TransWest Express Transmission Project Interregional Transmission Project Submittal

Similar documents
TransWest Express and Gateway South

North Gila-Imperial Valley #2 Transmission Project

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group

Project Presentation April, 2017

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

July 26, Dear Mr. Millar:

From: Laura Manz, Vice President of Market & Infrastructure Development

PacifiCorp Transmission Energy Gateway Update. John Cupparo Vice President, Transmission January 2010

WIND. Representing clients across the renewable energy industry. Troutman Sanders LLP. troutman.com

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

PacifiCorp Transmission Technical Workshop

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

Presentation to Local/State/Federal Agency Mtg November 10, 2015

Public Service Company of New Mexico

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

Stem Beach Solar 1041 Application

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace.

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

Integrated Resource Planning April 20, 2010

Interconnection and Transmission

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

Mocuba The First Utility Scale PV Project in Mozambique

Q44 Generation Interconnection

ITC HOLDINGS, CORP. Edison Electric Institute 9

Specific topics covered in this brief include:

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

Memorandum. This memorandum requires Committee action.

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

SESSION 2.2 (Wed 15h20) Accelerating Renewable Grid Connections And Improving Network Resilience Enabling Transmission Grid Access Current and Future

ATC Zone 2 Projects Update U.P. Energy Summit

MEMORANDUM. June 30, Council Members. Update on Transmission Planning Activities

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019

Brookfield Transmission Development LLC. Pre-qualification and Filing Package

SRP Ten Year Transmission Plan

Transmission Infrastructure By Public-Private Model

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

DOE Initiatives in the U.S. Transmission Sector

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

Corridor Management Committee. January 12, 2017

Generator Interconnection Process. Wholesale Transmission Overview

Reliability Coordinator Procedure

Copyright 2015, First Solar, Inc.

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

The GCC Interconnection Grid

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

NWPP Market Assessment and. August 3, 2012

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

NERC History, Mission and Current Issues Southern States Energy Board. October 16, 2011

Northeast Coordinated System Plan and Other Interregional Activities

Exhibit to Agenda Item #1a

Generation Interconnection Feasibility Study Report

Downtown Boise Multimodal Center

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Elia Grid International Your expert in power system solutions

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

NTTG 2019 Annual Interregional Information

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

Expanding Transmission Capacity: Options and Implications. What role does renewable energy play in driving transmission expansion?

BPA and NERC, WECC, ERO

Energy.

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

RFP Attachment 13. January 2010

Agreements and Queue Management

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Competitive Solicitation Process Enhancements. Status Update / Issue Paper

Agreements and Queue Management

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

Electric Program Investment Charge Joint IOU Stakeholder Webinar

Annual Policy Initiatives Roadmap Process Straw Proposal

EIM Entity Readiness Criteria May 6, 2015

MDCSystems. MICHAEL A. BAKER, P.E., M.S.E.M. Consulting Engineer

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused

Supporting Strategic Customers Needs

San Dimas TDC Solar Project. John Handy, Federal Business Development Manager September 28, 2016

P. O. Box 52025, MS POB100 Phoenix, Arizona (602) Feb 9, 2018

RESOLUTION NO. 14-R-

MR. PATRICIO CHRISTIAN VALENZUELA VÁSQUEZ Mobile: SUMMARY

Dynamic Transformation of the Energy Industry JUNE 25-27, 2019 COEUR D ALENE, IDAHO REGISTRATION

System Expansion Implementation Plan. Board Meeting, April 2017

Reston Town Center North Development. Community Update

Initiation of Periodic Regional Reviews: Region 1 Project Update

Small Hydro Regulatory and Permitting Requirements California

Progress Report on the GCC Electricity Grid Interconnection in the Middle East

Georgia: Power Transmission Enhancement Project financed by Asian Development Bank (ADB)

Moving Forward with Transit Oriented Communities

Transcription:

TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March 31, 2016

TransWest Express Transmission Project: 2016 2017 Cycle Interregional Transmission Project Submittals at a Glance Regional Entities California Independent System Operator WestConnect Northern Tier Transmission Group Physical Connection Yes Yes Yes Cost Allocation Requested Yes Yes No, not at this time 1 Identified Primary Need CA 50%, AZ and NV RPS Compliance [Accommodate planned resources] Load and Resource Data Proposed Capacity Load served by high quality Wyoming wind resources The Chokecherry and Sierra Madre Wind Energy Project, and natural gas plants at Northern Terminal Phased 1,500/3,000 MW between CAISO & WestConnect system in NV and NTTG system in WY Proposed Technology Two Terminal, 600 kv, Bipole HVDC Circuit length 730 miles In service Date December 2020 or later as needed Permitting Status FEIS issued May 2015, ROD in 2016 System Study Status Phase 2B in WECC Path Rating, Southern Terminal SIS underway Other Transmission Project Dependency Project Alternatives Project website Project Sponsor None. Proposed HVDC project will complement 500 kv AC build out among Regional Entities similar to DC and AC buildout along the West Coast Initial capacity can be greater. Potential mid terminal at Intermountain Power Project and/or 500 kv AC north and/or south of IPP. Potential connection to WestConnect system in Wyoming. www.transwestexpress.net TransWest Express LLC David Smith (303) 299 1545 david.smith@tac denver.com 1 TransWest Express LCC may request Cost Allocation from NTTG, if the NTTG 2016 2017 Study Plan includes additional needs (e.g. EIM benefits, etc.) and/or the ultimate TWE Project configuration (e.g. 500 kv AC, IPP terminal, etc. ) results in TWE Project meeting NTTG needs. 2

TransWest Express Transmission Project: An Interregional Transmission Solution Proposed Project designed to provide needed transmission capacity from Desert Southwest Region to Wyoming wind resources 1,500 MW initial/3,000 MW final, 600 kv HVDC Nevada connections: CAISO, WestConnect Wyoming connections: NTTG, potential WestConnect Potential Utah connections: NTTG, WestConnect Bi directional operation Potential use of 500 kv AC as alternative configuration 3

Project Need: Proposed TWE Project Meets Interregional Needs TWE Project developed as a Interregional Transmission Project to provide critical capacity between California and Rocky Mountain regions California RETI 2.0, CAISO Transmission Planning Process and WestConnect 2016 2017 examining required transmission to access Wyoming wind to help meet California s 50% RPS established in 2015 by SB 350 (Policy Need) Other potential needs: (Economic) increased transmission capacity between CAISO and PacifiCorp BAAs could provide benefits due to the EIM and potential regional ISO, common dispatch capacity sharing, PV solar over generation management, etc. 4

Cost Effectiveness: HVDC and HVAC Technology Complement One Another In Meeting Interregional and Regional Needs HVDC technology is cost effective for interregional distances over 400 miles HVAC technology is cost effective for regional distances, where nodes are needed every 100 to 300 miles The PDCI/PACI on the Pacific coast is a great example of efficient technology application http://www.transwestexpress.net/wecc/docs/conceptual_technical_report.pdf 5

TWE Project Development Status Development initiated in 2008 with primary focus on permitting. TransWest and Western Area Power Administration jointly working on development since 2010. Bureau of Land Management and Western completed the Final Environmental Impact Statement in 2015. Federal Records of Decision and right of way grants for federal land (67% of line route) anticipated in 2016. 1,500 MW Phase 2 WECC Path Rating and Interconnection Studies underway. Three year construction schedule planned. TWE Project can be placed in service as early as 2020 or as needed. TransWest Express affiliates are developing the 3,000 MW Chokecherry and Sierra Madre Wind Energy Project 2 and potential natural gas generating plant located near the TWE Project s Northern Terminal. 2 www.powercompanyofwyoming.com 6

TWE Project Siting and Alternative Routes Examined in Final Environmental Impact Statement

WECC Path Rating and Transmission Interconnection Studies Phase 2 Path Rating Process Kick off in 2010, revised Study Plan in 2015, in Phase 2B Seeking initial 1,500 MW north to south Path Rating System Impact Studies PacifiCorp performing studies for northern interconnection TransWest performing studies for southern interconnections 8

Technical Data Submitted Configuration Alternatives The TWE Project Plan of Development includes the potential to build a third terminal to connect to the 345 kv bus at the Intermountain Power Project in Delta, Utah, and to use 500 kv AC technology in lieu of HVDC in the segment from Wyoming to Utah and/or the segment from Utah to Nevada. Phasing Alternatives The proposed TWE Project is to build a 3,000 MW line and only 1,500 MW of terminal capacity and add in parallel a 1,500 MW of terminal equipment later. The initial capacity can be between 1,500 to 2,500 MW and there are alternative phasing approaches that would lower costs if the period between initial and final build out is shortened. TransWest submitted the power flow models being used in the ongoing WECC and Interconnection studies to the planning entities. Capital Cost estimate The initial 1,500 MW phase, $2.4B. To increase the capacity to 3,000 MW, $0.6B. TransWest has also estimated capital costs for the various alternatives listed above. 9

Development, Construction and Operation Plans TransWest plans to continue development activities including state and county permits, private ROW acquisition, Interconnection Agreements, Technical Specifications and project financing. TransWest project delivery plans are to use an Engineer, Procure, Construct (EPC) approach. The HVDC equipment will be procured separately and provided to the EPC contractor for installation. Alternative project delivery approaches may be used depending on the make up the TWE Project owners and access to balance sheet financing at the time of financial close for construction. The TWE Project will require full time operators at both terminals along with maintenance staff. AC substation and transmission line operations and maintenance will be contracted out. Western, PacifiCorp and other utilities that operate in the region are likely candidates to perform these services. 10

TransWest Express LLC TransWest Express LLC is a wholly owned affiliate of The Anschutz Corporation. The Anschutz Corporation is a privately held, multibillion dollar diversified company with worldwide investments in natural resources including oil and gas, pipelines, ranching and in other diverse industries. Anschutz has extensive experience in developing, constructing, financing and operating many large projects in the natural resources, real estate, sports and entertainment industries. The Anschutz Corporation has sufficient financial resources to provide the equity investment, although future equity partners will be obtained in the market. The Anschutz Corporation has on many occasions secured equity investments in other projects and continues to possess the appropriate reputation and relationships to attract such investments. 11

Interregional Project Review Considerations Reliability Assessments Multiple reliability assessments currently underway with Path Rating and SIS work with multiple entities from three regional planning groups plus Columbia Grid are already directly participating. Requires coordination among TransWest, Project Review Group(s) and Regional Planning Entities to ensure reliability assessments are conducted efficiently for configurations under consideration. Policy and Economic Assessments Proposed Project designed to meet CAISO and WestConnect Policy and Economic needs. Proposed Project not designed to meet NTTG regional needs included within 2014 2015 Transmission Plan. NTTG 2016 2017 Study Plan expected to include similar needs. Alternative Configurations may help meet NTTG needs. However, CAISO and WestConnect as the Regional Planning Agencies that will be considering cost allocation would need to initiate review of alternatives and coordinate with NTTG and TransWest. Cost Allocation Consideration Seeking Cost Allocation consideration from CAISO and West Connect. Not currently seeking Cost Allocation consideration from NTTG. Cost Allocation of DC Project avoids common transmission cost allocation pitfalls of AC projects. DC controllability allows for subscription capacity process and limits free rider benefits. 12

Additional Information TransWest looks forward to working with the regional entities and all stakeholders to provide additional information on the project and the opportunities. Interregional Transmission has been built in the past and still provides benefits today! (TransWest and U.S. Forest Service Meeting in Wasatch Forest, Utah, August 2015. Great meeting location for many reasons.) 13