RFP Attachment 13. January 2010

Similar documents
PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Energy Gateway Update. John Cupparo Vice President, Transmission January 2010

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

TransWest Express and Gateway South

Grid Interconnection of Renewable Generation

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

Small Generator Interconnection System Impact Study Report. Completed For Q0047

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

INTERCONNECTION FACILITIES STUDY REPORT

Transmission Planning Attachment K Public Input Meeting

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Process. Wholesale Transmission Overview

Feasibility Study on Load Flow and Short Circuit Project

Generation Interconnection Feasibility Study Report

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Public Service Company of New Mexico

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Q44 Generation Interconnection

This report is printed on recycled paper

Memorandum. This memorandum requires Committee action.

NTTG 2019 Annual Interregional Information

TSR A & B - FACILITIES STUDY REPORT

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Minnesota Hosting Capacity Analysis

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

Interconnection and Transmission

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Studies Overview and Data Requirements. Robert Pan

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

Generation Interconnection Feasibility Study Report

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014

From: Laura Manz, Vice President of Market & Infrastructure Development

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

MEMORANDUM. June 30, Council Members. Update on Transmission Planning Activities

TransWest Express Transmission Project Interregional Transmission Project Submittal

Small Generator Interconnection System Impact Study Report. Completed for Q0373

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

Assessing Reliability in the Western Interconnection. Vijay Satyal and Byron Woertz, WECC

ITC HOLDINGS, CORP. Edison Electric Institute 9

ColumbiaGrid Planning Overview. Marv Landauer July 13, 2010

INTERCONNECTION FACILITIES STUDY REPORT

Local Area Studies Update - PACW Kevin Putnam

System Studies for American Transmission Co. s Benson Lake SVC Project

Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study

Redefining Renewables SCADA

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

Transforming the Electric Grid

XXXXX XXXX Wind Generation Project

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

ATTACHMENT I: Generator Interconnection Procedures (GIP)

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

ISO New England Data Modeling Requirements

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Stem Beach Solar 1041 Application

Updates and Modifications to Report

July 26, Dear Mr. Millar:

Generation, Transmission, and End User Facilities

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

Pacific Northwest Smart Grid Demonstration. Larry Bekkedahl VP Engineering & Technical Services Bonneville Power Administration

WISP. Western Interconnection Synchrophasor Program. Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012

Interconnection Re-MAT September 11, 2013

Colstrip Transmission System. Transmission Service and Interconnection Processes and Procedures

Agreements and Queue Management

Karl Iliev, San Diego Gas & Electric Company

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc.

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

ATC Zone 2 Projects Update U.P. Energy Summit

Feeder Hosting Capacity and Impacts of Distribution Connected Generation. NGN Tutorial. Prepared for GOTF October 22, 2017

Flexible Distributed Generation. FDG-A March Area (EPN) December 2016

Updates and Modifications to Report

Voltage Control in Southwest Utah With the St. George Static Var System

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Network Configuration Document Selection for New Substations Framework

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

POWER INFRASTRUCTURE PLAN 2016

STCP22-1 Issue 003 Production of Models for GB System Planning

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

Model Parts and Assembly. Jay Britton Britton Consulting LLC

MODULAR HUB AND SPOKE 17 NOVEMBER 2017

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

Sapphire Wind Farm 330/33kV Substation

Hosting Capacity Webinar. Summary of April 28, 2017 Stakeholder Engagement Group Meeting

Transcription:

PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission

PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt Detail Interconnection Request Study Information 2

Integrated Resource Plan Attachment 13 Methodology PacifiCorp IRP identified points of receipt for potential resource and load bubble needs High level planning review of the required transmission infrastructure needs required to deliver the resource to adjacent network load bubbles 3

Integrated Resource Plan Attachment 13 represents proxy results only Actual infrastructure requirements Resulting costs Any off system resources require firm transmission through any third party provider as required to deliver to points of receipt identified in Attachment 13 Attachment t 13 costs will be used as one dt data point by independent evaluators to short list projects 4

Study Result Accuracy Reviews based on existing information, i.e. past studies (local and regional) and known information on the existing system capabilities Generator specifics, size, actual interconnection ti configuration, and queue priority were not known at the time Attachment 13 was prepared p Actual interconnection system impact study is more in depth and results may/will change actual requirements LGIA studies include: load dflow, fault study, stability, and impacted system analysis that determine final infrastructure needs 5

Cost Estimate Energy Gateway project costs are excluded from Attachment 13 integration i costs (this is a modification from the posted Draft version dated July 3, 2008) Estimates use PacifiCorp s estimating tool based on high level information with very generic project scope (no engineering design, EPC delivery strategy) Recent vendor quotes, material and labor costs continue to rise over historic trends Costs are based upon requirements without complete design (without line routes, final structures, etc) from study requirements or from a facility design Summary Estimates are based on applying standard cost data for what is known at this time and are subject to change when detailed studies are conducted 6

Energy Gateway Project Topology 7

Relevant Transmission Projects Priority One Base Load Service and Reliability Gateway Segments Segment B (Populus to Terminal 345-kV) 2010 Segment C (Mona to Oquirrh 500/345-kV) 2013 Segment G (Sigurd to Red Butte 345-kV) 2014 Other Projects Wallula to McNary 230-kV 2011 Vantage to Pomona Heights 230-kV 2012 Priority Two Gateway Segments Wind Integration and Resource Adequacy Segment D (Windstar to Populus 500-kV) 2014/16 8

Attachment 13 Transmission Integration Costs Background Information Draft version - July 3, 2008 http://www.oasis.pacificorp.com/oasis/ppw/draft7-30-2008rfpattachment13.doc pacificorp com/oasis/ppw/draft7 9

Salt Lake Valley 138 kv $100 Million 600 MW delivered into the Salt Lake load bubble Upgrades to unknown lines (underlying transmission system) Reconstruction and upgrades to multiple 138 kv lines Upgrades to multiple 138 kv substations 10

Lakeside 345 kv $66 Million 600 MW delivered into the Salt Lake load bubble New 345 kv substation at Lakeside Looping the existing Camp Williams to Emery and Camp Williams to Spanish Fork 345 kv lines into the new sub New 15 mile Lakeside to Camp Williams 345 kv line Additions to Camp Williams, Emery, and Spanish Fork substations to accommodate line terminations and operation Subsequent review indicates the Lakeside to Camp Williams presents permitting challenges alternatives are under review to improve schedule and ensure delivery 11

Mona Current Creek $62 Million io (update to pio prior Attachment 13) 600 MW delivered into the Salt Lake load bubble New 0.6 mile 345 kv Current Creek to Mona line Additions to Current Creek and Mona substations Energy Gateway projects as noted below: (required but excluded from costs above) New 90 mile Mona to Oquirrh line (existing lines are fully subscribed to firm contracts) Additions i to substations 12

Glen Canyon $310 Million (update to prior Attachment 13) 600 MW delivered into the Salt Lake load bubble New 160 mile 345 kv Glen Canyon to Sigurd line (existing line is fully subscribed to firm contracts) Significant permitting issues expected Phase shifting transformer at Glen Canyon Additions at Glen Canyon, and Sigurd substations to accommodate termination and operation of the new lines Energy Gateway projects as noted below: New 90 mile Mona to Oquirrh line (existing lines are fully subscribed to firm contracts) Additions to substations 13

Gonder $282 Million (update to prior Attachment 13) 600 MW delivered into the Salt Lake load bubble New 190 mile 345 kv Gonder to Mona line (existing line is subscribed to firm contracts) Additions at Gonder and Mona for the termination and operation of the new line Energy Gateway projects as noted below: New 90 mile Mona to Oquirrh line (existing lines are fully subscribed to firm contracts) Additions to substations 14

Harry Allen $73 Million (update to posted Attachment 13) 600 MW delivered into the Salt Lake load bubble Additions at Harry Allen and Red Butte substations for the termination and operation of the new line Includes a second 230/345 kv transformer at Harry Allen, static VAr compensation, and series compensation Energy Gateway projects as noted below: A second 160 mile 345 kv Sigurd to Red Butte transmission line (new line is proposed for Red Butte load service and excluded from costs) Existing line is fully subscribed to firm contracts New 90 mile Mona to Oquirrh line (existing lines are fully subscribed to firm contracts) Additions to substations 15

Crystal $415 Million (updated cost from Attachment 13) 600 MW delivered into the Salt Lake load bubble New 120 mile line Crystal to Red Butte 345 kv transmission line Additions at Crystal and Red Butte substations for the termination and operation of the new lines Includes a phase shifting i and transformation at Crystal Energy Gateway projects as noted below: New 90 mile Mona to Oquirrh line (existing lines are fully subscribed to firm contracts) Additions to substations A second 160 mile 345 kv Sigurd to Red Butte transmission line (new line is proposed for Red Butte load service) 16

Four Corners $738 Million (update to prior Attachment 13) 600 MW delivered into the Salt Lake load bubble New 255 mile 345 kv Four Corners to Emery transmission i line Existing line is fully subscribed to firm contracts Significant permitting issues expected New 80 mile 345 kv Emery to Mona transmission line existing line is fully subscribed to firm contracts Energy Gateway projects as noted bl below: New 90 mile Mona to Oquirrh line (existing lines are fully subscribed to firm contracts) Additions to substations 17

Wyoming $160 Million Substation upgrades 400 MW delivered to the Energy Gateway project at the new Windstar, Aelolus, or Bridger hub Requires new Energy Gateway West or South infrastructure (current schedule is 2014 to 2016) Resources located south or west of the Naughton Monument 230 kv line may not be as impacted by existing i Wyoming export constraints once the Populus to Terminal upgrade is completed 18

Borah, Brady, or Kinport Zero $ Assumes proposed Energy Gateway segment B (Path C) upgrade is completed December 2010 or later Resources located off system must include firm transmission rights through any third party transmission provider 19

Mid Columbia Zero $ 600 MW delivered to Yakima load bubble Completion of new 60 mile 230 kv Vantage to Pomona Heights transmission line In service date is currently 2012, driven by permitting issues Additions at Vantage and Pomona Heights substations for the termination and operation of the new line 20

California Oregon Border $290 Million 600 MW delivered to Southern Oregon load bubble Some incremental capacity required to existing COI rights New 60 mile 230 kv Dixonville to Alvey transmission line Existing line is fully subscribed dto firm contracts t Additions at Dixonville and Alvey substations for the termination and operation of the new line 21

Paul 500 kv $14 million per year for 3 rd party transmission wheeling to deliver resources to PacifiCorp loads from Paul Costs represent renewal of a wheeling contract with BPA to move energy to PacifiCorp loads from the Paul point of receipt eeip 22

Portland Troutdale $200 Million 400 MW delivered to the Portland load bubble New 55 mile 230 kv Troutdale to Bethel transmission line existing line is fully subscribed to firm use Additions at Troutdale and Bethel substations for the termination and operation of the new line 23

Willamette Valley $290 Million 600 MW delivered to Willamette Valley load bubble New 60 mile 230 kv Dixonville to Alvey transmission line existing line is fully subscribed to firm use Additions at Dixonville and Alvey substations for the termination and operation of the new line 24

Chiloquin Southern Oregon $100 Million Delivery of 400 MW into the southern Oregon load bubble New 30 mile 230 kv Chiloquin to Klamath Falls transmission line existing line is fully subscribed to firm use Additions at the Chiloquin and Klamath Falls substations for the termination and operation of the new line 25

Typical Interconnection Study Timeline Preliminary Activities Feasibility System Impact Facilities Study Study Study Generator Interconnection Agreement Construction Begins Feasibility Agreement SIS Agreement Facilities Agreement Approved Project Executed GIA Large Generator > 20 MW 30-45 days Up to 45 days Up to 90 days Up to 90 days Up to 60 days 2 4 years Small Generator < 20 MW 30-45 days Up to 30 days 30 to 45 business days 30 to 45 business days Up to 60 days 2 4 years Customer Customer Customer Customer Customer Planning Planning Construction Engineering Engineering Engineering Grid Ops Grid Ops Grid Ops Project Services Project Services Project Services 45-day Feasibility Study - includes: Circuit breaker short circuit capability limits exceeded Thermal overload or voltage limit violations Description and cost estimate of facilities required If network resource, a description and cost estimate of transmission modifications required to deliver generation to network load 26 90-day System Impact Study - includes: Short circuit analysis Stability analysis Power flow analysis Estimate of the cost responsibility Estimated time to construct

LGIA Network Resource/Energy Resource Generators don t need a network resource interconnection for PacifiCorp Merchant to designate them as a network resource in the transmission service queue If generators do insist on a network resource interconnection agreement, the interconnection procedures require them to fund all transmission upgrades necessary to deliver the power to load, funding subject to refunds 27

LGIA Customer Data Requirements Application Complete application Site control Deposit Feasibility Study One line diagram Step up transformer data Radial interconnecting line data 28

Data Requirements, continued System Impact Study: Non wind: Generator data Excitation system block diagram Power system stabilizer block diagram/data Governor system block diagram/data Wind: One line diagram showing layout of wind farm and impedances for all segments Wind turbine model Size and increments of supplemental reactive compensation 29