100 % Design/Construction Update Community Meeting May 23, 2016
Meeting Agenda May 23, 2016 Introductions Welcome School Board Member Kathleen Kat Butler Gordon Project Update Facilities Meeting Organizer Architect: Rhodes+Brito Architects Construction Manager: Pirtle Construction Company Transportation Update Questions and Answers Adjournment 2
Planned Facility: NEW Campus to Meet District Standards for Elementary Schools: Prototypical Core Spaces Enhanced Learning Environment: Latest Technology Planned Site Circulation Safety Community Asset 3
Planned Facility: NEW Campus to Meet District Standards for Elementary Schools: Prototypical Core Spaces Enhanced Learning Environment: Latest Technology Planned Site Circulation Safety Community Asset 4
Site Plan 5
Site Plan 5
First Floor Plan 6
Second Floor Plan 7
Example Classroom 8
Example Classroom 9
Planned Facility: Technology : Campus The technology package will include: Student and teacher computers (3 laptops) Interactive Flat Panel White boards Video on demand Two computer laboratories Secure card access Security cameras Wireless Access Audio Enhancement 10
Planned Facility: Media Center The Media Center will include: Lab with 22 student laptops Library tables for an entire class Story telling area CCTV studio Professional library Audio Enhancement Example Media Center 11
Planned Facility: Cafeteria The Cafeteria will include: New Kitchen Two Serving Lines Teacher Dining Elevated Stage Extended Day Office Restrooms Example Cafeteria 12
Planned Facility: Specialty Classrooms Art Classroom with kiln Science Classroom Music Classroom Example Music Classroom 13
Planned Facility: Administration The administrative area includes: Single point of entry during school hours Lobby Administrative offices, workroom & storage Large conference room Clinic Teacher planning areas Example Administration / Lobby 14
Planned Facility: Physical Education Physical Education will include: PE Office and storage Covered play structure Basketball Courts Tot lot play structure Youth lot play structure Playfields Example Play Equipment 15
Planned Facility: Site Circulation On site car stacking (142 cars) On site parking (129 spaces) Bus loop Covered walkways Safe pedestrian paths Bike racks Example Main Entry 16
Sustainable Features Site: Low Impact Design (LID) stormwater design Native/low water plants reduce water consumption Building: 10% more energy efficient than ASHRAE 90.1 standard High Efficiency Chillers (8% energy reduction) Light colored roof to reduce heat gain and improves energy performance Energy Star rated equipment Water saving toilets, faucets, and fixtures All general classrooms have daylighting Over 75% of ALL spaces have daylighting Thermal efficient windows/glazing Fully automated building controls system 10% more energy Sustainable Features 17
EAST ELEVATION 18
SOUTH ELEVATION 19
WEST ELEVATION 19
NORTH ELEVATION 21
Southwest / Main Entry Elevation 22
Schedule Task Duration Completed Design Bidding Start Construction Building Construction Move-in Date 23 May 2016 Jun 2016 Jul 2016 Aug 2016 Sep 2016 Oct 20156 Nov 2016 Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 20167 May 2017 Jun 2017 Jul 2017 Aug 2017
Orange County Public Schools PIRTLE Laydown and Storage Beecher Street Construction Access Construction Parking Hernandez Drive Construction Access Preliminary Site Utilization Plan 24
QUESTIONS? 25