AT&T Switched Ethernet Service SM

Similar documents
AT&T Dedicated Internet (ADI formerly known as MIS) and Private Network Transport (PNT)

AT&T Dedicated Internet (ADI formerly known as MIS) and Private Network Transport (PNT)

AT&T Virtual Private Network Service (VPN) and AT&T VPN Express

AT&T Virtual Private Network Service (VPN) and AT&T VPN Express

Add an AT&T Switched Ethernet Service port to your site

SPOS (Station Point of Sale) 200. SFTP (Station Fare Transaction Processor) 35. CQD (Card Query Device) 35. HCR (Handheld Card Reader) Cradles 120

Tarleton State University. Specifications

PoP ROOM: INSIDE AND OUTSIDE PLANT RULES & REGULATIONS

Construction Guidelines. for Providing Communications Services

The power behind competitiveness. Delta Infrasuite Power Management. Power Distribution Unit. User Manual.

AT&T Collaborate. IAD (s)

Installation Notes TII Model 341 Protector

SPECIAL INSTRUCTIONS FOR CAPACITORS COMPACT GENERATORS

Office of the Chief Information Officer Technical Note: IT-960-TN14 Effective: 05/25/2006 Last Revised: 02/17/2012 Issuing Office: OCIO

Target Interface / Construction Compliance Inspection Checklist

Basketball Shot Clock Set LX2180 Manual

Omnitron Systems Technology, Inc. 1. iconverter. 19-Module Managed Power Chassis User s Manual

Business Customer Demarcation Information

CSM200 Expansion Tray

WiredScore Report. Tanfield. 1 Tanfield, Edinburgh, EH3 5DA. Audit Reported Points. Building Connectivity 37 / 45. Building Infrastructure 28 / 41

4100/ VDC Converter Installation Instructions

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

COMPUTER NETWORK WIRING SYSTEMS FOR PLCs

HydroGuard 4 to 20 ma Output Module. For use with HydroGuard Water Quality Monitor and Controller

NZQA unit standard version 2 Page 1 of 5

Computer Network Design Guide Existing Systems 1 / 6

Spring Test 9 due 05/11/2013

Site Preparation CHAPTER

SECTION FARE COLLECTION SYSTEM

Qualified Partner Programme QPP. Installation Practice Felice Guarna Wetzikon, July 2001

SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS

Broadband Automatic Disconnect Switch. User Manual

Some material previously on this page now appears on Original Page 1.1

State of California Level3 Communications IFB STPD B Refresh Statewide Technology Procurement Division

A. System design shall be completed by a Registered Communications Distribution Designer (RCDD).

Power Supply (48Vdc, 2.5A)

Quick Start. This document describes how to install the Juniper Networks PTX5000 Packet Transport

Installing the Cisco MDS 9020 Fabric Switch

Explore installation guide

Replacing an ESM/IOM CRU in the CSM200 Drive Module

ANSI/TIA/EIA-568-B Cabling Standard NOTE

General. Exterior Cameras. Camera Towers

CENTRAL TELEPHONE COMPANY NEVADA DIVISION ( SPRINT ) NEVADA LOCAL TERMS OF SERVICE

Intelligent Channel Bank Shelf

INSTALLATION INSTRUCTIONS FOR THE MINI-KEY SYSTEM. Doc Rev B

iconverter 2-Module Power Chassis

Installation. MGE Galaxy 3500 and Smart-UPS VT. Maintenance Bypass, Distribution and Transformer Cabinet

Installation Toolkit. changing healthcare, changing lives. California Telehealth Network P Street, Suite 100. Sacramento, CA 95811

Managed WAN SLA. Contents

FEMTOCELL MULTI-BAND SOHO B2/B4 (SS2FII)

ANSI/TIA/EIA-568-B Cabling Standard

AT&T EXCHANGE GUIDEBOOK Original Page 1. PART 3 - Data Offerings Effective: June 26, 2015

MICHIGAN DEPARTMENT OF TRANSPORTATION

DATA CENTER COLOCATION BUILD VS. BUY

PIX 520. PIX 520 Product Overview CHAPTER

It is acceptable to place all required information in the main element (such as G4010) and delete the sub-elements provided in this template.

Target Interface / Construction Compliance Inspection Checklist

Configurable Output Distribution. 120V / 208V / 240V 60Hz. User Manual English

ADVANCED CUSTOMER SUPPORT ORACLE STANDARD SYSTEM INSTALLATION ( OSSI ) with SITE AUDIT SERVICES EXHIBIT

17. Microwave Collocation 17.1 General

PARTNER Contact Closure Adjunct

Cabling Infrastructure

Documentation on all Paxton products can be found on our web site -

Our Customer Relationship Agreement NBN FIBRE SERVICE DESCRIPTION

Managed WAN SLA. Contents

Target Interface / Construction Compliance Inspection Checklist

AT&T INTERSTATE ACCESS GUIDEBOOK PART Special Access Services - East

InnoMedia Business VoIP ATA Models

1.0 Executive Summary. 2.0 Features and Benefits

ATS-16 HV USER MANUAL. Automatic Transfer Switch 16A / 230Vac V090318

v2.5 was updated May 10, v2.6 is an updated copy from March 1, 2017.

RFP Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service

SYSTIMAX 360 ipatch Network Manager Module Faceplate Instructions

Target Interface / Construction Compliance Inspection Checklist

Form C contact for remote monitoring UL 1449, UL 1283, cul recognized component, CE 5 Year Limited Warranty

Form C contact for remote monitoring UL 1449, UL 1283, cul recognized component, CE 5 Year Limited Warranty

Electrical Demand Specification (Reference SOP: )

BS 287 DUAL CHANNEL POWER SUPPLY. User Manual. January 2017 V1.0

Single-Core PVC 6491X

Stan Greer Area Managerr External Affairs

Target Interface / Construction Compliance Inspection Checklist

Installation, Operation, and Service Manual SIEMENS HEALTHCARE INTEGRATED ELECTRICAL CABINET

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MICROWAVE VEHICLE DETECTION SYSTEM

DRAFT. Application Note: Modbus/RS485 Wiring for Conext Core XC Series Inverters. 1.0 Introduction DANGER. 1.1 Related Documents

ADTRAN ProServices Description of Service Offering. ProStart Remote Installation Services ActivReach Ethernet Switches

T3 Interface Converters

PS 289 DUAL CHANNEL POWER SUPPLY USER MANUAL

Obtaining Documentation and Submitting a Service Request, page xvii Safety Warnings, page xvii Safety Guidelines, page xx

2.3 SCOPE OF WORK MATRIX TO BE INCLUDED IN DISTRICT PROJECTS

INTERIM COMMUNICATIONS INFRASTRUCTURE PLANNING GUIDELINES

Pretium EDGE HD Solutions A LANscape Pretium Solutions Product

Choose from four different ways to power these hardened media converters.

TIA/EIA 568A Sub-system HORIZONTAL CABLING

Installation Instructions for the AUTOcard-SA System

User Manual. AN A GPON Optical Network Unit. Version: A. Code: MN Date: December 2011

Northpower Fibre UFB Services Agreement Service Description for Direct Fibre Access Service

6. Secured Collocation Open Physical Environment (SCOPE) 6.1 Description

Installation Guide. Getting Started with MaxAttach NAS 6000 Rack Mount Base Unit Systems

Who Needs Remote Power Management for Power Distribution, Power Measurement and Power Control of 48 VDC Equipment?

4 Channel 4~20mA/0~10VDC Analog Data Fiber Link System

Transcription:

Site Preparation Guide AT&T Switched Ethernet Service SM December 2016 2016 AT&T Intellectual Property. All rights reserved. AT&T, Globe logo, Mobilizing Your World and DIRECTV are registered trademarks and service marks of AT&T Intellectual Property and/or AT&T affiliated companies. All other marks are the property of their respective owners.

AT&T Switched Ethernet site preparation guide Introduction: AT&T (with EFC offer) or Customer will provide Entrance Facility as follows: Customer will perform the following: Meet with the AT&T engineer An AT&T engineer will explain to your site contact all customer responsibilities shown on this page The engineer will reach out to the site contact within 48 hours of your order to schedule a visit If you are eligible and have contracted AT&T to provide Entrance Facility Construction*, AT&T will complete items 2-5 on this list. This will occur after you obtain a signed System Permission Form if required according to the building circumstances. If you are not eligible or have not selected the AT&T Entrance Facility Construction, you (or your chosen contractor) will be responsible for completing the steps 2-5 on this list. *The Entrance Facility Construction offer is described beginning on page 10. Your AT&T representative can help you determine if your location is eligible and if so, can include it with your order request. Outside conduit specifications (Property Line to your building) Minimum 2 4 conduit with pull rope Minimum 3 sweeping radius Pull box required when: There are 3 or more right angles The path is longer than 300 *Dimensions for pull box 12 x 12 x 18 Wall mounted backboard 4 x 4 x 3/4 Fire retardant plywood Mounted to studs Electrical specifications AC power outlet on a dedicated fused breaker rated min. 15 amps OR Nominal voltage, 48VDC, +24/-24VDC, 110V Either power option needs to be located within 6 ft. of the AT&T equipment Relay racks / cabinets must be grounded Inside conduit specifications (Demarcation point to router) Needs to be completed prior to installation You may hire an electrical vendor to complete inside wiring A conduit or cable tray is required, and a clear path for access Minimum 2 conduit Additional inside wiring Inside wiring, unless otherwise noted, is your responsibility; you can do it yourself or hire a vendor Inside wiring includes: From the demarcation point to your equipment (e.g. router) Note: Incomplete inside wiring is the number one reason for service delays Note: In some buildings, AT&T may be able to serve your new service from existing AT&T equipment with spare capacity. In such cases no additional site preparation work is required. On or before the due date a technician will be dispatched to provide circuit demarcation and perform test and turn-up activity. 2

AT&T Switched Ethernet Site Preparation Guide Site survey: Site contact responsibilities: Site contact responsibilities: If in a multi tenant building: AT&T will reach out to your local site contact to schedule a site survey, if applicable. Please provide the local customer site contact information: Name / Title Phone number / Email The site contact will work with AT&T to schedule building access, provide the installation address to the ordering team and problem solve, as needed. Obtaining building access and being familiar with the telecom rooms Showing AT&T where the circuit demarcation (demarc) is located. The demarc is inside the building where the service terminates from the street Guiding AT&T during the site survey visit, noting further action needed to complete the site requirements (take notes) Overseeing the site build out and confirming the completion dates. The contact should be fully empowered to make decisions Informing AT&T of any parking, noise or time restrictions; unloading zones, elevators, asbestos, hazardous materials, etc. Providing adequate working space, a clear path and easy access to the backboard, patch panel and power outlets Working with the property manager or building owner to determine the location of your company s demarc Acting as a liaison and advocate when working with the building owner or manager Confirming the demarc is in the same room as the router Providing inside wiring if the building s demarc is not in your location or on a different floor than your equipment (e.g. router) 3

AT&T Switched Ethernet Site Preparation Guide Site preparation delays Customer site not ready What to expect during site survey visit AT&T will negotiate a project schedule with all parties to enable service completion as close to your desired date as possible However, any changes to plans or any delays associated with site preparation can have a corresponding or greater impact to the service delivery date Please try to complete the site preparation as soon as possible from the time you place your order. This includes any electrical requirements, the backboard for the network equipment and any applicable extended inside wire. This will help avoid an installation delay Please contact the AT&T ordering team and your account team representative if delays are anticipated so work forces can be rescheduled There are billing implications if the site is not ready in time The local site contact will meet with the AT&T engineers to walk through what the customer will need to complete before we can install the service It s a good idea to take notes and keep the name and contact information of the engineer in case there is a question later We will keep the site contact notified if there are any delays on our end, such as special construction, or facility delays 4

AT&T Switched Ethernet Site Preparation Guide General requirements Inside path The following pages contain information and a list of general requirements associated with fiber optic-based services. The AT&T engineer or field technician will identify actual requirements for the specific installation during the site survey. Share this information with your electrical contractor There are typically four (4) areas of customer obligation to facilitate timely equipment installation and delivery of service: Inside path Ground Power Floor space and environmental requirements For an additional fee, you can hire AT&T or an electrician to complete the inside wiring The inside path is the wiring that goes from the point where we bring the service to your building (demarc) to your equipment (e.g. router) The conduit must be a minimum 2 with a hard plastic corrugated interior duct, with pull rope If the building is shared by multiple tenants, the router and the demarc will likely not be in the same location. You will need to work with the building manager or building owner to coordinate the inside wiring Inside wire extensions take time, so you will want to schedule that as soon as possible. The AT&T engineer will be able to answer any questions 5

AT&T Switched Ethernet Site Preparation Guide Grounding Grounding your router is your responsibility, we encourage you to consult with your electrical contactor AT&T provided equipment, customer relay racks, cabinets and router must be grounded by placing an exposed #6 or larger grounding wire to the building s ground source All equipment requires a properly grounded 110v, 15 amp, 3-prong AC outlet A #6 stranded ground is required from your earth electrode system to the equipment room. This would be connected to a grounding bus bar, or otherwise directly connected to different components A #6 stranded ground is required from the grounding bus bar to the network terminating equipment This ground wire will be attached to the closest ground rod (earth ground) or building bus bar available and run to the network terminating equipment location in the room Improper grounding of equipment will result in service quality and maintenance issues Specific requirements may also be discussed with the AT&T access engineer or AT&T field technician at the time of the site survey visit 6

AT&T Switched Ethernet Site Preparation Guide Power Wall Mount (preferred) or Rack Mount Network device Please provide a dedicated 110V circuit breaker rated at a minimum of 15 amps for the network device that connects your building to the AT&T network. The power cord must not be touching any other cables AT&T also supports DC powered installations upon request Customer A 4 x 4 x 3/4, environmental fire retardant responsibilities backboard, fastened to studs is responsibilities required Operating environment should be between 40 (degrees) F and 85 (degrees) F to 85% relative humidity Because of the small size of most network termination equipment, a wall mounted installation is recommended (please see illustration on the next page) Another option would be a (customer provided) 19 rack of suitable strength and quality is also acceptable The choice for placement should be decided before the order is placed and is subject to confirmation following the site survey In a standard fiber installation, transport equipment is placed in a common area with access to the entire building. Please contact AT&T as soon as the site preparation is complete so that the project schedule can be maintained. 7

AT&T Switched Ethernet Site Preparation Guide Basic and PPCoS Ports Wall mount example fiber entrance facilities from Central Office 4 X 4 X 3/4 fire retardant plywood backboard mounted to studs Ethernet electrical patch cable Fiber termination panel Orange Customer provided Blue- AT&T provided Optional fiber jumpers (caution: bend radius) Fiber drop Cable to customer router (optical handoff) Fiber panel (not available on 100M ports) Network termination equipment 110V power cord 110V amp outlet, properly grounded, 3 prong 8

AT&T Switched Ethernet Site Preparation Guide Broadband Ports Wall mount example loop cable facilities from Central Office 2 x2 x 3/4 fire retardant plywood backboard mounted to studs 1000BaseT Ethernet patch cable Facility Termination panel Orange Customer provided Blue- AT&T provided copper pairs Network termination equipment 110V power cord 110V amp outlet, properly grounded, 3 prong 9

Site Preparation Guide AT&T Provided Entrance Facility Construction 2016 AT&T Intellectual Property. All rights reserved. AT&T, Globe logo, Mobilizing Your World and DIRECTV are registered trademarks and service marks of AT&T Intellectual Property and/or AT&T affiliated companies. All other marks are the property of their respective owners.

Entrance Facility For AT&T Switched Ethernet Service Traditionally customers have been responsible for conducting the Entrance Facility to enable the provision of fiber based service. With AT&T Switched Ethernet Service, the customer can continue to do this work, or can outsource to a contractor, or can contract with AT&T to do it. AT&T offers Entrance Facility Construction (EFC) which includes: Conduit, Core Drilling & Weatherproofing, Interior Raceway Support Structure, Backboard and Power Outlet & Ground for AT&T Provided NTE (Network Terminating Equipment) Inside Wire/Extended Demarc NOT INCLUDED - Conduit Constructed From Property Line to MPOE Maximum distance 1,000 Ft. 11 2015 AT&T Intellectual Property. All rights reserved. AT&T and the AT&T logo are trademarks of AT&T Intellectual Property. AT&T Proprietary (Internal Use Only) Not for use or disclosure outside the AT&T companies except under written agreement. NOTE: Customers (or their landlords) will own the completed entrance facility and are responsible for arranging their own maintenance as needed Pag e 11

EFC Customer Eligibility Requirements Customer site must be within AT&T ILEC franchise area Conduit from property line to Minimum Point Of Entry (MPOE) in customer s building must not be more than 1,000 feet (as measured by AT&T) Customers must schedule a site visit to take place within 10 calendar days from the date they are contacted by AT&T engineering for this purpose Following the site visit, if the site qualifies for entrance facility work, AT&T will (when necessary) provide a System Permission Form (SPF) to the building/premises owner(s) or authorized representative(s). Customers are responsible for ensuring the SPF is signed by the building/premises owner(s) or authorized representative(s) and returned to AT&T within 10 business days after receipt from AT&T in order for AT&T to proceed with Entrance Facility construction. Some sites / services are excluded from this offer including diversity, service ordered via Network on Demand process, carrier Point of Presence (POP) locations, residential buildings, and sites which AT&T determines EFC would be unduly expensive or not feasible 12