I/O Choices for the ATLAS. Insertable B Layer (IBL) Abstract. Contact Person: A. Grillo

Size: px
Start display at page:

Download "I/O Choices for the ATLAS. Insertable B Layer (IBL) Abstract. Contact Person: A. Grillo"

Transcription

1 I/O Choices for the ATLAS Insertable B Layer (IBL) ATLAS Upgrade Document No: Institute Document No. Created: 14/12/2008 Page: 1 of 2 Modified: 8/01/2009 Rev. No.: 1.00 Abstract The ATLAS Pixel System Design Task Force for SLHC Upgrade has looked at the needed requirements of the R/O links for the Insertable B-Layer (IBL). In this document are summarised the issues that have to be considered for their design and implementations. Whenever possible, at this stage of the system knowledge, the task force makes their recommendations for the preferred options. Contact Person: A. Grillo Prepared by: ATLAS Pixel System Design Task Force for SLHC Upgrade A. Grillo, F. Anghinolfi, M.B. Barbero, R. Beccherle, G. Darbo, F. Philippe, D. Ferrere, M. Garcia-Sciveres, T.B. Huffman, S. Kersten, S. Malyukov, D.J. Nelson, F. Hügging. Checked by: Approved by: ATLAS Pixel Upgrade Distribution List

2 ATLAS Project Document No: Page: 2 of 7 Version Date Description of changes 1.0 8/1/09 Document for general distribution

3 ATLAS Project Document No: Page: 3 of 7 1 Introduction In the course of discussing the I/O options for the FE-I4 for the SLHC and the IBL as well as the services chain for the IBL, the task force has arrived at the following set of recommendations for the IBL. It is recognized that these may very well be different for the SLHC pixel system and may require different I/O components for the FE-I4 chip, but given the different development schedules for IBL and SLHC and the likely different system environment, this may be unavoidable. Again given the nature of the IBL plan with a relatively short time for development and the need to install during a close-to-normal LHC down period plus very minimal commissioning time, preference was given to maintaining as much of the existing system architecture as possible. The recommendations embody the simplest way to meet the IBL requirements using existing elements. This path should minimize needed development, cost, and integration time with the existing, running detector. Because the IBL is a relatively small system, it is unlikely that new elements could be qualified and understood at the same level as the elements already in use in the present detector. Therefore, we favor using existing elements wherever they meet requirements. This is not to say that no validation would be needed. Work towards a vertical slice system test should begin as soon as possible. In this case, the use of existing components makes it possible to begin system-testing parts of the I/O chain right away, whereas such testing would come much later if the components had to be developed. In particular, the end-of-stave to opto-board electrical communication can be prototyped immediately as proposed. The decision to use existing elements wherever possible has the implicit assumption that those elements continue to function adequately in the present detector. This is in fact a necessary condition to begin with, because the IBL is not a stand-alone detector, but rather an add-on to the present detector, such that if the present detector were to cease to function the reliability of the IBL would be irrelevant. We have also assumed that the IBL inherits its as-built quality requirements from the present B-Layer, and these can therefore be achieved using existing elements (because it was achieved -exceeded in fact- for the present B-Layer). 2 Data Rates for Output Links The simulations for a B-Layer at 3.7 cm radius and a luminosity of x3 LHC indicate that a data rate of at least 86 Mbps per FE-I4 is required. This estimate assumes the same data encoding as presently used by the Pixel FE-I3 chip and does not include any safety factor. Some improved efficiency might be gained by a more sophisticated encoding of the hit data but some safety margin is also needed to allow for the ~30% uncertainty in the occupancy simulation and for possible extra overhead to add a more sophisticated transmission encoding. Therefore, the output bandwidth requirement has been set at 160 Mbps for each front-end chip. Given that the envisioned stave will consist of a single row of FE-I4 chips, the concept for the data output link would be one per chip running at 160 Mbps. An alternate estimate that has smaller uncertainty also leads to 160 Mbps per chip bandwidth. This estimate simply scales the existing layers 1 and 2 (L1 and L2) maximum bandwidth to 3.7 cm radius using relative hit rates from simulation. The relative hit rates have smaller uncertainty than the absolute hit rate (for example there is no uncertainty from the minimum bias cross section). The 8(4) Mbps/cm 2 for L1(L2) scales to 120 Mbps/FE-I4 at 3.7 cm. This assumes that bandwidth scales exactly like hit rate, which is conservative because in FE-I4 one has 4-bit TOT instead of 8-bit, and the higher the hit rate the

4 ATLAS Project Document No: Page: 4 of 7 smaller the overhead due to headers and trailers. There is no need to add a safety margin to such an estimate because the maximum L1 and L2 and width are already fixed. Therefore, 120 Mbps is the maximum FE-I4 net bandwidth (before DC balancing overhead) that is useful for IBL. 3 Clock and Command Two options were considered: sending a 40 MHz clock and providing a clock multiplier on the FE-I4 or sending an 80 MHz clock and using both clock edges as is now done at 40 MHz to achieve the 160 Mbps data output. The former option would allow the TTC chain to operate as it now does but requires a new clock multiplier circuit on the front-end readout chip. The latter would require modifications to the BOC and possibly the ROD to produce the higher speed TTC. Additionally, a synchronization protocol would have to be developed and built into FE-I4 to provide for the correct phasing of the beam crossings to the 80 MHz clock. It would also require a new DORIC chip to decode the clock at twice the frequency. While the BOC and some parts of the ROD will have to be modified in any case to handle the higher bandwidth data stream, being able to keep the TTC chain as presently designed including using the existing DORIC chip and not modifying the ROD & BOC to generate an 80 MHz clock and command stream was considered a very positive aspect of the 40 MHz clock scheme. A first discussion with the FE-I4 designers did not raise any serious concerns about the implementation of a clock multiplier, however, this circuit will need to be designed and its robustness tested, especially against possible upsets from SEU. Also, the present thinking for the upgrade strip readout calls for a clock multiplier in the module controller chip. The design of such a circuit for the IBL could likely be used for the upgrade strip readout as well. In keeping with the idea to maintain as much of the present TTC link as possible, the proposal is to take the decoded clock (40 MHz) and commands (40 Mbps) from the DORIC and propagate them as separate LVDS lines from the opto-boards to the FE-I4s. Furthermore, it should be possible at this frequency to connect two FE-I4 chips to each of the LVDS clock and command lines thus reducing the number of electrical links by a factor of two. 4 Data Output Links As stated above the data output links must run at 160 Mbps, one link from each FE-I4. These LVDS links will run to the opto-boards where a VDC chip and VCSEL will convert them to optical, one optical link per LVDS link. No further multiplexing or encoding will be done on the opto-boards. Given that the data rate will be four times the base clock rate at the BOC/ROD and that the shorter clock period for the data makes phase adjustments more critical, it has been decided to provide some encoding of the data at the front-end chip such that the data clock can be re-synchronized to the data back at the BOC. Preliminary investigation indicates that 8bit/10bit encoding is adequate for this purpose and there should be sufficient bandwidth to accommodate it. The FE-I4 chip will have to encode the output data and the BOC decode and re-synchronize the receiving clock. We believe that these BOC functions can be accomplished in an FPGA and firmware to do it may already exist in the public domain. Likewise, the 8bit/10bit scheme is so widely used that examples of the necessary circuitry for the FE-I4 may also exist.

5 ATLAS Project Document No: Page: 5 of 7 The actual encoding of hit information in the FE-I4 (e.g. header, hit address, TOT, etc.) is still under development and no firm proposal is yet ready. 5 BOC/ROD The BOC will need to be redesigned to handle receipt of the 160 MHz data stream and to decode the 8bit/10bit data to its raw form. The simplest adaptation will be to have the BOC hand off the data to the ROD as four 40 Mbps data streams for each input link as it now separates the 80 Mbps data stream into two 40 Mbps streams. This will minimize changes to the ROD and require still one S-Link per BOC/ROD but will mean more new RODs are required. It may be possible by the substitution of faster versions of some of the ROD FPGAs for the BOC to pass 80 Mbps data streams to the ROD, however, then two S-Links would be required per BOC/ROD. These decisions require more study by the BOC and ROD designers. In any case a strong requirement is that the RODs built for the IBL be backward compatible with the existing ROD so that they can be used as spares for the present system. 6 Possible Opto-board Upgrade There has been discussion about possible upgrades to the existing opto-board as part of the IBL project. In particular, it has been suggested that some redundancy could be added to allow dead TTC or Data Out links to be replaced by spare channels. Also, separate control of the VCSEL optical power would improve robustness. These added features would have been helpful for the existing system and should be seriously considered for the SLHC upgrade, however, they appear not to be a good use of scarce resources for the IBL project. If these enhancements were designed into new opto-boards, they would be used only for the new IBL and not for the existing Pixel layers since no access to those opto-boards is planned. This means that the enhanced opto-boards would only improve the reliability of a small fraction of the Pixel system, one that is expected to have a much shorter lifetime than the larger fraction already installed and required to continue operation with the IBL. Also, these new opto-boards will be positioned at a larger, safer radius and accessible during yearly down periods. Therefore, it is recommended not to include these upgrades to the opto-board for the IBL if the existing components are verified to meet the requirements. Improvements could instead be made to the optical receivers on the BOC such that they could be tuned over a wider range. This could mitigate the lack of individual control of VCSEL optical power on the VCSEL arrays inside the detector for both the existing layers as well as the new IBL. 7 DCS and Interlocks The general plan is to use the same components that are used in the present Pixel system, however, more study is needed to determine the exact configuration and location of components. This will be covered in a future document. 8 Near Term Tests Several aspects of this proposed plan for the IBL should be tested in the very near future. Reliable electrical transmission of DC balanced 160 Mbps signals over the estimated 4 meters from FE-I4 chips to

6 ATLAS Project Document No: Page: 6 of 7 the planed location of opto-boards should be verified. The LVDS test chip recently fabricated can be used for this. The ability of the existing VDC chip to drive 160 Mbps must be tested. Likewise the reliability of the present DORIC chip to transmit 40 MHz clock and 40 Mbps commands over the same 4 m must be verified, as well as the possibility of two FE-I4 chips sharing the same clock and command signals. A test of this services chain using an existing opto-board and the LVDS test chip should be employed as soon as possible as the results of these tests impact these architectural decisions. To assure that there is some margin for the 4 m transmission, testing at 4 m, 5 m and 6 m should be attempted. 9 Options to Keep in Design for the Near Term Some options should be included in the FE-I4 design. The FE-I4 command set should include a reset-clock-multiplier command, which can be used to reset the clock multiplier circuit if it should be upset. Since the bulk of the FE-I4 chip including the command decoder will run off the 40 MHz clock, this is quite possible. The FE-I4, for the time being, should be provided with a second 80 MHz clock input and the option to either use the result of the clock multiplier or this alternate input. If the above tests show some difficulty transmitting data at 160 Mbps, pre-emphasis circuitry can be added to the FE-I4 output drivers. Likewise, if the present DORIC has trouble with reliable transmission of clock and command signals over 4 m, an LVDS buffer chip with pre-emphasis can be added or similar pre-emphasis circuitry could be added to the DORC outputs in a modified chip.

7 ATLAS Project Document No: Page: 7 of 7 10 Summary of IBL I/O Recommendations TTC Optical Downlink Electrical links DORC to FE-I4 Data Output Electrical link FE-I4 to VDC Optical Uplink BOC/ROD TTC Data Input BPM encoded 40 MHz clk and 40 Mbps commands 2x LVDS 40 MHz clk & 40 Mbps commands Each link drives two FE-I4 chips One LVDS / FE-I4 at 160 Mbps Encoded as 8bit/10bit One optical link/fe-i4 at 160 Mbps 40 MHz/40 Mbps BPM encoded as present system 160 Mbps input links 8bit/10bit decoded in BOC Data passed to ROD as 4 x 40 Mbps streams 8 input links per BOC/ROD

Radiation-Hard ASICS for Optical Data Transmission in the First Phase of the LHC Upgrade

Radiation-Hard ASICS for Optical Data Transmission in the First Phase of the LHC Upgrade Radiation-Hard ASICS for Optical Data Transmission in the First Phase of the LHC Upgrade A. Adair, W. Fernando, K.K. Gan, H.P. Kagan, R.D. Kass, H. Merritt, J. Moore, A. Nagarkar, S. Smith, M. Strang The

More information

Summary of Optical Link R&D

Summary of Optical Link R&D Summary of Optical Link R&D K.K. Gan The Ohio State University November 6, 2008 K.K. Gan ATLAS Tracker Upgrade Workshop 1 Outline Introduction Plan for insertable B-layer Status of Versatile Link Project

More information

Results on Array-based Opto-Links

Results on Array-based Opto-Links Results on Array-based Opto-Links, H.P. Kagan, R.D. Kass, H. Merritt, J. Moore, A. Nagarkar, D. Pignotti, S. Smith, M. Strang The Ohio State University P. Buchholz, A. Wiese, M. Ziolkowski Universität

More information

Tracker Optical Link Upgrade Options and Plans

Tracker Optical Link Upgrade Options and Plans Tracker Optical Link Upgrade Options and Plans K.K. Gan The Ohio State University July 19, 2005 K.K. Gan ATLAS Tracker Upgrade Workshop 1 Outline current pixel/strip opto-links lessons learned upgrade

More information

A Possible Redundancy System for Opto-Links

A Possible Redundancy System for Opto-Links A Possible Redundancy System for Opto-Links A. Adair, W. Fernando, K.K. Gan, H.P. Kagan, R.D. Kass, H. Merritt, J. Moore, A. Nagarkar, S. Smith, M. Strang The Ohio State University P. Buchholz, A. Wiese,

More information

MCC-DSM Specifications

MCC-DSM Specifications DETECTOR CHIP BUMP ELECTRONIC CHIP MCC Design Group Receiver Issue: Revision: 0.1 Reference: ATLAS ID-xx Created: 30 September 2002 Last modified: 7 October 2002 03:18 Edited By: R. Beccherle and G. Darbo

More information

Prototype Opto Chip Results

Prototype Opto Chip Results Prototype Opto Chip Results K.K. Gan, H.P. Kagan, R.D. Kass, J. Moore, S. Smith The Ohio State University Nov 5, 2008 K.K. Gan ATLAS Tracker Upgrade Workshop 1 Outline Introduction VCSEL driver chip PIN

More information

The Phase-2 ATLAS ITk Pixel Upgrade

The Phase-2 ATLAS ITk Pixel Upgrade The Phase-2 ATLAS ITk Pixel Upgrade T. Flick (University of Wuppertal) - on behalf of the ATLAS collaboration 14th Topical Seminar on Innovative Particle and Radiation Detectors () 03.-06. October 2016

More information

Radiation-Hard/High-Speed Parallel Optical Links

Radiation-Hard/High-Speed Parallel Optical Links Radiation-Hard/High-Speed Parallel Optical Links K.K. Gan, H. Kagan, R. Kass, J. Moore, D.S. Smith The Ohio State University P. Buchholz, M. Ziolkowski Universität Siegen July 3, 2013 K.K. Gan RD13 1 Outline

More information

Upgrading the ATLAS Tile Calorimeter electronics

Upgrading the ATLAS Tile Calorimeter electronics ITIM Upgrading the ATLAS Tile Calorimeter electronics Gabriel Popeneciu, on behalf of the ATLAS Tile Calorimeter System INCDTIM Cluj Napoca, Romania Gabriel Popeneciu PANIC 2014, Hamburg 26th August 2014

More information

Update on PRad GEMs, Readout Electronics & DAQ

Update on PRad GEMs, Readout Electronics & DAQ Update on PRad GEMs, Readout Electronics & DAQ Kondo Gnanvo University of Virginia, Charlottesville, VA Outline PRad GEMs update Upgrade of SRS electronics Integration into JLab DAQ system Cosmic tests

More information

Quad Module Hybrid Development for the ATLAS Pixel Layer Upgrade

Quad Module Hybrid Development for the ATLAS Pixel Layer Upgrade Quad Module Hybrid Development for the ATLAS Pixel Layer Upgrade Lawrence Berkeley National Lab E-mail: kedunne@lbl.gov Maurice Garcia-Sciveres, Timon Heim Lawrence Berkeley National Lab, Berkeley, USA

More information

Status Report of the ATLAS SCT Optical Links.

Status Report of the ATLAS SCT Optical Links. Status Report of the ATLAS SCT Optical Links. D.G.Charlton, J.D.Dowell, R.J.Homer, P.Jovanovic, T.J. McMahon, G.Mahout J.A.Wilson School of Physics and Astronomy, University of Birmingham, Birmingham B15

More information

Construction of the Phase I upgrade of the CMS pixel detector

Construction of the Phase I upgrade of the CMS pixel detector Forward Pixel Barrel Pixel TECHNOLOGY AND INSTRUMENTATION IN PARTICLE PHYSICS 2017, May 22-26, 2017 Construction of the Phase I upgrade of the CMS pixel detector Satoshi Hasegawa Fermi National Accelerator

More information

Module Performance Report. ATLAS Calorimeter Level-1 Trigger- Common Merger Module. Version February-2005

Module Performance Report. ATLAS Calorimeter Level-1 Trigger- Common Merger Module. Version February-2005 Module Performance Report ATLAS Calorimeter Level-1 Trigger- Common Merger Module B. M. Barnett, I. P. Brawn, C N P Gee Version 1.0 23 February-2005 Table of Contents 1 Scope...3 2 Measured Performance...3

More information

LHC Detector Upgrades

LHC Detector Upgrades Su Dong SLAC Summer Institute Aug/2/2012 1 LHC is exceeding expectations in many ways Design lumi 1x10 34 Design pileup ~24 Rapid increase in luminosity Even more dramatic pileup challenge Z->µµ event

More information

CMX (Common Merger extension module) Y. Ermoline for CMX collaboration Preliminary Design Review, Stockholm, 29 June 2011

CMX (Common Merger extension module) Y. Ermoline for CMX collaboration Preliminary Design Review, Stockholm, 29 June 2011 (Common Merger extension module) Y. Ermoline for collaboration Preliminary Design Review, Stockholm, 29 June 2011 Outline Current L1 Calorimeter trigger system Possible improvement to maintain trigger

More information

THE ALFA TRIGGER SIMULATOR

THE ALFA TRIGGER SIMULATOR Vol. 46 (2015) ACTA PHYSICA POLONICA B No 7 THE ALFA TRIGGER SIMULATOR B. Dziedzic Tadeusz Kościuszko Cracow University of Technology, Institute of Physics Podchorążych 1, 30-084 Kraków, Poland K. Korcyl

More information

The new detector readout system for the ATLAS experiment

The new detector readout system for the ATLAS experiment LInk exange The new detector readout system for the ATLAS experiment Soo Ryu Argonne National Laboratory On behalf of the ATLAS Collaboration ATLAS DAQ for LHC Run2 (2015-2018) 40MHz L1 trigger 100kHz

More information

Ignacy Kudla, Radomir Kupczak, Krzysztof Pozniak, Antonio Ranieri

Ignacy Kudla, Radomir Kupczak, Krzysztof Pozniak, Antonio Ranieri *** Draft *** 15/04/97 *** MK/RK/KTP/AR *** ***use color print!!!*** RPC Muon Trigger Detector Control Ignacy Kudla, Radomir Kupczak, Krzysztof Pozniak, Antonio Ranieri $Ã&06 Ã*(1(5$/ RPC Muon Trigger

More information

CMS Tracker PLL Reference Manual

CMS Tracker PLL Reference Manual CMS Tracker PLL Reference Manual P. Placidi, A. Marchioro and P. Moreira CERN - EP/MIC, Geneva Switzerland July 2 Version 2. Clock and Trigger Distribution 3 ASIC architecture...4 I2C Interface 6 Tracker

More information

BES-III off-detector readout electronics for the GEM detector: an update

BES-III off-detector readout electronics for the GEM detector: an update BES-III off-detector readout electronics for the GEM detector: an update The CGEM off-detector collaboration ( INFN/Univ. FE, INFN LNF, Univ. Uppsala ) 1 Outline Reminder Update on development status Off-detector

More information

First experiences with the ATLAS pixel detector control system at the combined test beam 2004

First experiences with the ATLAS pixel detector control system at the combined test beam 2004 Nuclear Instruments and Methods in Physics Research A 565 (2006) 97 101 www.elsevier.com/locate/nima First experiences with the ATLAS pixel detector control system at the combined test beam 2004 Martin

More information

Electronics on the detector Mechanical constraints: Fixing the module on the PM base.

Electronics on the detector Mechanical constraints: Fixing the module on the PM base. PID meeting Mechanical implementation ti Electronics architecture SNATS upgrade proposal Christophe Beigbeder PID meeting 1 Electronics is split in two parts : - one directly mounted on the PM base receiving

More information

Modules and Front-End Electronics Developments for the ATLAS ITk Strips Upgrade

Modules and Front-End Electronics Developments for the ATLAS ITk Strips Upgrade Modules and Front-End Electronics Developments for the ATLAS ITk Strips Upgrade Carlos García Argos, on behalf of the ATLAS ITk Collaboration University of Freiburg International Conference on Technology

More information

CMX Hardware Status. Chip Brock, Dan Edmunds, Philippe Yuri Ermoline, Duc Bao Wojciech UBC

CMX Hardware Status. Chip Brock, Dan Edmunds, Philippe Yuri Ermoline, Duc Bao Wojciech UBC Hardware Status Chip Brock, Dan Edmunds, Philippe Laurens@MSU Yuri Ermoline, Duc Bao Ta @CERN Wojciech Fedorko @ UBC Michigan State University 25-Oct-2013 Outline Review of hardware project (Some) hardware

More information

Electrical Data Transmission

Electrical Data Transmission Electrical Data Transmission ACES Workshop Martin Kocian 8 March 2015 Martin Kocian (SLAC) Electrical Data Transmission 8 March 2015 1 / 23 Why copper links? High levels of radiation close to the beam

More information

Prototyping of large structures for the Phase-II upgrade of the pixel detector of the ATLAS experiment

Prototyping of large structures for the Phase-II upgrade of the pixel detector of the ATLAS experiment Prototyping of large structures for the Phase-II upgrade of the pixel detector of the ATLAS experiment Diego Alvarez Feito CERN EP-DT On Behalf of the ATLAS Collaboration 2017 IEEE NSS and MIC 26/10/2017

More information

Token Bit Manager for the CMS Pixel Readout

Token Bit Manager for the CMS Pixel Readout Token Bit Manager for the CMS Pixel Readout Edward Bartz Rutgers University Pixel 2002 International Workshop September 9, 2002 slide 1 TBM Overview Orchestrate the Readout of Several Pixel Chips on a

More information

2008 JINST 3 S Online System. Chapter System decomposition and architecture. 8.2 Data Acquisition System

2008 JINST 3 S Online System. Chapter System decomposition and architecture. 8.2 Data Acquisition System Chapter 8 Online System The task of the Online system is to ensure the transfer of data from the front-end electronics to permanent storage under known and controlled conditions. This includes not only

More information

The Track-Finding Processor for the Level-1 Trigger of the CMS Endcap Muon System

The Track-Finding Processor for the Level-1 Trigger of the CMS Endcap Muon System The Track-Finding Processor for the Level- Trigger of the CMS Endcap Muon System D. Acosta, A. Madorsky (Madorsky@phys.ufl.edu), B. Scurlock, S.M. Wang University of Florida A. Atamanchuk, V. Golovtsov,

More information

Improving Packet Processing Performance of a Memory- Bounded Application

Improving Packet Processing Performance of a Memory- Bounded Application Improving Packet Processing Performance of a Memory- Bounded Application Jörn Schumacher CERN / University of Paderborn, Germany jorn.schumacher@cern.ch On behalf of the ATLAS FELIX Developer Team LHCb

More information

The ALICE trigger system for LHC Run 3

The ALICE trigger system for LHC Run 3 The ALICE trigger system for LHC Run 3, D. Evans, K.L. Graham, A. Jusko, R. Lietava, O. Villalobos Baillie and N. Zardoshti School of Physics and Astronomy, The University of Birmingham, Edgbaston, Birmingham,

More information

Status and planning of the CMX. Wojtek Fedorko for the MSU group TDAQ Week, CERN April 23-27, 2012

Status and planning of the CMX. Wojtek Fedorko for the MSU group TDAQ Week, CERN April 23-27, 2012 Status and planning of the Wojtek Fedorko for the MSU group TDAQ Week, CERN April 23-27, 2012 : CMM upgrade Will replace CMM: Backplane rate 40 160Mbs Crate to system rate (LVDS) 40 160Mbs Cluster information

More information

COMPUTER NETWORKS UNIT I. 1. What are the three criteria necessary for an effective and efficient networks?

COMPUTER NETWORKS UNIT I. 1. What are the three criteria necessary for an effective and efficient networks? Question Bank COMPUTER NETWORKS Short answer type questions. UNIT I 1. What are the three criteria necessary for an effective and efficient networks? The most important criteria are performance, reliability

More information

RPC Trigger Overview

RPC Trigger Overview RPC Trigger Overview presented by Maciek Kudla, Warsaw University RPC Trigger ESR Warsaw, July 8th, 2003 RPC Trigger Task The task of RPC Muon Trigger electronics is to deliver 4 highest momentum muons

More information

GLAST Silicon Microstrip Tracker Status

GLAST Silicon Microstrip Tracker Status R.P. Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Mechanical Design Detector Procurement Work list for the Prototype Tracker Construction. ASIC Development Hybrids

More information

Application Note: Optical data transmission with the Avocet Image Sensor

Application Note: Optical data transmission with the Avocet Image Sensor : Optical data transmission with the Avocet Image Sensor This application note presents a reference design for using optical data transmissions with the MLX75411 Avocet image sensor. The MLX75605 optical

More information

Irradiation Results and Transmission on Small Cables/Fiber

Irradiation Results and Transmission on Small Cables/Fiber Irradiation Results and Transmission on Small Cables/Fiber W. Fernando, K.K. Gan, A. Law, H.P. Kagan, R.D. Kass, A. Rau, S. Smith The Ohio State University M.R.M. Lebbai, P.L. Skubic University of Oklahoma

More information

The Design and Testing of the Address in Real Time Data Driver Card for the Micromegas Detector of the ATLAS New Small Wheel Upgrade

The Design and Testing of the Address in Real Time Data Driver Card for the Micromegas Detector of the ATLAS New Small Wheel Upgrade The Design and Testing of the Address in Real Time Data Driver Card for the Micromegas Detector of the ATLAS New Small Wheel Upgrade L. Yao, H. Chen, K. Chen, S. Tang, and V. Polychronakos Abstract The

More information

Copyright 2014 Shaw-Pin Chen

Copyright 2014 Shaw-Pin Chen Copyright 2014 Shaw-Pin Chen Readout Driver Firmware Development for the ATLAS Insertable B-Layer Shaw-Pin Chen A thesis submitted in partial fulfillment of the requirements for the degree of Master of

More information

Scintillator-strip Plane Electronics

Scintillator-strip Plane Electronics Scintillator-strip Plane Electronics Mani Tripathi Britt Holbrook (Engineer) Juan Lizarazo (Grad student) Peter Marleau (Grad student) Tiffany Landry (Junior Specialist) Cherie Williams (Undergrad student)

More information

Study of 1.5m data paths along CALICE slabs

Study of 1.5m data paths along CALICE slabs Study of 1.5m data paths along CALICE slabs the problem & its scale technology and architecture choices test-slab design options current status outlook and plans 1 The problem & its scale Single side of

More information

Timing distribution and Data Flow for the ATLAS Tile Calorimeter Phase II Upgrade

Timing distribution and Data Flow for the ATLAS Tile Calorimeter Phase II Upgrade Timing distribution and Data Flow for the ATLAS Tile Calorimeter Phase II Upgrade Fernando Carrió Argos on behalf of the ATLAS Tile Calorimeter Group Tile Calorimeter Segmented calorimeter of steel plates

More information

Token Ring and. Fiber Distributed Data Interface (FDDI) Networks: Token Ring and FDDI 1

Token Ring and. Fiber Distributed Data Interface (FDDI) Networks: Token Ring and FDDI 1 Token Ring and Fiber Distributed Data Interface (FDDI) Networks: Token Ring and FDDI 1 IEEE 802.5 Token Ring Proposed in 1969 and initially referred to as a Newhall ring. Token ring :: a number of stations

More information

Deployment of the CMS Tracker AMC as backend for the CMS pixel detector

Deployment of the CMS Tracker AMC as backend for the CMS pixel detector Home Search Collections Journals About Contact us My IOPscience Deployment of the CMS Tracker AMC as backend for the CMS pixel detector This content has been downloaded from IOPscience. Please scroll down

More information

Optimizing latency in Xilinx FPGA Implementations of the GBT. Jean-Pierre CACHEMICHE

Optimizing latency in Xilinx FPGA Implementations of the GBT. Jean-Pierre CACHEMICHE Optimizing latency in Xilinx FPGA Implementations of the GBT Steffen MUSCHTER Christian BOHM Sophie BARON Jean-Pierre CACHEMICHE Csaba SOOS (Stockholm University) (Stockholm University) (CERN) (CPPM) (CERN)

More information

Level-1 Data Driver Card of the ATLAS New Small Wheel Upgrade Compatible with the Phase II 1 MHz Readout

Level-1 Data Driver Card of the ATLAS New Small Wheel Upgrade Compatible with the Phase II 1 MHz Readout Level-1 Data Driver Card of the ATLAS New Small Wheel Upgrade Compatible with the Phase II 1 MHz Readout Panagiotis Gkountoumis National Technical University of Athens Brookhaven National Laboratory On

More information

Expected feedback from 3D for SLHC Introduction. LHC 14 TeV pp collider at CERN start summer 2008

Expected feedback from 3D for SLHC Introduction. LHC 14 TeV pp collider at CERN start summer 2008 Introduction LHC 14 TeV pp collider at CERN start summer 2008 Gradual increase of luminosity up to L = 10 34 cm -2 s -1 in 2008-2011 SLHC - major increase of luminosity up to L = 10 35 cm -2 s -1 in 2016-2017

More information

Project Specification Project Name: Atlas SCT HV Power Supply (ASH) Version: V2.04. Project History

Project Specification Project Name: Atlas SCT HV Power Supply (ASH) Version: V2.04. Project History Page 1 of 9 Project Specification Project Name: Atlas SCT HV Power Supply (ASH) Version: V2.04 Project History Version Description Group Date Primary requirements for n-on-n detectors. Voltage range 50-300V.

More information

Status of Control System. Hiroshi Kaji

Status of Control System. Hiroshi Kaji Status of Control System Hiroshi Kaji 2 Introduction The aim of control system is to increase integrated luminosity, which directly affects the accuracy of physics results. Our control system are required

More information

PETsys SiPM Readout System

PETsys SiPM Readout System SiPM Readout System FEB/A_v2 FEB/S FEB/I The SiPM Readout System is designed to read a large number of SiPM photo-sensor pixels in applications where a high data rate and excellent time resolution is required.

More information

Dominique Gigi CMS/DAQ. Siena 4th October 2006

Dominique Gigi CMS/DAQ. Siena 4th October 2006 . CMS/DAQ overview. Environment. FRL-Slink (Front-End Readout Link) - Boards - Features - Protocol with NIC & results - Production.FMM (Fast Monitoring Module) -Requirements -Implementation -Features -Production.Conclusions

More information

SoLID GEM Detectors in US

SoLID GEM Detectors in US SoLID GEM Detectors in US Kondo Gnanvo University of Virginia SoLID Collaboration Meeting @ JLab, 08/26/2016 Outline Design Optimization U-V strips readout design Large GEMs for PRad in Hall B Requirements

More information

SEE Tolerant Self-Calibrating Simple Fractional-N PLL

SEE Tolerant Self-Calibrating Simple Fractional-N PLL SEE Tolerant Self-Calibrating Simple Fractional-N PLL Robert L. Shuler, Avionic Systems Division, NASA Johnson Space Center, Houston, TX 77058 Li Chen, Department of Electrical Engineering, University

More information

CSC Trigger Motherboard

CSC Trigger Motherboard CSC Trigger Motherboard Functions of TMB Tests: Performance at summer 2003 test beam Radiation, magnetic fields, etc. Plans for TMB production and testing 1 Cathode LCT CSC Trigger Requirements Identify

More information

Architectural Differences nc. DRAM devices are accessed with a multiplexed address scheme. Each unit of data is accessed by first selecting its row ad

Architectural Differences nc. DRAM devices are accessed with a multiplexed address scheme. Each unit of data is accessed by first selecting its row ad nc. Application Note AN1801 Rev. 0.2, 11/2003 Performance Differences between MPC8240 and the Tsi106 Host Bridge Top Changwatchai Roy Jenevein risc10@email.sps.mot.com CPD Applications This paper discusses

More information

UNIT-II OVERVIEW OF PHYSICAL LAYER SWITCHING & MULTIPLEXING

UNIT-II OVERVIEW OF PHYSICAL LAYER SWITCHING & MULTIPLEXING 1 UNIT-II OVERVIEW OF PHYSICAL LAYER SWITCHING & MULTIPLEXING Syllabus: Physical layer and overview of PL Switching: Multiplexing: frequency division multiplexing, wave length division multiplexing, synchronous

More information

CMS FPGA Based Tracklet Approach for L1 Track Finding

CMS FPGA Based Tracklet Approach for L1 Track Finding CMS FPGA Based Tracklet Approach for L1 Track Finding Anders Ryd (Cornell University) On behalf of the CMS Tracklet Group Presented at AWLC June 29, 2017 Anders Ryd Cornell University FPGA Based L1 Tracking

More information

Radiation Abort Policy

Radiation Abort Policy Radiation Abort Policy My completely unbiased summary Fair and Balanced (TM) Talks from Maarten, Brian, Gabrielle, Michael, Toru, Witold, Tanja, John and plenty of discussion during and after the talks

More information

outline Reliable State Machines MER Mission example

outline Reliable State Machines MER Mission example outline Reliable State Machines Dr. Gary R Burke California Institute of Technology Jet Propulsion Laboratory Background JPL MER example JPL FPGA/ASIC Process Procedure Guidelines State machines Traditional

More information

Optimal Management of System Clock Networks

Optimal Management of System Clock Networks Optimal Management of System Networks 2002 Introduction System Management Is More Challenging No Longer One Synchronous per System or Card Must Design Source-Synchronous or CDR Interfaces with Multiple

More information

Picture of memory. Word FFFFFFFD FFFFFFFE FFFFFFFF

Picture of memory. Word FFFFFFFD FFFFFFFE FFFFFFFF Memory Sequential circuits all depend upon the presence of memory A flip-flop can store one bit of information A register can store a single word, typically 32-64 bits Memory allows us to store even larger

More information

A LVL2 Zero Suppression Algorithm for TRT Data

A LVL2 Zero Suppression Algorithm for TRT Data A LVL2 Zero Suppression Algorithm for TRT Data R. Scholte,R.Slopsema,B.vanEijk, N. Ellis, J. Vermeulen May 5, 22 Abstract In the ATLAS experiment B-physics studies will be conducted at low and intermediate

More information

L1Calo FW Meeting. Progress and Plans: FEX ATCA Hub. Dan Edmunds, Yuri Ermoline Brian Ferguson, Wade Fisher, Philippe Laurens, Pawel Plucinski

L1Calo FW Meeting. Progress and Plans: FEX ATCA Hub. Dan Edmunds, Yuri Ermoline Brian Ferguson, Wade Fisher, Philippe Laurens, Pawel Plucinski L1Calo FW Meeting Progress and Plans: FEX ATCA Hub Dan Edmunds, Yuri Ermoline Brian Ferguson, Wade Fisher, Philippe Laurens, Pawel Plucinski 11 August 2016 Overview of Efforts Three primary categories

More information

Alexandria University

Alexandria University Alexandria University Faculty of Engineering Computer and Communications Department CC322: CC423: Advanced Computer Architecture Sheet 3: Instruction- Level Parallelism and Its Exploitation 1. What would

More information

Simulation of digital pixel readout chip architectures with the RD53 SystemVerilog-UVM verification environment using Monte Carlo physics data

Simulation of digital pixel readout chip architectures with the RD53 SystemVerilog-UVM verification environment using Monte Carlo physics data Journal of Instrumentation OPEN ACCESS Simulation of digital pixel readout chip architectures with the RD53 SystemVerilog-UVM verification environment using Monte Carlo physics data To cite this article:

More information

PSEC-4: Review of Architecture, etc. Eric Oberla 27-oct-2012

PSEC-4: Review of Architecture, etc. Eric Oberla 27-oct-2012 PSEC-4: Review of Architecture, etc. Eric Oberla 27-oct-2012 PSEC-4 ASIC: design specs LAPPD Collaboration Designed to sample & digitize fast pulses (MCPs): Sampling rate capability > 10GSa/s Analog bandwidth

More information

CMX Hardware Overview

CMX Hardware Overview Hardware Overview Chip Brock, Dan Edmunds, Philippe Laurens@MSU Yuri Ermoline @CERN Wojciech Fedorko @UBC Michigan State University 12-May-2014 Common Merger extended module () 12-May-2014 2 Overall project

More information

Interface electronics

Interface electronics Peter Göttlicher, DESY-FEB, June 11th 2008 1 Interface electronics Links to backend/control implications to mechanical design, to effort in FPGA's Peter Göttlicher, DESY-FEB specifications of signals at

More information

SVT detector Electronics Status

SVT detector Electronics Status SVT detector Electronics Status On behalf of the SVT community Mauro Citterio INFN Milano Overview: - SVT design status - F.E. chips - Electronic design - Hit rates and data volumes 1 SVT Design Detectors:

More information

FPGA Provides Speedy Data Compression for Hyperspectral Imagery

FPGA Provides Speedy Data Compression for Hyperspectral Imagery FPGA Provides Speedy Data Compression for Hyperspectral Imagery Engineers implement the Fast Lossless compression algorithm on a Virtex-5 FPGA; this implementation provides the ability to keep up with

More information

ATLAS NOTE. December 4, ATLAS offline reconstruction timing improvements for run-2. The ATLAS Collaboration. Abstract

ATLAS NOTE. December 4, ATLAS offline reconstruction timing improvements for run-2. The ATLAS Collaboration. Abstract ATLAS NOTE December 4, 2014 ATLAS offline reconstruction timing improvements for run-2 The ATLAS Collaboration Abstract ATL-SOFT-PUB-2014-004 04/12/2014 From 2013 to 2014 the LHC underwent an upgrade to

More information

The MROD. The Read Out Driver for the ATLAS MDT Muon Precision Chambers

The MROD. The Read Out Driver for the ATLAS MDT Muon Precision Chambers The MROD The Read Out Driver for the ATLAS MDT Muon Precision Chambers Design Review Report Overview Marcello Barisonzi, Henk Boterenbrood, Rutger van der Eijk, Peter Jansweijer, Gerard Kieft, Jos Vermeulen

More information

Overview of SVT DAQ Upgrades. Per Hansson Ryan Herbst Benjamin Reese

Overview of SVT DAQ Upgrades. Per Hansson Ryan Herbst Benjamin Reese Overview of SVT DAQ Upgrades Per Hansson Ryan Herbst Benjamin Reese 1 SVT DAQ Requirements and Constraints Basic requirements for the SVT DAQ Continuous readout of 23 040 channels Low noise (S/N>20 to

More information

Readout-Nodes. Master-Node S-LINK. Crate Controller VME ROD. Read out data (PipelineBus) VME. PipelineBus Controller PPM VME. To DAQ (S-Link) PPM

Readout-Nodes. Master-Node S-LINK. Crate Controller VME ROD. Read out data (PipelineBus) VME. PipelineBus Controller PPM VME. To DAQ (S-Link) PPM THE READOUT BU OF THE ATLA LEVEL- CALORIMETER TRIGGER PRE-PROCEOR C. chumacher Institut fur Hochenergiephysik, Heidelberg, Germany (e-mail: schumacher@asic.uni-heidelberg.de) representing the ATLA level-

More information

MPEG4 VIDEO OVER PACKET SWITCHED CONNECTION OF THE WCDMA AIR INTERFACE

MPEG4 VIDEO OVER PACKET SWITCHED CONNECTION OF THE WCDMA AIR INTERFACE MPEG4 VIDEO OVER PACKET SWITCHED CONNECTION OF THE WCDMA AIR INTERFACE Jamil Y. Khan 1, Pratik Das 2 School of Electrical Engineering and Computer Science, University of Newcastle, Callaghan, NSW 238,

More information

Validation of the front-end electronics and firmware for LHCb vertex locator.

Validation of the front-end electronics and firmware for LHCb vertex locator. Validation of the front-end electronics and firmware for LHCb vertex locator. Antonio Fernández Prieto Universidade de santiago de compostela, Spain E-mail: antonio.fernandez.prieto@cern.ch Pablo Vázquez

More information

GNAM for MDT and RPC commissioning

GNAM for MDT and RPC commissioning GNAM for MDT and RPC commissioning G. Crosetti, D. Salvatore, P.F. Zema (Cosenza) M. Della Pietra (Napoli) R. Ferrari, G. Gaudio, W. Vandelli (Pavia) 10 th Muon Week, Cetraro July 2005 Summary * GNAM and

More information

InfiniBand SDR, DDR, and QDR Technology Guide

InfiniBand SDR, DDR, and QDR Technology Guide White Paper InfiniBand SDR, DDR, and QDR Technology Guide The InfiniBand standard supports single, double, and quadruple data rate that enables an InfiniBand link to transmit more data. This paper discusses

More information

Executive Summary. Functional and Performance Validation of the 80S32 µc. Deliverable D5.2 - Report Workpackage 5 Evaluation Kit

Executive Summary. Functional and Performance Validation of the 80S32 µc. Deliverable D5.2 - Report Workpackage 5 Evaluation Kit Functional and Performance Validation of the 80S32 µc Executive Summary Deliverable D5.2 - Report Workpackage 5 Evaluation Kit Author(s): T.Lampaounas, C.Papadas, E.Politis, G.Dramitinos, K.Makris Reviewer(s):

More information

L1 and Subsequent Triggers

L1 and Subsequent Triggers April 8, 2003 L1 and Subsequent Triggers Abstract During the last year the scope of the L1 trigger has changed rather drastically compared to the TP. This note aims at summarising the changes, both in

More information

A responsive, fully-featured MIDI controller at an affordable price

A responsive, fully-featured MIDI controller at an affordable price Project Name: 2 Project Description: Team Members: Outside Collaborators: Component Description: Author: A responsive, fully-featured MIDI controller at an affordable price Graham Boylan, Khaled Albaddah,

More information

A generic firmware core to drive the Front-End GBT-SCAs for the LHCb upgrade

A generic firmware core to drive the Front-End GBT-SCAs for the LHCb upgrade A generic firmware core to drive the Front-End GBT-SCAs for the LHCb upgrade F. Alessio 1, C. Caplan, C. Gaspar 1, R. Jacobsson 1, K. Wyllie 1 1 CERN CH-, Switzerland CBPF Rio de Janeiro, Brazil Corresponding

More information

ZPD Test Plan 1. 3 April 2003 S. Bailey, G. Brandenburg, N. Felt, M. Morii, J. Oliver, E. Won For the BABAR DCT Upgrade Final Design Review

ZPD Test Plan 1. 3 April 2003 S. Bailey, G. Brandenburg, N. Felt, M. Morii, J. Oliver, E. Won For the BABAR DCT Upgrade Final Design Review ZPD Test Plan 1 3 April 2003 S. Bailey, G. Brandenburg, N. Felt, M. Morii, J. Oliver, E. Won For the BABAR DCT Upgrade Final Design Review This document describes the plan for testing the ZPD modules.

More information

Detector Housing CASCADE-U 100. Bottom-flange. Top-flange with Teflon insulating ring and special Wilson-flange designed to fit the UCN beam pipe

Detector Housing CASCADE-U 100. Bottom-flange. Top-flange with Teflon insulating ring and special Wilson-flange designed to fit the UCN beam pipe Detector Housing CASCADE-U 100 Bottom-flange with shielding of the readout electronics Shielding of the readout electronics Top-flange with Teflon insulating ring and special Wilson-flange designed to

More information

Detector Control System board for FAIR. J. A. Lucio Martínez Infrastructure and Computer Systems in Data Processing (IRI) Goethe University Frankfurt

Detector Control System board for FAIR. J. A. Lucio Martínez Infrastructure and Computer Systems in Data Processing (IRI) Goethe University Frankfurt Detector Control System board for FAIR J. A. Lucio Martínez Infrastructure and Computer Systems in Data Processing (IRI) Goethe University Frankfurt For the PANDA Collaboration Meeting in Darmstadt, 08.06.2016

More information

Latency on a Switched Ethernet Network

Latency on a Switched Ethernet Network Page 1 of 6 1 Introduction This document serves to explain the sources of latency on a switched Ethernet network and describe how to calculate cumulative latency as well as provide some real world examples.

More information

Proposal for Digitizer-to-SLINK Interface Card

Proposal for Digitizer-to-SLINK Interface Card Proposal for Digitizer-to-SLINK Interface Card J. Pilcher (for Haifeng Wu) 10-Sept-1999 Overview Located in drawers (1 interface board/drawer) Input from 8 digitizer boards (16 DMU chips) Output to ROD

More information

a) Memory management unit b) CPU c) PCI d) None of the mentioned

a) Memory management unit b) CPU c) PCI d) None of the mentioned 1. CPU fetches the instruction from memory according to the value of a) program counter b) status register c) instruction register d) program status word 2. Which one of the following is the address generated

More information

ALIBAVA: A portable readout system for silicon microstrip sensors

ALIBAVA: A portable readout system for silicon microstrip sensors ALIBAVA: A portable readout system for silicon microstrip sensors Marco-Hernández, R. a, Bernabeu, J. a, Casse, G. b, García, C. a, Greenall, A. b, Lacasta, C. a, Lozano, M. c, Martí i García, S. a, Martinez,

More information

ARC-48: 8-Channel CCD Video Processing Board

ARC-48: 8-Channel CCD Video Processing Board ARC-48: 8-Channel CCD Video Processing Board This manual describes the 8-channel CCD video processor board, model ARC-48 Rev. 1A. The board serves two functions - processing and digitizing the video outputs

More information

The First Integration Test of the ATLAS End-Cap Muon Level 1 Trigger System

The First Integration Test of the ATLAS End-Cap Muon Level 1 Trigger System 864 IEEE TRANSACTIONS ON NUCLEAR SCIENCE, VOL. 50, NO. 4, AUGUST 2003 The First Integration Test of the ATLAS End-Cap Muon Level 1 Trigger System K. Hasuko, H. Kano, Y. Matsumoto, Y. Nakamura, H. Sakamoto,

More information

White Paper Compromises of Using a 10-Gbps Transceiver at Other Data Rates

White Paper Compromises of Using a 10-Gbps Transceiver at Other Data Rates White Paper Compromises of Using a 10-Gbps Transceiver at Other Data Rates Introduction Many applications and designs are adopting clock data recovery-based (CDR) transceivers for interconnect data transfer.

More information

STUDY, DESIGN AND SIMULATION OF FPGA BASED USB 2.0 DEVICE CONTROLLER

STUDY, DESIGN AND SIMULATION OF FPGA BASED USB 2.0 DEVICE CONTROLLER STUDY, DESIGN AND SIMULATION OF FPGA BASED USB 2.0 DEVICE CONTROLLER 1 MS. PARUL BAHUGUNA CD 1 M.E. [VLSI & Embedded System Design] Student, Gujarat Technological University PG School, Ahmedabad, Gujarat.

More information

(Refer Slide Time: 1:43)

(Refer Slide Time: 1:43) (Refer Slide Time: 1:43) Digital Circuits and Systems Prof. S. Srinivasan Department of Electrical Engineering Indian Institute of Technology, Madras Lecture - 27 Pattern Detector So, we talked about Moore

More information

The LHCb upgrade. Outline: Present LHCb detector and trigger LHCb upgrade main drivers Overview of the sub-detector modifications Conclusions

The LHCb upgrade. Outline: Present LHCb detector and trigger LHCb upgrade main drivers Overview of the sub-detector modifications Conclusions The LHCb upgrade Burkhard Schmidt for the LHCb Collaboration Outline: Present LHCb detector and trigger LHCb upgrade main drivers Overview of the sub-detector modifications Conclusions OT IT coverage 1.9

More information

SoLID GEM Detectors in US

SoLID GEM Detectors in US SoLID GEM Detectors in US Kondo Gnanvo University of Virginia SoLID Collaboration Meeting @ JLab, 05/07/2016 Outline Overview of SoLID GEM Trackers Design Optimization Large Area GEMs for PRad in Hall

More information

UNIT- 2 Physical Layer and Overview of PL Switching

UNIT- 2 Physical Layer and Overview of PL Switching UNIT- 2 Physical Layer and Overview of PL Switching 2.1 MULTIPLEXING Multiplexing is the set of techniques that allows the simultaneous transmission of multiple signals across a single data link. Figure

More information

Memory Supplement for Section 3.6 of the textbook

Memory Supplement for Section 3.6 of the textbook The most basic -bit memory is the SR-latch with consists of two cross-coupled NOR gates. R Recall the NOR gate truth table: A S B (A + B) The S stands for Set to remember, and the R for Reset to remember.

More information