG&E Direct Access Rule 22... L1-D-1 L1-D.1.2.2. PG&E, as an MSP, will provide, install, maintain and test the following meter equipment... L1-D-2 L1-D.1.2.3. PG&E, as an MDMA, will provide the following meter data services... L1-D-2 L1-D.1.2.4. All PG&E Load Entities will provide, install and maintain... L1-D-3 L1-D.2. REQUIREMENTS OF REVENUE-METERING POINT... L1-D-4 L1-D.3. COMMUNICATION CIRCUITS... L1-D-4 L1-D.4. GROUND POTENTIAL RISE... L1-D-5 SECTION L1-T: REVENUE-METERING REQUIREMENTS FOR TRANSMISSION-ONLY AND LOAD- ONLY ENTITIES... L1-T-1 PURPOSE... L1-T-1 i

L1-T.1. REVENUE-METERING REQUIREMENTS FOR LOAD ENTITIES AND TRANSMISSION ENTITIES CONNECTING LOAD TO THE PG&E TRANSMISSION SYSTEM... L1-T-1 L1-T.1.1. Wholesale Service... L1-T-1 L1-T.1.2. End User (Retail Service)... L1-T-1 L1-T.1.2.1. Bundled Service... L1-T-2 L1-T.1.2.2. Direct Access Service... L1-T-2 L1-T.1.2.3. Equipment Requirements:... L1-T-3 L1-T.1.3. Additional Requirements... L1-T-4 L1-T.2. LOCATION OF REVENUE METERING POINT... L1-T-5 L1-T.3. COMMUNICATIONS CIRCUITS... L1-T-6 FORM L1-1... L1-T-7 SECTION L2: PROTECTION AND CONTROL REQUIREMENTS FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES... L2-1 PURPOSE... L2-1 APPLICABILITY... L2-1 L2.1. PROTECTIVE RELAY REQUIREMENTS... L2-1 L2.2. RELIABILITY AND REDUNDANCY... L2-3 L2.3. RELAY SPECIFICATIONS RELIABILITY AND REDUNDANCY... L2-3 L2.4. LINE PROTECTION... L2-4 L2.4.1. Fault-Interrupting Devices... L2-5 L2.4.1.1. Circuit Breakers... L2-6 L2.4.1.2. Circuit Switchers... L2-6 L2.4.1.3. Fuses... L2-7 L2.4.1.4. Relay Class Current Transformers (CT)... L2-7 L2.5. STANDBY/BACKUP SOURCE... L2-8 L2.5.1. Standby Source... L2-8 L2.5.2. Backup Generators... L2-8 SECTION L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES... L3-1 PURPOSE... L3-1 L3.1. DEAD-END STRUCTURE... L3-1 L3.2. TRANSFORMERS... L3-1 L3.3. VOLTAGE REGULATION... L3-2 L3.4. POWER FACTOR... L3-3 L3.5. CIRCUIT BREAKER OR OTHER FAULT INTERRUPTING DEVICES... L3-3 L3.6. RULES FOR TAPPING TRANSMISSION LINES... L3-3 L3.7. SWITCHES... L3-4 L.3.7.1. Manual Disconnects... L3-4 L3.7.2. Tap Switch... L3-5 L3.7.3. Line Selector Switches... L3-5 L3.8. INTERCONNECTION OF LOAD ENTITY S OR TRANSMISSION ENTITY S SUBSTATION WITH PG&E S SYSTEM... L3-5 L3.9. LOAD ENTITY OR TRANSMISSION ENTITY INTERFERENCE WITH POWER QUALITY... L3-6 SECTION L4: OPERATING PROCEDURES AND REQUIREMENTS FOR LOAD-ONLY AND TRANSMISSION-ONLY ENTITIES... L4-1 PURPOSE... L4-1 APPLICABILITY... L4-1 L4.1. JURISDICTION OF THE ISO AND THE DESIGNATED PG&E CONTROL CENTER... L4-1 L4.2. COMMUNICATIONS... L4-1 L4.3. ATTENDED LOAD FACILITIESOR TRANSMISSION FACILITIES REQUIREMENTS... L4-2 L4.3.1. Voltage Control Device Operation and Special Service Requirements... L4-2 L4.3.2. Connecting and Separating from the Power System... L4-2 L4.3.3. Clearances and Switching Requests... L4-2 ii

L4.3.4. Unusual or Emergency Conditions... L4-2 L4.3.5. Other Communications... L4-3 L4.4. UNATTENDED LOAD FACILITIES REQUIREMENTS... L4-4 L4.4.1. Verification of Energized Circuit... L4-4 L4.4.2. Separation/Restoration... L4-4 L4.5. SPECIAL SERVICE REQUIREMENTS... L4-4 L4.6. LOAD ENTITY OR TRANSMISSION ENTITY INTERFERENCE WITH POWER QUALITY... L4-4 SECTION L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES... L5-1 PURPOSE... L5-1 L5.1. TESTS REQUIRED FOR LOAD ENTITIES PRIOR TO ENERGIZING... L5-1 L5.1.1. Proving Insulation... L5-1 L5.1.2. Proving Ratios... L5-2 L5.1.3. Circuit Breakers and Circuit Switchers... L5-2 L5.1.4. Current Transformers and Current Circuits... L5-2 L5.1.5. Relays... L5-3 L.5.1.6. Primary Disconnect Switch... L5-3 L.5.1.7. Station Battery... L5-3 L5.2. ENERGIZING... L5-3 L5.3. GENERAL NOTES... L5-4 CONTACT INFORMATION SHEET... L5-5 SECTION G1: METERING REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES... G1-1 PURPOSE:... G1-1 APPLICABILITY... G1-1 G1.1. BASIC METERING REQUIREMENTS FOR GENERATORS... G1-1 G1.2. DETAILED METERING REQUIREMENTS FOR GENERATORS... G1-3 G1.2.2. Metering Configurations For New Generators... G1-3 G1.2.3. Metering Requirements For New Generators... G1-3 G1.2.3.1. Wholesale Generators... G1-3 G1.2.3.2. Metering Generator s Loads... G1-4 G1.3. TELEMETERING REQUIREMENTS FOR GENERATOR MONITORING... G1-4 G1.3.1. For New Generation Facilities 1,000 kw or Greater... G1-4 G1.3.2. For New Generation Facilities Less Than 1,000 kw... G1-4 G1.4. METERING CURRENT AND VOLTAGE TRANSFORMERS FOR GENERATORS... G1-4 SECTION G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES... G2-1 PURPOSE... G2-1 APPLICABILITY... G2-1 G2.1. PROTECTIVE RELAY REQUIREMENTS... G2-1 G2.2. RELIABILITY AND REDUNDANCY... G2-3 G2.3. RELAY GRADES... G2-4 G2.4. LINE PROTECTION... G2-4 G2.5. GENERATOR PROTECTION AND CONTROL... G2-7 G2.5.1. Phase Overcurrent... G2-9 G2.5.2. Over/Undervoltage Relay... G2-9 G2.5.3. Over/Underfrequency Relay... G2-9 G2.5.4. Ground and Phase Fault Sensing Scheme... G2-9 G2.5.4.1. General:... G2-9 G2.5.4.2. Ground Grid Requirements... G2-9 G2.5.5. Overcurrent Relay with Voltage Restraint/Voltage Control or Impedance Relay... G2-10 G2.5.6. Reverse Power Relay... G2-10 G2.6. DEDICATED TRANSFORMER... G2-10 G2.7. MANUAL DISCONNECT SWITCH... G2-11 G2.7.1. General... G2-11 iii

G2.7.2. Specifications... G2-12 G2.8. FAULT-INTERRUPTING DEVICES... G2-12 G2.8.1. Circuit Breakers... G2-12 G2.8.2. Circuit Switchers... G2-13 G2.8.3. Relay Class Current Transformers (CT)... G2-13 G2.9. SYNCHRONOUS GENERATORS... G2-13 G2.9.1. Synchronizing Relays... G2-13 G2.9.1.1. Automatic Synchronizers Approved by PG&E See Table G2-4 for PG&E-approved devices.. G2-14 G2.9.1.2. Automatic Synchronizers (not on PG&E s approved list) Supervised by a PG&E-Approved Synchronizing Relay... G2-14 G2.9.1.3. Manual Synchronization Supervised by a Synchronizing Relay... G2-14 G2.9.1.4. Manual Synchronization With Synch-Check Relay... G2-15 G2.9.2. Frequency/Speed Control... G2-15 G2.9.3. Excitation System Requirements... G2-15 G2.9.4. Voltage Regulator... G2-16 G2.9.5. Power Factor Controller... G2-17 G2.10. INDUCTION GENERATORS... G2-17 G2.11. DC GENERATORS... G2-17 G2.11.1. Inverters Capable of Stand-Alone Operation... G2-17 G2.11.2. Inverters Incapable of Stand-Alone Operation... G2-18 G2.12. SPECIAL PROTECTION SYSTEMS... G2-19 G2.13. REMEDIAL ACTION SCHEME (RAS) PARTICIPATION REQUIREMENT FOR GENERATION FACILITIES... G2-19 G2.14. EVENT RECORDER... G2-20 G2.15. EMERGENCY GENERATOR REQUIREMENTS... G2-20 G2.15.1. Break Before Make... G2-20 G2.15.2. Make Before Break... G2-20 G2.15.3. Interconnection Requirements... G2-20 G.2.15.3.1. Interconnection Protection Study... G2-21 G.2.15.3.2. Transfer Switch... G2-21 G.2.15.3.3. Notification and Documentation... G2-21 G2.15.3.4. Operation/Clearance... G2-21 G2.15.3.5. Break Before Make Specific Requirements... G2-21 G2.15.3.5.1. Transfer Switch... G2-21 G2.15.3.6. Make Before Break Requirements... G2-22 G2.15.3.6.1. Transfer Switch... G2-22 G2.15.3.6.2. Manual Disconnect... G2-22 G2.15.3.6.3. Synchronizing Function... G2-22 G2.15.3.6.4. Protection... G2-23 G2.15.3.6.5. Dedicated Transformer... G2-23 G2.16. PARALLEL-ONLY (NO SALE) GENERATOR REQUIREMENT... G2-23 G2.17. GENERATION ENTITY-OWNED PRIMARY OR TRANSMISSION VOLTAGE TAP LINES (60 KV AND ABOVE)... G2-24 G2.18. PG&E PROTECTION AND CONTROL SYSTEM CHANGES WHICH MAY BE REQUIRED TO ACCOMMODATE GENERATOR INTERCONNECTION... G2-24 G2.19. DIRECT TELEPHONE SERVICE... G2-25 G2.20. STANDBY STATION SERVICE... G2-25 G2.21. STATION BATTERY... G2-25 SECTION G3: OPERATING REQUIREMENTS FOR TRANSMISSION GENERATIN ENTITIES... G3-1 PURPOSE... G3-1 APPLICABILITY... G3-1 G3.1. REACTIVE AND VOLTAGE COLTROL REQUIREMENTS FOR GENERATORS... G3-1 G3.1.1. Synchronous Generator Control... G3-2 G3.1.1.1. Frequency/Speed Control... G3-2 G3.1.1.2. Voltage Control... G3-2 G3.1.1.3. Power System Stabilizer Operating Requirements For Generators... G3-2 G3.1.1.4. Power Factor Control... G3-2 G3.1.2. Non-Synchronous Generator Control (without Var Control)... G3-3 iv

G3.1.2.2. Induction Generators Larger Than 40 kw... G3-3 G3.1.3. Inverter-Based Generating Facilities... G3-3 G3.2. GENERATOR STEP-UP TRANSFORMER... G3-4 G3.3. POWER QUALITY REQUIREMENTS... G3-4 G3.3.1. Voltage Fluctuation Limits... G3-4 G3.3.2. Harmonic Limits... G3-4 G3.4. VOLTAGE RIDE-TROUGH REQUIREMENTS... G3-5 SECTION G4: OPERATING PROCEDURES FOR TRANSMISSION GENERATION ENTITIES... G4-1 PURPOSE... G4-1 APPLICABILITY... G4-1 G4.1. JURISDICTION OF THE CAISO AND THE PG&E GRID CENTER (GCC)... G4-1 G4.2. COMMUNICATIONS... G4-1 G4.2.1. Daily Capacity and Energy Reports... G4-2 G4.2.2. Voltage Control Operation and Other Service Requirements... G4-2 G4.2.3. Paralleling to and Separating from PG&E (Attended Generating Facilities Only)... G4-3 G4.2.4. Clearances and Switching Requests... G4-3 G4.2.5. Unusual or System Emergency Conditions... G4-3 G4.2.6. Emergency/Backup Generators... G4-4 G4.2.7. Other Communications... G4-4 G4.3. UNATTENDED GENERATING FACILITIES... G4-5 G4.3.1. Verification of Energized Circuit... G4-5 G4.3.2. Loss of Power/Automatic Re-paralleling... G4-5 G4.3.3. Event Recorder... G4-6 G4.4. PROCEDURES ON TRANSFER TRIP PROTECTION FOR GENERATION FACILITIES... G4-6 G4.4.1. Purpose and Definition... G4-6 G4.4.2. Separation Following Loss of Transfer-Trip Protection... G4-7 G4.4.3. Procedures... G4-7 G4.4.4. Separation Orders... G4-8 G4.4.5. Non-Compliance Separation Order... G4-8 G4.4.5. Re-parallel of Generating Facility After Restoration of TT Protection... G4-8 G4.5. GENERATION ENTITY INTERFERENCE WITH POWER QUALITY... G4-9 SECTION G5: ENERGIZATION AND SYNCHRONIZATION REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES... G5-1 PURPOSE... G5-1 G5.1. TEST RESULTS AND/OR INFORMATION REQUIRED PRIOR TO PRE-PARALLEL TESTING... G5-1 G5.1.1. Proving Insulation... G5-1 G5.1.2. Proving Ratios... G5-2 G5.1.3. Circuit Breakers and Circuit Switchers... G5-2 G5.1.4. Current Transformers and Current Circuits... G5-2 G5.1.5. Relays... G5-3 G5.1.6. Primary Disconnect Switch... G5-3 G5.1.7. RTU/RIG/DPU... G5-3 G5.1.8. Station Battery... G5-3 G5.2. PRE-PARALLEL INSPECTION (PPI)... G5-3 G5.2.1. Functional Tests... G5-4 G.5.2.2. Data Telemetry Tests... G5-4 G5.3. REQUIREMENTS FOR PARALLEL GENERATOR OPERATION... G5-5 G5.3.1. Clearance for Parallel Operation (For Testing Purposes Only)... G5-5 G5.3.2. Impedance and Directional Relay Tests... G5-5 G5.3.3. Generator Load Tests... G5-6 G5.3.4. Power System Stabilizer (PSS)... G5-6 G5.3.5. Model Testing and Validation Report... G5-8 G5.3.6. Signage Requirements... G5-8 v

G5.4. PERMISSION TO COMMENCE COMMERCIAL OPERATION... G5-8 G5.5. GENERAL NOTES... G5-9 SECTION G6: SITING POLICY AND REQUIREMEENTS FOR TRANSMISSION GENERATION ENTITIES... G6-1 PURPOSE... G6-1 APPLICABILITY... G6-1 POLICY... G6-1 G6.1. CRITERIA FOR NEW OR PROPOSED RE-POWERING PROJECTS... G6-1 G6.1.1. 60/70 kv, 115kV, 230kV & 500kV TRANSMISSION FACILITIES... G6-1 G6.1.2. GENERATOR TAP LINES... G6-1 APPENDIX A: WHERE TO OBTAIN REFERENCE DOCUMENTS AND INFORMATION... AA-1 APPENDIX D: ENGINEERING NUMBERED DOCUMENTS... AD-1 APPENDIX F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES... AF-1 F.0. NOTIFICATION... AF-2 F.1. APPLICATIONS... AF-2 F.2. GENERAL REQUIREMENTS... AF-3 F2.1. EMS/SCADA Telemetering... AF-4 F2.1.1. SCADA Telemetering for all Generation Facilities... AF-4 F2.1.2. EMS/SCADA Telemetering for Generation Facilities 1 MW or Greater... AF-5 F2.2. Protection... AF-6 F2.3. Business Telephone and Revenue Metering... AF-9 F2.4. Environmental Considerations.... AF-9 F.3. INSTALLATION OF LEC ENTRANCE CABLE IN SUBSTATIONS (RISK - SEE SECTION F.0. NOTIFICATION)... AF-10 F.4. CIRCUIT REQUIREMENTS FOR PROTECTIVE RELAYING AND EMS/SCADA CIRCUITS INSTALLED BETWEEN GENERATION FACILITY STATIONS AND PG&E POWER SUBSTATIONS (RISK - SEE SECTION F.0. NOTIFICATION)... AF-10 F.5. ADDITIONAL DIRECT TRANSFER TRIP (DTT) TELECOMMUNICATION OPTIONS... AF-12 F.5.1. Option 1. All Fiber... AF-12 F.5.2. Option 2. Fiber / Channelized T1 using fiber based HVP protection... AF-13 F5.3. Option 3 - Copper / Channelized T1 using copper HVP... AF-14 F.6. DEFINITIONS... AF-15 F7.0 FIGURES... AF-17 APPENDIX H: POWER SYSTEM STABILIZER... AH-1 APPENDIX I: LOAD OPERATING AGREEMENT... AI-1 PURPOSE... AI-1 APPLICABILITY... AI-1 ATTACHMENT... AI-1 APPENDIX J: SPECIAL AGREEMENT FOR ELECTRICAL STANDBY SERVICE... AJ-1 PURPOSE... AJ-1 APPLICABILITY... AJ-1 RELEVANT DOCUMENTS... AJ-1 APPENDIX K: LOAD SPECIAL FACILITIES AGREEMENT... AK-1 APPENDIX L: INTERCONNECTION AGGREMENTS FOR GENERATORS CONNECTING TO THE ISO CONTROLLED GRID... AL-1 PURPOSE AND APPLICABILITY... AL-1 RELEVANT DOCUMENTS... AL-1 APPENDIX M: GENERATION INTERCONNECTION DATA SHEET... AM-1 vi

APPENDIX N: GENERATOR DATA SHEET FOR SYNCHRONOUS GENERATORS CONNECTED TO PG&E ELECTRIC SYSTEM... AN-1 APPENDIX Q: GENERATOR AUTOMATIC SYNCHRONIZERS FOR GENERATION ENTITIES... AQ-1 Q1.1. OPERATION AND PERFORMANCE REQUIREMENTS...AQ-1 APPENDIX R: PROTECTIVE RELAY REQUIREMENTS AND APPROVALS... AR-1 R.1. REQUIREMENTS... AR-2 APPENDIX S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS... AS-1 S1. STANDARD INTERCONNECTION METHODS WITH TYPICAL CIRCUIT CONFIGURATION FOR SINGLE OR MULTIPLE UNITS... AS-1 S1.1. Generator Connected Into a Ring Bus... AS-1 S1.2. Generator Connected Into a Breaker-and A-Half (BAAH) Bus... AS-1 S1.3. Bus Fault Clearing... AS-2 S2. INTERCONNECTION METHODS WITH SPECIAL CIRCUIT CONFIGURATIONS FOR SINGLE UNIT... AS-2 S2.1. Alternative--Generator Tapping To Existing Transmission Line between Two Terminals, considered only at voltages below 230kV... AS-2 S2.3. Generator Tapping closely outside the Substation Between Two Existing Terminals... AS-3 S2.4. Generator Connected Close Outside the Substation with a Dedicated Line... AS-4 S2.5. Requirements for S2.3 and S2.4 Alternatives... AS-4 S2.6. Additional Items for Consideration... AS-5 APPENDIX T: BATTERY REQUIREMENTS FOR INTERCONNECTION TO PG&E SYSTEM... AT-1 vii